NFPS Offshore Compression Complexes Project COMP2
COMPANY Contract No.: LTC/C/NFP/5128/20
CONTRACTOR Project No.: 033734
Document Title
:
TECHNICAL QUERY PROCEDURE
COMPANY Document No.
: COMP2-SPM-PE-PRC-00005
Saipem Document No.
: 33734-A-D-00-SPM-EM-P-10005
Discipline
: ADMINISTRATIVE, ENGINEERING MANAGEMENT
Document Type
: PROCEDURE
Document Category/Class
: 1
Document Classification
:
Internal
B
A
14-Mar-2023
02-Feb-2023
Issued for Approval
Paramasivam
Sandeep Maiti
Parag Patil
Issued for Review
Paramasivam
Matteo Mauri
Parag Patil
REV.
DATE
DESCRIPTION OF REVISION
PREPARED BY CHECKED BY
APPROVED BY
Saipem S.p.A.
Company No._Rev. COMP2-SPM-PE-PRC-00005_B
1 of 19
NFPS Offshore Compression Complexes Project COMP2 TECHNICAL QUERY PROCEDURE
REVISION HISTORY
Revision
Date of Revision
Revision Description
A1
A
B
05-Dec-2022
Issued for Inter-Discipline Check
10-Jan-2023
14-Mar-2023
Issued for Review
Issued for Approval
HOLDS LIST
Hold No
Hold Description
Company No._Rev. COMP2-SPM-PE-PRC-00005_B
2 of 19
NFPS Offshore Compression Complexes Project COMP2 TECHNICAL QUERY PROCEDURE
TABLE OF CONTENTS
1
2
3
4
5
6
7
8
9
INTRODUCTION … 4
1.1 PROJECT OBJECTIVE … 4 1.2 PROJECT SCOPE … 4
DEFINITIONS AND ABBREVIATIONS … 6
2.1 DEFINITIONS … 6 2.2 ABBREVIATIONS … 7
REFERENCE, RULES, CODES AND STANDARDS … 8
3.1 COMPANY DOCUMENTS … 8 3.2 PROJECT DOCUMENTS … 9 3.3 CONTRACTOR DOCUMENTS … 9
SCOPE AND PURPOSE … 9
TQ NUMBERING PROCEDURE … 10
PROCEDURE … 11
6.1 GENERAL … 11 6.2 TQ WORKFLOW DIAGRAM BETWEEN CONTRACTOR AND COMPANY … 12
RESPONSIBILITY … 13
7.1 LEAD DISCIPLINE ENGINEER RESPONSIBILITY … 13 7.2 ENGINEERING MANAGER/TECHNICAL MANAGER RESPONSIBILITY … 13 7.3 DOCUMENT CONTROLLER RESPONSIBILITY… 13 7.4 PROJECT MANAGER RESPONSIBILITY … 13 7.5 COMPANY RESPONSIBILITY … 13
TQ REVIEW AND APPROVAL AUTHORITY … 13
TECHNICAL QUERY … 13
9.1 TQ INITIATION BY CONTRACTOR … 14 9.2 TQ INITIATED BY VENDOR … 14 9.3 TQ APPROVAL WITHIN CONTRACTOR ORGANIZATION … 15 9.4 TQ TRANSMITTAL TO COMPANY … 15 9.5 TQ RESPONSE BY COMPANY … 15 9.6 TQ REVIEW AND IMPLEMENTATION … 15 9.7 TQ FOLLOW-UP … 15 9.8 TECHNICAL QUERY REPORTING, TRACKING & REGISTER … 16
10
APPENDICES … 17
10.1 APPENDIX 1:- TECHNICAL QUERY FORM … 18 10.2 APPENDIX 2: - TECHNICAL QUERY REGISTER … 19
Company No._Rev. COMP2-SPM-PE-PRC-00005_B
3 of 19
NFPS Offshore Compression Complexes Project COMP2 TECHNICAL QUERY PROCEDURE
1
INTRODUCTION
The North Field is the world’s largest natural gas field and accounts for nearly all of the state of Qatar’s gas production. The reservoir pressure in the North Field has been declining due to continuous production since the early 1990s. The principal objective of the NFPS Project is to sustain the plateau from existing QG South Operation (RL Dry Gas, RGE Wet gas) and existing QG North Operation (QG1 & QG2) production areas by implementing an integrated and optimum investment program consisting of subsurface development, pressure drop reduction steps and compression. Refer to the figure below for a schematic of the North Field.
