NFPS Offshore Compression Complexes Project COMP2
COMPANY Contract No.: LTC/C/NFP/5128/20
CONTRACTOR Project No.: 033734
Document Title
:
DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
COMPANY Document No.
: COMP2-SPM-PE-REP-00002
Saipem Document No.
: 033734-A-D-00-SPM-EM-R-10007
Discipline
:
ADMINISTRATIVE, ENGINEERING MANAGEMENT
Document Type
: REPORT
Document Category/Class
: 1
Document Classification
: INTERNAL
B
A
10-May-2023
Issued for Approval
22-Mar-2023
Issued for Review
Hackean Hazeldene Hackean Hazeldene
Neil Demaisip
Sandeep Maiti
Neil Demaisip
Chandrababu Paramasivam
REV.
DATE
DESCRIPTION OF REVISION
PREPARED BY
CHECKED BY
APPROVED BY
Saipem S.p.A.
Company No._Rev. COMP2-SPM-PE-REP-00002_B
1 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
REVISION HISTORY
Revision
Date of Revision
Revision Description
A1
A
B
14-Feb-2023
22-Mar-2023
10-May-2023
Issued for Inter-Discipline Check
Issued for Review
Issued for Approval
HOLDS LIST
Hold No
Hold Description
Company No._Rev. COMP2-SPM-PE-REP-00002_B
2 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
TABLE OF CONTENTS
1
2
3
4
5
6
7
8
INTRODUCTION … 4
1.1 PROJECT OBJECTIVE … 4 1.2 PROJECT SCOPE … 4
DEFINITIONS AND ABBREVIATIONS … 6
2.1 DEFINITIONS … 6 2.2 ABBREVIATIONS … 7
REFERENCE, RULES, CODES AND STANDARDS … 8
3.1 COMPANY DOCUMENTS … 8 3.2 PROJECT DOCUMENTS … 9 3.3 CONTRACTOR DOCUMENTS … 9 3.4 SUB-CONTRACTOR DOCUMENTS … 9 INTERNATIONAL CODES AND STANDARDS … 10 3.5
PURPOSE … 10
OBJECTIVE … 10
RESPONSIBILITY … 11
PROCESS EXECUTION … 12
7.1 STEPS FOR WORKSHOP … 12
RISK RATING … 12
8.1 CONSEQUENCE RATING … 12 8.2 PROBABILITY OF OCCURRENCE … 14 8.3 WORKSHOP FLOW AND DECISION MAKING … 16 8.4 SURVEILLANCE ACTIVITIES … 17
9
10
11
WORKSHOP SCHEDULE (DATE/TIME) … 19
TOPICS DISCUSSED DURING THE WORKSHOP … 20
WORKSHOP CONCLUSION… 20
11.1 GENERAL … 20 11.2 BY DISCIPLINE … 20
11.2.1 Structural … 20
11.2.2 Mechanical … 20
11.2.3
Instrument … 20
11.2.4 Electrical … 21
11.2.5 Piping … 21
11.2.6 Technical Safety and Loss Prevention … 21
11.2.7 Telecom … 21
RECOMMENDATIONS … 21
REFERENCES - METHODOLOGY … 23
APPENDICES … 26
12
13
14
14.1 APPENDIX 1 DDE EQUIPMENT CRITICALITY MATRIX (WORKSHOP 15-DEC-22) … 27 14.2 APPENDIX 2 DDE EQUIPMENT CRITICALITY WORKSHOP – ATTENDANCE RECORD … 41 14.3 APPENDIX 3 DDE EQUIPMENT CRITICALITY WORKSHOP – MINUTES OF MEETING 15 DEC 22 … 43
Company No._Rev. COMP2-SPM-PE-REP-00002_B
3 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
1
INTRODUCTION
The North Field is the world’s largest natural gas field and accounts for nearly all of the state of Qatar’s gas production. The reservoir pressure in the North Field has been declining due to continuous production since the early 1990s. The principal objective of the NFPS Project is to sustain the plateau from existing QG South Operation (RL Dry Gas, RGE Wet gas) and existing QG North Operation (QG1 & QG2) production areas by implementing an integrated and optimum investment program consisting of subsurface development, pressure drop reduction steps and compression. Refer to the figure below for a schematic of the North Field.
Qatargas Operating Company Limited is leading the development of the North Field Production Sustainability (NFPS) Project.
1.1 Project Objective
The objective of this Project includes:
• Achieve standards of global excellence in Safety, Health, Environment, Security and Quality
performance.
• Sustain the Qatargas North Field Production Plateau by installing new Compression Complex facilities CP6S & CP7S in QG south with integration to the existing facilities under Investment #3 program.
• Facility development shall be safe, high quality, reliable, maintainable, accessible, operable,
and efficient throughout their required life.
1.2 Project Scope
The Project Scope includes detailed engineering, procurement, construction, transportation & installation, hook-up and commissioning, tie-in to EXISTING PROPERTY and provide support for start- up activities of the following facilities and provisions for future development. The WORK shall be following the specified regulations, codes, specifications and standards, achieves the specified performance, and is safe and fit‐for‐purpose in all respects.
Offshore
CP6S and CP7S Compression Complexes that are part of QG-S RGE facilities as follows:
• CP6S Compression Complex
• Compression Platform CP6S, Living Quarters LQ6S, Flare FL6S
• Bridges BR6S-2, BR6S-3, BR6S-4, BR6S-5
• Bridge linked Tie-in to RP6S
Production from existing wellheads (WHP6S & WHP10S) and new wellhead (WHP14S) are routed via riser platform RP6S to compression platform CP6S to boost pressure and export to onshore via two export lines through the existing WHP6S pipeline and a new 38” carbon steel looping trunkline from RP6S (installed by EPCOL). CP6S is bridge-linked to RP6S.
• CP7S Compression Complex
• Compression Platform CP7S, Living Quarters LQ7S, Flare FL7S
• Bridges BR7S-2, BR7S-3, BR7S-4, BR7S-5
• Bridge linked Tie-in to RP7S
Company No._Rev. COMP2-SPM-PE-REP-00002_B
4 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
CP7S shall receive production from existing wellheads (WHP5S & WHP7S) and new wellhead (WHP13S). There is only one export line for CP7S through the existing export pipeline from WHP7S. CP7S is bridge-linked to RP7S.
RGA Complex Destressing
Migration of the Electrical power source, Telecoms, Instrumentation and Control systems from WHPs and RHPs hosted by RGA to the respective Compression Complexes listed below:
• WHP6S, WHP10S, WHP14S, RP6S and RP10S to CP6S Compression Complex
• WHP5S, WHP7S, WHP13S and RP7S to CP7S Compression Complex
Destressing of Telecoms, Instrumentation and Control system in RGA Complex Control Room, which would include decommissioning and removal of telecom system devices and equipment that would no longer be required post migration and destressing activity.
Onshore
An Onshore Collaborative Center (OCC) will be built under EPC-9, which will enable onshore based engineering teams to conduct full engineering surveillance of all the offshore facilities. The OCC Building will be located in Ras Laffan Industrial City (RLIC) within the Qatar Gas South Plot. MICC & Telecommunication, ELICS related scope will be performed in the OCC building.
Figure 1.2.1: NFPS Compression Project COMP2 Scope
Company No._Rev. COMP2-SPM-PE-REP-00002_B
5 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
2 DEFINITIONS AND ABBREVIATIONS
2.1 Definitions
Definition
Description
COMPANY
Qatargas Operating Company Limited.
CONTRACTOR
Saipem S.p.A.
DELIVERABLES
FACILITIES
All products (drawings, equipment, services) which must be submitted by CONTRACTOR to COMPANY at times specified in the contract. All machinery, apparatus, materials, articles, components, systems and items of all kinds to be designed, engineered, procured, manufactured, constructed, supplied, tested and permanently installed by CONTRACTOR at SITE in connection with the NFPS Project as further described in Exhibit 6.
fabricated,
MILESTONE
A reference event splitting a PROJECT activity for progress measurement purpose.
PROJECT
NFPS Offshore Compression Complexes Project COMP2
SITE
(i) any area where Engineering, Procurement, Fabrication of the FACILITIES related to the CP6S and CP7S Compression Complexes are being carried out and (ii) the area offshore required for installation of the FACILITIES in the State of Qatar.
SUBCONTRACT
Contract signed by SUBCONTRACTOR and CONTRACTOR for the performance of a certain portion of the WORK within the Project.
SUBCONTRACTOR
Any organization selected and awarded by CONTRACTOR to supply a certain Project materials or equipment or whom a part of the WORK has been Subcontracted.
WORK
Scope of Work defined in the CONTRACT.
WORK PACKAGE
The lowest manageable and convenient level in each WBS subdivision.
VENDOR
The person, group, or organization responsible for the design, manufacture, testing, and load-out/shipping of the Equipment/ Material.
Company No._Rev. COMP2-SPM-PE-REP-00002_B
6 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
2.2 Abbreviations
Code
Definition
DDM
DM
DPR
EDMS
EM
FAT
GDP
IDC
DCL
MDR
PCM
PLE
PM
PMT
PQM
PSL
PVA
ROC
TM
Document Distribution Matrix
Department Manager
Daily Progress Report
Electronic Document Management System
Engineering Manager
Factory Acceptance Test
General Distribution Process
Inter-Discipline Check
Document Control Lead
Master Document Register
Project Control Manager
Planning Engineer
Project Manager
Project Management Team
Project Quality Manager
Project Specialist Leader
Preparation / Verification / Approval Workflow In EDMS
Record of Conversation
Technical Manager
Company No._Rev. COMP2-SPM-PE-REP-00002_B
7 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
3 REFERENCE, RULES, CODES AND STANDARDS
The following codes, standards and specification are referenced within the document shall be considered as part of this specification. Conflict among applicable specification and / or codes shall be brought to the attention of the COMPANY for resolution COMPANY decision shall be final and shall be implemented. The latest editions of codes and specification effective as on date of contract shall be followed.
In general, the order of precedence shall be followed:
a) Qatari Governmental and Regulatory Requirements
b) COMPANY Procedures, Policies and Standards (Exhibit 5 Appendix I)
c) Project Specifications.
d) Industry Codes and Standards
e) COMPANY and CONTRACTOR’s Lessons Learned
If CONTRACTOR/SUBCONTRACTOR deems any deviations from the specifications will result in significant project cost and schedule saving, proposal to such deviations shall be submitted to COMPANY for review and approval. CONTRACTOR/SUBCONTRACTOR shall not proceed with any deviation to the specifications without prior COMPANY approval. In general, all design activities shall conform to legal and statutory regulations, and recognized industry best practices.
3.1 Company Documents
S. No
Document Number
Title
PRJ-PJL-PRC-004_07
Facilities Engineering and Vendor Document Numbering Procedure
PRJ-PJL-PRC-005_21
Facilities, System and Unit Number Codes and Descriptions Procedure
PRJ-PJL-PRC-006_01
Project Information Handover Procedure
PRJ-PJL-PRC-048_11
PRJ-PJL-PRC-049_01
Facilities Documentation Metadata Requirements Procedure Project Acceptance Procedure
Information Handover, Verification
and
COMP-QG-PE-PRO-0002 Equipment Criticality Workshop Charter
TCH AIG-078
Company Material Equipment Criticality Determination Process
TCH-ASV-PRC-036
Asset Criticality Assessment Process
COMP-TPF-PE-REP- 00036
Equipment Criticality Workshop Report FEED
Equipment Criticality Matrices (FEED) for Offshore Ph 1A, 1B, 2 and Onshore
Company No._Rev. COMP2-SPM-PE-REP-00002_B
8 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
3.2 Project Documents
S. No
Document Number
Title
LTC/C/NFP/5128/20
Contract Agreement
EXHIBIT 5
EXHIBIT 6
Project Instructions
Scope of Work
3.3 Contractor Documents
S. No
Document Number
Title
COMP2-SPM-PM-PLN-00001
Project Execution Plan
COMP2-SPM-PE-PLN-00003
Engineering Execution Plan
3.4 Sub-Contractor Documents
S. No
Document Number
Title
033734-Z-Z-00-PRW-EM-P-00001
Project Execution Plan
033734-Z-Z-00-PRW-EM-P-00002
Project Information Management Plan
033734-Z-Z-00-PRW-EM-P-00003
Digital Project Delivery Plan
033734-Z-Z-00-PRW-PC-P-00001
Project Control Procedure
033734-Z-Z-00-PRW-PC-P-00002
Document Control Procedure
033734-Z-Z-00-PRW-PC-P-00003
Progress Measurement Procedure
033734-Z-Z-00-PRW-HS-P-00001
Project HSES Plan
033734-Z-Z-00-PRW-HS-P-00002
Incident Investigation & Reporting Procedure
033734-Z-Z-00-PRW-QA-P-00001
Project Quality Plan
Company No._Rev. COMP2-SPM-PE-REP-00002_B
9 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
3.5
International Codes and Standards
S. No
Document Number
Title
ISO 9001:2015
Quality Management Systems – Requirements
ISO 9000:2015
ISO 10005:2018
ISO 10006:2017
4 PURPOSE
Quality Management Systems – Fundamentals and Vocabulary
Quality Management Systems – Guidelines for Quality Plans
Quality Management Systems – Guidelines for Quality Management in Projects
The purpose of this Workshop is to review and assess the criticality rating of equipment, systems and module/skid packages in the NFPS Compression Project FEED Criticality Matrix for final implementation by the necessary parties involved in the project.
The ratings will apply to all equipment and materials where requisitions are prepared, purchase orders issued, inspection conducted, and shipments received.
This Equipment Criticality Workshop is based on the following Qatargas References:
-
Equipment Criticality Workshop Charter COMP-QG-PE-PRO-0002
-
Company Material Equipment Criticality Determination Process (TCH AIG-078)
-
Asset Criticality Assessment Process (TCH-ASV-PRC-036)
-
Equipment Criticality Matrices (FEED) for Offshore Ph 1A, 1B, 2 and Onshore
5 OBJECTIVE
The outcome of the Criticality Assessment workshop to be jointly held among SUBCONTRACTOR (Ranhill Worley) CONTRACTOR and COMPANY and COMPANY Operations team will establish the severity ratings required during design, manufacturing, installation and start up.
Results of criticality assessment shall be used to determine the level of inspection required in Inspection and Test Plan (ITP), etc.
Surveillance action plans for design, manufacturing, installation and start-up will be recommended at each phase and which shall be implemented during EPC stage.
Company No._Rev. COMP2-SPM-PE-REP-00002_B
10 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
6 RESPONSIBILITY
Criticality Rating Assessment Workshop (DDE) is a multi-discipline activity. Overall responsibility for its effective implementation remains with the Project Management Team and the Sub-contractor and Contractor.
The responsibilities and activities are summarized in the following matrix:
Notes:
-
Engineering Manager may assign or delegate the works or tasks to Project Engineer, if required.
-
Quality Manager may delegate the tasks to QA Engineer as and when required.
-
Lead Disciplines may seek consultation with Head of Departments or specialists as and when
required.
Workshop Responsibility Matrix
Item
Activity
Project Manager
Engineering Manager
Project Quality Manager
Discipline Leads
Remarks
1 2 3 4 5 6 7 8
Prepare the Workshop ToR Approve and review the ToR. Ensure that adequate personnel and resources are available to carry out the requirements set forth in this document. Responsible for Workshop implementation. Facilitate the Workshop Prepare Workshop Report Review and approve the Workshop Report Ensure appropriate distribution of the final Equipment Criticality Matrix.
A
A
A
A
A
A
A
A
C
R
R
R
C
R
R
C
C
C
R
R
R
C
C
C
C
C
Responsibility Matrix Legend:
R
A
C
Responsible for performing the action Accountable to ensure action happens Consulted during action
Company No._Rev. COMP2-SPM-PE-REP-00002_B
11 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
7 PROCESS EXECUTION
7.1 Steps for Workshop
The following steps were followed during the workshop:
Leads to review the FEED Matrix at discipline level – Add any equipment not found in the List, assess/determine the Criticality. Focus on key equipment.
Leads to review the FEED Matrix at discipline level - if any equipment Criticality Rating found not suitable, amend/provide justification. Focus on key equipment.
Workshop on Criticality Rating
Issue the Report
During the workshop, the ratings are jointly agreed and populated accordingly. The final rating is taken as the assigned rating where the calculated default ratings can be upgraded or reduced based on project requirements.
