NFPS Offshore Compression Complexes Project COMP2
COMPANY Contract No.: LTC/C/NFP/5128/20
CONTRACTOR Project No.: 033734
Document Title
:
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
COMPANY Document No.
: COMP2-SPM-QM-SPC-00002
Saipem Document No.
: 033734-Z-Z-00-SPM-QA-S-10002
Discipline
: QUALITY MANAGEMENT
Document Type
: SPECIFICATION
Document Category/Class
: 1
Document Classification
:
INTERNAL
C
B
A
22-MAR-2023
Issued for Approval
21-FEB-2023
Issued for Review
15-DEC-2022
Issued for Review
Manoj Raut (QCMP)
Manoj Raut (QCMP)
Manoj Raut (QCMP)
Sergio Mezzotero (PQM)
Sergio Mezzotero (PQM)
Ennore Paoli (PD) Ennore Paoli (PD)
Sergio Mezzotero (PQM)
Ennore Paoli (PD)
REV.
DATE
DESCRIPTION OF REVISION
PREPARED BY
CHECKED BY
APPROVED BY
Saipem S.p.A.
COMP2-SPM-QM-PRC-00002_C
1 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
REVISION HISTORY
Revision
Date of Revision
Revision Description
A1
A
B
C
22-NOV-2022
15-DEC-2022
21-FEB-2023
22-MAR-2023
Issued for Inter-Discipline Check
Issued for Review
Issued for Review
Issued for Approval
HOLDS LIST
Hold No
Hold Description
COMP2-SPM-QM-SPC-00002_C
2 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
TABLE OF CONTENTS
1
2
3
4
5
6
INTRODUCTION …5
1.1 PROJECT OBJECTIVE …5 1.2 PROJECT SCOPE …5
DEFINITIONS AND ABBREVIATIONS …7
2.1 DEFINITIONS …7 2.2 ABBREVIATIONS …9
REFERENCE, RULES, CODES AND STANDARDS … 11
3.1 COMPANY DOCUMENTS … 11 3.2 PROJECT DOCUMENTS… 11 3.3 INDUSTRY STANDARDS … 12 3.4 ORDER OF PRECEDENCE … 12
COMPANY AND EPC CONTRACTOR’S LESSONS LEARNED PURPOSE … 12
AREA OF APPLICATION … 12
RESPONSIBILITIES … 13
6.1 PROJECT MANAGER (PM) … 13 6.2 PROJECT MATERIAL MANAGER (PMM) … 13 6.3 PROJECT QUALITY MANAGER (PQM) … 13 6.4 QUALITY CONTROL MANAGER PROCUREMENT(QCMP) … 14 6.5 PROJECT SPECIALIST LEADER (PSL) … 14
7
QUALITY ASSURANCE & QUALITY CONTROL REQUIREMENTS … 14
7.1 GENERAL PRINCIPLES … 14 7.2 QUALITY MANAGEMENT SYSTEM (QMS) … 15 7.3 DOCUMENTATION MANAGEMENT … 17 7.3.1 CONTRACTUAL DOCUMENTATION … 17 7.3.2 DOCUMENT PROGRESS REGISTER … 18 7.3.3 THIRD PARTY APPROVAL … 18 7.3.4 RESOURCES MANAGEMENT … 18 7.3.5 PERSONNEL QUALIFICATION … 18 7.3.6 INSPECTION RELEASE NOTE (IRN) … 20 7.3.7 TRAINING & INDUCTION … 20 7.3.8 DOCUMENTS TO BE SUBMITTED BY SUPPLIER’S … 20 7.3.9 PROJECT QUALITY PLAN (PQP) … 21 CONTRACTOR QUALITY AUDITS … 22 7.3.10 SUPPLIER QUALITY SURVEILLANCES AND AUDITS … 23 7.3.11 QA/QC MEETINGS … 23 7.3.12 INSPECTION AT EX-STOCK SUPPLIER … 24 7.3.13 NONCONFORMITY MANAGEMENT … 24 7.3.14 SUPPLIER DEVIATION AND CONCESSION REQUESTS … 26 7.3.15 PRE-INSPECTION MEETING (PIM) … 28 7.3.16 MANUFACTURING RECORD BOOK (MRB) … 28 7.3.17
7.3.17.1 GENERAL … 28 7.3.17.2 MRB COMPILATION … 28 7.3.17.3 MRB FORMAT … 29 7.3.17.4 MRB SUBMISSION … 30 7.3.17.5 MRB INDEX (MINIMUM GUIDELINES) … 31 7.4 QUALITY CONTROL PLANNING … 35 7.4.1 INSPECTION AND TEST PLAN (ITP) … 35 7.4.2 INSPECTION LEVEL ASSIGNMENT … 35
COMP2-SPM-QM-SPC-00002_C
3 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
7.4.3 TEST REPORTS (CERTIFICATES) … 36 7.4.4 PURCHASE ORDERS WITH NO NEED OF WITNESS INSPECTIONS (REVIEW ONLY) … 37 7.4.5 CONTROL OF MANUFACTURING PROCESS … 37 7.4.6 SUPPLIER PERFORMANCE VERIFICATION BY CONTRACTOR… 38 7.4.7 INSPECTION AND TESTING … 38 7.4.8 SPECIAL PROCESSES … 39 7.4.9 MATERIALS CERTIFICATION, IDENTIFICATION & TRACEABILITY … 39 MATERIAL & EQUIPMENT MANAGEMENT AND CONTROL … 40 7.4.10 CONTROL OF MONITORING AND MEASURING DEVICES … 42 7.4.11 QUALITY SURVEILLANCR BY SUPPLIER DURING MANUFACTURING ACTIVITIES … 43 7.4.12
8
ANNEX … 44
8.1 NON-CONFORMITY REPORT SAMPLE (MINIMUM REQUIREMENT) … 44 8.2 PUNCH LIST FORM SAMPLE (MINIMUM REQUIREMENT) … 46 8.3 ITP TYPICAL FORMAT FORM SAMPLE (MINIMUM REQUIREMENT) … 47 8.4 MDR INDEX PREPARATION SAMPLE (MINIMUM REQUIREMENT) … 48 8.5 VENDOR DOCUMENT REGISTER (VDR) SAMPLE (MINIMUM REQUIREMENT) … 49
COMP2-SPM-QM-SPC-00002_C
4 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
1
INTRODUCTION
The North Field is the world’s largest natural gas field and accounts for nearly all of the state of Qatar’s gas production. The reservoir pressure in the North Field has been declining due to continuous production since the early 1990s. The principal objective of the NFPS Project is to sustain the plateau from existing QG South Operation (RL Dry Gas, RGE Wet gas) and existing QG North Operation (QG1 & QG2) production areas by implementing an integrated and optimum investment program consisting of subsurface development, pressure drop reduction steps and compression. Refer to the figure below for a schematic of the North Field.
Qatargas Operating Company Limited is leading the development of the North Field Production Sustainability (NFPS) Project.
1.1 Project Objective
The objective of this Project includes:
• Achieve standards of global excellence in Safety, Health, Environment, Security and Quality
performance.
• Sustain the Qatargas North Field Production Plateau by installing new Compression Complex facilities CP6S & CP7S in QG south with integration to the existing facilities under Investment #3 program.
• Facility development shall be safe, high quality, reliable, maintainable, accessible, operable,
and efficient throughout their required life.
1.2 Project Scope
The Project Scope includes detailed engineering, procurement, construction, transportation & installation, hook-up and commissioning, tie-in to EXISTING FACILITIES and provide support for start-up activities of the following facilities and provisions for future development. The WORK shall conform to the specified regulations, codes, specifications and standards, achieves the specified performance, and is safe and fit
purpose in all respects.
for
Offshore
‐
‐
CP6S and CP7S Compression Complexes that are part of QG-S RGE facilities as follows:
• CP6S Compression Complex • Compression Platform CP6S, Living Quarters LQ6S, Flare FL6S • Bridges BR6S-2, BR6S-3, BR6S-4, BR6S-5 • Bridge linked Tie-in to RP6S
Production from existing wellheads (WHP6S & WHP10S) and new wellhead (WHP14S) are routed via riser platform RP6S to compression platform CP6S to boost pressure and export to onshore via two export lines through the existing WHP6S pipeline and a new 38” carbon steel looping trunkline from RP6S (installed by EPCOL). CP6S is bridge-linked to RP6S.
• CP7S Compression Complex • Compression Platform CP7S, Living Quarters LQ7S, Flare FL7S
COMP2-SPM-QM-SPC-00002_C 5 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
• Bridges BR7S-2, BR7S-3, BR7S-4, BR7S-5 • Bridge linked Tie-in to RP7S
CP7S shall receive production from existing wellheads (WHP5S & WHP7S) and new wellhead (WHP13S). There is only one export line for CP7S through the existing export pipeline from WHP7S. CP7S is bridge-linked to RP7S.
RGA Complex Destressing
Migration of the Electrical power source, Telecoms, Instrumentation and Control systems from WHPs and RHPs hosted by RGA to the respective Compression Complexes listed below:
• WHP6S, WHP10S, WHP14S, RP6S and RP10S to CP6S Compression Complex • WHP5S, WHP7S, WHP13S and RP7S to CP7S Compression Complex
Destressing of Telecoms, Instrumentation and Control system in RGA Complex Control Room, which would include decommissioning and removal of telecom system devices and equipment that would no longer be required post migration and destressing activity.
Onshore
An Onshore Collaborative Center (OCC) will be built under EPC-9, which will enable onshore based engineering teams to conduct full engineering surveillance of all the offshore facilities. The OCC Building will be located in Ras Laffan Industrial City (RLIC) within the Qatar Gas South Plot. MICC & Telecommunication, ELICS related scope will be performed in the OCC building.
Figure 1.2.1: NFPS Compression Project COMP2 Scope
COMP2-SPM-QM-SPC-00002_C 6 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
2 DEFINITIONS AND ABBREVIATIONS
2.1 DEFINITIONS
Definition
Description
COMPANY
Qatargas Operating Company Limited
CONTRACTOR
Saipem S.p.A.
CONTRACT
DELIVERABLES
GOODS
A voluntary, deliberate, and legally binding agreement between two or more competent parties.
All products (drawings, equipment, services) which shall be submitted by CONTRACTOR to COMPANY at times specified in the contract. Material, component, device, functional unit, machine, equipment, subsystem or system manufactured by a Vendor and required to carry out Saipem Group activities.
