Infinity

Not logged in
Home

❯

Reference Examples

❯

Q 21699 Saipem COMP2

❯

RFQ Files

❯

Instrumentation

❯

200 51 IN SPC 00021_00

NFPS Offshore Compression Complexes Project COMP2

COMPANY Contract No.: LTC/C/NFP/5128/20

CONTRACTOR Project No.: 033734

Document Title

:

INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

COMPANY Document No.

: 200-51-IN-SPC-00021

Saipem Document No.

: 033734-B-D-30-SPM-AS-S-10007

Discipline

: INSTRUMENTATION

Document Type

: SPECIFICATION

Document Category/Class

: 1

Document Classification

: Internal

00

26-May-2023

Approved for Construction

Nor Hariyanetti

Muhaimin

B

A

14-Apr-2023

Issued for Approval

Nor Hariyanetti

Muhaimin

10-Feb-2023

Issued for Review

Nor Hamizah

Kanakaiah Panala

Azionn Aziz / Nitin Shanware Azionn Aziz / Nitin Shanware Azionn Aziz / Nitin Shanware

REV.

DATE

DESCRIPTION OF REVISION

PREPARED BY

CHECKED BY

APPROVED BY

Saipem S.p.A.

Company No._Rev. 200-51-IN-SPC-00021_00

1 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

REVISION HISTORY

Revision

Date of Revision

Revision Description

A1

A

B

00

13-Jan-2023

Issued for Inter-Discipline Check

10-Feb-2023

14-Apr-2023

26-May-2023

Issued for Review

Issued for Approval

Approved for Construction

HOLDS LIST

Hold No

Hold Description

Company No._Rev. 200-51-IN-SPC-00021_00

2 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

TABLE OF CONTENTS

1

INTRODUCTION … 5

1.1 PROJECT OBJECTIVE … 5 1.2 PROJECT SCOPE … 5

2

DEFINITIONS AND ABBREVIATIONS … 7

2.1 DEFINITIONS … 7 2.2 ABBREVIATIONS … 8

3

REFERENCE, RULES, CODES AND STANDARDS … 12

3.1 COMPANY DOCUMENTS … 12 3.2 PROJECT DOCUMENTS … 12 3.3 CONTRACTOR DOCUMENTS … 13 INTERNATIONAL CODES AND STANDARDS … 14 3.4

4

5

6

PURPOSE … 16

SCOPE … 16

GENERAL TECHNICAL DESIGN CRITERIA … 16

6.1 DESIGN LIFE … 16 6.2 ENVIRONMENTAL CONDITION AND WEATHER PROTECTION … 16 6.3 INSTRUMENTATION STANDARDIZATION … 19 6.4 ELECTRICAL HAZARDOUS AREA PROTECTION … 19 6.5 OBSOLESCENCE MANAGEMENT … 19 6.6 ELECTROMAGNETIC COMPATIBILITY … 19 6.7 MECHANICAL SHOCK AND VIBRATION COMPATIBILITY … 19 6.8 LIGHTNING PROTECTION AND ELECTRICAL SURGE PROTECTION … 20 6.9 INSTRUMENT SIGNAL DEFINITION … 20 6.10 MATERIAL REQUIREMENT … 21 6.11 UTILITIES AND POWER SUPPLIES … 21 6.12 ENGINEERING UNITS … 23 6.13 PAINTING AND COATING … 25 6.14 NAMEPLATE AND IDENTIFICATION … 25 6.15 INSTRUMENT IDENTIFICATION AND NUMBERING … 26 6.16 INSTRUMENT ENGINEERING DATABASE … 26 6.17 INSTRUMENT QR CODE … 26

7

PACKAGE TYPE DEFINITION AND CONTROL PHILOSOPHY … 26

7.1 GENERAL … 26 7.2 P1 TYPE PACKAGE … 27 7.3 P2 TYPE PACKAGE … 27 7.4 P3 TYPE PACKAGE … 28 7.5 P4 TYPE PACKAGE … 29 7.6 FACILITIES CONTROL PHILOSOPHY … 29