8 RISK RATING
8.1 Consequence Rating
Risk Rating is calculated by multiplying the Consequence and Probability score of critical equipment listed in the Equipment List. Individual Risk Rating is identified for each phases listed below:
-
Design
-
Manufacturing
-
Installation & Start-up
For the design phase, the engineering team will be providing oversight on the design development process at this particular stage.
The Consequence of the risk will be assigned for each item on the scale of “1” to “4” with “1” as the likely to greatest consequence and “4” as the least consequence.
Criticality Element: Consequence is divided into 4 categories and asses as outlined below. Consequence estimates the impact of the Equipment risk of failure in terms of: Health, Safety & Environment- safety risk during commissioning and start-up.
Cost for the Equipment itself and related installation Asset Schedule of the Project – schedule impact risk, market/vendor to deliver pre-award/post award Performance / Operation of the Facilities / final product / Production Loss.
Company No._Rev. COMP2-SPM-PE-REP-00002_B
12 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
For Safety, Health, Environment Consequence Factor (SHE) - Further categorization is done based on medium of fluids i.e. sour hydrocarbon, Fuel gas, helicopter fuel, non-hydrocarbon which will assist in streamlining the criticality of the elements rated.
For performance consequence - it is further streamlined into full production loss, some production loss and no production loss due to spares.
The selected consequence base case number will be the smallest number with the greatest consequence.
Table 1: Safety, Health, Environment Consequence Factor
Table 2: Project Cost Consequence
Company No._Rev. COMP2-SPM-PE-REP-00002_B
13 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
Table 3: Execution / Schedule Consequence Factor
Table 4: Performance Consequence Factor
8.2 Probability of Occurrence
The Probability of occurrence of the risk will be assigned for each item on the Equipment List on the scale of “A” to “D” with “A” as the highest Probability of occurrence and “D” as the lowest Probability of occurrence.
The Probability estimates the likelihood of the Equipment & Material “risk of failure” for each particular phase of the Project due to:
Company No._Rev. COMP2-SPM-PE-REP-00002_B
14 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
-
Design novelties, complexity, etc.
-
Manufacturing & Testing complexity, associated risks transferred to suppliers, etc.
-
Installation (obviously important for Offshore/Subsea Projects but which can also be applied
Onshore during the Construction phase).
Table 5: Design Probability Factor
Table 6: Manufacturing Probability Factor
Company No._Rev. COMP2-SPM-PE-REP-00002_B
15 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
Table 7: Installation Probability Factor
8.3 Workshop Flow and Decision Making
Rate the Criticality Element-Consequence
Obtain Consequence Base Number which will be the minimum rating of above
Rate the Criticality Element for Probability
Discuss the Default Matrix Rating
Assign the Criticality by either taking the Default matrix rating or upgrading/lowering the rating based on project requirement
Use the Asigned Criticality to determine Surveillance Activities
Surveillance Activity of I,II,III,IV is selected based on assigned ratings
Company No._Rev. COMP2-SPM-PE-REP-00002_B
16 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
8.4 Surveillance Activities
Surveillance Activities
The surveillance activities have been divided into 3 categories i.e. design, manufacturing and installation & start up.
Category I: will be the most critical rating with a dedicated team in charge of the equipment/packages.
Category II: will be the moderately critical rating with monthly inspection and attendance during key activities.
Category III: will be a less severe rating with regards to review and selected witness of key activities equipment/packages.
Category IV: will be the least critical rating with mostly review and communication with supplier on the equipment/packages involved. A detailed breakdown is as tabulated below.
Table 8: Design
Company No._Rev. COMP2-SPM-PE-REP-00002_B
17 of 47
Design DCR Engineering Oversight RFQ Development COMPANY PMT Contractor COMPANY PMT Contractor I Participate in key meetings with Contractor; review documents (response is required); attendance at key engineering activities is required; consider assigning dedicated PMT resource to steward package Assign dedicated Package Engineer; prepare engineering documents. Jointly develop RFQ with Contractor. TBE to be approved by CPY All deviations from TBE to be approved prior to PO. Jointly develop RFQ with Company Develops TBE Submits All deviations for approval prior to PO. II Assign Package Engineer; prepare engineering documents. III Review documents (response is required); attendance at key engineering activities is optional Assign Package Engineer; prepare engineering documents. Receive documentation for review (response is required) Prepare documentation and provide to Company for review (response is required) IV Review of documentation only on an exception basis Engineer to prepare engineering documents. Receive documentation for info/review as per the quality specifications (response is optional) Prepare documentation and provide to Company for info/review (response is optional)
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
Table 9: Manufacturing (Procurement)
Company No._Rev. COMP2-SPM-PE-REP-00002_B
18 of 47
Manufacturing (Procurement) MCR Source Inspection & Testing Suppliers and Sub-Suppliers Engagement COMPANY PMT Contractor COMPANY PMT Contractor I Weekly (minimum) inspection visits and all selected ITP points, including FAT attendance. Provide full-time resident inspector (w/ PMT approval;) minimum 2 inspection visits per week and all selected ITP points Dedicated Package Engineer to attend kick-off meeting and all ITP points including FAT Conduct PM (or PM designate) level visit with Supplier (preferably at vendor’s shop); attend key activities and witness key tests Conduct PM (or PM designate) level visit with Supplier (preferably at vendor’s shop); weekly teleconferences with Supplier; attend key activities and witness key tests II Monthly (minimum) inspection visits and all selected ITP points, including FAT attendance. Minimum 1 inspection visit per week and all selected ITP points Package Engineer to attend kick-off meeting and selected ITP points including FAT III Random inspection visits and random witness of tests as per approved ITP. Selected ITP points Package Engineer attend FAT and final inspection only Attend key activities and witness key tests Bi-weekly teleconferences with Supplier; visits for key activities and witness key tests IV As per the approved ITP. Document reviews and final inspection (unless written waiver is provided by Company) Participate in key discussions with Supplier Establish standing teleconference with Supplier to review status and any outstanding issues
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
Table 10: Installation / Start-up
9 WORKSHOP SCHEDULE (DATE/TIME)
Below was the timeline for the Workshop:
01–06 Dec 22: Leads Breakout Session at Discipline Level (Leads from RW and Saipem). The team sit down and reviewed the Discipline Criticality Matrices. The focus was on the key equipment.
07-08 Dec 22: Internal Meeting was held among RW and Saipem Leads and PMT. All RW/Saipem Leads took turn to present the outcome of their session to the Team.
Team (RW/Saipem) has agreed on the outcome of the breakout session which were presented to Company during the Workshop.
13 Dec 22: Team sent the Workshop Terms of Reference (ToR) to Company for review prior to the workshop.
15 Dec 22: Workshop was conducted with the participation of RW, Saipem and Company Teams from 01.00 pm to 05.00 pm.
Company No._Rev. COMP2-SPM-PE-REP-00002_B
19 of 47
Installation, Pre-Comm, Comm & Start-Up ICR COMPANY PMT Contractor I Approves Installation & Start-up Procedure. Participate/witness (full time) installation & start-up activities. (Including Preservation) Dedicated Package Engineer with site supervision team to manage interfaces. Ensure physical attendance of respective Vendor/OEM at site. Participate/witness (full time) installation & start-up activities. (Including Preservation) II Approves selected Equipment Installation & Start-up Procedure. Participate/witness installation & start-up activities (Including Preservation) as and when required. Package Engineer with site supervision team to manage interfaces. Ensure physical attendance of respective Vendor/OEM at site. Participate/witness installation & start-up activities (Including Preservation) as and when required. III Review of documentation. Site Installation Supervisor manages the activities according to Procedures (including preservation). Vendor assistance if required only. IV Monitor only. Site Installation Supervisor manages the activities according to Procedures.
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
10 TOPICS DISCUSSED DURING THE WORKSHOP
The following topics were discussed during the Workshop:
- Missing line items from FEED (4 nos.)
• Probability factor (Design / Manufacturing / Installation) - None
• Consequence factor - Not challenged except Pedestal Crane – 1 no.
• Views on ratings where assigned rating is conservative than default ratings - 2nos.
-
Total Equipment identified for workshop – 7nos.
-
Probability Factor is reviewed for “Design” to ensure MDR and document review categories
alignment.
- Another workshop is anticipated for Manufacturing & Installation Criticality Ratings.
11 WORKSHOP CONCLUSION
Team has agreed to conduct another workshop for Manufacturing and Installation/Start-up. To be done on Week 4 Jan 23. Date to be confirmed.
11.1 General
- Proposal to consider the Design Probability for QG and without QG experience be taken as the
same – Team conclusion: It will depend on the type of equipment.
11.2 By Discipline
11.2.1 Structural
-
FEED did not assign a rating to Sea Water Lift Pump Caisson.
-
Team agreed to assess the Design Criticality and agreed to a DCR = III (D1). This rating applies
to all caisson with pump.
11.2.2 Mechanical
- Propose to change the Safety Consequence for Pedestal Crane from 1 to 2. Team conclusion -
No change
- Team agreed to add and assess the Exhaust Extension Ducting for Gas Turbine. Team agreed
to a DCR = III (B3)
11.2.3 Instrument
-
Missing line items from FEED (1 nos.) – 4 nos. cladded 24in Control valves.
-
Team agreed to assess and agreed to a DCR = III (D1).
Note: Consequence 1 was chosen due to assume control valve leaking through stem.
Company No._Rev. COMP2-SPM-PE-REP-00002_B
20 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
11.2.4 Electrical
- Missing line items from FEED (3 nos.) - LV Cables, Cable Trays and Ladders, Electrical Bulk
items (Lighting, LCS, sockets, welding receptacles, etc.)
- Team agreed to assess and agreed to a DCR = IV (D2)
11.2.5 Piping
- No change
11.2.6 Technical Safety and Loss Prevention
- No change
11.2.7 Telecom
- No change (per info post workshop)
12 RECOMMENDATIONS
The following are the recommendations for the implementation of the surveillance ratings during design.
-
Referenced in Specification for Package Equipment and Basis of Design for all disciplines.
-
For the EPC ITT Package, the critical ratings will be mentioned in EPC Scope of Work and this
document shall be referred.
-
Equipment Classification into Smart Plant Materials Database or equivalent (where used) throughout the supplier chain. See Figure 12-1. This shall be used specifically for Ratings of I.
-
It will become a part of the basis for the Procurement Execution Plan.
-
All deviations need to be raised as Specification Deviation Request (SDRs) prior to PO
placement, even for CAT III and IV equipment items.
Company No._Rev. COMP2-SPM-PE-REP-00002_B
21 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
Figure 12-1: Equipment Attribute in Smart 3D
The Surveillance activities is proportional to the expected efforts to be carried out in order to manage the associated risks and shall be used to determine the pro-active activities to pre-qualify/qualify suppliers/manufacturers. It can also be used to evaluate supplier capabilities especially in the area of technical maturity.
Risk criticality shall be reviewed periodically during the project execution to reflect changes in the project environment, execution strategy, scope of supply, asset or other conditions that may have occurred. This shall be an integral part of the project.
During Execution Phase, results on this assessment shall be used to;
• Establish the level of inspection required in the ITP
• Condition based monitoring requirements
• Access, material and mechanical handling
• Preservation and storage plans
• Spare parts management
• Maintenance strategies
•
Installation surveillance
Ratings shall also be used in the EPC CONTRACTOR’s Quality Control Surveillance (QCS) Inspection Procedure where;
• Work processes and main rules shall be applied to the design, manufacturing, inspection, quality
and installation control surveillance.
• All equipment, material and packages purchased and manufactured for the project to be
assessed.
• Site Quality Control Surveillance activities shall be prepared separate and read in conjunction
with the EPC CONTRACTOR’s QCS Inspection Procedure.
Company No._Rev. COMP2-SPM-PE-REP-00002_B
22 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
13 REFERENCES - METHODOLOGY
Table 11: Equipment Criticality Assessment
Table 12: Criticality Element - Consequence
Company No._Rev. COMP2-SPM-PE-REP-00002_B
23 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
Table 13: Criticality Element - Probability
Table 14: Criticality Rating - Categories
Company No._Rev. COMP2-SPM-PE-REP-00002_B
24 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
Table 15: Criticality Assessment – Surveillance Activities Matrices (Design, Manufacturing/Procurement, Installation/Pre-Comm/Comm/Start-up)
Company No._Rev. COMP2-SPM-PE-REP-00002_B
25 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
14 APPENDICES
Appendix 1 Appendix 2 Appendix 3
DDE Equipment Criticality Matrix (Workshop 15-Dec-22) DDE Equipment Criticality Workshop – Attendance Record DDE Equipment Criticality Workshop – Minutes of Meeting 15 Dec 22
Company No._Rev. COMP2-SPM-PE-REP-00002_B
26 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
14.1 Appendix 1
DDE Equipment Criticality Matrix (Workshop 15-Dec-22)
Company No._Rev. COMP2-SPM-PE-REP-00002_B
27 of 47
Procurement Criticality Instructions
Timing
Responsible
Criticality Assessment Worksheet Content (Worksheet Tab 3. Proc Criticality Assessment, of this workbook)
Appendix 1 - DDE Equipment Criticality Matrix (Workshop 15-Dec-22)
Add / Populate rows PO’s / Equipment / Commodity / Component Descriptions Update Column B/C
For respective discipline scopes: Add addittional rows for key PO’s / Equipment / Commodites / Components / Suppliers / Sub- Suppliers, Update Columns B/C Populate Pertinent Notes / Comments - Column (D) Utilizing Procurement Criticality Matrix (Worksheet 2. of this file): Populate Consequences - Columns (E, F, G, H) Populate Probailities - Column (I, J, K) Review Default Criticality Matrix Rating - Column (M, P, S) Propose Project Assigned Criticality if recommended different than Default - Column (O, Q, T) Propose Assigned Criticality Justification / Comments - Column (U) Review Prepopulated Procurement Criticality Assessment Worksheet (All data should be pre-populated prior to workshop) Finalize and Align on data entered from Disciplines.
1 Project Engineer (PE) assigned by Project Manager (PM) for
At / Near CP1 - Start of FEED
Project Manager (PM)
Procurement Criticality
2 Pre-requisites (Equipment List / PO List) obtained by PE and initial
At / Near CP1 - Start of FEED
Project Engineer (PE)
population of Procurement Criticality Assessment Template 3 Workshop Charter Drafted with Pre-Populated Procurement
Criticality Assessment Template ( PO’s / Equipment / Commodity / Component Descriptions) and reviewed / approved by Engineering and Procurement Manager and key stakeholders
At / Near CP1 - Start of FEED
PE
4 Disciplines Pre-Populate Procurement Criticality Assessment
At / Near CP1 - Start of FEED
Disciplines
Template (Add relevant equipment, components, Assign Probabilties and Consequences Ratings)
5 Workshop Conducted to review and align on Procurement Criticalities
At / Near CP1 - Start of FEED
(Using discipline pre-population as basis for workshop)
6 Procurement Criticalities Issued for use 7 Procurement Criticalities incorporated into Procurement Surveillance
At / Near CP1 - Start of FEED At / Near CP1 - Start of FEED
Activities
8 Update Procurement Criticalities based on FEED progression, LLE, Early Works Scope / Vendor and Supplier lists, Conduct Workshop (Repeat steps 2-5)
Prior to Gate 3 / ITT
9 Update Procurement Criticalities based on Contractor / Vendor
Prior to Gate 3 / ITT
Selections / Capability / Market Conditions (Including LLE)
10 Update Procurement Criticalities / Conduct Workshop Post Gate 3 w/ EPC Contractor near start of detailed design based on Contractor / Vendor Selections / Capability / Market Conditions (Including LLE) (Repeat steps 2-5)
Post Gate 3 - Detailed Design
PE / Procurement Manager / Engineering Manager / Leads / Quality
- Disciplines walk through their respective scope / input PE PE / Disciplines
PE
PE
PE
11 Update Procurement Criticalities based on Contractor / Vendor
Post Gate - As PO’s Awarded
PE
Selections / Capability (Including LLE)
Company No._Rev. COMP2-SPM-PE-REP-00002_B
28 of 47
Appendix 1 - DDE Equipment Criticality Matrix (Workshop 15-Dec-22)
Equipment Criticality Matrix
Criticality Element - Probability
Design Probability Factor Considerations: Experience base with design; Company familiarity with design and previous experience; Contractor experience implementing design and/or with Vendor / Subcontractor doing the design
New innovative design; not previously used by Industry or with unproven reliability or non-code based requirements
Extrapolation of proven design with limited reliability data or previous experience. First time use of proprietary technology or proprietary technology used beyond limits of known operating data. Contractor/Vendor with no QG experience.