COMP2-SPM-QM-SPC-00002_C 7 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
INSPECTION AND TEST PLAN
Inspection Release Note
Inspection Report
Material Certificates
MAY
Non-Conformity Report (NCR)
Notification of Tested Material
Packing List
PROJECT
Project Material Manager
Punch List
Purchase Order (P.O)
Quality Control Manager Procurement
The list of inspection activities provided by Vendors, completed with reference documents, acceptance criteria, verification documents, inspection frequency and witnessing parties Document identifying Goods that have passed the inspection and that meet the purchase order requirements (drawings and specifications). The document issued by inspector which describes the surveillance activities performed by the inspector; it shall be issued after each examination, inspection, or test visit. Documentation and certificates intermediate and final Specification, QG and International Standard
issued by the Vendors after ITP,
tests, as required by approved
Verbal form used to indicate a course of action permissible within the limits of the document.
Document prepared and issued by the Inspector showing the non- conformities observed, the possible solutions and the clearance of the corrective actions. Upon acceptance of material and receipt of IRN from Inspector, Contractor shall issue Notification of tested material acceptance to vendor for further shipment. Document containing all the information related to the shipment (lot numbers, weight, size, marking, packaging, description of items, etc.). Engineering, Procurement, Construction, Installation (EPCI) for NFPS OFFSHORE COMPRESSION COMPLEXES PROJECT - COMP2. Person within a project responsible for planning and coordinating post order management for materials up to their delivery to the site. The Project Material Manager also ensures the integration of these activities with project objectives, liaising with the Project Manager, the Procurement, Engineering, Management and Construction functions and their representatives on the project, as well as with the Client. Document issued by the Inspector during inspections in order to track the missing activities that need to be completed on the Material prior to shipment or accepted by the CONTRACTOR to be completed at Site with open NCR Document issued by the Procurement Department for the purchase relevant of materials and equipment. This document and attachments, defines the parties’ mutual obligations of CONTRACTOR and Vendors. Person within a project responsible for Purchased Materials Quality Control activities.
SHALL
Verbal form used to indicate requirements strictly to be followed to conform to the document.
COMP2-SPM-QM-SPC-00002_C 8 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
SHOULD
Verbal form used to indicate that among several possibilities one is recommended as particularly suitable, without mentioning or excluding others, or that a certain course of action is preferred but not necessarily required.
Technical Documents
Drawings, calculations, specifications, procedures, technical reports, etc.
TIER-SUPPLIER
A party who is providing subcontracted services specified and ordered by SUPPLIER.
SUPPLY / WORK
The provision of goods / the performance of services, or both.
SUB-SUPPLIER/ SUB-VENDOR
SUPPLIER/ VENDOR
A person, company, or group that is the recipient of an “indirect” purchase order who sells materials and equipment that are manufactured, fabricated, assembled, and / or packaged for a SUPPLIER. A person, company, or group that is the recipient of a “direct” purchase order who sells materials and equipment that are manufactured, fabricated, assembled, and / or packaged for COMPANY through CONTRACTOR. In this context, a “direct” order is one issued to a Supplier by a CONTRACTOR or COMPANY; an “indirect” order is one issued by a Supplier (recipient of a direct order) for materials and equipment, fabricated components or sub-assemblies to another Supplier.
2.2 ABBREVIATIONS
Code
Definition
QG
SPM
FTC
IRN
ITP
KOM
MR
MRB
NCR
QATARGAS
SAIPEM S.p.A
Final Test Certificate
Inspection Release Note
Inspection Test Plan
Kick Off Meeting
Material Requisition
Manufacturing Record Book
Non-Conformity Report
COMP2-SPM-QM-SPC-00002_C 9 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
NDT
NTM
PM
PMI
PMM
PMT
PCR
PD
PIM
PM
PMC
PO
PQM
PR
PSL
Non-Destructive Testing
Notification of Tested Material
Project Manager
Positive Material Identification
Project Material Manager
Project Management Team
Procurement Criticality Rating
Project Director
Pre-Inspection Meeting
Project Manager
Project Material Classification
Purchase Order
Project Quality Manager
Purchase Request
Project Specialist Leader
QCMP
Quality Control Manager - Procurement
RFQ
QA
QC
QMS
SAP
SML
TM
WPS
PQR
Request for Quotation
Quality Assurance
Quality Control
Quality Management System
Integrated company software system
Supply Management Leads
Technical Manager
Welding Procedure Specification
Procedure Qualification Record
COMP2-SPM-QM-SPC-00002_C 10 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
3 REFERENCE, RULES, CODES AND STANDARDS
3.1 COMPANY DOCUMENTS
Ref
Document Number
Title
/1/
/2/
/3/
/4/
/5/
/6/
/7/
/8/
/9/
/10/
/11/
/12/
/13/
/14/
/15/
Exhibit 5 FINAL incl. Appendices PROJECT Instructions
Exhibit 6 FINAL
Scope of Work
200-20-CC-PRC-00094
Specification for preservation
200-20-QM-PRC-00098
Quality Assurance Requirements for Suppliers
200-20-QM-PRC-00099
Quality Control Requirements for Suppliers
COMP-QG-QM-PLN-00002
Procurement Criticality Matrix
COMP-QG-QM-PLN-00003
Procurement Quality Surveillance Plan
PRM-PJM-PRC-004
Majors Project Quality Plan
OFGN-CE-SPC-00001
Specification for Painting Production Facilities (Offshore)
TCH-AIG-PRC-017
Protective Coating
TCH-AIG-PRC-019
Pressure Testing Procedure
TCH-AIG-SI-002_00
Amendments to Pressure Testing Procedure
TCH-AIG-PRC-021
Control of Welding
PRJ-000-PRC-008
Lessons Learned
TCH-AIG-PRC-055
Risk Based Inspections and Strategies
/16/
TCH-AIG-PRC-089
QA/QC Requirements for material receiving inspection – Static equipment and components Procedure
/17/
/18/
TCH-AIG-PRC-103
Conventional Non-Destructive Testing
PRJ-PJL-PRC-006
Project Information Handover (PIH)
3.2 PROJECT DOCUMENTS
Ref
Document Number
Title
/1/
/2/
/3/
/4/
/5/
/6/
COMP2-SPM-QM-PLN-00001
PROJECT QUALITY PLAN
COMP2-SPM-QM-PRC-00001
COMP2-SPM-QM-PRC-00002
COMP2-SPM-QM-PRC-00003
COMP2-SPM-QM-PRC-00005
COMP2-SPM-PE-PRC-00006
LESSON LEARNED PROCEDURE PROJECT NON-CONFORMITY MANAGEMENT PROCEDURE PROJECT QUALITY AUDITS PROCEDURE
SOURCE INSPECTION PROCEDURE VENDOR DOCUMENT MANAGEMENT PROCEDURE
COMP2-SPM-QM-SPC-00002_C 11 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
3.3
INDUSTRY STANDARDS
Ref
Document Number
Title
/1/
/2/
/3/
/4/
/5/
/6/
ISO 9000:2015
“Quality Management Systems - Fundamentals and Vocabulary”
ISO 9001:2015
“Quality Management Systems – Requirements”
ISO 10005:2018
ISO 17025:2017
ISO 10006:2017
ISO 10005:2005
Quality Management Systems - Guidelines for Quality Plans. General Requirements for the competence of testing and calibration laboratories Quality Management Systems – Guidelines for Quality Management in Projects “Quality Management – Guidelines for Quality Plans”
3.4 ORDER OF PRECEDENCE
The Applicable Codes, Standards and Specification or equivalent standards which are referenced within the document shall be considered as part of this specification. Conflict among applicable specification and / or codes shall be brought to the attention of the COMPANY for resolution. COMPANY decision shall be final and shall be implemented. The latest editions of codes and specification effective as on date of contract shall be followed.
In general, the order of precedence shall be followed:
a) Qatari Governmental and Regulatory Requirements
b) COMPANY Policies and Procedures
c) Project Specifications
d) Industry Codes and Standards
4 COMPANY and EPC CONTRACTOR’S lessons learned PURPOSE
This document defines the Quality Control requirements that the VENDOR/ SUPPLIER must comply to ensure that the level of Quality specified for the Scope of Supply will be achieved. It also forms part of VENDOR’s Project’s Quality Plan.
5 AREA OF APPLICATION
This document applies to all Quality Requirements for VENDOR/SUPPLIER activities to be conducted during this project execution and shall be updated accordingly to project needs if necessary.
This document shall be considered as an integral part of the PO/ MR along with documents herewith referenced in Section 3.
All requirements prescribed within this document shall be flowed down the supply chain by the SUPPLIER to their SUB-SUPPLIERs for on the base of their relevant Scope of Supply.
COMP2-SPM-QM-SPC-00002_C 12 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
6 RESPONSIBILITIES
SUPPLIER is responsible for the implementation and management of the work process for Quality Assurance and Quality Control relevant to his work scope on the Project and to apply the Quality Requirements stated in this document and in the COMPANY/Project documents referenced in the Purchase Order between CONTRACTOR and SUPPLIER and in the Project Documentation.
It is supplier responsibility to control and supervise their sub-suppliers that Sub-supplier comply with the quality requirements. CONTRACTOR to ensure and supervise that SUPPLIER(s) comply with the Quality requirements expressed in this document.
6.1 PROJECT MANAGER (PM)
He is responsible for the following:
- Coordinate the engineering and construction activities liaising with relevant disciplines
mangers.
- Support the Project Director in the coordination of the procurement activities.
- Manage subcontracts.
Involved in Interface management both external and internal.
6.2 PROJECT MATERIAL MANAGER (PMM)
Reporting to Supply Chain Manager,
He is responsible for the following:
- Planning and coordinating post order management for materials up to their delivery to the
site.
-
Ensures the integration of these activities with project objectives, liaising with the Project Manager, Procurement, Engineering, Management, Construction functions and their representatives on the project, as well as with the Client.
-
Ensures delivery of project material to site as per project schedule.
6.3 PROJECT QUALITY MANAGER (PQM)
Reporting to Project Director,
He is responsible for the following:
- The Quality Manager is responsible for overseeing of all quality-related activities of the
CONTRACTOR in particular, his responsibilities include the following:
- Plan and Implement Project Quality Management System activities within the project.
- Plan and ensure the project quality Control activities implementation.
- Act as focal point for quality related matters within the project.
COMP2-SPM-QM-SPC-00002_C 13 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
6.4 QUALITY CONTROL MANAGER PROCUREMENT(QCMP)
Reporting to Project Quality Manager,
He is responsible for the following:
- Manage and coordinate with all Procurement QC Supervisors assigned to the project.
- Review and assign Inspection level as per Procurement Criticality rating for materials.
- Review and update PCR during Monthly meeting and liaise with COMPANY for risk
assessment findings.
- Communicate / coordinate with QG Representative for all procurement quality related issues
and suggestions for improvement.
-
Coordinate with project personnel and vendors / manufacturer for discussion and resolution of non-compliances arising with vendors and manufacturers Communicate inspection results with QG and also recommend corrective actions, if any
-
Shall ensure approval of any repair procedure from COMPANY prior to commencement of
repair work.
