Annotated Compendium of the 7 Documents
1. Instrumentation Spec Summary ADNOC
ADNOC Instrumentation Specification Summary
File: Instrumentation_Spec_Summary_ADNOC.pdf
What it is:
A summary table capturing ADNOC’s (Abu Dhabi National Oil Company) essential technical and environmental requirements for instrumentation—particularly for instruments furnished with packaged units on projects.
Key contents:
-
Design Life: 30 years
-
Environmental: Tropical/marine, high humidity, dust/salt air
-
Certifications/Standards: IP65 minimum, Zone 1/Class I Div 1, ANSI/IEC/API/NACE
-
Vendor requirement: ADNOC-approved only (Honeywell, Siemens, etc.)
-
Integration: With Honeywell MAC/ICSS
-
Testing: FAT, SAT, CIT, SIT, IFAT per specific procedures
Rationale:
This document acts as the benchmark for compliance. Any vendor or supplied system must meet or exceed these criteria to be approved for ADNOC projects.
2. Hughes Safety Showers Commercial Quotation (H2 Green Steel)
File: Q-27065-13.pdf
example-quote
What it is:
A detailed vendor commercial quote from Hughes Safety Showers to McDermott for a Swedish project.
Key contents:
-
Equipment: Emergency tank showers with eyewash (ATEX/non-ATEX), portable showers, eyewash stations
-
Breakdown: Unit prices, quantities, specs, painting requirements, instrumentation, electricals, alarm integration, delivery terms, deviations, and clarifications
-
Deviations: Notes on any vendor-standard practice differing from client spec (e.g., cable type, weld certs)
Rationale:
This is a real-world vendor response to a project RFP, itemizing what’s being offered and specifying where it may diverge from strict ADNOC-style requirements.
3. Instrumentation RFI to Hughes (ADNOC)
File: Instrumentation_RFI_to_Hughes_ADNOC.pdf
Request for Information (RFI) – Instrumentation Compliance Review
What it is:
A Request for Information (RFI) from the project owner/contractor to Hughes Safety Showers, seeking clarifications and confirming compliance with ADNOC’s instrumentation specs.
Key contents:
-
Requests confirmation on:
-
30-year design life
-
Exact temperature/humidity ratings
-
IP ratings
-
EMC & surge protection
-
Power supply compatibility
-
Integration with MAC/ICSS/MEES/TSI
-
Inclusion of full test scope
-
Rationale:
This is the compliance check: the buyer is verifying that the Hughes offer matches the ADNOC technical benchmark (Doc 1), flagging any gaps before procurement.
4. ADNOC Project Datasheet: Safety Showers & Eye Wash
File: 4422-SS-FP-000000001907_01.pdf
EMERGENCY SAFETY SHOWER AND EYE WASH DATASHEETS
What it is:
The official ADNOC project datasheet for emergency safety showers and eyewash stations, for the Hail & Ghasha Onshore project (part of the Ghasha concession), showing project requirements and specs.
Key contents:
-
Operating conditions:
-
Temp: 3°C to 58°C
-
Humidity: up to 97%
-
Flow rates, water temp, discharge time, etc.
-
-
Materials/specs:
-
Chiller/insulation for tanks
-
Marine/saline/dust-proofing
-
Certifications, hazardous area classification
-
Visual/audible alarms, IP ratings, language requirements
-
Piping, mounting, water disposal
-
-
Diagrams:
- Typical arrangement (page 4) shows instrument and alarm integration
Rationale:
This is the primary technical reference that all vendors (and internal teams) must design and quote against. It informs the requirements summarized in Doc 1 and checked in Doc 3.
- Typical arrangement (page 4) shows instrument and alarm integration
5. Material Requisition for Emergency Safety Showers & Eye Washes
File: 4422-SS-MR-CN0000008000_A1.pdf
MATERIAL REQUISITION FOR EMERGENCY SAFETY SHOWERS AND EYE WASHES
What it is:
The formal ADNOC material requisition document, specifying the types and quantities of safety showers and eyewash units required for the Hail & Ghasha Onshore project.
Key contents:
-
Material breakdown:
-
Quantities for process (hydrogen, non-hydrogen) and utility units
-
25 portable eyewash units
-
-
References:
- Cites all the key project documents/specs (including the datasheet, design criteria, testing procedures, HSE philosophy, and P&IDs for water supply)
-
Instructions to vendor:
- Requirements for documentation, spare parts, and technical data sheets
Rationale:
This is the official order/trigger document: it makes the specs and datasheets contractually binding, specifying exactly what needs to be delivered, in what quantity, and referencing all controlling documents.