Design
DCR =
Modification of proven design with known reliability and past experience. Contractor/Vendor has EM experience.Contractor/Vendor has QG experience.
Frequently used and well proven design and easily obtainable spare parts. Contractor/Vendor has substantial EM experience on similar work.
Base Rating
A
B
C
D
Manufacturing Probability Factor Considerations: materials, geography/location/logistics, amount of specification (Company specs vs. Vendor Standards), recent changes to key processes / procedures, etc.
Multiple complex mfg. processes or exotic materials or difficult to source materials; Multiple Sub- vendors/interfaces,location highly problematic for logistics, materials, work skills and/or communication
One complex mfg. process or special material, highly specified to Company specs; Recent changes in mfg. processes and/or implementation of new industry technologies in the execution of work scope; Located in a remote area with some material, worker, logistics and/or communication issues
Manufacturing
MCR =
Large number of routine manufacturing processes, common materials, supplier standard product; Located in an emerging market area with limited Company experience
Few routine manufacturing processes, common materials, non-engineered product (off-the-shelf); Located in a developed area with good access to workers, materials and ease of logistics
g n i t a R k s i R y t i l i
b a b o r P
A
B
C
D
Installation Probability Factor Considerations: Complexity of installation activites. Obviously important for Offshore/Subsea Projects but which can also be applied Onshore during the Construction phase
Complex and unusual activities for selected Asset or requiring Asset modification / upgrade.
Many complex or critical activities nearing battery limits of selected Asset.
Significant number of known and simple activities for selected Asset.
Installation
ICR =
PCR = Procurement Criticality Rating
Straightforward installation involving only few known and simple activities for selected Asset.
A
B
C
D
Design Criticality
e c n e u q e s n o C
1
2
3
4
Mfg. Criticality
e c n e u q e s n o C
1
2
3
4
Installation Criticality
e c n e u q e s n o C
1
2
3
4
Probability
B
I
II
III
IV
C
II
III
IV
IV
Probability
B
I
II
III
IV
C
II
III
IV
IV
Probability
B
I
II
III
IV
C
II
III
IV
IV
D
III
IV
IV
IV
D
III
IV
IV
IV
D
III
IV
IV
IV
A
I
I
II
III
A
I
I
II
III
A
I
I
II
III
Criticality Element - Consequence
Base Rating
SHE - Safety, Health, Environment Consequence Factor Would failure during commissioning, start-up and/or initial operation jeopardize health and safety of personnel or the environment?
Significant risk to personnel and/or environment from inventory or process; or global structural failure - Sour Hydrocarbon
Medium risk to personnel and/or environment from inventory or process; or area structural failure- Non Sour hydrocarbon, Heli Fuel, Fuel Gas
Moderate risk to personnel and/or environment from inventory or process; or local structural failure- Non-hydrocarbon,utilities
Low risk to personnel, environment, and structure (Non hydrocarbon, utilities)
1
2
3
4
Project Cost Consequence Factor What would be the likely financial consequences to the Project of equipment failure during commissioning and start-up? ( Financial consequences associated with deferred production is addressed as part of Engineering Criticality via assessment of the Facilities Consequence Factor.)
Repair / replacement / rework cost above 10M USD
Repair / replacement / rework cost between 500k USD and 10M USD
Repair / replacement / rework cost between 50k USD and 500k USD
Repair / replacement / rework cost below 50k USD
1
2
3
4
Execution / Schedule Consequence Factor What would be the likely impact to the overall project schedule for late equipment delivery or equipment failure during commissioning and start-up? ( Financial consequences associated with deferred production is addressed as part of Engineering Criticality via assessment of the Facilities Consequence Factor.)
g n i t a R k s i R e c n e u q e s n o C
s e c i r t a M y t i l
a c i t i r C t o t u p n
i
r o f
r o t c a F e c n e u q e s n o C t s e h g i h e S U
3 month S/U or handover delay
1 to 3 month S/U or handover delay
< 1 month S/U or handover delay
No S/U or handover delay
1
2
3
4
Performance Consequence Factor What would be the likely impact of equipment failure on performance of the facilities (before or after being put in service)
Hazardous operating conditions with severe or unacceptable consequences on operation of the Facilities- Full production loss
By-pass or replacement of defective item with loss of functional integrity of the Facilities- some production loss
Limited consequences due to presence of standby equipment, by-pass of defective item or ease of replacement- No production loss due to spares
No consequence on operation of the Facilities
1
2
3
4
Company No._Rev. COMP2-SPM-PE-REP-00002_B
29 of 47
Appendix 1 - DDE Equipment Criticality Matrix (Workshop 15-Dec-22)
Equipment Criticality Assessment
Consequence
Probability
Equipment Criticality Rating
Equipment Criticality
Design
Manufacturing
Installation
e n
i l
p i c s i D
Asset
Unit No.
Tag #
Equipment / Commodity / Component Description
Notes / Comments
y t e f a S
t s o C t c e o r P
j
l
e u d e h c S
/ n o i t u c e x E
t c a p m
I e c n a m r o f r e P
e c n e u q e s n o C
r e b m u N e s a B
n g i s e D
g n i r u t c a f u n a M
n o i t a
l l
a t s n
I
MechStatic MechStatic
RP6S RP6S
MechStatic
CP6S
MechStatic
CP6S
MechStatic MechStatic MechStatic MechStatic MechStatic MechStatic MechStatic MechStatic MechStatic MechStatic MechStatic MechStatic MechStatic MechStatic MechStatic
CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S
23 23
23
23
23 23 23 23 23 23 23 23 23 23 23 23 23 23 23
233-V2301 233-V2301
Test Separator Test Separator (Upgrade)
560-V2303
Solid Separator (Future)
560-E2301A
Inlet Cooler
560-E2301B 560-E2301C 560-E2301D 560-E2301E 560-E2301F 560-E2301G 560-E2301H 560-V2301A 560-V2301B 560-V2302A 560-V2302B 560-V2302C 560-V2302D 560-V2302E 560-V2302F
Inlet Cooler Inlet Cooler Inlet Cooler Inlet Cooler Inlet Cooler Inlet Cooler Inlet Cooler Inlet Separator Inlet Separator Compressor Suction Scrubber Compressor Suction Scrubber Compressor Suction Scrubber Compressor Suction Scrubber Compressor Suction Scrubber Compressor Suction Scrubber (Future)
MechRotating
CP6S
23
560-P2303A
Suction Scrubber Pump
MechRotating
CP6S
MechRotating
CP6S
MechRotating
CP6S
MechRotating
CP6S
MechRotating
CP6S
23
23
23
23
23
560-P2303B
Suction Scrubber Pump
560-P2303C
Suction Scrubber Pump
560-P2303D
Suction Scrubber Pump
560-P2303E
Suction Scrubber Pump
560-P2303F
Suction Scrubber Pump (Future)
MechRotating
CP6S
23
560-K2301A
Export Compressor Package
MechRotating
CP6S
23
560-K2301F
Export Compressor (Future)
MechStatic
CP6S
MechStatic
CP6S
MechStatic
CP6S
MechStatic
CP6S
MechStatic
CP6S
MechStatic
CP6S
MechStatic
CP6S
23
23
23
23
23
23
23
560-E2302A
Discharge Cooler
560-E2302B
Discharge Cooler
560-E2302C
Discharge Cooler
560-E2302D
Discharge Cooler
560-E2302E
Discharge Cooler
560-E2302F
Discharge Cooler
560-E2302G
Discharge Cooler
Installation rating B due to the identified location & BF
Performance rating based on 1 shell failure resulting in some production loss
Cost shown as 4 taking into account repair and not replacement.Performance is considered as 3 taking into account liquids can be sent to closed drain vessel via XV.This will have some minor environmental impact due to gas flashing.
Manufacturing selected as “A” due to complex manufacturing process at multiple locations. Package includes: 1.MMS:Machine monitoring system 2.CPMS: Condition and Performance monitoring system 3.CEMS: Continuous Emission monitoring system Installation is classified as “B” since there is no deck extension. This does not take into account conversion from single stage to two stage compression.
Performance rating based on 1 shell failure resulting in some production loss
Performance rating based on 1 shell failure resulting in some production loss
Performance rating based on 1 shell failure resulting in some production loss
Performance rating based on 1 shell failure resulting in some production loss
Performance rating based on 1 shell failure resulting in some production loss
Performance rating based on 1 shell failure resulting in some production loss
Performance rating based on 1 shell failure resulting in some production loss
1 1
1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2 3
2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
4
4
4
4
4
4
1
1
2
2
2
2
2
2
2
3 3
2
1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
3
3
3
3
3
3
1
1
1
1
1
1
1
1
1
3 3
2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
3
3
3
3
3
3
2
2
2
2
2
2
2
2
2
1 1
1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
D C
C
C C C C C C C C C C C C C C C C
D
D
D
D
D
D
B
B
C
C
C
C
C
C
C
C C
C
B B B B B B B B B B B B B B B B
B
B
B
B
B
B
A
A
B
B
B
B
B
B
B
C C
B
C C C C C C C C C C C C C C C B
D
D
D
D
D
C
B
B
C
C
C
C
C
C
C
Company No._Rev. COMP2-SPM-PE-REP-00002_B
30 of 47
Assigned Criticality Justification / Comments
Design- Scope is limited to single vendor for internal upgrades only
Standard design pressure vessel. Challenge on the installation during BF
Standard design pump and procedure except for metallurgy.Manufacturing is classified as II due to standard design. Standard design pump and procedure except for metallurgy.Manufacturing is classified as II due to standard design. Standard design pump and procedure except for metallurgy.Manufacturing is classified as II due to standard design. Standard design pump and procedure except for metallurgy.Manufacturing is classified as II due to standard design. Standard design pump and procedure except for metallurgy.Manufacturing is classified as II due to standard design. Standard design pump and procedure except for metallurgy.Manufacturing is classified as II due to standard design.
n o i t a c o L
x i r t a M
D1 C1
C1
C1 C1 C1 C1 C1 C1 C1 C1 C1 C1 C1 C1 C1 C1 C1 C1
D1
D1
D1
D1
D1
D1
B1
B1
C1
C1
C1
C1
C1
C1
C1
x i r t a M
t l u a f e D
g n i t a R
III II
II
II II II II II II II II II II II II II II II II
III
III
III
III
III
III
I
I
II
II
II
II
II
II
II
y t i l
a c i t i r C d e n g i s s A III III
II
II II II II II II II II II II II II II II II II
III
III
III
III
III
III
I
I
II
II
II
II
II
II
II
n o i t a c o L
x i r t a M
C1 C1
C1
B1 B1 B1 B1 B1 B1 B1 B1 B1 B1 B1 B1 B1 B1 B1 B1
B1
B1
B1
B1
B1
B1
A1
A1
B1
B1
B1
B1
B1
B1
B1
x i r t a M
t l u a f e D
g n i t a R
II II
II
y t i l
a c i t i r C d e n g i s s A II II
II
I I I I I I I I I I I I I I I I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I I I I I I I I I I I I I I I I
II
II
II
II
II
II
I
I
I
I
I
I
I
I
I
n o i t a c o L
x i r t a M
C1 C1
B1
C1 C1 C1 C1 C1 C1 C1 C1 C1 C1 C1 C1 C1 C1 C1 B1
D1
D1
D1
D1
D1
C1
B1
B1
C1
C1
C1
C1
C1
C1
C1
x i r t a M
t l u a f e D
g n i t a R
II II
I
II II II II II II II II II II II II II II II I
III
III
III
III
III
II
I
I
II
II
II
II
II
II
II
y t i l
a c i t i r C d e n g i s s A II II
II
II II II II II II II II II II II II II II II I
III
III
III
III
III
II
I
I
II
II
II
II
II
II
II
e n
i l
p i c s i D
Asset
Unit No.
Tag #
Equipment / Commodity / Component Description
Notes / Comments
MechStatic
CP6S
MechStatic
CP6S
MechStatic
CP6S
MechStatic
CP6S
MechStatic
CP6S
MechRotating
CP6S
MechRotating
CP6S
MechRotating
CP6S
MechRotating
CP6S
MechRotating
CP6S
MechRotating
CP6S
HVAC HVAC HVAC HVAC HVAC HVAC HVAC
HVAC
CP6S CP6S CP6S CP6S CP6S CP6S CP6S
CP6S
HVAC
CP6S
HVAC
CP6S
HVAC
CP6S
HVAC
CP6S
MechStatic
CP6S
MechPackage MechPackage MechRotating MechRotating MechRotating MechRotating MechRotating MechRotating
CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S
Structural
CP6S
Structural
CP6S
23
23
23
23
23
23
23
23
23
23
23
42 42 42 42 42 42 42
42
42
42
42
42
79
79 82 82 82 82 82 82 82
82
82
560-E2302H
Discharge Cooler
560-E2302I
Discharge Cooler
560-E2302J
Discharge Cooler
560-E2302K
Discharge Cooler (Future)
560-E2302L
Discharge Cooler (Future)
560-P2301A
Export Booster pump Package
560-P2301B
Export Booster pump Package
560-P2301C
Export Booster pump Package
560-P2302A
Export Pump Package
560-P2302B
Export Pump Package
560-P2302C
Export Pump Package
560-YH4201ACP01 HVAC Control Panel CP 560-YH4201EF01A Exhaust Fan Battery Rm 560-YH4201EF01B Exhaust Fan Battery Rm 560-YH4201EF02A Exhaust Fan Mech W/Shop 560-YH4201EF03A Exhaust Fan Lab 560-YH4201EF03B Exhaust Fan Lab 560-YH4201EF02B Exhaust Fan Mech W/Shop
560-YH4201FU01 Filter Coalescer PAC-01 Air Intake
Performance rating based on 1 shell failure resulting in some production loss
Performance rating based on 1 shell failure resulting in some production loss
Performance rating based on 1 shell failure resulting in some production loss
Performance rating based on 1 shell failure resulting in some production loss
Performance rating based on 1 shell failure resulting in some production loss Review the need for an additional spare pump(uninstalled). Review the need for an additional spare pump(uninstalled). Review the need for an additional spare pump(uninstalled). Review the need for an additional spare pump/VFD(uninstalled). Review the need for an additional spare pump/VFD(uninstalled). Review the need for an additional spare pump/VFD(uninstalled).
Addition post Rev A EL Addition post Rev A EL Addition post Rev A EL Addition post Rev A EL Addition post Rev A EL
560-YH4201PAC01A Air Cooled Packaged Unit System 1
Add (ACCU & AHU in Single Skid)
560-YH4201PAC01B Air Cooled Packaged Unit System 1
Add (ACCU & AHU in Single Skid)
560-YH4201PAC02A Air Cooled Packaged Unit System 2
Add (ACCU & AHU in Single Skid)
560-YH4201PAC02B Air Cooled Packaged Unit System 2
Add (ACCU & AHU in Single Skid)
560-T7901
Tote Tank
560-Y7901 560-Y8203 560-P8201A 560-P8201B 560-P8201C 560-P8201D 560-P8201E 560-P8201F
Chemical Injection Package Water Chlorination Package Seawater Lift Pump Seawater Lift Pump Seawater Lift Pump Seawater Lift Pump Seawater Lift Pump Seawater Lift Pump (Future)
560-X8201A
Seawater Lift Pump Caisson
TBA
Firewater Pump Caissons (All)
Not classified as it is not under project document scope. This will be supplied by the Chemical Vendors. For Layout and Design Development, Company to provide tote tank dimensions and capacity.
Not applicable-part of jacket installation- offshore installation. Interface with seawater lift pump caisson.
Not applicable-part of jacket installation- offshore installation. Interface with seawater lift pump caisson.
Not applicable-part of jacket installation- offshore installation. Interface with seawater lift pump caisson.
Not applicable-part of jacket installation- offshore installation. Interface with seawater lift pump caisson.