- Shall ensure any disposition to “USE-AS-IS” is approved by COMPANY and documented on
a concession request.
6.5 PROJECT SPECIALIST LEADER (PSL)
- Reporting to Technical Manager
- He is responsible for the following:
- Manage Engineering Project team and technical documentation.
- Ensure timely issue and approval of MR and relevant technical procedures / plans,
Specifications, Drawings etc. Issue of correct PRs & TBEs.
- Ensure all technical, quality & Inspection requirements are included in MR/PR/PO.
- Suggest and approve Corrective actions for the non-compliances, if any.
7 QUALITY ASSURANCE & QUALITY CONTROL REQUIREMENTS
7.1 GENERAL PRINCIPLES
This document forms an integral part of the Request for Quotation (RFQ) and the Purchase Order (PO).
The execution by VENDOR / SUPPLIER Quality Control shall be in accordance with, but not limited to, the requirements and instructions of all applicable Company requirements, International Codes and Standards, and project specifications mentioned in the purchase order including requirements specified under the clause 8 of Exhibit 5
In case the requirements for Quality and / or any other requirement referred to in this document are unclear, with respect to the specific Scope of Work, the SUPPLIER shall obtain all relevant clarifications and confirmations from CONTRACTOR.
COMP2-SPM-QM-SPC-00002_C 14 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
For any issue arising after that term, SUPPLIER shall issue a technical query / deviation / concession request (or any other specific instrument defined by the Purchase Order (PO) that CONTRACTOR / COMPANY or both, shall REVIEW for acceptance / rejection purposes.
Relevant Scope of Work shall clarify the technical details. Relevant sections of the actual specification outline the minimum required documentation that SUPPLIER is supposed to submit to CONTRACTOR to obtain relevant APPROVAL from a Quality standpoint.
SUPPLIER shall ensure the availability of resources needed for the realization of the Works, irrespectively from the fabrication process to be implemented.
SUPPLIER shall provide and maintain infrastructure needed to achieve conformity to Works requirements and shall maintain premises in a state of order consistent with the Works realization processes needs.
At all times, the SUPPLIER shall be able to prove conformance with contractual documentation and QA/QC Requirements embedded in this specification.
When unacceptable defects are found, SUPPLIER shall conduct all necessary remedial actions or repairs and perform inspections, examinations and tests until conformity is obtained.
7.2 QUALITY MANAGEMENT SYSTEM (QMS)
The SUPPLIER shall be responsible for establishing and implementing their own Quality Management System (QMS) conforming to the requirements of ISO 9001:2015 and the Purchase Order (PO) signed with the CONTRACTOR.
SUPPLIER is responsible for implementing and maintaining the Quality Management System up to the completion of scope of work for this project.
If the SUPPLIER’s QMS is certified by a 3rd Party Certification Company, the SUPPLIER shall provide a copy of the valid (i.e., not expired) ISO 9001 Certification issued by any recognized 3rd Party Certification Bodies. The Scope of ISO 9001 certification should cover the manufacturing, design and development activities (where applicable) for the Project.
If the SUPPLIER’s QMS is not certified by a 3rd Party Certification Company, the SUPPLIER shall provide a matrix comparison of their QMS documentations to all ISO 9001 requirements for confirmation by CONTRACTOR; if any of the ISO 9001 requirements needs to be waived, specific concession shall be requested to CONTRACTOR. This waiver does not apply to the SUPPLIER who participates in the Design and Development of the items and relevant Scope of Work.
If any part of the Purchase Order (PO) is sub-contracted, the SUB-SUPPLIERs shall also comply with the requirements of this document and any other specific contract requirements. The SUPPLIER, however, shall remain accountable for the QMS implemented to meet all the Purchase Order (PO) requirements. This also includes testing of the items to be performed by the accredited ISO 17025 3rd Party laboratories by National Accreditation Bodies.
The SUPPLIER shall remain responsible for the delivery of the scope of work to the prescribed
COMP2-SPM-QM-SPC-00002_C 15 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
requirements.
The Suppliers’ Quality Management System shall include all control / inspection / testing personnel and equipment required to assure conformance of the requirements and governing specifications.
The SUPPLIER shall appoint an adequate number of competent Quality Assurance, Inspection (Quality Control) and Verification Personnel to ensure adequate Quality Management during the execution and delivery of the work scope.
The CONTRACTOR reserves the right to audit SUPPLIERs quality management system and production management system at any time throughout the duration of the work, to assess the compliance of the product against specified requirements. Such rights are to be extended to SUB- SUPPLIERs as required.
The SUPPLIER documented QMS shall be adapted to the contractual scope of work and requirement to ensure full compliance with specific project quality procedures, expectations and needs including but not limited to:
-
Planning of product realization including details of the organization structure, qualifications, roles and responsibilities, lines of authority, communication and interfaces of management and staff personnel implementing QA/QC activities.
-
Document control procedures to control status and ensure that only the latest approved revision of documents is available for the work, including applicable codes and standards.
-
Procedure(s) to control all changes or modifications to design documents and as built
documentation.
- Procedure(s)
for verification of Fabrication purchased material
including Material APPROVAL, in-process inspection, surveillance, release and quality auditing of SUB- SUPPLIERs s as applicable to the contractual scope.
-
Procedure(s) for material receiving inspections, for the control of handling, storage and preservation of material and equipment including those supplied by CONTRACTOR / Company, as applicable.
-
Procedure(s) for identification and traceability of material and equipment from receiving
through installation and handover.
- Procedure(s) for special processes qualification. This shall include specific qualification and
tests for any special process and related personnel.
- Procedure(s) for controlling the production and the implementation of Inspection and Test
Plans, including the control of manufacturing and special processes.
- Method(s) for tracking and maintaining status of field/shop Inspections.
- Method(s) for controlling calibration of monitoring and measuring devices.
- Method(s) for maintenance of production tools, such as: welding equipment, cutting
machines, etc.
- Procedure(s) and plan for internal audits and external audits of sub-Suppliers.
- Procedure(s) for identification, reporting, tracking and resolution of non-conformances at the
workshop.
- Procedure(s) for identifying, performing, and documenting training in the field/ shop.
- Procedure(s) for verifying compliance and quality records to support shop tested equipment
/ Items including & up to mechanical completion of system / plant as required.
COMP2-SPM-QM-SPC-00002_C 16 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
7.3 DOCUMENTATION MANAGEMENT
QMS documentation shall be available, suitable for use, where and when it is needed, it is protected (e.g., from the loss of confidentiality, improper use, loss of integrity) at the premises where the scope of work is performed.
The SUPPLIER shall maintain the latest revision of the relevant Purchase Order (PO) Documents, Drawings, Specifications, Procedures, Standards and Work Instruction and any relevant medium whether in hardcopy and softcopy at the location where the Scope of work is being conducted.
A documented information control procedure shall be available that address the following activities:
- Distribution, access, retrieval, and use.
- Storage and preservation, including preservation of legibility.
- Control of changes (e.g., revision control).
- Retention and disposition.
External origin documented information e.g., ISO, API, ASME and ASTM standards as determined by the SUPPLIER to be necessary for the planning and operation of the quality management system shall be identified as appropriate and be controlled.
Documented information retained as evidence of conformity to meet Scope of Work shall be protected from unintended alterations.
Relevant CONTRACTOR and / or COMPANY related Project Documentation shall be maintained properly filed, updated, identified and traceable.
CONTRACTOR and COMPANY representatives shall have free of access of documentation this includes by providing the full copies of relevant documentation at any stage.
7.3.1 CONTRACTUAL DOCUMENTATION
SUPPLIER shall ensure that all contractual and technical documents as referenced into the relevant Contract, including the quality-related documentation indicated in this document are available prior to execution.
SUPPLIER shall also check upon receipt all applicable contractual documents and drawings, notifying CONTRACTOR of any discrepancy or missing information prior to the commencement of the Scope of work. SUPPLIER shall be responsible to inform CONTRACTOR about any anomaly to obtain correct information on time, to avoid any impact on costs, schedule and final supply / work quality and performance.
The SUPPLIER shall ensure, prior to commencement of all manufacturing, purchase of bulk’s (including stockist material) and fabrication activities that a “PO Compliance Assessment” is conducted with the EPC CONTRACTOR at SUPPLIER premises to conform the alignment with PO requirements and COMPANY specifications.
COMP2-SPM-QM-SPC-00002_C 17 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
7.3.2 DOCUMENT PROGRESS REGISTER
VENDOR/SUPPLIER shall prepare a Vendor Document Register (VDR) showing the list of the documentation to be developed or applicable for the Supply.
In case no particular format is required by CONTRACTOR, such register shall contain as a minimum, for each record:
- Title of the document.
- CONTRACTOR identification code of the document (when contractually required).
- SUPPLIER identification code.
- Control and progress dates (issuing, APPROVAL, revision, submission to CONTRACTOR /
COMPANY / Third Parties and so forth).
- Revision status.
- Personnel entitled to prepare, verify, and approve deliverables.
- TN (transmittal IN / OUT).
Such register shall include also applicable SUB-SUPPLIERs documentation applicable for the Supply (e.g., procedures, work instructions, manuals, quality plans and Inspection Test Plan,).
This register shall be provided to CONTRACTOR as required by the Purchase Order (PO).
SUPPLIER should refer to the Document Control Specifications embedded in the Purchase Order (PO) awarded to SUPPLIER.
7.3.3 THIRD PARTY APPROVAL
In case supply documentation required the formal APPROVAL from a Third-Party Authority, SUPPLIER shall guarantee and give evidence of such APPROVAL upon CONTRACTOR request.
7.3.4 RESOURCES MANAGEMENT
The SUPPLIER shall provide the Overall Organization Chart including departmental Organization Chart and detailed documented roles, responsibilities and authorities for each personnel that shall be involved for the execution of the Supply with specific emphasis on area superintendent level and inter-discipline coordinators for each area.
SUPPLIER Organization Chart shall clearly indicate independent and dedicated Quality Assurance and Quality Control functions, including clear reference to their communication and reporting lines. Even though separated, Quality Control functions shall maintain communication line with production functions and shall maintain full authority and integrity with reference to quality-related matters.
7.3.5 PERSONNEL QUALIFICATION
All personnel appointed by the SUPPLIER to perform Work within the Purchase Order (PO) shall be suitably qualified and experienced to conduct the activities undertaken. They shall have previous experience on similar Work Scopes of an equivalent extent and be formally qualified in their relevant discipline. SUPPLIER shall provide detailed QA/QC organization chart to be updated at any change.