Qatargas Operating Company Limited is leading the development of the North Field Production Sustainability (NFPS) Project.
1.1 Project Objective
The objective of this Project includes:
• Achieve standards of global excellence in Safety, Health, Environment, Security and Quality
performance.
• Sustain the Qatargas North Field Production Plateau by installing new Compression Complex facilities CP6S & CP7S in QG south with integration to the existing facilities under Investment #3 program.
• Facility development shall be safe, high quality, reliable, maintainable, accessible, operable,
and efficient throughout their required life.
1.2 Project Scope
The Project Scope includes detailed engineering, procurement, construction, transportation & installation, hook-up and commissioning, tie-in to EXISTING PROPERTY and provide support for start- up activities of the following facilities and provisions for future development. The WORK shall be following the specified regulations, codes, specifications and standards, achieves the specified performance, and is safe and fit
purpose in all respects.
for
Offshore
‐
‐
CP6S and CP7S Compression Complexes that are part of QG-S RGE facilities as follows:
• CP6S Compression Complex
• Compression Platform CP6S, Living Quarters LQ6S, Flare FL6S
• Bridges BR6S-2, BR6S-3, BR6S-4, BR6S-5
• Bridge linked Tie-in to RP6S
Production from existing wellheads (WHP6S & WHP10S) and new wellhead (WHP14S) are routed via riser platform RP6S to compression platform CP6S to boost pressure and export to onshore via two export lines through the existing WHP6S pipeline and a new 38” carbon steel looping trunkline from RP6S (installed by COMP2). CP6S is bridge-linked to RP6S.
• CP7S Compression Complex
• Compression Platform CP7S, Living Quarters LQ7S, Flare FL7S
• Bridges BR7S-2, BR7S-3, BR7S-4, BR7S-5
• Bridge linked Tie-in to RP7S
Company No._Rev. COMP2-SPM-PE-PRC-00005_B
4 of 19
NFPS Offshore Compression Complexes Project COMP2 TECHNICAL QUERY PROCEDURE
CP7S shall receive production from existing wellheads (WHP5S & WHP7S) and new wellhead (WHP13S). There is only one export line for CP7S through the existing export pipeline from WHP7S. CP7S is bridge-linked to RP7S.
RGA Complex Destressing
Migration of the Electrical power source, Telecoms, Instrumentation and Control systems from WHPs and RHPs hosted by RGA to the respective Compression Complexes listed below:
• WHP6S, WHP10S, WHP14S, RP6S and RP10S to CP6S Compression Complex
• WHP5S, WHP7S, WHP13S and RP7S to CP7S Compression Complex
Destressing of Telecoms, Instrumentation and Control system in RGA Complex Control Room, which would include decommissioning and removal of telecom system devices and equipment that would no longer be required post migration and destressing activity.
Onshore
An Onshore Collaborative Center (OCC) will be built under EPC-9, which will enable onshore based engineering teams to conduct full engineering surveillance of all the offshore facilities. The OCC Building will be located in Ras Laffan Industrial City (RLIC) within the Qatar Gas South Plot. MICC & Telecommunication, ELICS related scope will be performed in the OCC building.
Figure 1.2.1: NFPS Compression Project COMP2 Scope
Company No._Rev. COMP2-SPM-PE-PRC-00005_B
5 of 19
NFPS Offshore Compression Complexes Project COMP2 TECHNICAL QUERY PROCEDURE
2 DEFINITIONS AND ABBREVIATIONS
2.1 Definitions
Definition
Description
COMPANY
Qatargas Operating Company Limited.
CONTRACTOR
Saipem S.p.A.
DELIVERABLES
FACILITIES
All products (drawings, equipment, services) which must be submitted by CONTRACTOR to COMPANY at times specified in the contract. All machinery, apparatus, materials, articles, components, systems and items of all kinds to be designed, engineered, procured, tested and manufactured, constructed, supplied, permanently installed by CONTRACTOR at SITE in connection with the NFPS Project as further described in Exhibit 6.
fabricated,
MILESTONE
A reference event splitting a PROJECT activity for progress measurement purpose.
PROJECT
NFPS Offshore Compression Complexes Project COMP2
SITE
(i) any area where Engineering, Procurement, Fabrication of the FACILITIES related the CPS6S and CP7S Compression Complexes are being carried out and (ii) the area offshore required for installation of the FACILITIES in the State of Qatar.
to
SUBCONTRACT
Contract signed by SUBCONTRACTOR and CONTRACTOR for the performance of a certain portion of the WORK within the Project.