MechRotating
CP6S
82
560-X8201B
Seawater Lift Pump Caisson
MechRotating
CP6S
82
560-X8201C
Seawater Lift Pump Caisson
Appendix 1 - DDE Equipment Criticality Matrix (Workshop 15-Dec-22)
Consequence
Probability
Equipment Criticality Rating
y t e f a S
t s o C t c e o r P
j
l
e u d e h c S
/ n o i t u c e x E
t c a p m
I e c n a m r o f r e P
1
1
1
1
1
1
1
1
1
1
1 2 2 2 2 2 2 2
2
2
2
2
2
3 2 3 3 3 3 3 3
4
4
2
2
2
2
2
3
3
3
3
3
3 3 4 4 4 4 4 4
4
3
3
3
3
3 3 2 2 2 2 2 2
2
2
1
1
1
1
1
2
2
2
2
2
2 3 3 3 3 3 3 3
3
3
3
3
3
3 3 2 2 2 2 2 2
2
2
2
2
2
2
2
3
3
3
3
3
3 3 3 3 3 3 3 3
3
3
3
3
3
3 3 3 3 3 3 3 3
1
1
Equipment Criticality
Design
Manufacturing
Installation
g n i r u t c a f u n a M
B
B
B
B
B
B
B
B
B
B
B C D D D D D D
D
C
C
C
C
D C C C C C C C
e c n e u q e s n o C
r e b m u N e s a B
n g i s e D
C
C
C
C
C
C
C
C
C
C
C D D D D D D D
D
D
D
D
D
D D C C C C C C
D
D
1
1
1
1
1
1
1
1
1
1
1 2 2 2 2 2 2 2
2
2
2
2
2
3 2 2 2 2 2 2 2
1
1
0
0
n o i t a
l l
a t s n
I
C
C
C
C
C
C
C
C
C
C
C D D D D D D D
D
D
D
D
D
D C B B B B B B
x i r t a M
t l u a f e D
g n i t a R
II
II
II
II
II
II
II
II
II
II
II IV IV IV IV IV IV IV
IV
IV
IV
IV
IV
IV IV III III III III III III
III
III
y t i l
a c i t i r C d e n g i s s A
II
II
II
II
II
II
II
II
II
II
II IV IV IV IV IV IV IV
IV
IV
IV
IV
IV
III III II II II II II II
III
III
n o i t a c o L
x i r t a M
C1
C1
C1
C1
C1
C1
C1
C1
C1
C1
C1 D2 D2 D2 D2 D2 D2 D2
D2
D2
D2
D2
D2
D3 D2 C2 C2 C2 C2 C2 C2
D1
D1
0
0
n o i t a c o L
x i r t a M
B1
B1
B1
B1
B1
B1
B1
B1
B1
B1
B1 C2 D2 D2 D2 D2 D2 D2
D2
C2
C2
C2
C2
D3 C2 C2 C2 C2 C2 C2 C2
x i r t a M
t l u a f e D
g n i t a R
I
I
I
I
I
I
I
I
I
I
I III IV IV IV IV IV IV
IV
III
III
III
III
IV III III III III III III III
y t i l
a c i t i r C d e n g i s s A
I
I
I
I
I
II
II
II
II
II
II III IV IV IV IV IV IV
IV
III
III
III
III
III III II II II II II II
n o i t a c o L
x i r t a M
C1
C1
C1
C1
C1
C1
C1
C1
C1
C1
C1 D2 D2 D2 D2 D2 D2 D2
D2
D2
D2
D2
D2
D3 C2 B2 B2 B2 B2 B2 B2
x i r t a M
t l u a f e D
g n i t a R
II
II
II
II
II
II
II
II
II
II
II IV IV IV IV IV IV IV
IV
IV
IV
IV
IV
IV III II II II II II II
y t i l
a c i t i r C d e n g i s s A
II
II
II
II
II
II
II
II
II
II
II III IV IV IV IV IV IV
IV
III
III
III
III
III III II II II II II II
Assigned Criticality Justification / Comments
For installation, “C” is selected even though it is BF, the installation is straightforward.
For installation, “C” is selected even though it is BF, the installation is straightforward.
Standard manufacture process.
Standard manufacture process.
Standard manufacture process.
Standard manufacture process.
Standard manufacture process.
Standard manufacture process.
SAT
“III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. Further review on final assigned criticality during EPC stage. Further review on final assigned criticality during EPC stage. Further review on final assigned criticality during EPC stage. Further review on final assigned criticality during EPC stage. Further review on final assigned criticality during EPC stage. Further review on final assigned criticality during EPC stage.
Updated based on ECA Workshop 15th December 2022
Added based on ECA Workshop 15th December 2022
Applicable to All Caissons including to Service Water Pump on CP and LQ
Rating apply the same with 560-X8201A as per ECA Workshop
Rating apply the same with 560-X8201A as per ECA Workshop
Company No._Rev. COMP2-SPM-PE-REP-00002_B
31 of 47
Appendix 1 - DDE Equipment Criticality Matrix (Workshop 15-Dec-22)
Consequence
Probability
Equipment Criticality Rating
Equipment Criticality
Design
Manufacturing
Installation
e n
i l
p i c s i D
Asset
Unit No.
Tag #
Equipment / Commodity / Component Description
Notes / Comments
y t e f a S
t s o C t c e o r P
j
l
e u d e h c S
/ n o i t u c e x E
t c a p m
I e c n a m r o f r e P
e c n e u q e s n o C
r e b m u N e s a B
n g i s e D
g n i r u t c a f u n a M
n o i t a
l l
a t s n
I
MechRotating
CP6S
82
560-X8201D
Seawater Lift Pump Caisson
MechRotating
CP6S
82
560-X8201E
Seawater Lift Pump Caisson
MechRotating
CP6S
82
560-X8201F
Seawater Lift Pump Caisson
Not applicable-part of jacket installation- offshore installation. Interface with seawater lift pump caisson.
Not applicable-part of jacket installation- offshore installation. Interface with seawater lift pump caisson.
Not applicable-part of jacket installation- offshore installation. Interface with seawater lift pump caisson.
Not applicable-part of jacket installation- offshore installation. Interface with seawater lift pump caisson. Package comprises of 3+1 filter units and failure is limited to one unit.
Procured by Project as the current basis.
No standby filter provided.
MechRotating
CP6S
MechPackage
CP6S
MechStatic MechRotating
Piping
Piping MechRotating MechRotating MechRotating MechStatic MechStatic MechStatic MechStatic MechStatic Safety Safety Safety Safety Safety Safety Safety Safety
Safety
Safety
CP6S CP6S
RP6S
RP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S
CP6S
CP6S
Safety
CP6S
Safety
CP6S
Safety
CP6S
Safety
CP6S
MechPackage Electrical
Electrical
CP6S CP6S
CP6S
MechStatic
CP6S
MechStatic MechStatic MechStatic MechRotating MechRotating MechRotating MechRotating
CP6S CP6S CP6S CP6S CP6S CP6S CP6S
MechRotating
CP6S
MechRotating MechRotating
CP6S CP6S
MechRotating
CP6S
MechRotating
CP6S
82
82
94 94
93
93 94 94 94 94 94 94 94 94 83 83 83 83 83 83 83 83
83
83
83
83
83
83
84 84
84
87
84 87 87 87 87 87 87
87
87 87
87
91
560-X8203
Seawater Disposal Caisson
560-Y8201
Seawater Filter Package
560-V9401 560-P9401A
233-Y9301
233-Y9302 560-P9401B 560-P9401C 560-P9401D 560-S9401 560-E9401A 560-E9401B 560-E9401C 560-E9401D 560-DV8301A 560-DV8301B 560-DV8301C 560-DV8301D 560-DV8301E 560-DV8301F 560-DV8301G 560-P8301
560-FM8301 to 05 560-X8301
560-XZ831A
Cooling Medium Expansion Drum Cooling Medium Circulation Pump Temporary Fuel Gas Pig Receiver
Fuel Gas Pig Receiver Cooling Medium Circulation Pump Cooling Medium Circulation Pump Cooling Medium Circulation Pump Side Stream Filter Cooling Medium/Seawater Cooler Cooling Medium/Seawater Cooler Cooling Medium/Seawater Cooler Cooling Medium/Seawater Cooler Deluge Valve Deluge Valve Deluge Valve Deluge Valve Deluge Valve Deluge Valve Deluge Valve Firewater Pump
Remotely operated monitor
FW Pump Caisson
NOVEC 1230 Bottle Rack (to replace ‘INERGEN Bottle Rack’)
560-XZ831B
NOVEC 1230 Bottle Rack
560-XZ831C
NOVEC 1230 Bottle Rack
560-XZ831D
NOVEC 1230 Bottle Rack
560-Y8401 560-H8401A
Flare Ignition Package HP Flare KO Drum Electric Heater
560-H8401B
HP Flare KO Drum Electric Heater
560-H8701
560-V8401 560-V8701 560-T8701 560-P8701A 560-P8701B 560-P8702A 560-P8702B
LP Flare KO / Closed Drain Drum Electric Heater HP Flare KO Drum LP Flare KO / Closed Drains Drum Open Drain Tank Closed Drain Booster Pump Closed Drain Booster Pump Closed Drain Pump Closed Drains Pump
560-P8703
Open Drain Caisson Pump
560-P8704A 560-P8704B
Open Drain Oil Pump Open Drain Oil Pump
560-X8701
Open Drain Caisson
560-GD9101
Emergency Diesel Generator Package
Not applicable Centralized for Electrical Room 1, Electrical Room 2, Instrument Room and UPS Room Centralized for Electrical Room 1, Electrical Room 2, Instrument Room and UPS Room Centralized for Electrical Room 1, Electrical Room 2, Instrument Room and UPS Room Centralized for Electrical Room 1, Electrical Room 2, Instrument Room and UPS Room
Equipment belong to Mechanical discipline Equipment belong to Mechanical discipline
“3” is selected based on non installed spare and intermittent service.
Not applicable-part of jacket installation- offshore installation. Interface with seawater lift pump caisson.
0
0
0
0
2 1 2
2 2 2 2 2 3 3 3 3 3 1 1 1 1 1 1 1 3
1 0
2
2
2
2 1 1
1
1 1 1 3 1 1 1 1
2 2 2
3
4 4 4
2 2 4 4 4 4 4 4 4 4 3 3 3 3 3 3 3 3
3
2
2
2
2 1 1
1
1 1 1 3 1 1 1 1
2 2 2
3
3 3 3
3 3 3 3 3 4 3 3 3 3 4 4 4 4 4 4 4 3
4
4
4
4
4 3 4
4
4 3 3 4 3 3 3 3
4 4 4
3
2 2 2
4 4 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3
3
3
3
3
3 2 3
3
3 2 2 3 3 3 3 3
3 3 3
3
3 1 3
4 4 3 3 3 3 3 3 3 3 1 1 1 1 1 1 1 3
1
3
3
3
3 1 3
3
3 1 1 3 3 3 3 3
3 3 3
3
D D D
D D D D D D D D D D D D D D D D D D
D
D
D
D
D C D
D
D C C B C C C C
D D D
C D C
D D C C C D C C C C D D D D D D D C
D
D
D
D
D C C
C
C B B D B B B B
C C C
D D D
B B D D D D D D D D D D D D D D D C
D
C
C
C
C C D
D
D D D D C C C C
C C C
Company No._Rev. COMP2-SPM-PE-REP-00002_B
32 of 47
n o i t a c o L
x i r t a M
0
0
0
0
D2 D1 D2
D2 D2 D2 D2 D2 D3 D3 D3 D3 D3 D1 D1 D1 D1 D1 D1 D1 D3
D1 0
D2
D2
D2
D2 C1 D1
D1
D1 C1 C1 B3 C1 C1 C1 C1
D2 D2 D2
x i r t a M
t l u a f e D
g n i t a R
y t i l
a c i t i r C d e n g i s s A
n o i t a c o L
x i r t a M
x i r t a M
t l u a f e D
g n i t a R
y t i l
a c i t i r C d e n g i s s A
n o i t a c o L
x i r t a M
x i r t a M
t l u a f e D
g n i t a R
y t i l
a c i t i r C d e n g i s s A
Assigned Criticality Justification / Comments
Rating apply the same with 560-X8201A as per ECA Workshop
Rating apply the same with 560-X8201A as per ECA Workshop
Rating apply the same with 560-X8201A as per ECA Workshop
Rating apply the same with 560-X8201A as per ECA Workshop
“III” is selected based on minimum inspection requirements.
“III” is selected based on minimum inspection requirements.
“III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements.
“II & III” is selected based on minimum inspection requirements.
Off the shelves item and standard installation It is a standard pressure vessel. It is a standard pressure vessel. “III” is selected based on minimum inspection requirements. Standard manufacture process. Standard manufacture process. Standard manufacture process. Standard manufacture process.
“III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements.
IV III IV
IV IV IV IV IV IV IV IV IV IV III III III III III III III IV
III
IV
IV
IV
IV II III
III
III II II III II II II II
IV IV IV
III III III
III III III III III III III III III III III III III III III III III III
III
IV
IV
IV
IV II III
III
III II II III II II II II
III III III
C2 D1 C2
D2 D2 C2 C2 C2 D3 C3 C3 C3 C3 D1 D1 D1 D1 D1 D1 D1 C3
D1 0
D2
D2
D2
D2 C1 C1
C1
C1 B1 B1 D3 B1 B1 B1 B1
C2 C2 C2
III III III
IV IV III III III IV IV IV IV IV III III III III III III III IV
III
IV
IV
IV
IV II II
II
II I I IV I I I I
III III III
III III III
III III III III III III III III III III III III III III III III III III
III
IV
IV
IV
IV II III
III
III II II III II II II II
III III III
D2 D1 D2
B2 B2 D2 D2 D2 D3 D3 D3 D3 D3 D1 D1 D1 D1 D1 D1 D1 C3
D1 0
C2
C2
C2
C2 C1 D1
D1
D1 D1 D1 D3 C1 C1 C1 C1
C2 C2 C2
IV III IV
II II IV IV IV IV IV IV IV IV III III III III III III III IV
III
III
III
III
III II III
III
III III III IV II II II II
III III III
III III III
II II III III III III III III III III III III III III III III III II
III
III
III
III
III II III
III
III III III IV II II II II
III III III
D
B
C
D3
IV
II
B3
III
II
C3
IV
II
“II” is selected based on minimum inspection requirements.Offshore start-ups critical.
Appendix 1 - DDE Equipment Criticality Matrix (Workshop 15-Dec-22)
Consequence
Probability
Equipment Criticality Rating
e n
i l
p i c s i D
Asset
Unit No.