- Requirements for documentation, spare parts, and technical data sheets
6. Hughes Commercial Offer (ADNOC Ghasha)
File: Commercial Offer Q-30493-8_Priced EUR.pdf
commercial-offer
What it is:
A comprehensive commercial offer (quotation) from Hughes Safety Showers to MAIRE Tecnimont for the ADNOC Hail & Ghasha project, showing pricing in EUR, and tailored to the specific quantities and technical requirements outlined in the material requisition.
Key contents:
-
Equipment:
-
25 tank showers for process units (hydrogen/non-hydrogen)
-
15 for utility units
-
25 portable eyewash units
-
24 hazardous area chillers
-
-
Compliance notes:
-
References to certifications (IECEx, ECAS, etc.), hazardous area suitability, and project paint/specs
-
Explicit deviations and clarifications (e.g., use of SCH40 pipe, fastener grades, AVL)
-
List of optional/extra-cost items
-
-
Documentation included:
- GA drawings, O&M, wiring diagrams, certificate of conformity
-
Warranties, shipping, payment, storage, bonds
Rationale:
This is the actual vendor response to the material requisition, tailored for the ADNOC project—where every spec, deviation, and compliance item is mapped to project documentation.
7. Compliance Matrix – Industrial Safety Showers
File: Compliance_Matrix_-_Industrial_Safety_Showers.csv
What it is:
A matrix (CSV file) presumably listing each technical requirement from the ADNOC spec or the project datasheet, cross-referenced against the Hughes Safety Showers offering, with notes on compliance or deviations.
Key contents:
-
Row-by-row assessment: Likely itemizes each clause or technical point (IP rating, temperature, alarms, integration, certification, etc.), stating whether Hughes complies or if there’s a deviation/clarification.
-
Purpose: Provides a transparent, auditable trail showing how the vendor’s offer stacks up to the official requirements.
How These Documents Relate to Each Other
The Project Flow
-
Requirements Definition
-
Instrumentation Spec Summary (1): Sets ADNOC’s baseline standards for instrumentation.
-
Project Datasheet (4): Details specific requirements for the emergency shower/eyewash application.
-
-
Procurement Trigger
- Material Requisition (5): Officially specifies what’s needed (quantities, types), referencing the technical documents above.
-
Vendor Engagement & Quotation
-
Hughes Quotation (2): A generic/commercial quote from Hughes (for a different client, but similar products).
-
ADNOC Ghasha Offer (6): Hughes’ tailored commercial offer for the ADNOC project, mapped to the exact quantities/specs in the requisition.
-
-
Compliance Verification
-
RFI to Hughes (3): The project team checks that the vendor’s proposal truly meets all requirements, flagging any mismatches.
-
Compliance Matrix (7): Documents this “gap analysis” in detail for each clause or requirement.
-
Visual Map: Document Relationships
-
1 + 4 = Project standards & datasheets —>
-
5 = Official order, cites 1 & 4 —>
-
6 = Vendor’s tailored response to 5 (and, by reference, 1 & 4)
-
3 = Owner checks that 6 matches 1 & 4
-
7 = Evidence/matrix showing outcome of 3
-
2 = Example quote for another similar project—useful as a baseline, but not strictly for ADNOC Ghasha
Rationale for the Connections
-
Everything flows from the ADNOC standards/specs. The project datasheet (4) and specification summary (1) are controlling.
-
The material requisition (5) formalizes what must be purchased, tying all requirements together.
-
Vendor offers (2 & 6) are responses to these requirements. Offer 6 is the direct, detailed response to requisition 5, while 2 provides useful context for vendor practices.
-
Compliance and due diligence (3 & 7): Project team ensures what’s being offered is truly compliant—documenting and justifying any deviations.
-
The compliance matrix (7) is the final check, referencing all the above to verify alignment.
Summary Table of Each Document’s Role
# | Document | Role/Purpose | Main Connection |
---|---|---|---|
1 | Instrumentation Spec Summary ADNOC | Baseline spec for all instrumentation | Reference for 4, 5, 3 |
2 | Hughes Safety Showers Quotation (H2 Green Steel) | Vendor commercial offer (not for ADNOC) | Example vs. 6 |
3 | Instrumentation RFI to Hughes (ADNOC) | Owner compliance check to vendor | Verifies 6 vs. 1/4 |
4 | ADNOC Project Datasheet: Safety Showers & Eye Wash | Detailed technical requirements | Cited in 5, source for 3 |
5 | Material Requisition for Emergency Showers & Eye Washes | Official project purchase request | Drives 6, references 1/4 |
6 | Hughes Commercial Offer (ADNOC Ghasha) | Vendor’s detailed project-specific quote | Direct response to 5 |
7 | Compliance Matrix – Industrial Safety Showers | Clause-by-clause compliance evidence | Outcome of 3, covers 6 |