All the CV of Quality Assurance / Control personnel designated for the position in said chart &
COMP2-SPM-QM-SPC-00002_C 18 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
Inspectors shall be nominated and shall be submitted for APPROVAL to CONTRACTOR before starting of the work.
Personnel performing work affecting quality shall be familiar with QA/QC Documentations and with quality system procedures, working procedures, Inspections methods and related applicable acceptance criteria.
CONTRACTOR shall be the final authority for the determination of equivalency for all SUPPLIER qualifications, certifications, or experience of SUPPLIER QA/QC proposed personnel including their independent Third Party Inspectors.
SUPPLIER shall give the full rights and privilege to CONTRACTOR and / or COMPANY to REVIEW their relevant Personnel Qualifications (this includes SUB-SUPPLIERs Personnel Qualifications in case any part of the Supply or Scope of Supply being sub-contracted), in accordance with CONTRACTOR contractual and standard requirements as specified.
CONTRACTOR shall REVIEW such qualifications to ensure that compliance with relevant requirements is met. In case a qualification did not comply, CONTRACTOR has the right to ask SUPPLIER personnel replacement. It shall be then SUPPLIER responsibility to adhere and replace personnel that has not been accepted by CONTRACTOR.
The SUPPLIER shall have an independent Quality Control organization with sufficient resources to oversee the Works.
The SUPPLIER shall appoint sufficient Quality Assurance and Quality Control personnel as to ensure that the QMS, Quality Assurance and Quality Control / Inspections are conducted and maintained throughout the duration of the Purchase Order (PO), including those relevant to material or service furnished by its SUB-SUPPLIERs s.
QA/QC Team shall be provided with clerical personnel sufficient to accomplish a timely submittal of Inspection notifications, inspections status summary reports necessary to control completion of the work and to ensure the availability of the required documentation.
QA/QC Manager shall be on-site / workshop during all working hours and shall designate alternate approved individual to assume responsibilities during his temporary absence or when overtime work is being performed. Any leave / absence / rotation shall be timely communicated to Contractor.
The SUPPLIER’s Quality Assurance and Quality Control personnel shall:
- Be based at the location where the Supply is being executed.
- Not be involved into the execution process of the Works.
- Have no other duties or responsibilities unless prior APPROVAL in writing is granted by
CONTRACTOR.
Where elements of Quality Control are part of the responsibilities of workers involved into the execution process, the SUPPLIER shall identify independent verification requirements and provide adequate coverage.
The SUPPLIER is required to document, or to conduct, specifically requested qualifications of personnel performing special processes (e.g., welding, NDT), according to applicable related
COMP2-SPM-QM-SPC-00002_C 19 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
approved and recognized codes / standard / rules approved by CONTRACTOR / COMPANY. SUPPLIER shall furthermore verify / ensure the proper qualification of SUB-SUPPLIERs S personnel in charge of special processes and guarantee availability, accessibility and retrievability of relevant documentation / certificates during CONTRACTORs / COMPANY’s audit / inspection.
7.3.6
INSPECTION RELEASE NOTE (IRN)
Refer Contractor issued SOURCE INSPECTION PROCEDURE- COMP2-SPM-QM-PRC-00005 for the more details related to IRN.
7.3.7 TRAINING & INDUCTION
SUPPLIER shall develop and execute a training plan to assure that all SUPPLIER personnel assigned to the Project receive suitable induction and awareness training on project specific requirements, Quality Requirements, SUPPLIER’s Approved Quality Plan and Inspection Test Plans, processes and procedures associated with their role and responsibilities. Records of training shall be documented and available on request by CONTRACTOR.
SUPPLIER shall provide training to their workers in the bonding procedures used in fabrication of any special MATERIALS such as GRE/GRP spools, fittings and supports. Only personnel who have been trained and qualified by the pipe manufacturer shall fabricate and erect the GRE/GRP Spools.
7.3.8 DOCUMENTS TO BE SUBMITTED BY SUPPLIER’S
PCR
Inspection Level
Minimum set of Quality Documents to be submitted with the Bid:
I, II
1, 1+, 2
- Drafted Project Quality Plan including ISO 9001 Certification or API/ASME certification as applicable including Organization Chart showing QA/QC job roles & responsibilities proposed for the Supply, Personnel’s qualifications, Quality Audit Program, QA/QC procedures for the scope of supply
- Inspection Test Plan
Minimum set of Quality Documents to be submitted for CONTRACTOR REVIEW and APPROVAL within 15 calendar days after the Purchase Order (PO) or other agreed date if any:
- Specific Project Quality Plan including ISO 9001 Certification or API/ASME certification as applicable including Organization Chart showing QA/QC job roles & responsibilities proposed for the Supply, Personnel’s qualifications, Quality Audit Program, QA/QC procedures for the scope of supply
- Inspection Test Plan
III
IV
IV
3
4
-
ISO 9001 certification or API/ASME certification as applicable including organizational chart
-
Inspection Test Plan
-
ISO 9001 certification or API/ASME certification as applicable including organizational chart
-
Inspection Test Plan
-
ISO 9001 certification or API/ASME certification as applicable.
-
Inspection Test Plan-(Case to case basis/Based on PCR Matrix)
-
ISO 9001 certification or API/ASME certification as applicable.
-
Inspection Test Plan-(Case to case basis/Based on PCR Matrix)
No Inspection
- ISO 9001 certification or API/ASME certification as applicable.
NIL
COMP2-SPM-QM-SPC-00002_C 20 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
Depending on the criticality of the Work, more documentation may be requested within the Purchase Order (PO).
Note- All requested documentation shall be in English language.
7.3.9 PROJECT QUALITY PLAN (PQP)
SUPPLIER shall develop and maintain an adequate PQP as to cover all the aspects of the Supply.
SUPPLIER shall consider the approved PQP as an integral part of the Contract and shall effectively demonstrate its execution through planned audits and REVIEWs. The PQP issued by SUPPLIER shall include (but not be limited to) the followings items:
a) Quality statement or Quality Policy signed by the manager empowered for the execution of
the Purchase Order (PO) or by the SUPPLIER’s top management.
b) Description of the project organization, including organization chart(s) with details on Quality organization, key function(s) appointed for the execution of the Purchase Order (PO), including the indication of subcontracts. c) Detailed Purchase Order (PO) REVIEW. d) List of the applicable Codes and Standards. e) List of applicable project contract requirements and technical reference documentation. f) Risk Assessment and Management related to the Scope of Supply or Work factors that may
affect the quality or the on-time delivery of the required product and/or services.
g) Contingency planning to mitigate the identified risks. h) Description of activities, responsibilities, and procedures, explaining how the Supply shall be
managed with respect to contractual and ISO 9001 requirements.
i) Description and oversight of outsourced processes. j)
Index of Quality-related documents pertinent to the Scope of Supply or Work, including (but not limited to) QA/QC and technical / operating procedures. k) List of Inspection and Test Plans (including SUB-SUPPLIERs). l) SUPPLIER’s Quality internal and external audit procedure and program for the Purchase
Order (PO).
m) Interfaces with COMPANY, CONTRACTOR, and SUB-SUPPLIERs as applicable, to ensure
that the Quality requirements identified for this Project are applied.
n) Document management system. o) Product non-conformities management system. p) Identification and traceability system (for materials and welding). q) Class or third-party requirements management system (if applicable). r) List of resulting Quality records. s) Performance indicators. t) Lessons learned management, particularly describing how they are fed into the system at
the beginning of the project.
COMP2-SPM-QM-SPC-00002_C 21 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
7.3.10 CONTRACTOR QUALITY AUDITS
At any time during project execution, CONTRACTOR shall have the right to perform or appoint a representative to conduct quality and technical compliance audits on SUPPLIER and involved TIER- SUB-SUPPLIERs QMS, Scope of Supply as deemed necessary.
Quality and/or technical compliance audits scope shall be relevant but not limited to:
SUPPLIER / SUB-SUPPLIERs implementation of the QMS (full or partial); Compliance to contractual quality requirements. Performance of inspections, examinations and testing as per approved project ITPs. Conformity of the Works or part thereof completed. REVIEW of the SUPPLIER / SUB-SUPPLIERs and QA/QC related documentation. Verification of NCR disposition and corrective action follow-up and close-out. Any other QA/QC verification as deemed necessary to provide confidence that SUPPLIER
is in conformance with all quality provisions.
The SUPPLIER shall provide unrestricted access and suitable assistance to representatives of COMPANY, CONTRACTOR or Third-Party auditors appointed by CONTRACTOR at any location where the Supply is being performed, to conduct audits of technical execution and quality.
This shall be guaranteed at any time before and during the Purchase Order (PO) execution and shall be valid also for SUB-SUPPLIERs.
CONTRACTOR shall give 5 working days’ notice to the SUPPLIER and / or TIER-SUPPLIERS/SUB- SUPPLIERs, of its intention to conduct a scheduled audit, giving at least details of:
Audit Scope. Terms of reference. Reference documents. CONTRACTOR personnel involved. Audit plan with anticipated times and audit durations etc.,
The SUPPLIER shall identify the nominated representatives and process owner(s) to be involved in the audit. If the availability of the nominated representative is compromised on the day of the audit, the SUPPLIER / SUB-SUPPLIERs shall provide a suitable alternative representative.
In case nominated SUPPLIER’s involved Process Owner/s shall not be in the position to attend a planned audit at the agreed date, the same organization shall need to identify a competent and aware substitute.
Only in case of major and valid reasons CONTRACTOR shall re-schedule their audit to comply with SUPPLIER’s request.
In case the Purchase Order (PO) provides that a Resident Inspector / Third Party Inspector (or a Team of Inspectors) is required to be present at the SUPPLIER’s premises, the latter shall provide adequate office facilities, safety inductions / training and communications facilities in this respect without any additional costs to CONTRACTOR.
If needed, audits may also be performed during the bidding phase, to confirm the adequacy of
COMP2-SPM-QM-SPC-00002_C 22 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
SUPPLIER’s QMS.
When CONTRACTOR identifies an audit non-conformity, SUPPLIER shall define and start to implement a corrective action program within 48 hours from detection, at SUPPLIER’s expense, to the satisfaction of CONTRACTOR and to be completed within the agreed close-out date.
COMPANY may participate to audits as Active Observers. COMPANY shall have the privilege to assess the effectiveness closure of any non-conformity issues.
7.3.11 SUPPLIER QUALITY SURVEILLANCES AND AUDITS
The extent SUPPLIER surveillance and audits shall be indicated in the SUPPLIER’s Project Quality Plan and approved by CONTRACTOR.
The SUPPLIER shall maintain a fully operational Project Auditing System in place, complete with Project Audit Program and implemented progressively during the Supply execution.
The SUPPLIERs shall develop a program for internal and external quality audit to be submitted to CONTRACTOR for APPROVAL.