Tag #
Equipment / Commodity / Component Description
Notes / Comments
y t e f a S
t s o C t c e o r P
j
l
e u d e h c S
/ n o i t u c e x E
t c a p m
I e c n a m r o f r e P
Equipment Criticality
Design
Manufacturing
Installation
e c n e u q e s n o C
r e b m u N e s a B
n g i s e D
g n i r u t c a f u n a M
n o i t a
l l
a t s n
I
n o i t a c o L
x i r t a M
x i r t a M
t l u a f e D
g n i t a R
y t i l
a c i t i r C d e n g i s s A
n o i t a c o L
x i r t a M
x i r t a M
t l u a f e D
g n i t a R
y t i l
a c i t i r C d e n g i s s A
n o i t a c o L
x i r t a M
x i r t a M
t l u a f e D
g n i t a R
y t i l
a c i t i r C d e n g i s s A
Assigned Criticality Justification / Comments
MechRotating
CP6S
91
560-GT9101A
Gas Turbine Generator Package
Package includes:
1.MMS:Machine monitoring system 2.CPMS: Condition and Performance monitoring system 3.CEMS: Continuous Emission monitoring system
2
2
1
3
1
C
B
B
C1
II
II
B1
I
I
B1
I
I
MechRotating
CP6S
91
TBA
Exhaust Duct Extension for Gas Turbine
3
3
3
3
3
B
B
B
B3
III
III
15 Dec: Reviewed for Exhaust stack
MechRotating
CP6S
91
560-GT9101B
Gas Turbine Generator Package
MechRotating
CP6S
91
560-GT9101C
Gas Turbine Generator Package
MechRotating
CP6S
91
560-GT9101D
Gas Turbine Generator Package
Instrument Electrical
Electrical
MechRotating MechRotating MechStatic MechStatic MechStatic MechStatic MechStatic MechStatic MechStatic MechStatic Safety Safety Safety
CP6S CP6S
CP6S
CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S CP6S
Safety
CP6S
Safety
CP6S
Safety
CP6S
Safety
CP6S
Safety
CP6S
Safety
CP6S
Safety
CP6S
MechStatic MechStatic
LQ6S LQ6S
93 93
93
93 93 93 93 93 93 93 93 93 93 20 20 20
83
20
20
20
20
20
20
93 93
560-Y9301 560-H9301A
Fuel Gas Metering Skid Fuel Gas Superheater
560-H9301B
Fuel Gas Superheater
560-P9301A 560-P9301B 560-S9301A 560-S9301B 560-S9303 560-S9303B 560-S9304A 560-S9304B 560-T9301 560-V9301 560-EW2001 560-SEW2001 560-SEW2002
Diesel Transfer Pump Diesel Transfer Pump Fuel Gas Filter Fuel Gas Filter Diesel Filter Coalescer Diesel Filter Coalescer Fuel Gas Inlet Filter Fuel Gas Inlet Filter Diesel Storage Tank Fuel Gas Scrubber Eyewash Station Combined Safety Shower and Eye Wash Combined Safety Shower and Eye Wash
560-V8301
Firewater Pump Air Start Vessel
560-XZ2008A
Liferaft (25 men) with ramp
560-XZ2008B
Liferaft (25 men) with ramp
560-XZ2008C
Liferaft (25 men) with ramp
560-XZ2008D
Liferaft (25 men) with ramp
560-XZ2008E
Liferaft (25 men) with ramp
560-XZ2008F
Liferaft (25 men) with ramp
562-S9303 562-S9303B
Diesel Filter Coalescer Diesel Filter Coalescer
Package includes: 1.MMS:Machine monitoring system 2.CPMS: Condition and Performance monitoring system 3.CEMS: Continuous Emission monitoring system
Package includes: 1.MMS:Machine monitoring system 2.CPMS: Condition and Performance monitoring system 3.CEMS: Continuous Emission monitoring system
Package includes: 1.MMS:Machine monitoring system 2.CPMS: Condition and Performance monitoring system 3.CEMS: Continuous Emission monitoring system
Equipment belong to Mechanical discipline Equipment belong to Mechanical discipline
Ratings not required.Off the shelf. Frames cradle installed at yard.to be rated Ratings not required.Off the shelf. Frames cradle installed at yard.to be rated Ratings not required.Off the shelf. Frames cradle installed at yard.To be rated. Ratings not required.Off the shelf. Frames cradle installed at yard.To be rated. Ratings not required.Off the shelf. Frames cradle installed at yard.To be rated. Ratings not required.Off the shelf. Frames cradle installed at yard.To be rated.
2
2
1
3
1
C
B
B
C1
II
II
B1
2
2
1
3
1
C
B
B
C1
II
II
B1
2 2 2
2 3 3 2 2 3 3 2 2 3 2 3 3 3
4
4
4
4
4
4
4 3 3
2 3 3
3 4 4 4 4 4 4 4 4 4 3 4 4 4
3
4
4
4
4
4
4 4 4
1 2 3
3 3 3 3 3 3 3 3 3 4 4 4 4 4
3
4
4
4
4
4
4 3 3
3 3 3
3 3 3 3 3 3 3 3 3 3 3 4 4 4
3
4
4
4
4
4
4 3 3
1 2 2
2 3 3 2 2 3 3 2 2 3 2 3 3 3
3
4
4
4
4
4
4 3 3
C D D
D D D D D D D D D D C D D D
D
D
D
D
D
D
D D D
B C C
C C C D D D D D D D B D D D
D
D
D
D
D
D
D D D
B D D
D D D D D D D D D D C D D D
D
D
D
D
D
D
D D D
C1 D2 D2
D2 D3 D3 D2 D2 D3 D3 D2 D2 D3 C2 D3 D3 D3
D3
D4
D4
D4
D4
D4
D4 D3 D3
II IV IV
IV IV IV IV IV IV IV IV IV IV III IV IV IV
IV
IV
IV
IV
IV
IV
IV IV IV
II III III
III III III IV IV IV IV IV IV IV III IV IV IV
III
IV
IV
IV
IV
IV
IV IV IV
B1 C2 C2
C2 C3 C3 D2 D2 D3 D3 D2 D2 D3 B2 D3 D3 D3
D3
D4
D4
D4
D4
D4
D4 D3 D3
I
I
I III III
III IV IV IV IV IV IV IV IV IV II IV IV IV
IV
IV
IV
IV
IV
IV
IV IV IV
I
I
I II III
III III III IV IV IV IV IV IV IV II IV IV IV
III
IV
IV
IV
IV
IV
IV IV IV
B1
B1
B1 D2 D2
D2 D3 D3 D2 D2 D3 D3 D2 D2 D3 C2 D3 D3 D3
D3
D4
D4
D4
D4
D4
D4 D3 D3
I
I
I IV IV
IV IV IV IV IV IV IV IV IV IV III IV IV IV
IV
IV
IV
IV
IV
IV
IV IV IV
II
II
II III III
III III III IV IV IV IV IV IV IV III IV IV IV
II
“II & III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements.
“III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements.
“III” is selected based on minimum inspection requirements. ‘II” rating is seleted for installation as no available bypass if its failed/leaked/faulty and may cause FWP pneumatic starter to fail if there are rust/debris from the vessel.
III
To verify the right location prior to installation.
III
To verify the right location prior to installation.
III
To verify the right location prior to installation.
III
To verify the right location prior to installation.
III
To verify the right location prior to installation.
To verify the right location prior to installation.
III IV IV
Company No._Rev. COMP2-SPM-PE-REP-00002_B
33 of 47
Appendix 1 - DDE Equipment Criticality Matrix (Workshop 15-Dec-22)
Consequence
Probability
Equipment Criticality Rating
Equipment Criticality
Design
Manufacturing
Installation
e n
i l
p i c s i D
Asset
Unit No.
Tag #
Equipment / Commodity / Component Description
Notes / Comments
y t e f a S
t s o C t c e o r P
j
l
e u d e h c S
/ n o i t u c e x E
t c a p m
I e c n a m r o f r e P
e c n e u q e s n o C
r e b m u N e s a B
n g i s e D
g n i r u t c a f u n a M
n o i t a
l l
a t s n
I
MechStatic MechStatic MechStatic MechStatic MechStatic
LQ6S LQ6S LQ6S LQ6S LQ6S
MechStatic
LQ6S
MechStatic
LQ6S
MechRotating
LQ6S
MechRotating
LQ6S
MechRotating
LQ6S
MechRotating MechRotating MechRotating MechRotating MechRotating MechRotating MechRotating MechRotating MechRotating MechRotating MechRotating MechPackage MechPackage MechPackage
LQ6S LQ6S LQ6S LQ6S LQ6S LQ6S LQ6S LQ6S LQ6S LQ6S LQ6S LQ6S LQ6S LQ6S
MechPackage
LQ6S
MechPackage
LQ6S
MechPackage
LQ6S
MechPackage
LQ6S
MechPackage
LQ6S
MechPackage MechPackage MechPackage MechPackage MechPackage MechPackage MechPackage MechPackage MechPackage HVAC
HVAC
LQ6S LQ6S LQ6S LQ6S LQ6S LQ6S LQ6S LQ6S LQ6S LQ6S
LQ6S
HVAC
LQ6S
HVAC
LQ6S
HVAC
HVAC
HVAC
LQ6S
LQ6S
LQ6S
HVAC
LQ6S
HVAC
LQ6S
HVAC
HVAC HVAC HVAC HVAC HVAC HVAC HVAC
HVAC
HVAC
HVAC
LQ6S
CP6S LQ6S LQ6S LQ6S LQ6S LQ6S LQ6S
LQ6S
LQ6S
LQ6S
87 93 94 94 94
95
96
91
82
82
87 87 93 93 94 94 94 94 94 82 82 95 95 87
20
82
87
93
94
94 95 95 95 95 95 95 95 96 42
42
42
42
42
42
42
42
42
42
42 42 42 42 42 42 42
42
42
42
No production loss due to available bypass. No production loss due to available bypass.
Not applicable Not applicable
Not applicable
Package comprises of N+1 filter units and failure is limited to one unit. No production loss due to available bypass.
562-T8701 562-T9301 562-T9401A 562-T9401B 562-T9402
Open Drain Tank Diesel Storage Tank Fresh Water Storage Tank Fresh Water Storage Tank Demineralized Water Tank
562-V9501
Instrument Air Receiver
562-V9601
Nitrogen Receiver
562-GD9101
Emergency Diesel Generator
562-P8202A
562-P8202B
562-P8701A 562-P8701B 562-P9301A 562-P9301B 562-P9401A 562-P9401B 562-P9402A 562-P9402B 562-P9403 562-X8202A 562-X8202B 562-V9513A 562-V9513B 562-X8701
Service Water Lift Pumps/ FW Jockey Pumps Service Water Lift Pumps/ FW Jockey Pumps Open Drain Pump Open Drain Pump Diesel Transfer Pump Diesel Transfer Pump Fresh Water Transfer Pumps Fresh Water Transfer Pumps Demineralized Water Transfer Pumps Demineralized Water Transfer Pumps Wash Down Pump Service Water Lift Pumps Caisson Service Water Lift Pumps Caisson Breathing Air Cylinder Rack Breathing Air Cylinder Rack Sewage Disposal Caisson
562-XC2001
Pedestal Crane
562-Y8202
Service Water Filter Package
562-Y8701
Sewage Treatment Package
562-Y9301
Helifuel Package
562-Y9401
562-Y9402 562-Y9501A 562-Y9501B 562-Y9501C 562-Y9502A 562-Y9502B 562-Y9502C 562-Y9503 562-Y9601
Reverse Osmosis & Demineralized Water Package UV Sterilisation Air Comp. Package Air Comp. Package Air Comp. Package Air Dryer Package Air Dryer Package Air Dryer Package Breathing Air Compressor Package Inert Gas Generation Package
562-YH4201ACCU ACCU System 1 LQ
ACCU & AHU is not in a Single Skid
ACCU & AHU is not in a Single Skid
ACCU & AHU is not in a Single Skid
ACCU & AHU is not in a Single Skid
ACCU & AHU is not in a Single Skid
inside LER
ACCU & AHU is not in a Single Skid
ACCU & AHU is not in a Single Skid
ACCU & AHU is not in a Single Skid
ACCU & AHU is not in a Single Skid
ACCU System 3 LQ
ACCU System 3 LQ
562- YH4201ACCU03A 562- YH4201ACCU03B 562- YH4201ACCU04A 562- YH4201ACCU04B 562-YH4201ACP01 HVAC Control Panel LQ
ACCU System 4 LQ
ACCU System 4 LQ
AIR HANDLING UNITS system 4 (LQ roof)
AIR HANDLING UNITS system 3 (LQ roof)
AIR HANDLING UNITS system 3 (LQ roof)
562- YH4201AHU03A 562- YH4201AHU03B 562- YH4201AHU04A 562- YH4201AHU04B 560-YH4201EF01A Exhaust Fan Battery Room Rooftop 562-YH4201EF01B Exhaust Fan Battery Room Rooftop 562-YH4201EF02 Exhaust Fan Rooftop (Toilet) 562-YH4201EF03A Exhaust Fan Infirmary & Toilet Lvl 3 562-YH4201EF03B Exhaust Fan Infirmary & Toilet Lvl 3 562-YH4201EF04A Exhaust Fan Battery Rm Cellar Deck 562-YH4201EF04B Exhaust Fan Battery Rm Cellar Deck
AIR HANDLING UNITS system 4 (LQ roof)
562-YH4201EF05A Exhaust Fan Mechanical Workshop Level 1
562-YH4201EF05B Exhaust Fan Mechanical Workshop Level 1
562-YH4201EF06A Exhaust Fan Laundry Rm Lvl 2
4 3 4 4 4
4
4
2
3
3 3 3 3 3 4 4 4 4 4
4 4
1
4
3
1
3 4 4 4 4 4 4 4 4 4 2
2
2
2
2 2
2
2
2
2 2 2 2 2 2 2 2
2
2 2
4 4 4 4 4
3
3
3
3
3 4 4 4 4 4 4 4 4 4
4 4
2
3
3
2
4 4 2 2 2 2 2 2 3 3 3
3
3
3
3 3
3
3
3
3 3 3 3 3 3 3 3
3
3 3
4 4 4 4 4
3
3
3
3
3 3 3 3 3 3 3 3 3 3
4 4
2
2
3
3
3 4 2 2 2 2 2 2 4 3 3
3
3
3
3 3
3
3
3
3 3 3 3 3 3 3 3
3
3 3
4 3 3 3 3
3
3
3
3
3 3 3 3 3 3 3 3 3 3
3 3
4
3
4
1
3 4 3 3 3 3 3 3 3 3 3
3
3
3
3 3
3
3
3
3 3 3 3 3 3 3 3
3
3 3
4 3 3 3 3
3
3
2
3
3 3 3 3 3 3 3 3 3 3 0 0 3 3 0
1
2
3
1
3 4 2 2 2 2 2 2 3 3 2
2
2
2
2 2
2
2
2
2 2 2 2 2 2 2 2
2
2 2
D D D D D
D
D
D
D
D D D D D D D D D D
D D
B
D
C
D
D D C C C C C C D D D
D
D
D
D D
D
D
D
D D D D D D D D
D
D D
D D D D D
D
D
B
C
C D D C C C C C C C
D D
B
C
C
C
D D C C C C C C D D C
C
C
C
C C
C
C
C
C C C C C C C C
C
C C
D D D D D
D
D
C
C
C D D D D D D D D D
D D
B
D
D
D
D D C C C C C C D D D
D
D
D
D D
D
D
D
D D D D D D D D
D
D D
Company No._Rev. COMP2-SPM-PE-REP-00002_B
34 of 47
Assigned Criticality Justification / Comments
“III” is selected based on minimum inspection requirements.
“III” is selected based on minimum inspection requirements. “II” is selected based on minimum inspection requirements.Offshore start-ups critical.
“III” is selected based on minimum inspection requirements.
“III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements.
Reviewed during 15th December 2022 Workshop. The conclusion is to maintain the consequences matric
“III” is selected based on minimum inspection requirements.
“III” is selected based on minimum inspection requirements. “II” for installation and overall rating is selected due to flammability medium of helifuel. Zero tolerance on leaks and cleanliness
“III” is selected based on minimum inspection requirements.
“III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements.
n o i t a c o L
x i r t a M
D4 D3 D3 D3 D3
D3
D3
D2
D3
D3 D3 D3 D3 D3 D3 D3 D3 D3 D3 0 0 D3 D3 0
B1
D2
C3
D1
D3 D4 C2 C2 C2 C2 C2 C2 D3 D3 D2
D2
D2
D2
D2 D2
D2
D2
D2
D2 D2 D2 D2 D2 D2 D2 D2
D2
D2 D2
x i r t a M
t l u a f e D
g n i t a R
IV IV IV IV IV
IV
IV
IV
IV
IV IV IV IV IV IV IV IV IV IV
IV IV
I
IV
IV
III
IV IV III III III III III III IV IV IV
IV
IV
IV
IV IV
IV
IV
IV
IV IV IV IV IV IV IV IV
IV
IV IV
y t i l
a c i t i r C d e n g i s s A
IV IV IV IV IV
III
III
II
III
III IV IV III III III III III III IV
IV IV
I
III
III
II
IV IV III III III III III III III III IV
IV
IV
IV
IV IV
IV
IV
IV
IV IV IV IV IV IV IV IV
IV
IV IV
n o i t a c o L
x i r t a M
D4 D3 D3 D3 D3
D3
D3
B2
C3
C3 D3 D3 C3 C3 C3 C3 C3 C3 C3
D3 D3
B1
C2
C3
C1
D3 D4 C2 C2 C2 C2 C2 C2 D3 D3 C2
C2
C2
C2
C2 C2
C2
C2
C2
C2 C2 C2 C2 C2 C2 C2 C2
C2
C2 C2
x i r t a M
t l u a f e D
g n i t a R
IV IV IV IV IV
IV
IV
II
IV
IV IV IV IV IV IV IV IV IV IV
IV IV
I
III
IV
II
IV IV III III III III III III IV IV III
III
III
III
III III
III
III
III
III III III III III III III III
III
III III
y t i l
a c i t i r C d e n g i s s A
IV IV IV IV IV
III
III
II
III
III IV IV III III III III III III IV
IV IV
I
III
III
II
III IV III III III III III III III III III
III
III
III
III III
III
III
III
III III III III III III III III
III
III III
n o i t a c o L
x i r t a M
D4 D3 D3 D3 D3
D3
D3
C2
C3
C3 D3 D3 D3 D3 D3 D3 D3 D3 D3
D3 D3
B1
D2
D3
D1
D3 D4 C2 C2 C2 C2 C2 C2 D3 D3 D2
D2
D2
D2
D2 D2
D2
D2
D2
D2 D2 D2 D2 D2 D2 D2 D2
D2
D2 D2
x i r t a M
t l u a f e D
g n i t a R
IV IV IV IV IV
IV
IV
III
IV
IV IV IV IV IV IV IV IV IV IV
IV IV
I
IV
IV
III
IV IV III III III III III III IV IV IV
IV
IV
IV
IV IV
IV
IV
IV
IV IV IV IV IV IV IV IV
IV
IV IV
y t i l
a c i t i r C d e n g i s s A
IV IV IV IV IV
III
III
II
III
III III III III III III III III III IV
IV IV
I
III
III
II
III IV III III III III III III III III III
III
III
III
III III
III
III
III
III III III III III III III III
III
III III
Appendix 1 - DDE Equipment Criticality Matrix (Workshop 15-Dec-22)
Consequence
Probability
Equipment Criticality Rating
Equipment Criticality
Design
Manufacturing
Installation
e n
i l
p i c s i D
Asset
Unit No.