SUBCONTRACTOR
Any organization selected and awarded by CONTRACTOR to supply a certain Project materials or equipment or whom a part of the WORK has been Subcontracted.
WORK
Scope of Work defined in the CONTRACT.
WORK PACKAGE
The lowest manageable and convenient level in each WBS subdivision.
VENDOR
The person, group, or organization responsible for the design, manufacture, testing, and load-out/shipping of the Equipment/ Material.
Company No._Rev. COMP2-SPM-PE-PRC-00005_B
6 of 19
NFPS Offshore Compression Complexes Project COMP2 TECHNICAL QUERY PROCEDURE
2.2 Abbreviations
Code
Definition
Document Distribution Matrix
Electronic Document Management System
Engineering Manager
Factory Acceptance Test
Inter-Discipline Check
Document Control Lead
Engineering Centre
Master Document Register
Project Control Manager
Planning Engineer
Project Manager
Project Management Team
Project Quality Manager
Project Specialist Leader
Preparation / Verification / Approval Workflow In EDMS
Record of Conversation
Ranhill Worley
Technical Manager
Technical Query
DDM
EDMS
EM
FAT
IDC
DCL
EC
MDR
PCM
PLE
PM
PMT
PQM
PSL
PVA
ROC
RW
TM
TQ
Company No._Rev. COMP2-SPM-PE-PRC-00005_B
7 of 19
NFPS Offshore Compression Complexes Project COMP2 TECHNICAL QUERY PROCEDURE
3 REFERENCE, RULES, CODES AND STANDARDS
The following codes, standards and specification are referenced within the document shall be considered as part of this specification. Conflict among applicable specification and / or codes shall be brought to the attention of the COMPANY for resolution COMPANY decision shall be final and shall be implemented. The latest editions of codes and specification effective as on date of contract shall be followed.
In general, the order of precedence shall be followed:
a) Qatari Governmental and Regulatory Requirements
b) COMPANY Procedures, Policies and Standards (Exhibit 5 Appendix I)
c) Project Specifications.
d) Industry Codes and Standards
e) COMPANY and CONTRACTOR’s Lessons Learned
If CONTRACTOR/SUBCONTRACTOR deems any deviations from the specifications will result in significant project cost and schedule saving, proposal to such deviations shall be submitted to COMPANY for review and approval. CONTRACTOR/SUBCONTRACTOR shall not proceed with any deviation to the specifications without prior COMPANY approval. In general, all design activities shall conform to legal and statutory regulations, and recognized industry best practices.
3.1 Company Documents
S. No
Document Number
Title
LTC/C/NFP/5128/20
Contract Agreement
EXHIBIT 5
Project Instructions
COMP2-SPM-CRPRC-10002 Correspondence Procedure
PRJ-PJL-PRC-004
PRJ-PJL-PRC-005
PRJ-PJL-PRC-006
PRJ-PJL-PRC-048
PRJ-PJL-PRC-049
Facilities Engineering and Vendor Document Numbering Procedure
Facilities, System and Unit Number Codes and Descriptions Procedure Project Information Handover Procedure
Facilities Documentation Metadata Requirements Procedure
•
•
•
IM-DD-T001 - Master Document Register – Engineering Document Numbering Request IM-MDR-T001 – Vendor Document Register – Vendor Document Numbering Request IM-VDR-T001 – Data Dictionary For MDR and VDR
Project Acceptance Procedure
Information Handover, Verification and
Company No._Rev. COMP2-SPM-PE-PRC-00005_B
8 of 19
NFPS Offshore Compression Complexes Project COMP2 TECHNICAL QUERY PROCEDURE
3.2 Project Documents
S. No
Document Number
Title
COMP2-SPM-PE-PRC-00001
Engineering Document Numbering Procedure
COMP2-SPM-CR-PRC-10002
Communication Procedure
and
Correspondence
COMP2-SPM-PN-PRC-00003
Progress Measurement Procedure
COMP2-SPM-IM-REG-00001
Master Document Register
COMP2-SPM-PE-PRC-00006
Vendor Documentation Management
COMP2-SPM-PE-PRC-00009
Specification Deviation Concession Request Procedure
and Contractor
COMP2-SPM-PE-PLN-00002
Engineering Management Plan
3.3 Contractor Documents
S. No
Document Number
Title
STD-COR-ENG-002-E
Project Engineering
STD-COR-ENG-044-E
Management of Field Engineering Activities
OPR-COR-ENG-005-E
Freezing of Design Documents
FORM-COR-ENG-002-E
Design Change Report
OPR-COR-ENG-006-E
Design Change Management
4 SCOPE AND PURPOSE
The scope of the document is to define a Technical Query Procedure on the COMP2 Project. The purpose of this procedure is to define the workflow and the responsibilities to raise Technical Query by CONTRACTOR, Fabrication Site, Subcontractors and Vendors to COMPANY during the different phases of COMP2 project.