The audit program shall include at least one audit for each work location discipline work and for each PMT department / process. Copies of audit and corrective actions reports shall be provided to CONTRACTOR within 10 working days from the audit. Where deficiencies are identified, follow up audit will be required to address them and confirm close out / compliance.
CONTRACTOR will ensure by means of inspections and audits that SUPPLIER has implemented his own audit program and REVIEW relevant audit results.
SUPPLIER shall maintain a summary log of all Non-Conformities and Corrective Action Requests raised during internal and external audits. This summary log to be sent to CONTRACTOR for REVIEW on monthly basis.
In case a significant part of the Supply is sub-contracted to any TIER-SUPPLIERS/SUB- SUPPLIERs, the SUPPLIER’s audit plan shall contain also adequate external audits to these organizations. SUPPLIER shall timely notify CONTRACTOR of any external audit activity conducted within Supply, to allow CONTRACTOR to participate as observer during the audit activity, if necessary. Such notification shall be issued at least 10 working days before the planned audit dates.
7.3.12 QA/QC MEETINGS
SUPPLIER shall participate to QA/QC meetings as directed by CONTRACTOR and with COMPANY participation wherever required. Meetings, in general, shall be held whenever required based on criticality of items.
Participants shall agree scope and agenda of the meeting according to the quality issues arising during the work. As a minimum quality meeting agenda shall include the following topics, that could be extended, as required / necessary:
QA/QC deliverable status including ITP. Previous meeting outstanding items.
COMP2-SPM-QM-SPC-00002_C 23 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
Inspection Notification status or cancellation if any
Quality related issues if any. Needs of quality improvement. Procurement inspection status and status log summary as applicable. Welding qualifications status, summary, and repair % ratio as applicable. Non-conformance including audit status. Cost of Quality in relation with NCRs issued and cost of reworks if any. Progressive Inspection Reports / Test records review/sign-off status by all involved parties
Inspection Release & Progressive MRB compilation Status
7.3.13 INSPECTION AT EX-STOCK SUPPLIER
Items procured through Ex-Stock are considered as Level-3 & Level 4 as per the MR and PCR matrix. The Source Inspection activity shall be carried out at SUPPLIER location accordingly. ITPs provided by the Ex-Stock suppliers shall be reviewed by CONTRACTOR and submitted to COMPANY for Approval. Inspections shall be carried out as per the ITP interventions.
7.3.14 NONCONFORMITY MANAGEMENT
All Non-Conformities on materials and/or equipment detected during fabrication will be handled in accordance with CONTRACTOR PROJECT NON-CONFORMITY MANAGEMENT PROCEDURE- COMP2-SPM-QM-PRC-00002 issued for this project.
Material physical deficiencies related to procurement shall be recorded on a Non-Conformity Report, this shall record all relevant details including but not limited to location, system, sub-system, specification requirements, actual situation, proposed solution.
CONTRACTOR to maintain a log of Non-Conformities for the NCRs issued to the VENDORs. The log shall include the material and/or equipment identification, the description of the non- conformity, the originator, the location, non-conformity disposition and corrective action description, NCR issuing status and close out dates.
VENDORs shall segregate all non-conforming materials and assemblies to a clearly designated rejection area or, as appropriate, to ensure identification and traceability of the item subjected to non-conformity procedure.
VENDORs shall rework or repair and re-inspect items in accordance with approved non-conformity disposition and CONTRACTOR approved method statement and procedures.
VENDOR NCRs with resolution as “Accept as is “shall be approved by CONTRACTOR and COMPANY through concession request.
If SUPPLIER fail to identify, record or act on non-conforming or defective Work, then CONTRACTOR reserves the right to issue a Non-Conformance Report against the SUPPLIER, Contractor’s
COMP2-SPM-QM-SPC-00002_C 24 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
assigned inspector or representative shall use the NCR form attached to this document as attachment # 2 to issue the NCR.
Non-conforming items detected by the SUPPLIER shall be addressed by issue of a supplier’s own internal Non-Conformity Report and shall be managed in compliance with supplier internal non - conformity management procedure. The supplier shall maintain a project dedicated NCR Control Log for all NCR issued. Any eventual corrective action shall be identified, recorded, authorized, and REVIEWED by competent qualified personnel. The correction & corrective action proposal shall be submitted to CONTRACTOR for REVIEW and APPROVAL. Each correction & corrective action shall define planned closing dates and appointed responsible persons. Evidence of positive close-out of the correction & corrective actions shall be submitted to CONTRACTOR for APPROVAL, for consequent definitive close-out of the non-Conformity.
SUPPLIER is responsible for the identification of non-conforming product and/or workmanship on the workshop and shall notify to CONTRACTOR any deviation/concession from applicable standards and any other applicable contractual requirements, before proceeding.
Root cause analysis (RCA) of all non-conformity shall be conducted and corrective/ preventive action shall be implemented to mitigate against reoccurrence.
The CONTRACTOR shall be notified of all correction and / or re-work, prior to the commencement of the correction and or re-work activities. No correction and / or re-work shall be conducted by the SUPPLIER or SUB-SUPPLIERs without authorization by the CONTRACTOR.
The CONTRACTOR shall be notified five (5) working days prior to the commencement of correction and / or re-work activities by vendor / supplier.
CONTRACTOR can, at any time, communicate to the SUPPLIER the need to open an NCR.
SUPPLIER shall respond within 48 hours and in writing to all NCR(s) and propose corrective action to eliminate the causes of nonconformities.
SUPPLIER QA/QC Manager shall be delegated the unequivocal authority and have direct access to SUPPLIER Senior Management to stop any works that are non-conforming.
CONTRACTOR reserves the right to request SUPPLIER to adopt and deploy CONTRACTOR’s NCR database system at any point of the project’s period.
Non-conformance shall be resolved by one of the following actions:
-
Reject and replace.
-
Rework to a conforming standard and re-inspect.
-
Repair to an acceptable standard and re-inspect – a Method Statement or Quality Procedure shall be prepared for each repair method, including acceptance criteria, and submitted for Contractor and Company approval.
-
Accept as-is as a Concession. This shall be documented on a Concession Request
which shall be submitted for Contractor and Company approval.
COMP2-SPM-QM-SPC-00002_C 25 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
The CONTRACTOR Assigned Inspector shall:
- Prepare the Non-Conformity Report as per project NCR template and attach the relevant
inspection reports detailing the occurred non-conformity and possible solution.
- Issue the Non-Conformity Report directly to the Manufacturer/VENDOR.
Manufacturer/VENDOR shall propose its action within 48 hours and send copy of NCR to QCMP & Responsible Function.
- Verify that the VENDOR has taken all action required to solve the non-Conformity and
report it.
- Ensure that Manufacturer/VENDOR follow NCR disposition and sign the NCR after
satisfactory check.
-
Send copy to QCMP and Responsible Function for final NCR file close out.
-
Ensure that close out NCR received and signed by Responsible Function, QCMP & PQM
and will be enclosed in dedicated section of the MRB.
Note: - When NCR is raised by the CONTRACTOR Assigned Inspector, Vendor representative shall sign the report to acknowledge receipt whether he agrees with the content or not.
The QCMP shall:
- Evaluate with Project Specialist Leader the proposed VENDOR solutions, as for their impact
on final quality of materials and their conformity.
- Inform MM, Expediter, PQM about non-conformity and shall copy it to the Company for
approval of suggested corrective actions.
-
Ensure that the non-conformity has been managed in a controlled manner.
-
Approve the NCR.
-
Sign the NCR close-out and send / transmit a copy of NCR closeout to Company for
information.
- Ensure that, the Vendor repair of non-conforming item(s) shall be in accordance with
documented procedure acceptable to the Contractor and Company.
7.3.15 SUPPLIER DEVIATION AND CONCESSION REQUESTS
Where the SUPPLIER is unable to meet with specified requirements and requires that these are modified or waived, prior to execution of activity, then SUPPLIER shall submit a Specification Deviation Request in accordance with the Contractual requirements.
Where the SUPPLIER has already completed activity, which is not in accordance with specified requirements, and requires that these are modified or waived retrospectively, then SUPPLIER shall submit a Concession Request for consideration. This shall contain the same information required as for the Specification Deviation Request and shall follow the same APPROVAL process.
COMP2-SPM-QM-SPC-00002_C 26 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
For the avoidance of doubt, any APPROVAL of a Concession Request shall be granted on a limited exceptional basis only and does not apply in any other circumstances except those specifically stated and does not set any precedent for application elsewhere.
The SUPPLIER shall implement a formal concession request process to address any good or product that deviates from the original design. Examples being, but not limited to:
Non-conforming product with a decision to leave as is without re-work or repair. Change in material grade. Changes in product characteristics, etc.…
A formal concession request shall be submitted by SUPPLIER to the CONTRACTOR for REVIEW and APPROVAL. The CONTRACTOR shall inform the COMPANY and obtain COMPANY APPROVAL prior to returning the outcome to the SUPPLIER.
Material and/or equipment which does not meet the specified requirements shall not be supplied unless an approved Concession is obtained.
All deviations for the design requirements shall be identified on formal concession requests. All concessions shall be clearly identifying and referenced back to the as-built information in the Manufacturers Record Book (MRB).
The SUPPLIER shall clearly indicate whether the concession is proposing to deviate from the requirements or whether the concession is to address a non-conformity where an NCR has been issued.
All concessions will be considered against the following potential implication:
Cost. Delivery. Design & design interface implications. Health, safety and environmental. Weight. Reliability. Maintenance. Operational performance. Spares and interchangeability.
The output from the above considerations shall be included in the concession request sent for COMPANY APPROVAL.
Planned corrective action(s), if any, shall be clearly described and submitted along with Concession request.
The SUPPLIER shall indicate the following items in the request:
Status of non-conformity / request of deviation. Proposed resolution and reasons for technical justification. Root cause, correction & corrective action.
COMP2-SPM-QM-SPC-00002_C 27 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
The original Concession request, when completed and signed by all concerned parties, shall be maintained in the Manufacturing Record Book (MRB).
Corrective action(s) shall be planned and implemented to the satisfaction of CONTRACTORs Inspector and COMPANY representative (as required). The successful implementation of corrective actions shall be verified prior to closure of the concession request.
7.3.16 PRE-INSPECTION MEETING (PIM)
The purpose of the meeting is to promote and co-ordinate effort by CONTRATOR and VENDOR, to transfer previous experiences and to prevent problems which might result in rejection or Non- Conformance such to compromise the quality level and the final delivery schedule. Also, to verify and highlight, if any, potential discrepancies among the order requirements, specifications, and VENDOR interpretation of those requirements. The meeting is also intended to clarify and confirm all requirements and criteria for any inspection and tests before commencement of fabrication and to check and finalize the ITP.