Tag #
Equipment / Commodity / Component Description
Notes / Comments
y t e f a S
t s o C t c e o r P
j
l
e u d e h c S
/ n o i t u c e x E
t c a p m
I e c n a m r o f r e P
e c n e u q e s n o C
r e b m u N e s a B
n g i s e D
g n i r u t c a f u n a M
n o i t a
l l
a t s n
I
HVAC HVAC HVAC HVAC HVAC
HVAC
HVAC
HVAC HVAC HVAC HVAC
HVAC
Safety Safety
LQ6S LQ6S LQ6S LQ6S LQ6S
LQ6S
LQ6S
LQ6S LQ6S LQ6S LQ6S
LQ6S
LQ6S LQ6S
Safety
LQ6S
Safety
Safety
LQ6S
LQ6S
Safety
LQ6S
Safety
Safety Safety
Safety
LQ6S
LQ6S LQ6S
LQ6S
Safety
LQ6S
Safety
Safety Safety Safety Safety Safety MechPackage MechPackage
LQ6S
LQ6S LQ6S LQ6S LQ6S LQ6S FL6S FL6S
MechPackage
CP6S
MechPackage
CP6S
MechPackage
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
42 42 42 42 42
42
42
42 42 42 42
42
83 83
83
83
20
20
20
83 83
20
20
20
83 83 83 83 83 84 84
20
20
20
91
91
91
91
91
91
91
91
91
91
91
91
562-YH4201EF06B Exhaust Fan Laundry Rm Lvl 2 562-YH4201EF07A Exhaust Fan Galley Lvl 2 562-YH4201EF07B Exhaust Fan Galley Lvl 2 562-YH4201EF08A Exhaust Fan Toilet, Locker, & Janitor 562-YH4201EF08B Exhaust Fan Toilet, Locker, & Janitor
562-YH4201EF09B
562-YH4201EF09A
Exhaust Fan Medic Room, Infirmary & Isolation Ward Level 3 Exhaust Fan Medic Room, Infirmary & Isolation Ward Level 3 562-YH4201EF10A Supply Fan Galley Lvl 2 562-YH4201EF10B Supply Fan Galley Lvl 2 572-YH4201FF02A Supply Fan Laundry Lvl 1 572-YH4201FF02B Supply Fan Laundry Lvl 1
to check if it is supplied as a package or fabricated/procured separately to check if it is supplied as a package or fabricated/procured separately to check if it is supplied as a package or fabricated/procured separately Not applicable Not applicable to check if it is supplied as a package or fabricated/procured separately to check if it is supplied as a package or fabricated/procured separately to check if it is supplied as a package or fabricated/procured separately
Switchgear and UPS Room Telecom Equipment Room Instrument Rack Room
560-YH4201FU03
562-DV8301 562-P8301A
FILTER COALESCER - AHU03 AIR INTAKE (LQ roof) Deluge Valves Firewater Pump
562-V8301
Firewater Pump Air Start Vessel
562-P8301B
Firewater Pump
562-X2002A
Lifeboat winch and Davit
562-X2002B
Lifeboat winch and Davit
562-X2002C
Lifeboat winch and Davit
562-X8301A 562-X8301B
FW Pump Caisson FW Pump Caisson
562-XZ2012A
Lifeboat
562-XZ2012B
Lifeboat
562-XZ2012C
Lifeboat
562-Y8301 562-Y8302 562-XZ830A 562-XZ830B 562-XZ8303 564-FL8401 564-FL8402
Deck Integrated Fire Fighting(DIFFs SKID) Sprinkler Alarm Valve NOVEC 1230 Bottle Rack NOVEC 1230 Bottle Rack NOVEC 1230 Bottle Rack HP Flare Tip LP Flare Tip
560-XC2001
Pedestal Crane
560-XC2002
560-X2002
Pedestal Crane Material Handling Package ( generated list from material handling report)
SB-560601
11kV Switchboard
ET-560601A
Earth Transformer A for SB-560601
ET-560601B
Earth Transformer B for SB-560601
SB-560301
LV Normal Switchboard
SB-560302
LV Normal Switchboard
ESB-560303
LV Essential Switchboard
ELSB-560304
Essential Lighting and Small Power Switchboard
SB-560310
LV GTG A Aux MCC
SB-560311
LV GTG B Aux MCC
TR-560301A
11/0.42kV Transformer
TR-560301B
11/0.42kV Transformer
TR-560302A
11/0.42kV Transformer
2 2 2 2 2
2
2 2 2 2 2
2 3 3
4 3
1
1
1
1
1
1 1 3 2 2 2 1 1
1 3
3
2
2
2
2
2
2
2
2
2
2
2
2
3 3 3 3 3
3
3 3 3 3 3
3 4 3
3 3
4
4
4
4
4
4 2 4 4 4 4 2 2
2 2
4
3
3
3
3
3
3
3
3
3
3
3
3
3 3 3 3 3
3
3 3 3 3 3
3 3 3
3 3
3
3
3
3
3
3 3 3 3 3 3 1 1
2 2
3
3
3
3
3
3
3
3
3
3
3
3
3
3 3 3 3 3
3
3 3 3 3 3
3 1 3
3 3
1
1
1
1
1
1 1 1 3 3 3 1 1
4 4
3
3
3
3
3
3
3
3
3
3
3
3
3
2 2 2 2 2
2
2 2 2 2 2
2 1 3
3 3
1
1
1 0 0
1
1
1 1 1 2 2 2 1 1
1 2
3
2
2
2
2
2
2
2
2
2
2
2
2
D D D D D
D
D D D D D
D D D
D D
C
C
C
D
D
D D D D D D C C
B C
D
C
C
C
C
C
C
C
C
C
C
C
C
C C C C C
C
C C C C C
C D C
D C
C
C
C
D
D
D C D D D D C C
B B
D
C
C
C
C
C
C
C
C
C
C
C
C
D D D D D
D
D D D D D
D D C
D C
C
C
C
C
C
C D D C C C C C
B B
D
B
B
B
B
B
B
C
B
B
B
B
B
Company No._Rev. COMP2-SPM-PE-REP-00002_B
35 of 47
n o i t a c o L
x i r t a M
D2 D2 D2 D2 D2
D2
D2 D2 D2 D2 D2
D2 D1 D3
D3 D3
C1
C1
C1 0 0
D1
D1
D1 D1 D1 D2 D2 D2 C1 C1
B1 C2
D3
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
x i r t a M
t l u a f e D
g n i t a R
IV IV IV IV IV
IV
IV IV IV IV IV
IV III IV
IV IV
II
II
II
III
III
III III III IV IV IV II II
I III
IV
III
III
III
III
III
III
III
III
III
III
III
III
y t i l
a c i t i r C d e n g i s s A
IV IV IV IV IV
IV
IV IV IV IV IV
IV III III
III III
II
II
II
III
III
III III III IV IV IV II II
I
III
III
III
III
III
III
III
III
III
III
III
III
III
n o i t a c o L
x i r t a M
C2 C2 C2 C2 C2
C2
C2 C2 C2 C2 C2
C2 D1 C3
D3 C3
C1
C1
C1
D1
D1
D1 C1 D1 D2 D2 D2 C1 C1
B1 B2
D3
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
x i r t a M
t l u a f e D
g n i t a R
III III III III III
III
III III III III III
III III IV
IV IV
II
II
II
III
III
III II III IV IV IV II II
I II
IV
III
III
III
III
III
III
III
III
III
III
III
III
y t i l
a c i t i r C d e n g i s s A
III III III III III
III
III III III III III
III III III
III III
II
II
II
III
III
III II III IV IV IV II II
I
III
III
III
III
III
III
III
III
III
III
III
III
III
n o i t a c o L
x i r t a M
D2 D2 D2 D2 D2
D2
D2 D2 D2 D2 D2
D2 D1 C3
D3 C3
C1
C1
C1
C1
C1
C1 D1 D1 C2 C2 C2 C1 C1
B1 B2
D3
B2
B2
B2
B2
B2
B2
C2
B2
B2
B2
B2
B2
x i r t a M
t l u a f e D
g n i t a R
IV IV IV IV IV
IV
IV IV IV IV IV
IV III IV
IV IV
II
II
II
II
II
II III III III III III II II
I II
IV
II
II
II
II
II
II
y t i l
a c i t i r C d e n g i s s A
III III III III III
III
III III III III III
III III II
III II
II
II
II
II
II
II III III III III III II II
I
Assigned Criticality Justification / Comments
“II & III” is selected based on minimum inspection requirements. “III” is selected based on minimum inspection requirements. ‘II” rating is seleted for installation as no available bypass if its failed/leaked/faulty and may cause FWP pneumatic starter to fail if there are rust/debris from the vessel. “II & III” is selected based on minimum inspection requirements.
Reviewed during 15th December 2022 Workshop. The conclusion is to maintain the consequences matric
III
“III” is selected based on material handling report requirements.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package. For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
II
II
II
II
II
II
III
III
For electrical equipment/same category is selected and one team can be assigned to the package.
II
II
II
II
II
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
II
II
II
II
II
Appendix 1 - DDE Equipment Criticality Matrix (Workshop 15-Dec-22)
Consequence
Probability
Equipment Criticality Rating
Equipment Criticality
Design
Manufacturing
Installation
e n
i l
p i c s i D
Asset
Unit No.
Tag #
Equipment / Commodity / Component Description
Notes / Comments
y t e f a S
t s o C t c e o r P
j
l
e u d e h c S
/ n o i t u c e x E
t c a p m
I e c n a m r o f r e P
e c n e u q e s n o C
r e b m u N e s a B
n g i s e D
g n i r u t c a f u n a M
n o i t a
l l
a t s n
I
Part of GTG package. Rating will follow the parent
Part of GTG package. Rating will follow the parent
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
91
91
91
91
TR-560302B
11/0.42kV Transformer
TR-560303A
11/0.42kV Transformer
TR-560303B
11/0.42kV Transformer
BD-560301A
Busduct
Electrical
CP6S
91
BD-560301B
Busduct
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
BD-560302A
Busduct
BD-560302B
Busduct
BD-560303A
Busduct
BD-560303B
Busduct
CP-560380
Electrical Integrated Control system (ELICS) Panel
PMS-560381
Power Management System (PMS) Panel
CP-560382
Synchronising Panel
UPS-560501A
DC UPS A
BB-560501A
DC UPS A Battery Bank
CB-560501A
DC UPS A MCCB Box
UPS-560501B
DC UPS B
BB-560501B
DC UPS B Battery Bank
CB-560501B
DC UPS B MCCB Box
USB-560501
110V DC UPS Main Distribution Board
UPS-560401A
AC UPS A
BB-560401A
AC UPS A Battery Bank
CB-560401A
AC UPS A MCCB Box
UPS-560401B
AC UPS B
BB-560401B
AC UPS B Battery Bank
CB-560401B
AC UPS B MCCB Box
USB-560401A
AC UPS Main Distribution Board A
USB-560401B
AC UPS Main Distribution Board B
UPS-560403
Navigational Aid AC UPS
BB-560403
Battery for Navigational Aid UPS
2
2
2
3
3
3
3
3
3
3
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
3
3
3
3
3
3
3
3
3
3
2
2
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
2
2
2
2
2
2
3
1
1
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
2
2
2
2
2
2
2
2
2
3
1
1
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
B
B
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
B
B
B
C
C
C
C
C
C
C
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
C
C
Company No._Rev. COMP2-SPM-PE-REP-00002_B
36 of 47
n o i t a c o L
x i r t a M
C2
C2
C2
C2
C2
C2
C2
C2
C2
C3
C1
C1
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
x i r t a M
t l u a f e D
g n i t a R
y t i l
a c i t i r C d e n g i s s A
III
III
III
III
III
III
III
III
III
IV
II
II
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
II
II
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
n o i t a c o L
x i r t a M
C2
C2
C2
C2
C2
C2
C2
C2
C2
C3
B1
B1
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
x i r t a M
t l u a f e D
g n i t a R
y t i l
a c i t i r C d e n g i s s A
III
III
III
III
III
III
III
III
III
IV
I
I
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
I
I
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
n o i t a c o L
x i r t a M
B2
B2
B2
C2
C2
C2
C2
C2
C2
C3
B1
B1
B2
B2
B2
B2
B2
B2
B2
B2
B2
B2
B2
B2
B2
B2
B2
C2
C2
x i r t a M
t l u a f e D
g n i t a R
II
II
II
III
III
III
III
III
III
IV
I
I
II
II
II
II
II
II
II
II
II
II
II
II
II
II
II
III
III
y t i l
a c i t i r C d e n g i s s A
II
II
II
II
II
II
II
II
II
Assigned Criticality Justification / Comments
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package. Vendor presence is mandatory during installation.
For electrical equipment/same category is selected and one team can be assigned to the package. Vendor presence is mandatory during installation.
For electrical equipment/same category is selected and one team can be assigned to the package. Vendor presence is mandatory during installation.
For electrical equipment/same category is selected and one team can be assigned to the package. Vendor presence is mandatory during installation.
For electrical equipment/same category is selected and one team can be assigned to the package. Vendor presence is mandatory during installation.
For electrical equipment/same category is selected and one team can be assigned to the package. Vendor presence is mandatory during installation.
Vendor presence is mandatory during installation, pre-comm and commissioning.
III
II
II
II
II
II
II
II
II
II
II
II
II
II
II
II
II
II
II
II
Part of GTG package.
Part of GTG package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
Appendix 1 - DDE Equipment Criticality Matrix (Workshop 15-Dec-22)
Consequence
Probability
Equipment Criticality Rating
Equipment Criticality
Design
Manufacturing
Installation
e n
i l
p i c s i D
Asset
Unit No.