The objectives of this document are to ensure:
• Well informed decision making
• Timely resolutions of TQs
• Clear reasoning for any request that can potentially initiate a deviation
• Any ambiguity or inconsistencies in the technical documents are clarified
Communication and interactions are formalized and properly recorded. This procedure describes the
steps:
Company No._Rev. COMP2-SPM-PE-PRC-00005_B
9 of 19
NFPS Offshore Compression Complexes Project COMP2 TECHNICAL QUERY PROCEDURE
• To define the process used for technical queries so that the queries are correctly resolved and
documented in a traceable and easily retrievable manner.
• To define the process used for site queries addressing the nature of certain aspects of the work
to be performed on a particular site (onshore and offshore).
This procedure does not cover the following.
• Specification Deviation Request and Concession Request which are covered in Document
number COMP2-SPM-PE-PRC-00009
• Management of Technical Changes Procedure which is covered in Document Number COMP2-
SPM-PE-PRC-00003
• Commercial /Contractual changes which is covered in CHANGE MANAGEMENT SYSTEM AND
CHANGE CONTROL PROCEDURE (Document No: COMP2-SPM-CR-PRC-00001)
5 TQ NUMBERING PROCEDURE
All Technical Queries will be identified by numbering structure as below:
Project Code AAA
-
Originator
-
Discipline
-
BBB
-
CC
Document Type
-
DDD
Sequences Number
- NNNNN
AAA – Company Project Code - COMP2
BBB – Originator Code shall be as follows:
Originator Saipem SpA
Code SPM
Any additional Originator code shall be taken from COMPANY Metadata if needed. Refer to COMP2- SPM-PE-PRC-00001 - Document Numbering Procedure and COMPANY specification PRJ-PJL-PRC- 048 - FACILITIES DOCUMENTATION METADATA REQUIREMENTS PROCEDURE for details.
CC - All Technical Query shall be identified with discipline as below.
Discipline Description Architectural Construction and Commissioning Corrosion Engineering Civil Drilling Electrical Geosciences HVAC ICS Security Instrumentation Loss Prevention Mechanical Marine Operations Material Technology
Discipline AB CC CE CL DR EL GS HV IC IN LP ME MO MT
Company No._Rev. COMP2-SPM-PE-PRC-00005_B
10 of 19
NFPS Offshore Compression Complexes Project COMP2 TECHNICAL QUERY PROCEDURE
Discipline Description Operations Administrative, Engineering Management Piping Pipelines Process Quality Management HSE&Q Subsurface Structural Telecommunications
Discipline OP PE PI PL PR QM SH SS ST TC
DDD- All Technical Query will be identified by document code as below.
Document Type Description Technical Query
Document Type TQY
NNNNN- Sequential Running number. Each discipline shall have independent sequence number.
All Technical Query shall be registered in registers as per Appendix 2.
The document number to the assigned Technical Query is normally by running number for each document submission.
Contractor Document Controller shall register all the Technical Query submitted by providing running number and recorded in registers before issuing to Company through transmittal.
First issue of TQ shall be in IFA status as Rev B. If TQ to be reissued after receipt of COMPANY response, next revision on TQ in Rev C etc., to be followed.
For Example
COMP2-SPM-PR-TQY-00001_B
Electronic file names shall be AAAA-BBB-CC-DDD-NNNNN
6 PROCEDURE
6.1 General
CONTRACTOR, Fabrication Sites, and its Subcontractors and Vendors will submit TQs. Subcontractors / Vendors initiated requests shall be submitted via CONTRACTOR who will screen requests and forward justified queries to COMPANY. All Technical Queries will be documented in accordance with project requirements.
The TQ shall not be used for any Specification Deviation Request / Contractor Concession Request/ Request for Information. TQ will be typically initiated from CONTRACTOR Engineering team and will be addressed to COMPANY Engineering team.