CONTRACTOR shall call for a Pre-Production/Pre-Inspection Meeting for Inspection Level 1+, 1, 2, and 3 items-(case to case basis).
Refer Contractor issued SOURCE INSPECTION PROCEDURE- COMP2-SPM-QM-PRC-00005 for the details & PIM process / agenda.
7.3.17 MANUFACTURING RECORD BOOK (MRB)
7.3.17.1 GENERAL
VENDOR shall prepare the Manufacturing Record Book, which shall consist in a compilation of quality control documentation, representative of the products manufacture, fabrication and test history of the ordered product and installed material.
The purpose of the MRB will be to ensure that quality documents and quality records originating at procurement, fabrication stages from multiple sources (VENDOR, Manufacturers, and their respective TIER-SUPPLIERS) will be retrievable in order to provide evidence that material used comply with the contract requirements at each step of the work till completion.
MRB shall be supplied by VENDOR to give evidence of the satisfactory results of all QC requirements and to document the relevant activities accordingly. The book shall provide sufficient information to demonstrate the product integrity, the quality of the workmanship and the conformity to the purchase order requirements.
The QC Manufacturing Data Book shall be compiled as the work is progressing to avoid delays in completion and consequent delays in equipment release.
SUPPLIER shall submit a proposed MRB Index to the CONTRACTOR for REVIEW and APPROVAL after purchase order award.
7.3.17.2 MRB COMPILATION
The MRB shall be compiled in a hard copy format which will later be presented as an electronic
COMP2-SPM-QM-SPC-00002_C 28 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
version after final REVIEW & APPROVAL of the hard copy version.
In addition to requirements specified in this document, MRB compilation & Formats shall be fully complied with the COMPANY PIH procedures- PRJ-PJL-PRC-006 and QUALITY CONTROL REQUIREMENTS FOR SUPPLIERS 200-20-QM-PRC-00099.
The MRB shall be compiled into sections of a bound dossier with a detailed index of contents, REVIEWED and discussed with CONTRACTOR.
The MRB shall be compiled progressively throughout the project manufacturing phase. This method will accelerate the final APPROVAL and reduce the submission time and delays in equipment release. The CONTRACTOR shall submit this to the COMPANY.
It is recommended that the SUPPLIER and SUB-SUPPLIERs conduct periodic interim REVIEWs of the MRB throughout the manufacturing period and document these interim REVIEWs as activities on the Inspection Test Plan. This will ensure that MRB production is up to date with the manufacturing process.
The content of the Manufacturing Record Book will vary dependent upon the type, size and complexity of the Supply.
The MRB will be initially REVIEWED at the SUPPLIER / SUB-SUPPLIERs facility by the CONTRACTORs Assigned Inspectors and or CONTRACTOR representative. The COMPANY or COMPANYs representative may also conduct a REVIEW at the SUPPLIER/ TIER SUPPLIERs workshop. Further REVIEW and APPROVAL shall be conducted by the CONTRACTOR/COMPANY after submission.
The MRB shall be structured by product and then broken down by manufacturing discipline and activity. Release of goods will be dependent on the successful; completion and compilation of the MRB.
The MRB may be split into two sections:
Section 1.0 - Containing common documents such as: procedures; drawings (as built); welder & NDT operator qualifications; calibration records; work instructions and material certificates.
Section 2.0 – Containing product specific documents such as: material traceability maps; NDT and inspection records, welding maps and dimensional control records.
7.3.17.3 MRB FORMAT
The MRB hard copy shall include bookmarks for each section and shall be in full compliance with index approved by CONTRACTOR and COMPANY, the different sections shall be separated by numbered dividers and any other requirements defined by the CONTRACTOR / COMPANY.
The CONTRACTORs standard project format for electronic MRB’s is Adobe Acrobat® Portable Document Format (PDF) i.e., in one single searchable PDF file only and not by various single PDF.
The preferred delivery is a single document in electronic neutral (PDF) format. For Acrobat pdf files please ensure the following requirements are addressed:
COMP2-SPM-QM-SPC-00002_C 29 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
Files in pdf format are acceptable for all documents where future updating is not required.
In all other cases, also original (native) file formats shall be provided.
Where native documents are required with signatures, both the native file and the signed
pdf-scanned file shall be provided.
When pdf files are created, they shall be converted directly from the native file (e.g., Word, Excel, DWG, etc.). In these cases, first printing, and then scanning to pdf is not acceptable.
Specific scanned certificates and signature pages shall be in pdf format. All pdf documents should be text-searchable and text-selectable and split in searchable
sections. If approved by the CONTRACTOR, scanned documents are to be provided by means of processed using OCR text recognition software (e.g., using Document- Paper Capture in Adobe Acrobat Standard) so that recognizable text within the document is searchable and text-selectable. In all cases, indexing with the pdf bookmark function shall be utilized.
As a minimum, and depending on the size of the document, bookmarking shall be used for
the first three heading levels.
For those documents which may be modified during the operating life of the facility, the
native file of the document shall also be provided along with a PDF version.
Page numbering shown in the Acrobat Viewer shall coincide with the page numbering given in the table of contents of the original source file. The document cover page shall always be numbered page 1.
Every effort shall be made to reduce the size of the pdf file without compromising quality of
the pdf.
All pdf files shall be of excellent quality and clearly legible. The CD-ROM shall reflect exactly the content of MRB hard copies.
The electronic file shall be completed with Bookmarks and a cascade structure inclusive of a detailed index of the documents contained within the book.
Each MRB shall include a first page with the following information, as a minimum:
Project Job number and name. SUPPLIER/ SUB-SUPPLIERs name. Document title. Purchase Order (PO) No. Equipment or Item description whichever applicable. SUPPLIER/SUB-SUPPLIERs contract/purchase order reference No. SUPPLIER/SUB-SUPPLIER ’s document No. Date of issue and revision No. (if any).
The Manufacturing Record Book is considered as a “deliverable to be submitted for payment of amount due at delivering of a Supply.”
7.3.17.4 MRB SUBMISSION
Prior to formal submission by the SUPPLIER, the Manufacturers Record Book shall be REVIEWED and approved by CONTRACTOR. Once approved the following shall be provided.
COMP2-SPM-QM-SPC-00002_C 30 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
When SUPPLIER sends the MRB to the CONTRACTOR, it is the SUPPLIERs responsibility to keep a copy of each manual/volume at their facility, to mitigate against: Loss, damage, or transportation problems.
7.3.17.5 MRB INDEX (MINIMUM GUIDELINES)
The content of this section to be used as reference by the SUPPLIER to build their MRB in compliance with the work deliverables embedded in the Purchase Order (PO) awarded by the CONTRACTOR to the SUPPLIER.
Note:
- The Common Documents MRB only needs to be one book, however this may consist of
many volumes.
- All MRB Books & Volumes shall have section dividers and sub section dividers. The sub
section shall contain an index to identify what is contained in the sub-section.
- Documents that are reference in a specific section of the Index below but are incorporated into another document shall be identified in the specified section, but reference shall be made to the relevant section & document that they are incorporated.
- The Product Specific MRB Book shall be built up by Product I.D.
- Identify the chapter or sub section number allocated to the individual line items.
- Sections to be indexed.
- Do not delete sections that are not relevant. Annotate with NA for “not applicable” sections.
Common MRB Documents (Guidelines)
Section
Title
Content
SUPPLIER Chapters
Cover Page
Cover page to include Equipment Name, CONTRACTOR Name, CONTRACTOR Purchase Order (PO) Number, SUPPLIER Job Number, Document number and revision number, etc… .
Contents & Index
Tabulated contents with section numbers, section titles, sub section numbers & titles and page numbers
1.0
Introduction
Introduction text to the content and Supply and scope the document etc…
2.0
Certificates
ISO Certificates
System Conformity
/ Sub-system Certificates
of
Declaration of product/good Conformity
Declaration of Performance
Type Test Certificates
Electrical Assurance Documents ATEX, FSA…)
(BS767,
COMP2-SPM-QM-SPC-00002_C 31 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
Section
Title
Content
Quality Plan
NDT Plan
3.0
Quality Planning
Inspection Test Plan
SUPPLIER Chapters
Audit Plan and internal/external audits reports
Manufacturing / Fabrication Execution Plan
Management of Changes
SUPPLIER Document Progress Register (SDR)
4.0
Registers & Schedules
Master Equipment List (MEL)
Procurement plan
Material Schedule
Production Test Program
Legal & Regulatory Compliance Register
As-built Drawing Schedule
QA Register (Schedule of Inspection Reports)
Design Decision Log
Final Design REVIEW Report
FEA Report
Design Drawings
Manufacturing Drawings
Calculations etc.…
Specifications (Coating, etc…)
Data Sheets (Paint etc.…)
5.0
Technical Documentation
6.0
Procurement
SUBCONTRACTS and TIER-SUPPLIERS Contracts /SUB-SUPPLIERs POs
7.0
Manufacturing Procedures
NDT Procedures [VIS]
NDT Procedures [ MPI]
NDT Procedures [UT]
NDT Procedures [DPI]
NDT Procedures [RAD]
Material Control Procedure
Welding Procedures [WPS + PQR]
COMP2-SPM-QM-SPC-00002_C 32 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
Section
Title
Content
SUPPLIER Chapters
Fatigue Grinding Procedure / Work Instruction
Dimensional Control Procedure
Test Procedures [FAT, Hydro, Load, Material etc.…]
Manufacturing Procedure Specification
Bending & Forming Procedure
Pre-heating Procedure
Electrical, Instrumentation & Telecommunications Installation Procedure
Electrical, Instrumentation & Telecommunications Mechanical Completion Procedure
Hot & Cold Straightening Procedure
Storage & Handling of Welding Consumables Procedure
Coating & Painting Procedure / Method Statement
Weight Control Procedure
Marking Procedure
Handling & Storage Procedure
Packing & Shipping Procedure (Load Out)
Welder Qualifications
Fatigue Grinding Operator Qualifications
NDT Operator Qualifications
NDT Operator Eye Test Certificates
Coatings & Paint Inspectors Certificate
Material Certification (Inc. machined items)
Material Test Records, Hardness, etc.…
Welding Consumable Certificates
Paint Batch Records
8.0
Manufacturing Operator Qualifications
9.0
Material Records (Mill & Manufacturer Certificates)
Product Specific MRB (Guidelines)
COMP2-SPM-QM-SPC-00002_C 33 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
Section
Title
Content
SUPPLIER Chapters
Cover Page
Contents & Index
Cover page to include Product name, COMPANY Name, COMPANY P.O. Number, Saipem Job Number, Document number and revision number, etc… .