Tag #
Equipment / Commodity / Component Description
Notes / Comments
y t e f a S
t s o C t c e o r P
j
l
e u d e h c S
/ n o i t u c e x E
t c a p m
I e c n a m r o f r e P
e c n e u q e s n o C
r e b m u N e s a B
n g i s e D
g n i r u t c a f u n a M
n o i t a
l l
a t s n
I
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
CP6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
CB-560403
Isolation Switch for Navigational Aid UPS
LDB-560403
Main Distribution Board Navigational Aid UPS
DTR-560304
Lighting & Small Power Distribution Transformer
EDTR-560304
Essential Lighting & Small Power Distribution Transformer
ELDB-560320
Indoor Emergency Lighting Distribution Board
ELDB-560321
Outdoor Emergency Lighting Distribution Board
LDB-560322
Indoor Normal Lighting Distribution Board
LDB-560323
Outdoor Normal Lighting Distribution Board
LDB-560324
Indoor Normal Small Power Distribution Board
LDB-560325
Outdoor Normal Small Power Distribution Board
LDB-560341
Space Heater Distribution Board
LDB-560340
Heat Tracing Distribution Board
LDB-560342
MOV Distribution Board
ESB-562301
LV Essential Switchboard
TR-562301A
11/0.42kV Transformer
TR-562301B
11/0.42kV Transformer
BD-562301A
Busduct
BD-562301B
Busduct
CP-562380
Electrical Integrated Control system (ELICS) Panel
UPS-562402A
AC UPS A
BB-562402A
AC UPS A Battery Bank
CB-562402A
AC UPS A MCCB Box
UPS-562402B
AC UPS B
BB-562402B
AC UPS B Battery Bank
CB-562402B
AC UPS B MCCB Box
USB-562402A
AC UPS Main Distribution Board A
USB-562402B
AC UPS Main Distribution Board B
UPS-562403
Navigational Aid AC UPS
BB-562403
Battery for Navigational Aid UPS
CB-562403
Isolation Switch for Navigational Aid UPS
LDB-562403
Main Distribution Board Navigational Aid UPS
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
3
3
3
2
2
2
2
2
2
2
2
2
2
2
2
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
2
2
2
2
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
3
2
2
2
2
2
2
2
2
2
2
2
2
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
B
B
B
B
B
B
B
B
C
C
C
C
Company No._Rev. COMP2-SPM-PE-REP-00002_B
37 of 47
n o i t a c o L
x i r t a M
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C3
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
x i r t a M
t l u a f e D
g n i t a R
y t i l
a c i t i r C d e n g i s s A
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
IV
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
n o i t a c o L
x i r t a M
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C3
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
x i r t a M
t l u a f e D
g n i t a R
y t i l
a c i t i r C d e n g i s s A
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
IV
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
n o i t a c o L
x i r t a M
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C3
B2
B2
B2
B2
B2
B2
B2
B2
C2
C2
C2
C2
Assigned Criticality Justification / Comments
x i r t a M
t l u a f e D
g n i t a R
y t i l
a c i t i r C d e n g i s s A
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package. Vendor presence is mandatory during installation.
For electrical equipment/same category is selected and one team can be assigned to the package. Vendor presence is mandatory during installation.
II
II
II
II
II
II
II
II
II
II
II
II
II
II
II
II
II
II
IV
III
Vendor presence is mandatory during installation, pre-comm and commissioning.
II
II
II
II
II
II
II
II
III
III
III
III
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
II
II
II
II
II
II
II
II
II
II
II
II
Appendix 1 - DDE Equipment Criticality Matrix (Workshop 15-Dec-22)
Consequence
Probability
Equipment Criticality Rating
Equipment Criticality
Design
Manufacturing
Installation
e n
i l
p i c s i D
Asset
Unit No.
Tag #
Equipment / Commodity / Component Description
Notes / Comments
y t e f a S
t s o C t c e o r P
j
l
e u d e h c S
/ n o i t u c e x E
t c a p m
I e c n a m r o f r e P
e c n e u q e s n o C
r e b m u N e s a B
n g i s e D
g n i r u t c a f u n a M
n o i t a
l l
a t s n
I
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
LQ6S
Electrical
All Platforms
Subsea package RP Subsea package RP
Subsea package RP
Subsea package RP
Subsea package RP
Subsea package RP
Pipeline package RP
Pipeline package RP
Instrument
Electrical
Electrical
Electrical
Electrical
Electrical
Subsea FO cable Subsea Umbilical Subsea Composite cable Subsea Composite cable Subsea Composite cable Subsea Composite cable
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
91
23 23
23
23
23
23
23
23
26
26
LDB-562320
Outdoor Normal Lighting and Small Power Distribution Board
LDB-562321
Indoor Normal Lighting and Small Power Distribution Board Level 1
LDB-562322
Indoor Normal Lighting and Small Power Distribution Board Level 2
LDB-562323
Indoor Normal Lighting and Small Power Distribution Board Level 3
LDB-562325
Outdoor Normal Lighting and Small Power Distribution Board
ELDB-562320
Outdoor Emergency Lighting Distribution Board
ELDB-562321
Indoor Emergency Lighting Distribution Board Level 1
ELDB-562322
Indoor Emergency Lighting Distribution Board Level 2
ELDB-562323
Indoor Emergency Lighting Distribution Board Level 3
ELDB-562325
Outdoor Emergency Lighting Distribution Board
PDB-562354
Laundry Facilities Distribution Board
PDB-562350
Galley Distribution Board 1
PDB-562351
Galley Distribution Board 2
PDB-562304
Duct Heater Distribution Board 1
PDB-562305
Duct Heater Distribution Board 2
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
same as CP
Multiple tags
MV Cable and termination
Multiple tags Multiple tags
Multiple tags
Multiple tags
Multiple tags Multiple tags
HPU Package TUTU Package Subsea Spur Skid Package (piping, barred tees and valves, structural frame and mudmat)
Subsea 32 inch ILT Package (piping, barred tees and valves, structural frame and mudmat)
Barzan 32 inch Skid Package (piping,valves, structural frame and mudmat) SUTU and flying leads Package
Multiple tags
Fuel Gas Trunkline (new) including risers,crossings and crossing structures
Multiple tags
Fuel Gas Trunkline (Barzan) including tie-in
Multiple tags
Subsea fiber optic cable
100% spares for FO cores
Multiple tags
Subsea Umbilical cable
Redundancy of approx 100% considered
26
Multiple tags
Subsea composite cable
Redundancy and approx 100% spare considered for FO
26
Multiple tags
LV Cable
26
Multiple tags
Cable Trays and Ladders
Instrument
CP6S/LQ6S
49,50
Instrument
CP6S
49,50 N/A
Multiple tags combination of multiple cabinets MICC Package HIPPS package
26
Electrical Bulk (Lighting, LCS, sockets, welding receptacles, etc.)
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
3 4 4
2
2
2 4
2
2
2
4
4
2
2
2
1 1
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
4 3 3
2
2
2 2
2
1
2
2
2
3
3
3
2 2
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3 3 3
2
2
2 3
2
2
2
2
2
3
3
3
3 2
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3 2 4
1
1
2 2
2
2
2
2
2
2
2
2
2 1
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
3 2 3
1
1
2 2
2
1
2
2
2
2
2
2
1 1
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
B D D
D
C
D D
D
D
C
C
B
D
D
D
B D
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
B D D
C
C
C C
C
C
C
B
B
D
D
D
C C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
B D D
C
B
B C
B
C
B
B
B
D
D
D
B C
Company No._Rev. COMP2-SPM-PE-REP-00002_B
38 of 47
n o i t a c o L
x i r t a M
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
B3 D2 D3
D1
C1
D2 D2
D2
D1
C2
C2
B2
D2
D2
D2
B1 D1
x i r t a M
t l u a f e D
g n i t a R
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III IV IV
III
II
IV IV
IV
III
III
III
II
IV
IV
IV
I III
y t i l
a c i t i r C d e n g i s s A
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III IV IV
III
II
III IV
III
III
III
II
II
IV
IV
IV
I III
n o i t a c o L
x i r t a M
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
B3 D2 D3
C1
C1
C2 C2
C2
C1
C2
B2
B2
x i r t a M
t l u a f e D
g n i t a R
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III IV IV
II
II
III III
III
II
III
II
II
y t i l
a c i t i r C d e n g i s s A
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
II III IV
II
II
II III
II
II
III
II
II
n o i t a c o L
x i r t a M
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
C2
B3 D2 D3
C1
B1
B2 C2
B2
C1
B2
B2
B2
x i r t a M
t l u a f e D
g n i t a R
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III
III IV IV
II
I
II III
II
II
II
II
II
y t i l
a c i t i r C d e n g i s s A
II
II
II
II
II
II
II
II
II
II
II
II
II
II
II
II III IV
II
I
II III
II
II
II
II
II
C1 C1
II II
II II
B1 C1
I II
I II
Assigned Criticality Justification / Comments
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
For electrical equipment/same category is selected and one team can be assigned to the package.
“II” is selected based on minimum inspection requirements.Cable termination to be done by trained and certified personnel. “III” is selected based on minimum inspection requirements.
“II & III” is selected based on minimum design and inspection requirements.
“II & III” is selected based on minimum design and inspection requirements.
not part of EPC 2
not part of EPC 2
15 Dec: Added line item and reviewed.
15 Dec: Added line item and reviewed.
15 Dec: Added line item and reviewed.
Appendix 1 - DDE Equipment Criticality Matrix (Workshop 15-Dec-22)
Consequence
Probability
Equipment Criticality Rating
e n
i l
p i c s i D
Asset
Unit No.
Tag #
Equipment / Commodity / Component Description
Notes / Comments
Instrument
RP6S/CP6S
23
Multiple tags
Actuated ON-OFF valves(SDV and BDV)
Instrument Instrument Instrument
Instrument Instrument
CP6S WHPs CP6S RP 3S,5S,9S,WHP 13N WHP 13N
23 23
23
23
Multiple tags Multiple tags Multiple tags
24 Inch Control Valve Choke Valves Analyzers
Multiple tags Multiple tags
HPU Package (Topside Valves) WH Control Panel
Critical valves (Riser SDVs, Riser MOVs, BDVs compressor suction and discharge shutdown valves), (excluding ASV by others) These 4 nos 24” Control valves are added as separate line due to application, size, and required
GC and other type of analyzers
Telecom
RL/RGE
52
Multiple tags
Telecom
RL/RGE
52
Multiple tags
Safety System • PAGA • GMDSS (Lifeboat) • AIS • RACON
Security Systems • ACS • Headcount (POB) • CCTV • IDS
Radio Communication systems • TRS • Crane Radio • VSAT • VHF-AM • VHF-FM • NDB
y t e f a S
t s o C t c e o r P
j
1
1 1 2
3 3
2
3
2
3 3 3
3 2
3
3
l
e u d e h c S
/ n o i t u c e x E
2
3 2 3
2 2
2
2
t c a p m
I e c n a m r o f r e P
1
2 3 3
2 2
2
3
e c n e u q e s n o C
r e b m u N e s a B
1
1 1 2
2 2
2
2
Equipment Criticality
Design
Manufacturing
Installation
g n i r u t c a f u n a M
C
C C C
D D
n g i s e D
D
D D C
D D
n o i t a
l l
a t s n
I
C
C C C
D D
n o i t a c o L
x i r t a M
D1
D1 D1 C2
D2 D2
x i r t a M
t l u a f e D
g n i t a R
III
III III III
IV IV
y t i l
a c i t i r C d e n g i s s A
III
III III III
IV III
n o i t a c o L
x i r t a M
C1
C1 C2
D2 D2
x i r t a M
t l u a f e D
g n i t a R
II
II III
IV IV
y t i l
a c i t i r C d e n g i s s A
II
II II
III II
n o i t a c o L
x i r t a M
C1
C1 C2
D2 D2
x i r t a M
t l u a f e D
g n i t a R
II
II III
IV IV
y t i l
a c i t i r C d e n g i s s A
II
II III
III III
B
C
C
B2
II
II
C2
III
III
C2
III
II
Assigned Criticality Justification / Comments
15 Dec: Consequence 1 was chosen due to assume control valve leaking through stem
“II” is selected based on minimum inspection requirements.
“III” is selected based on minimum inspection requirements. “II & III” is selected based on minimum inspection requirements.
• PAGA-II selected based on design min requirements • GMDSS (Lifeboat)III- selected based on design min requirements • AIS-II selected based on customized requirements • RACON-II selected based on customized requirements
C
D
D
C2
III
III
D2
IV
III
D2
IV
III
Category 3 is selected Headcount and CCTV specifically. “III” is selected based on system customized configuration requirements.
Telecom
RL/RGE
52
Multiple tags
2
3
2
2
2
B
C
C
B2
II
II
C2
III
III
C2
III
II
“II” for installation selected as TRS and VSAT shall be customized by the vendor offshore.
Infrastructure systems • SCS • OTN • AVS • IPT • WIFI • FOC • DWDM • DVR • Hotline
E. Misc. Telecoms • WMS • ENT (Satellite communication) • Telecom Tower
Telecom
RL/RGE
52
Multiple tags
Telecom
RL/RGE
52
Multiple tags
2
4
2
3
2
2
3
3
2
2
C
C
C
C2
III
III
C2
III
III
C2
III
III
Subsea FOC cable is a separate line item in this matrix.
D
D
D
D2
IV
IV
D2
IV
IV
D2
IV
III
“III” is selected based on minimum vendor mobilization requirements.
Company No._Rev. COMP2-SPM-PE-REP-00002_B
39 of 47
Appendix 1 - DDE Equipment Criticality Matrix (Workshop 15-Dec-22)
DCR
I
II
Design
Manufacturing (Procurement)
Engineering Oversight
RFQ Development
MCR
Source Inspection & Testing
Suppliers and Sub-Suppliers Engagement
Installation & Start-up
Installation & Start-Up
ICR
COMPANY PMT
Contractor
COMPANY PMT
Contractor
COMPANY PMT
Contractor
COMPANY PMT
Contractor
COMPANY PMT
Contractor
Participate in key meetings with Contractor; review documents (response is required); attendance at key engineering activities is required; consider assigning dedicated PMT resource to steward package
Assign dedicated Package Engineer; prepare engineering documents.
Jointly develop RFQ with Contractor. TBE to be approved by CPY All deviations from TBE to be approved prior to PO.
Jointly develop RFQ with Company Develops TBE Submits All deviations for approval prior to PO.
Review documents (response is required); attendance at key engineering activities is required; consider assigning dedicated PMT resource to steward package
Assign Package Engineer; prepare engineering documents.
Jointly develop data sheet with Contractor; assist as necessary with other RFQ docs; review documentation (response is required)
Jointly develop data sheet with Company; prepare all remaining RFQ docs for Company review (response is required)
Weekly (minimum) inspection visits and all selected ITP points.
Provide full-time resident inspector (w/ PMT approval;) minimum 2 inspection visits per week and all selected ITP points Dedicated Package Engineer to attend kick-off meeting and all ITP points including FAT
Monthly (minimum) inspection visits and all selected ITP points.
Minimum 1 inspection visit per week and all selected ITP points Package Engineer to attend kick-off meeting and selected ITP points including FAT
I
II
Conduct PM (or PM designate) level visit with Supplier (preferably at vendor’s shop); attend key activities and witness key tests
Conduct PM (or PM designate) level visit with Supplier (preferably at vendor’s shop); weekly teleconferences with Supplier; attend key activities and witness key tests
I
II
Approves Installation & Start- up Procedure. Participate/witness (full time) installation & start-up activities. (Including Preservation)
Dedicated Package Engineer with site supervision team to manage interfaces. Ensure physical attendance of respective Vendor/OEM at site. Participate/witness (full time) installation & start-up activities. (Including Preservation)
Approves selected Equipment Installation & Start-up Procedure. Participate/witness installation & start-up activities (Including Preservation) as and when required.
Package Engineer with site supervision team to manage interfaces. Ensure physical attendance of respective Vendor/OEM at site. Participate/witness installation & start-up activities (Including Preservation) as and when required.
III
Review documents (response is required); attendance at key engineering activities is optional
Assign Package Engineer; prepare engineering documents.
Receive documentation for review (response is required)
Prepare documentation and provide to Company for review (response is required)
III
Random inspection visits and random witness of tests as per approved ITP.
Selected ITP points Package Engineer attend FAT and final inspection only
Attend key activities and witness key tests
Bi-weekly teleconferences with Supplier; visits for key activities and witness key tests
III
Review of documentation.
Site Installation Supervisor manages the activities according to Procedures. Vendor assistance if required only.
IV
Review of documentation only on an exception basis
Engineer to prepare engineering documents.
Receive documentation for info/review as per the quality specifications (response is optional)
Prepare documentation and provide to Company for info/review (response is optional)
IV
As per the approved ITP.
Document reviews and final inspection (unless written waiver is provided by Company)
Participate in key discussions with Supplier
Establish standing teleconference with Supplier to review status and any outstanding issues
IV
Monitor only.
Site Installation Supervisor manages the activities according to Procedures.