Company No._Rev. COMP2-SPM-PE-PRC-00005_B
11 of 19
NFPS Offshore Compression Complexes Project COMP2 TECHNICAL QUERY PROCEDURE
6.2 TQ Workflow Diagram between CONTRACTOR and COMPANY
Company No._Rev. COMP2-SPM-PE-PRC-00005_B
12 of 19
NFPS Offshore Compression Complexes Project COMP2 TECHNICAL QUERY PROCEDURE
7 RESPONSIBILITY
7.1 Lead Discipline Engineer responsibility
• Verifying the content (including impacts) of the query before the query is submitted to the
• •
EM/TM. The technical accuracy and comprehension of the Technical Query Content For Greenfield facilities designed by Subcontractor, both the Leads from Subcontractor and Contractor jointly check and sign off the TQ prior to submission for Approval.
7.2 Engineering Manager/Technical Manager responsibility
• Verifying and validating the impacts of the QUERIES •
Initial approval of the QUERIES prior to submittal to COMPANY.
7.3 Document Controller responsibility
• Ensuring that the templates used for QUERIES is correct • Logging, tracking of all TQ and Maintaining the TQ register updated till the final closure • Ensuring that CONTRACTOR’S Authorized Representatives are provided with the applicable
Company replied QUERIES for implementation, verification, and closeout
• Ensuring the relevant correspondence and that the Distribution List (electronic or paper) is
maintained properly.
7.4 Project Manager responsibility
• Validation and signature of the QUERIES with major impacts before their official issuance to
COMPANY
7.5 COMPANY responsibility
• Reviewing and replying of TQ within the due time.
8 TQ REVIEW AND APPROVAL AUTHORITY
Type / Origin
Prepared by
Checked by
Technical Query
Vendor / Subcontractor / Contractor -
EC Senior / PSL
EC Specialist
(Note1)
Approved by
EM/TM
Table 8.1 :
TQ Review and Approval Authority
Note 1: For TQ initiated for Greenfield topsides scope will be jointly checked & signed by RW & CONTRACTOR Leads
9 TECHNICAL QUERY
The following definitions of QUERIES are considered:
Technical Query to COMPANY consist of:
• Request for clarification of COMPANY technical specification or another contractual document
Company No._Rev. COMP2-SPM-PE-PRC-00005_B
13 of 19
NFPS Offshore Compression Complexes Project COMP2 TECHNICAL QUERY PROCEDURE
• Request for resolution of a conflict between two or more COMPANY technical specifications
or other contractual documents,
• Request for clarification of conflicts between comments on two or more Project documents, • Request for additional technical information needed to perform the WORK. • Request for Clarification or additional information from supplier • Request addressing the nature of certain aspects of the work to be performed on a particular
site.
Originator shall provide detailed explanations and justifications for all Technical Queries, include all references, drawings, correspondences, etc. to support the TQ request and complete all parts of the TQ form. All initiated Technical Queries shall be endorsed by Engineering Subcontractor (related scope) prior to submittal to COMPANY.
9.1 TQ Initiation by CONTRACTOR
TQ will be raised by appropriate Engineering discipline (TQ Originator) on the TQ template form provided in Appendix 1. The TQ template CONTRACTOR section shall be duly filled and correctly implemented by CONTRACTOR in order to enable COMPANY to review the query and take decision and respond.
Potential impacts shall be preliminary evaluated and required reference documents shall be attached to the TQ.
9.2 TQ Initiated by Vendor
TQ will be raised by Vendor (TQ Originator) on the TQ template form provided in Appendix 1. The TQ template CONTRACTOR section shall be duly filled and correctly implemented by CONTRACTOR in order to enable COMPANY to review the query and take decision and respond. If vendor follow different TQ format, while issuing to COMPANY, vendor still have to use the Appendix – 1 template and formalize the TQ completing the TQ as Originator. Contractor shall complete the TQ and issue formally to COMPANY.
Potential impacts shall be preliminary evaluated and required reference documents shall be attached to the TQ.
All TQ shall be logged in a specific register where the query status is recorded. CONTRACTOR is responsible of this single register and of the transmission of the QUERIES to the COMPANY via Transmittal.
All TQ shall be logged in a specific register where the query status is recorded. CONTRACTOR is responsible of this single register and of the transmission of the QUERIES to the COMPANY via Transmittal.
When COMPANY response to a query is received, the DC will update the query Register and dispatch the response to the Author, Checker, and all Managers referred to within the query and the Distribution List. It is then evaluated by the Author who will define the necessary actions.