Tabulated contents with section numbers, section titles, sub section numbers & titles and page numbers
1.0
Introduction
Introduction text to the content and Supply and scope the document etc…
2.0
3.0
CONTRACTOR Acceptance Records
Produce Specific Certificates
Certificate of Compliance
Handover Certificate of Conformity
Weight Control Certificate
4.0
Calibration
Calibration Register & Certificates [Test, Inspection & Welding Plant]
As Built Drawings
Material Traceability Catalogue [maps]
Weld Traceability Catalogue [maps]
NDT Traceability Logs [maps]
NDT Test Reports & Certificates
Dimensional Control Reports
Heat Treatment Reports, Charts & Certificates
5.0
Manufacturing Records
Painting Daily Inspection Records
Coating & Paint Inspection Reports
Test Certificates (Load, Hydro, etc.…)
Mechanical Completion Records (ITRs) (Structural, Architectural, Electrical, Instrumentation,)
Discipline Specific Inspection Check Lists (ICLs) / Inspection
FAT Reports / Test Results
Cable Drum Schedule
Final Inspection Records
Deficiency Reports
Non Conformity Register & Reports
6.0
Non-compliance Records
COMP2-SPM-QM-SPC-00002_C 34 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
Section
Title
Content
SUPPLIER Chapters
Corrective Action Register & Requests
Punch Lists Register
Deviation Requests Register & Requests
Concession Requests Register & Requests
Remedial Works Reports
7.0
TIER- SUPPLIERS/SUB- SUPPLIER ‘s Documentation
(As a minimum, cross reference to the SUB- SUPPLIERs MRB packs for individual sub- assemblies or components with evidence MRB pack have been REVIEWED and accepted by CONTRACTOR).
7.4 QUALITY CONTROL PLANNING
SUPPLIER shall be responsible for preparing plans, procedures and any other documents which are required or necessary to perform the Works and to ensure that the required quality is attained in accordance with good engineering, professional and management practices, and in compliance with this specification and any other contractual quality requirements.
SUPPLIER shall develop for APPROVAL by the CONTRACTOR, the quality plan covering all the phases of the Supply and the Inspection & Test Plans for all phases of the WORK embedded in the Purchase Order (PO) between CONTRACTOR and SUPPLIER.
7.4.1
INSPECTION AND TEST PLAN (ITP)
VENDOR shall issue an Inspection and Test Plan (ITP) as per the requirement and instructions of the applicable Codes and Standards, Contractor’s specifications and other requirements called for in the Purchase Order. Supplier to refer typical ITP form provided in this document as attachment # 5.
Refer Contractor issued SOURCE INSPECTIN PROCEDURE- COMP2-SPM-QM-PRC-00005 for the more details related to ITP & It’s Intervention Requirements.
7.4.2
INSPECTION LEVEL ASSIGNMENT
Inspection level shall be assigned based Procurement Criticality Rating (PCR) derived from procurement criticality matrix (COMP-QG-QM-PLN-00002). The type and amount of source inspection required are defined by the inspection level that is assigned to each product.
CONTRACTOR shall determine inspection levels and obtain approval of inspection levels from COMPANY prior to placement of purchase order.
Procurement Criticality rating and Inspection level shall be specified in MR and made as part of RFQ, Purchase order documents.
COMP2-SPM-QM-SPC-00002_C 35 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
Procurement Criticality rated (I) through to (IV) with corresponding COMPANY and Contractor Inspection Levels. A combination of which; are used to prioritize Contractors and COMPANY oversight and surveillance for procured equipment and materials as per below table.
PCR Inspection
Inspection Level Definition
Level
COMPANY
CONTRACTOR
Lead QC Inspector:
Resident Inspection:
I
1+
Documentation verification and attends all ITP points
Full stage Inspection as below plus full-time resident Inspector(s)
QC Inspector:
Full Stage Inspection:
I or II
1
Documentation verification and attends all ITP points
Minimum 2 inspection visits per week and all selected ITP points
II
III
2
3
QC Inspector:
Systematic Stage Inspection:
Documentation verification and attends selected ITP points
Minimum 1 inspection visit per week and all selected ITP points
QC Inspector:
Selected Stage Inspection:
Random visits for documentation and the witness of selected ITP points and tests.
Selected ITP points, Factory Inspection Test & Final Inspection
IV
4
QC Inspector:
Random visits and final inspection
Final Inspection only
IV
No Inspection
Document review where required
No Source Inspection – Document review only (NO Issuance of IRN)
COMPANY reserves the right to increase inspection levels at its sole discretion with no cost or schedule impact.
7.4.3 TEST REPORTS (CERTIFICATES)
SUPPLIER shall issue all certificates/reports for the performed tests.
SUPPLIER shall submit all the certificates/reports and Quality records listed and referenced in the ITP(s) to the Contractor’s Inspector for review & sign-off.
COMP2-SPM-QM-SPC-00002_C 36 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
The Test Report/Certificates shall be filled up with all information required to record the details of the Test activity performed. For this purpose, the Certificates/Test Report shall be compiled with all information below indicated, as well as traceability and numbering information and data relevant to the test performed such as but not limited to:
Test checklist. Test details and condition. Applicable parameters. Reference acceptance criteria. Tolerances. Test results and/or evaluation. Test date. etc.
The Certificate shall be univocally coded.
SUPPLIER shall distribute copies of Certificate to all signatory and provide for an orderly collection, filing and distribution of all Certificates and prepare quality records for final documentation hand over.
Any certificate produced after inspections shall be color scanned at the minimum resolution of 300 dpi, producing a PDF file. This is also applicable to all scanned documents to ensure documents readability.
SUPPLIER shall scan the certificates daily, just after the last signature, and send them immediately to CONTRACTOR’ Quality department by the means agreed at their facility, (EMAIL, CD Rom, etc..) for the electronic filing.
7.4.4 PURCHASE ORDERS WITH NO NEED OF WITNESS INSPECTIONS (REVIEW ONLY)
The following operating modes shall be followed:
The appointed QC Home Contractor inspector checks the completeness and updating of
technical documentation.
The appointed QC home inspector:
• Reviews and approves certification in his discipline upon receipt and confirms
•
acceptance prior to issuing the Quality Statement. If the Certification is not acceptable the QC home inspector will follow up with the VENDOR the issuance of such certification.
The required copies plus the electronic file of the Final certification dossier shall be submitted to CONTRACTOR.
7.4.5 CONTROL OF MANUFACTURING PROCESS
Supplier production & planning team to ensure the control of manufacturing process and activities being carried out at shop floor. The competent production Supervisors shall be mobilized to monitor the fabrication processes.
QC Supervisor shall monitor the correct implementation of the project approved procedure and ITPs during the fabrication & complete execution of the purchase order.
COMP2-SPM-QM-SPC-00002_C 37 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
7.4.6 SUPPLIER PERFORMANCE VERIFICATION BY CONTRACTOR
CONTRACTOR have the right to perform or appoint a representative to verify the performance and/or the results of inspections, examinations and testing at any time during project execution and as per approved Project ITP, and/or as deemed necessary to provide confidence that SUPPLIER is performing the work in compliance with all quality provisions.
All activities under Quality Control shall be clearly defined in procedure or method statements, detailing: Supply, how and where it shall be performed, work execution and verification responsibilities and relevant quality records.
All stages of fabrication shall be inspected using the Project ITP, detailing the quality Inspections to be performed by the SUPPLIER QA/QC Organization with allowance for CONTRACTOR and COMPANY REVIEW / surveillance / witness / holds interventions points.
All certificates issued after inspections shall be recorded and shall be registered in a SUPPLIER electronic Database.
Status of all inspection shall be maintained up to the completion of the Supply as per Purchase Order (PO) between SUPPLIER and CONTRACTOR.
The Request for Inspection Notifications (IN) to be managed by SUPPLIER and must be managed in a SUPPLIER electronic Database.
Where CONTRACTOR has concerns over the quality of Works, it shall have the right to re-inspected.
Supplier shall ensure all inspection activities are completed in line with ITP intervention stages and inspection records / test reports / punch list have been documented and signed-off by all involved parties prior to packing.
7.4.7
INSPECTION AND TESTING
The SUPPLIER shall prepare documented procedures consistent with the requirements of Purchase Order (PO). The procedures shall incorporate the methodology and quantitative / qualitative acceptance criteria and shall specify acceptance criteria for all testing activities applicable to the work scope.
Activities that are identified as special processes shall be controlled via specific procedure. These procedures shall be REVIEWED and approved by the CONTRACTOR prior to commencement of the activity.
Factory Acceptance Tests (FAT) shall not be conducted prior to the REVIEW and APPROVAL by the CONTRACTOR of all Testing Check Lists and relevant FAT Procedures / Work Instructions.
Site Acceptance Tests (SAT) shall not be conducted prior to the REVIEW and APPROVAL by the CONTRACTOR of all Testing Check Lists and relevant SAT Procedures / Work Instructions.
In the event that any incomplete or non-conforming work is required to be transferred to Site, this shall be clearly documented on a Punch List and shall require prior authorization by CONTRACTOR and COMPANY. Contractor’s assigned inspector shall use the Punch List form attached to this
COMP2-SPM-QM-SPC-00002_C 38 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
document as attachment # 3 to issue the Punch List.
7.4.8 SPECIAL PROCESSES
Control of special processes (production or inspection) shall identify processes, such as welding, heat treating, non-destructive testing, pressure testing, painting and cleaning, etc., which require procedure qualification and qualification of the personnel using them.
When required by COMPANY standards, and prior to the start of the work, VENDOR shall submit to EPC CONTRACTOR for review and approval all VENDOR and its TIER-SUPPLIER’s procedures for special process. EPC CONTRACTOR shall review and approve those procedures before submitting them to COMPANY. Therefore, any working activity shall not start from VENDOR and its TIER-SUPPLIER’s side prior to the approval of the related special process procedure (at least approved with comments as noted).
7.4.9 MATERIALS CERTIFICATION, IDENTIFICATION & TRACEABILITY
VENDOR shall develop effective procedures for the material management and material identification and traceability in accordance with the relevant standards, project specification requirements, vendor recommended storage and preservation requirements for materials, parts and components, including partially fabricated assemblies. Identification shall be addressed either by using tags, stamps, color coding, stencils and labels or by traceability records throughout fabrication / assembly, erection, installation, repair, modification and use of materials and equipment’s.
Where full traceability is a specified requirement, SUPPLIER shall maintain, control and record the unique identification of the origin of materials and components throughout fabrication, erection, installation, repair, modification and use. The procedure shall require that verification of traceability of material and components be made prior to assembly / installation.
SUPPLIER shall provide sufficient and dedicated personnel to monitor and be in-charge of the receipt, handling, loading, unloading, transportation, inspection, storage and Installation of all MATERIALS and equipment.