*See also Engineering Surveillance Plan (COMP-TPF-QM-PLN-00020) for engineering document review
*See also Procurement Criticality Assessment (PRJ-PJL-PRC-072) for the surveillence activities as per Procument Criticality Rating
Company No._Rev. COMP2-SPM-PE-REP-00002_B
40 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
14.2 Appendix 2
DDE Equipment Criticality Workshop – Attendance Record
Company No._Rev. COMP2-SPM-PE-REP-00002_B
41 of 47
Appendix 2 - DDE Equipment Criticality Matrix - Attendance Record
-
Summary Meeting title Attended participants Start time End time Meeting duration Average attendance time
-
Participants
Equipment Criticality Workshop[External Sender] 34 12/15/22, 12:50:22 PM 12/15/22, 4:13:32 PM 3h 23m 11s 2h 2m 50s
Name
First join
Last leave
In-meeting duration
Participant ID (UPN)
Bahrom, Rasydan (Kuala Lumpur) Kumar, Ramesh Demaisip, Neil Ting, Timothy Aziz, Azionn Bhatt, Anand Azhari Othman (Guest) Chandrababu Paramasivam Chidambaram Muthiah Hesham Alsulaiti (Guest) Mojahid Elamin (Guest) Zijad Mrndic Huan, Yew Jin (Kuala Lumpur) Roy Alvin Magboo Abu Bakar, Rosli (Kuala Lumpur) Ahmed Elrowiny (Guest) Samir oualha (Guest) Kalyan (Guest) Nuh Ruby Manickam Selwyn Sriram Murthy Valiveti Meyyappan Narayanan Nimish Vyas Lim, Teck Yam (Kuala Lumpur) Menard Pierre Peddinti, Murali (Kuala Lumpur) Oprescu Luminita Othman, Muhammad Sany (Kuala Lumpur) Bhatt, Anand (Kuala Lumpur) Kumar, Ramesh (Kuala Lumpur) Mohammed Ali Al-Sulaiti Matt Howie (Guest) Mojahid Elamin (Guest) Yunus, Suhaili (Kuala Lumpur) Yusop, Ahmadzamani (Kuala Lumpur) Praveen Sharma (Guest) Magnani Matteo Shanware Nitin Ramchandra Francis Minah
12/15/22, 12:50:31 PM 12/15/22, 12:50:31 PM 12/15/22, 12:50:31 PM 12/15/22, 12:50:31 PM 12/15/22, 12:50:31 PM 12/15/22, 12:50:31 PM 12/15/22, 12:56:41 PM 12/15/22, 1:00:05 PM 12/15/22, 1:00:06 PM 12/15/22, 1:00:07 PM 12/15/22, 1:00:07 PM 12/15/22, 1:00:10 PM 12/15/22, 1:00:38 PM 12/15/22, 1:00:40 PM 12/15/22, 1:00:45 PM 12/15/22, 1:01:26 PM 12/15/22, 1:01:47 PM 12/15/22, 1:02:54 PM 12/15/22, 1:02:54 PM 12/15/22, 1:03:04 PM 12/15/22, 1:03:43 PM 12/15/22, 1:04:06 PM 12/15/22, 1:05:04 PM 12/15/22, 1:05:19 PM 12/15/22, 1:06:44 PM 12/15/22, 1:07:19 PM 12/15/22, 1:09:06 PM 12/15/22, 1:19:30 PM 12/15/22, 1:20:06 PM 12/15/22, 1:20:44 PM 12/15/22, 1:30:41 PM 12/15/22, 1:32:42 PM 12/15/22, 1:41:47 PM 12/15/22, 1:56:07 PM 12/15/22, 2:21:07 PM 12/15/22, 2:34:34 PM 12/15/22, 2:44:08 PM 12/15/22, 3:04:31 PM 12/15/22, 3:10:46 PM
12/15/22, 4:03:21 PM 3h 9m 50s 12/15/22, 4:03:21 PM 3h 9m 50s 12/15/22, 4:03:21 PM 3h 9m 50s 12/15/22, 4:03:21 PM 3h 9m 50s 12/15/22, 4:03:21 PM 3h 9m 50s 12/15/22, 4:03:21 PM 3h 9m 50s 12/15/22, 4:03:25 PM 3h 6m 44s 12/15/22, 4:03:24 PM 2h 49m 42s 12/15/22, 4:06:22 PM 3h 6m 15s 12/15/22, 4:03:20 PM 3h 3m 12s 12/15/22, 1:40:44 PM 40m 37s 12/15/22, 3:58:53 PM 2h 58m 43s 12/15/22, 3:01:12 PM 2h 34s 12/15/22, 4:03:22 PM 3h 2m 42s 12/15/22, 3:03:43 PM 2h 2m 58s 12/15/22, 4:03:21 PM 3h 1m 55s 12/15/22, 2:30:19 PM 1h 28m 32s 12/15/22, 3:58:56 PM 2h 56m 2s 12/15/22, 2:48:07 PM 1h 45m 12s 12/15/22, 4:03:18 PM 3h 13s 12/15/22, 3:59:00 PM 2h 55m 16s 12/15/22, 4:03:19 PM 2h 59m 13s 12/15/22, 2:55:29 PM 56m 31s 12/15/22, 2:58:27 PM 1h 53m 8s 12/15/22, 4:03:20 PM 2h 56m 35s 12/15/22, 2:54:13 PM 1h 46m 54s 12/15/22, 2:21:50 PM 1h 12m 44s 12/15/22, 4:03:22 PM 2h 43m 51s 12/15/22, 2:07:10 PM 47m 4s 12/15/22, 4:13:32 PM 2h 52m 47s 12/15/22, 4:03:21 PM 2h 32m 39s 12/15/22, 2:02:49 PM 30m 7s 12/15/22, 4:03:19 PM 2h 21m 32s 12/15/22, 3:53:39 PM 1h 57m 32s 12/15/22, 3:01:15 PM 40m 7s 12/15/22, 3:03:25 PM 28m 51s 12/15/22, 3:01:38 PM 17m 29s 12/15/22, 3:42:33 PM 38m 2s 12/15/22, 4:03:23 PM 52m 36s
Rasydan.Bahrom@Worley.com ramesh.kumar@worley.com neil.demaisip@worley.com timothy.ting@worley.com azionn.aziz@worley.com anand.bhatt@worley.com
Paramasivam.Chandrababu@saipem.com cmuthiah@qatargas.com.qa
Paramasivam.Chandrababu@saipem.com cmuthiah_qatargas.com.qa#EXT#@TECHNIP.onmicrosoft.com
zmrndic@qatargas.com.qa Huan.Yew.Jin@worley.com rmagboo@qatargas.com.qa Rosli.Bakar@worley.com
zmrndic_qatargas.com.qa#EXT#@saipem.onmicrosoft.com Huan.Yew.Jin@Worley.com rmagboo_qatargas.com.qa#EXT#@saipem.onmicrosoft.com Rosli.Bakar@Worley.com
Ruby.Nuh@saipem.com MSELWYN@qatargas.com.qa SriramMurthy.Valiveti@saipem.com MNarayanan@qatargas.com.qa ndvyas@qatargas.com.qa Lim.Teck.Yam@worley.com Pierre.Menard@saipem.com Murali.Peddinti@Worley.com Luminita.Oprescu@saipem.com MuhammadSany.Othman@Worley.com Anand.Bhatt@Worley.com Ramesh.Kumar@Worley.com MoAlSulaiti@qatargas.com.qa
Ruby.Nuh@saipem.com MSELWYN_qatargas.com.qa#EXT#@TECHNIP.onmicrosoft.com SriramMurthy.Valiveti@saipem.com MNarayanan_qatargas.com.qa#EXT#@TECHNIP.onmicrosoft.com ndvyas_qatargas.com.qa#EXT#@TECHNIP.onmicrosoft.com Teck.Yam.Lim@Worley.com Pierre.Menard@saipem.com Murali.Peddinti@Worley.com Luminita.Oprescu@saipem.com MuhammadSany.Othman@Worley.com Anand.Bhatt@Worley.com Ramesh.Kumar@Worley.com MoAlSulaiti_qatargas.com.qa#EXT#@TECHNIP.onmicrosoft.com
Suhaili.Yunus@Worley.com Ahmadzamani.Yusop@Worley.com
Suhaili.Yunus@Worley.com Ahmadzamani.Yusop@Worley.com
Matteo.Magnani@saipem.com NitinRamchandra.Shanware@saipem.com fcm@prism-ta.com
Matteo.Magnani@saipem.com NitinRamchandra.Shanware@saipem.com fcm@prism-ta.com
Role
Organizer
Facilitator
Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter Presenter
Company No._Rev. COMP2-SPM-PE-REP-00002_B
42 of 47
NFPS Offshore Compression Complexes Project COMP2 DDE EQUIPMENT CRITICALITY ASSESSMENT WORKSHOP REPORT
14.3 Appendix 3
DDE Equipment Criticality Workshop – Minutes of Meeting 15 Dec 22
Company No._Rev. COMP2-SPM-PE-REP-00002_B
43 of 47
Offshore Compression Complexes Project COMP2 MINUTES OF MEETING MOM – EQUIPMENT CRITICALITY WORKSHOP
MOM No.
COMP2-M-SPM-QG-00001
PROJ CODE:
033734
Page 1 of 4
Rev. 00
MINUTES TYPE:
WEEKLY
MONTHLY
✓ OTHER
CONTRACT NUMBER
LTC/C/NFP/5128/20
MEETING DATE:
15-DEC-2022 Meeting Location
L21 Naza Tower Meeting Room / Online Microsoft Teams
CONTRACT NAME
Offshore Compression Complexes Project – EPC 2
COMPANY Participants: (In person/Online) CONTRACTOR Participants : (In person/Online) See Attendance List
See Attendance List
Distribution: Attendees plus:
CPY:
CTR:
Minuted by: Neil Demaisip
Item
1.1
1.2
1.3
1.4
Notes
Action By
Due Date
HSE Safety Moment and Review of Project HSE Statistics / Status
Safety Moment shared was about AGRU Heater Failure.
Info
N/A
Administration
2.1
Nil
2.2
2.3
2.4
QA/QC
3.1
Nil
3.2
3.3
3.4
Engineering – Equipment Criticality Assessment Workshop - DDE
Before this Workshop, the Contractor and Subcontractor Teams have done internal review of the FEED Equipment Criricality Matrix and agreed to propose to Company changes to the Criticality Ratings.
4.1
Info
N/A
4.2
A Workshop Terms of Reference (TOR) was submitted to Company to seek approval to proceed with the Workshop.
Info
N/A
4.3
The proposed changes to the Criticality were the following:
Info
N/A
Company No._Rev. COMP2-SPM-PE-REP-00002_B
44 of 47
Appendix 3 - DDE Equipment Criticality Workshop - Minutes of Meeting 15 Dec 22
Offshore Compression Complexes Project COMP2 MINUTES OF MEETING MOM – EQUIPMENT CRITICALITY WORKSHOP
MOM No.
COMP2-M-SPM-QG-00001
PROJ CODE:
033734
Page 2 of 4
Rev. 00
MINUTES TYPE:
WEEKLY
MONTHLY
✓ OTHER
CONTRACT NUMBER
LTC/C/NFP/5128/20
MEETING DATE:
15-DEC-2022 Meeting Location
L21 Naza Tower Meeting Room / Online Microsoft Teams
CONTRACT NAME
Offshore Compression Complexes Project – EPC 2
- General - Proposal to consider the Design Probability for QG and without QG
experience be taken as the same.
- Structural Discipline - FEED did not assign a rating to Sea Water Lift Pump
Caisson. Proposed to assess the Criticality.
- Mechanical - Proposed to change the Safety Consequence for Pedestal Crane
from 1 to 2.
- Instrument - Missing line items from FEED (1 nos.) – 4 nos. cladded 24in
Control valves. Proposed to include and assess the Criticality.
- Electrical - Missing line items from FEED (3 no’s) - LV Cables, Cable Trays and (Lighting, LCS, sockets, welding
Ladders, Electrical Bulk receptacles, etc.). Proposed to include and assess the Criticality.
-
Piping – No change to the Matrix/Criticality
-
Technical Safety and Loss Prevention – No change to the Matrix/Criticality
-
Telecom – Discipline Leads were not able to do a review of the FEED Criticality Matrix and cannot present any proposal during this Workshop.
Info
N/A
Info
N/A
Info
N/A
Info
N/A
Info
Info
Info
N/A
N/A
N/A
Company agreed to discuss the proposed changes and proceeded with the joint Assessment Workshop.
Info
N/A
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
WORKSHOP CONCLUSION – The following have been agreed:
- To conduct another workshop for Manufacturing and Installation/Start-up. To be
done on Week 4 Jan 23. Date to be confirmed.
Team
02-Jan- 23
-
General – The proposal to consider the Design Probability for QG and without QG experience be taken as the same will depend on the type of equipment.
-
Structural - Team agreed to assess the Design Criticality and agreed to a
DCR = III (D1). This rating applies to all caisson with pump.
- Mechanical – NO CHANGE to the proposal to change the Safety Consequence
for Pedestal Crane from 1 to 2.
- Electrical - Team agreed to assess and agreed to a DCR = IV (D2) for LV Cables, Cable Trays and Ladders, Electrical Bulk (Lighting, LCS, sockets, welding receptacles, etc.)
4.18
- Piping – No change to the Matrix/Criticality
4.19
- Technical Safety and Loss Prevention – No change to the Matrix/Criticality
Info
N/A
Info
N/A
Info
N/A
Info
N/A
Info
Info
N/A
N/A
4.13
4.14
4.15
4.16
4.17
4.20
- Telecom – Discipline Leads to review FEED Criticality Matrix and present any for Manufacturing and the next Workshop
gaps during Installation/Start-up in week 4 January 2023.
Telecom Leads
Wk 4 Jan 23
Materials -Welding / NDT / FJC
5.1
Nil
Company No._Rev. COMP2-SPM-PE-REP-00002_B
45 of 47
Appendix 3 - DDE Equipment Criticality Workshop - Minutes of Meeting 15 Dec 22
Offshore Compression Complexes Project COMP2 MINUTES OF MEETING MOM – EQUIPMENT CRITICALITY WORKSHOP
MOM No.
COMP2-M-SPM-QG-00001
PROJ CODE:
033734
Page 3 of 4
Rev. 00
MINUTES TYPE:
WEEKLY
MONTHLY
✓ OTHER
CONTRACT NUMBER
LTC/C/NFP/5128/20
MEETING DATE:
15-DEC-2022 Meeting Location
L21 Naza Tower Meeting Room / Online Microsoft Teams
CONTRACT NAME
Offshore Compression Complexes Project – EPC 2
5.2
5.3
5.4
6.1
6.2
6.3
6.4
7.1
7.2
7.3
7.4
8.1
8.2
8.3
8.4
9.1
9.2
9.3
9.4
Procurement
Nil
Fabrication
Nil
Interfaces
Nil
Operations
Nil
Upcoming Meetings
10.1
The Criticality Workshop for Manufacturing and Installation/Start-up will be
conducted on Week 4 January 2023. Date to be agreed.
Team
Wk 4 Jan 23
10.2
10.3
10.4
Areas of Concern
11.1
11.2
11.3
11.4
11.5
11.6
Company No._Rev. COMP2-SPM-PE-REP-00002_B
46 of 47
Appendix 3 - DDE Equipment Criticality Workshop - Minutes of Meeting 15 Dec 22
Offshore Compression Complexes Project COMP2 MINUTES OF MEETING MOM – EQUIPMENT CRITICALITY WORKSHOP
MOM No.
COMP2-M-SPM-QG-00001
PROJ CODE:
033734
Page 4 of 4
Rev. 00
MINUTES TYPE:
WEEKLY
MONTHLY
✓ OTHER
CONTRACT NUMBER
LTC/C/NFP/5128/20
MEETING DATE:
15-DEC-2022 Meeting Location
L21 Naza Tower Meeting Room / Online Microsoft Teams
CONTRACT NAME
Offshore Compression Complexes Project – EPC 2
AOB
12.1
12.2
Attachments to MOM
-
Equipment Criticality Matrix – Update 15 Dec 2022
-
Criticality Assessment Workshop Terms of Reference (TOR) 15 Dec 22
-
Workshop Attendance List
Info
Info
Info
N/A
N/A
N/A
Agreed as a true record:
CONTRACTOR Representative:
COMPANY Representative:
Name, Signature, Title
Name, Signature, Title
Date:
Date:
Company No._Rev. COMP2-SPM-PE-REP-00002_B
47 of 47
Appendix 3 - DDE Equipment Criticality Workshop - Minutes of Meeting 15 Dec 22
Project: Q-21699 - Saipem COMP2 Folder: Administrative, Engineering Management