Each received query response is reviewed and a decision is made on the following basis:
•
•
Immediate implementation: if the query response is clear and complete and does not induce any impact. To revise the query: if the response is unclear and/or incomplete and/or is not possible to be implemented. The Author is responsible for revision of the query. Revised QUERIES are issued in the same manner as described above for the initial query.
• Advise his management line of reporting: if the Author believes that query response represents or might represents a Change to a Contract requirement, he will inform the Engineering Manager/Technical Manager who will approach the Contract Administrator and the Project Manager
Company No._Rev. COMP2-SPM-PE-PRC-00005_B
14 of 19
NFPS Offshore Compression Complexes Project COMP2 TECHNICAL QUERY PROCEDURE
9.3 TQ Approval within CONTRACTOR Organization
The respective CONTRACTOR Engineering Manager (EM)/Technical Manager (TM)/Site Engineering Manager is responsible for:
• Assessment of the necessity to issue the TQ • Evaluation that the TQ is complete, understandable, and required documents have been
attached.
• Verification of the potential impacts indicated on the TQ • Verification that alternatives, if any, have been considered. • Assessment if any other discipline or cross function interface is required • Authorization of the TQ
Engineering / Technical Manager is responsible to approve the TQ before sending to Company.
9.4 TQ Transmittal to COMPANY
After CONTRACTOR approval and sign-off the TQ is sent to DC for official issue to COMPANY through transmittal. Any correspondence of TQ will be done through transmittal.
9.5 TQ Response by COMPANY
If COMPANY considers that information provided in the TQ is not sufficient, the TQ is returned to the Originator with request for more information, otherwise, COMPANY replies the TQ by completing COMPANY section of TQ template within 15 working days.
COMPANY TQ response is received from COMPANY DC to CONTRACTOR DC and distributed by CONTRACTOR DC to Originator Engineering disciplines, EM, TM and PM.
EM/TM defines, if the TQ response should be distributed to other CONTRACTOR disciplines or functions. CONTRACTOR EM/TM should consult with COMPANY Engineering Manager on any TQ revision to be issued.
9.6 TQ Review and Implementation
Once COMPANY has given the response on the TQ, it has to be distribuited to originating discipline.
In case COMPANY TQ response is not considered by CONTRACTOR to be clear or fully resolving the query, a meeting will be arranged in order to have a verbal clarification. If the response is not resolving, TQ can be reissued in further revisions (Rev. 1, Rev. 2, etc) by CONTRACTOR keeping the same TQ number complete with the previous questions and responses, for ease tracking.
The status of Technical Queries shall be reviewed and discussed in project engineering meetings
9.7 TQ Follow-Up
The response of a TQ can result in various outcomes actions such as:
• Enable the activities to proceed immediately • Need to revise a technical document to proceed with the activities • Need to raise a Concession Request or Deviation Request • Need to initiate a Design Change Notification if the TQ response constitutes a change to
Contract.
It is also EM/TM responsibility to monitor the status of open Technical Queries with COMPANY. Register and status of TQs shall be included in weekly meetings between COMPANY and CONTRACTOR with focus on open / overdue TQs awaiting COMPANY responses.
Company No._Rev. COMP2-SPM-PE-PRC-00005_B
15 of 19
NFPS Offshore Compression Complexes Project COMP2 TECHNICAL QUERY PROCEDURE
9.8 Technical Query Reporting, Tracking & Register
A Technical Query register shall be developed and maintained by CONTRACTOR for all TQs issued during Execution stage by CONTRACTOR DC and will be shared with COMPANY on a weekly basis. TQ register template to be used is in Appendix 2 for weekly and monthly reporting.
Company No._Rev. COMP2-SPM-PE-PRC-00005_B
16 of 19
NFPS Offshore Compression Complexes Project COMP2 TECHNICAL QUERY PROCEDURE
10 APPENDICES
Appendix 1: - Technical Query Form Appendix 2: - Technical Query Register
Company No._Rev. COMP2-SPM-PE-PRC-00005_B
17 of 19
NFPS Offshore Compression Complexes Project COMP2 TECHNICAL QUERY PROCEDURE
10.1 Appendix 1:- Technical Query Form
Company No._Rev. COMP2-SPM-PE-PRC-00005_B
18 of 19
NFPS Offshore Compression Complexes Project COMP2 TECHNICAL QUERY PROCEDURE
10.2 Appendix 2: - Technical Query Register
Company No._Rev. COMP2-SPM-PE-PRC-00005_B
19 of 19
Project: Q-21699 - Saipem COMP2 Folder: Information Management and Document Control