Steel materials & welding consumables shall be supplied with certification in accordance with EN 10204:2004, either 3.2, 3.1, 2.2 & 2.1 as specified in the COMPANY specification 200-20-QM-PRC- 00099 and Material Requisition. Traceability shall be maintained throughout the manufacturing process. Traceability records shall be kept and maintained for inclusion in the MRB.
The SUPPLIER shall verify all mill / product certificates. Mill certificates shall be submitted for CONTRACTORs REVIEW / acceptance before the start of production (cutting in manufacturing workshop).
Prior to incorporation into the work, VENDOR shall remain responsible for ensuring that all material certificate and material inspection documents of the type specified in the purchase order, or sub- contract, are produced, and that the specified traceability levels are achieved.
This responsibility extends also to SUB-VENDORS and STOCKISTS.
VENDOR shall guarantee the traceability of any QC document (material certificates and test reports).
Each QC documents relevant to material specified in the purchase order or sub-contract shall be
COMP2-SPM-QM-SPC-00002_C 39 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
identified, as minimum, bearing Contractor’s Job number, Contractor’s Purchase Order number and Purchase Order item number.
All records shall be traceable to the equipment/instruments via equipment serial number(s) and shall be identified by equipment serial number, part number and description etc.,
Material test reports shall fully specify the results of all tests i.e., mechanical, chemical and visual that were carried out for each supply.
Relevant heat, cast and test number for each item supplied shall also be stated.
For all POs relevant to bulk material, independently from the relevant Inspection Levels associated, before each Material Shipping, Vendor shall send by email to Material Manager the full Material Traceability Record.
This action is required in order to obtain a complete traceability/correspondence among materials and relevant documents:
-
Order N.
-
Order Item No#
-
Manufacturer
-
Packing List N.
-
Material Description
-
Heat Number
-
Material Certification Number
-
Other Certifications (if applicable)
7.4.10 MATERIAL & EQUIPMENT MANAGEMENT AND CONTROL
SUPPLIER shall develop Project specific procedures for equipment, bulk material receiving and inspection, preservation, storage, handling, security and tracking throughout all phases of fabrication and provide such procedures to CONTRACTOR for REVIEW and APPROVAL. To avoid problems with the warranties of the equipment (itemized), SUPPLIER shall consider supplier recommendation for preservation.
SUPPLIER shall ensure adequate receiving, inspection, control, handling and preservation of customer (CONTRACTOR) supplied materials is implemented, in accordance with the material SUB- SUPPLIERs’ recommendations and the terms of the Purchase Order (PO).
SUPPLIER shall ensure that CONTRACTOR supplied materials at SUB-SUPPLIER are managed; stored and preserved in a controlled manner such that damage and / or deterioration is prevented.
SUPPLIER shall be entirely responsible for the receipt, handling, loading, unloading, transportation, inspection, storage and Installation of all MATERIALS and equipment in accordance with the SUPPLIER’s Material Control Procedure. SUPPLIER shall also be responsible for preservation of all MATERIALS and equipment’s during fabrication, handling, loading, unloading, transportation, inspection, storage and installation.
COMP2-SPM-QM-SPC-00002_C 40 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
SUPPLIER shall receive all items of equipment and MATERIALS. Immediately on receipt, all equipment and / or items shall be inspected by SUPPLIER for any overage, shortage or damage (herein after referred to as OS & D) during shipping and transit from VENDOR(s) WORKS. All OS & D shall be notified in writing to the carrier and vendor for immediate action to avoid any impact to the schedule of the project. CONTRACTOR shall be notified of the Overage, Shortage, Damage (OS & D) immediately post receipt and inspection.
CONTRACTOR shall provide proper, sufficient and designated safe storage space at SITE for the received items. The storage space (open and / or covered) shall be in environmental conditions suitable for the items of equipment and where they shall not be liable for damage, deterioration or corrosion and wherever applicable, in accordance with the vendor requirements. It shall be the responsibility of the SUPPLIER to obtain from CONTRACTOR/VENDOR(s) all the storage and preservation requirements and fully comply with the same. SUPPLIER shall provide the storage to location within SUPPLIER‟s WORKSITE CONTRACTOR/COMPANY SITE team for the SITE visit and inspection at any time.
accessibility
allow
and
full
to
SUPPLIER shall write a consistent procedure for receiving inspection, proper storage, maintenance, handling of materials and equipment’s and shall considers as a minimum also the following aspects:
Equipment storage categories. Equipment maintenance categories Equipment preservation categories Corrosion protection Required rigging and lifting drawings.
Materials and equipment maintenance and preservation logs shall summarize, as a minimum:
active maintenance requirements. dates of servicing. personnel responsible. lubricants used, etc.
type of service performed.
Emphasis shall be given to special alloy MATERIALS and equipment items, including the possible impact of the extreme adverse environment.
Particular attention is also required to prevent the degradation of sensitive equipment.
CONTRACTOR prepared preservation and protection procedures shall include the following as a minimum:
• Equipment and material preservation procedure shall include equipment / material from the time it leaves vendor’s shops through to facilities RFSU through the System Completions process.
• Preservation schedule for each equipment.
• Schedule outlining requirements for removal of preservatives
Dedicated procedure shall be developed for the integrated preservation and flawless execution philosophy with execution plans focusing all schedule critical equipment and MATERIALS. Such
COMP2-SPM-QM-SPC-00002_C 41 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
plans shall include but not limited to:
• All Long Lead Items (LLI).
• All Mechanical and E/I/T equipment.
• All pipes and fittings including Inconel, SS, GRE, CRA.
• All valves and actuators.
• All hubs, seal rings, hub connectors and flanges.
CONTRACTOR shall operate and maintain a computerized material management system for the Project and shall provide trained material control personnel for the purpose.
Material control requirements shall be in accordance with COMPANY and Project specifications.
Packing for goods included shall comply with CONTRACTOR Standard
As a minimum SUPPLIER/SUB-SUPPLIER shall:
Prepare the supply for shipment and deliver to nominated delivery point.
Furnish internal and external shipping braces required to prevent damage or movement
during transportation.
Furnish all the crates with relevant Packing List and Shipping Documentation.
The SUPPLIER/ SUB-SUPPLIER storage shall provide a suitable controlled and secure environment and adequate protection and preservation to ensure the maximum life and integrity of the stored items.
SUPPLIER/ SUB-SUPPLIER shall verify the performance properties and perform integrity verifications of all stored items to ensure they are maintained in a satisfactory condition for operation.
SUPPLIER/ SUB-SUPPLIER shall take all necessary precautionary measures to prevent damage to piping during fabrication. Piping shall be protected all times from falling objects, impacts, welding and grinding sparks, contamination, damage to protective coating etc.
7.4.11 CONTROL OF MONITORING AND MEASURING DEVICES
The SUPPLIER shall implement a procedure for the identification, maintenance, control and calibration of tools, gauges, instruments and other measuring and testing devices to be used in performing inspection and tests. All inspection and testing equipment shall be in good working order, suitable for the intended purposes and (where applicable) be calibrated to a recognized National or International Standard by a UKAS (or equivalent) certified laboratory.
All calibration records shall be made available for REVIEW by the CONTRACTOR Inspector.
All Inspection Reports and Test Records shall contain the necessary information to provide traceability of the measuring and testing equipment used.
The procedure shall ensure that measurements are conducted in a manner consistent to provide evidence of conformity of product to determined requirements.
COMP2-SPM-QM-SPC-00002_C 42 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
Calibration and setting shall be performed against certified equipment having a known valid relationship to internationally or nationally recognized standards. Where no such standards exist, the basis used for calibration shall be documented.
Tests undertaken shall identify the relevant calibration equipment used. Should the monitoring and measuring device be found to be out of calibration at the time of test, the validity of the results of previous inspection, and test conducted with the same measuring device shall be demonstrated by SUPPLIER at its own care and cost. When validity cannot be proven, SUPPLIER shall repeat all relevant tests with an approved calibrated measuring device.
All calibrated monitoring and measuring devices shall be provided with means (labels, nameplate, tag, card, etc…,) of immediate visual confirmation of the calibration status by means of and identification Sticker conforming with the following example:
TAG No.__________________ Calibration date: ____________ Re-calibration: _____________ Name: ________________ Signature_________________ Certificate n.________________
Calibration certificates shall be available as well as calibration record shall be maintained for each monitoring and measuring device. The log shall include the equipment description, serial number, identification tag number, calibration date, recalibration due date and any other pertinent information.
Calibration shall be checked before beginning of inspections and at established periods in accordance with the below table, or as otherwise agreed or required by specific Purchase Order (PO) requirements.
Calibration shall be checked before beginning of inspections and at established periods in accordance with applicable project specifications and/or international codes and standards. The more stringent shall be applied.
The calibration records shall be easily traceable to the equipment and maintained at workshop by SUPPLIER.
Prior to use any monitoring and measuring devices, SUPPLIER shall ensure that the effective calibration date has not expired and the equipment has not been visibly damaged.
The SUPPLIER shall maintain the updated list of approved monitoring and measuring devices and periodically submit the same on monthly basis to CONTRACTOR for REVIEW.
7.4.12 QUALITY SURVEILLANCR BY SUPPLIER DURING MANUFACTURING ACTIVITIES
SUPPLIER’s Quality personnels shall perform quality walks / surveillance along with production team and shall address the report on identified gaps, recommendations, good practices, findings and prepare a documented plan to correct and/or prevent any noticed deficiencies, hazards, etc.
All documents and drawings shall be in English language.
COMP2-SPM-QM-SPC-00002_C 43 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
8 ANNEX
8.1 NON-CONFORMITY REPORT SAMPLE (MINIMUM REQUIREMENT)
NCR Form- Page 1 of 2
COMP2-SPM-QM-SPC-00002_C 44 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
NCR Form- Page 2 of 2
COMP2-SPM-QM-SPC-00002_C 45 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
8.2 PUNCH LIST FORM SAMPLE (MINIMUM REQUIREMENT)
COMP2-SPM-QM-SPC-00002_C 46 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
8.3
ITP TYPICAL FORMAT FORM SAMPLE (MINIMUM REQUIREMENT)
COMP2-SPM-QM-SPC-00002_C 47 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
8.4 MDR INDEX PREPARATION SAMPLE (MINIMUM REQUIREMENT)
COMP2-SPM-QM-SPC-00002_C 48 of 49
NFPS Offshore Compression Complexes Project COMP2
PROJECT QUALITY REQUIREMENTS FOR SUPPLIERS
8.5 VENDOR DOCUMENT REGISTER (VDR) SAMPLE (MINIMUM REQUIREMENT)
COMP2-SPM-QM-SPC-00002_C 49 of 49
Project: Q-21699 - Saipem COMP2 Folder: Information Management and Document Control