8

SCOPE OF WORK AND SUPPLY … 30

8.1 DESIGN BASIS REQUIREMENTS FOR INSTRUMENTATION … 30 8.2 REQUIREMENTS FOR INSTRUMENT INSTALLATION AND EARTHING … 30

9

PACKAGE DESIGN CRITERIA … 30

9.1 POWER SUPPLY NETWORK … 30 9.2 INSTRUMENT AIR NETWORK … 31 9.3 FIELD INSTRUMENTATION AND VALVES … 31

10

UNIT CONTROL PANEL … 32

Company No._Rev. 200-51-IN-SPC-00021_00

3 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

10.1 UCP CONSTRUCTION AND DESIGN … 32 10.2 UCP LOCATION … 32 10.3 UCP CONTROL PHILOSOPHY … 32 10.4 PLC FEATURES … 33 10.5 TIME SYNCHRONIZATION … 35 10.6 HUMAN MACHINE INTERFACE (HMI) … 36 10.7 CPU / ENGINEERING WORKSTATION REQUIREMENTS … 38 10.8 VIRTUALIZATION … 39 10.9 SPECIAL TOOLS … 39

11

12

ALARM MANAGEMENT … 39

COMMUNICATION INTERFACES … 40

12.1 LIST OF PACKAGE INTERFACE… 40 12.2 HARDWIRED INTERFACE DESIGN … 43 12.3 SYSTEM INTERFACE … 45

13

14

15

16

REMOTE ACCESS AND CYBER SECURITY REQUIREMENT … 47

SPARE CAPACITIES (FOR P2 AND P3 TYPES PACKAGES) … 47

SOFTWARE LICENSES… 48

DOCUMENTATION … 49

16.1 DOCUMENTATION REQUIRED WITH QUOTATION … 49 16.2 INSTRUMENTATION AND CONTROL DOCUMENTATION DURING EXECUTION … 49

17

INSPECTION AND TEST REQUIREMENT … 51

17.1 GENERAL … 51 17.2 FACTORY ACCEPTANCE TEST (FAT)… 51 17.3 INTEGRATED FACTORY ACCEPTANCE TEST (IFAT) … 52 17.4 FAT / IFAT REPORT AND ACCEPTANCE … 53 17.5 SITE ACTIVITIES (INSTALLATION, PRE-COMMISSIONING/COMMISSIONING AND START-UP) … 53

18

19

PACKING, SHIPMENT AND PRESERVATION … 54

SPARE PARTS AND SPECIAL TOOLS … 54

19.1 SPARE PARTS … 54 19.2 SPECIAL TOOLS … 54

20

SERVICES … 54

20.1 TRAINING … 54 20.2 ATTENDANCE TO SPECIFIC REVIEWS: … 54

21

APPENDICES … 56

21.1 APPENDIX 1 PACKAGE SCOPE OF SUPPLY BATTERY LIMITS … 57 21.2 APPENDIX 2 PACKAGE EQUIPMENT COMPLIANCE LIST … 66 21.3 APPENDIX 3 GTC ARCHITECTURE DIAGRAM, GTG ARCHITECTURE DIAGRAM AND ANTI SURGE / … 73 LOAD SHARING ARCHITECTURE … 73

Company No._Rev. 200-51-IN-SPC-00021_00

4 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

1

INTRODUCTION

The North Field is the world’s largest natural gas field and accounts for nearly all of the state of Qatar’s gas production. The reservoir pressure in the North Field has been declining due to continuous production since the early 1990s. The principal objective of the NFPS Project is to sustain the plateau from existing QG South Operation (RL Dry Gas, RGE Wet gas) and existing QG North Operation (QG1 & QG2) production areas by implementing an integrated and optimum investment program consisting of subsurface development, pressure drop reduction steps and compression. Refer to the figure below for a schematic of the North Field.

Qatargas Operating Company Limited is leading the development of the North Field Production Sustainability (NFPS) Project.

1.1 Project Objective

The objective of this Project includes:

• Achieve standards of global excellence in Safety, Health, Environment, Security and Quality

performance.

• Sustain the Qatargas North Field Production Plateau by installing new Compression Complex facilities CP6S & CP7S in QG south with integration to the existing facilities under Investment #3 program.

• Facility development shall be safe, high quality, reliable, maintainable, accessible, operable,

and efficient throughout their required life.

1.2 Project Scope

The Project Scope includes detailed engineering, procurement, construction, transportation & installation, hook-up and commissioning, tie-in to EXISTING PROPERTY and provide support for start- up activities of the following facilities and provisions for future development. The WORK shall be following the specified regulations, codes, specifications, and standards, achieves the specified performance, and is safe and fit‐for‐purpose in all respects.

Offshore

CP6S and CP7S Compression Complexes that are part of QG-S RGE facilities as follows:

• CP6S Compression Complex

• Compression Platform CP6S, Living Quarters LQ6S, Flare FL6S

• Bridges BR6S-2, BR6S-3, BR6S-4, BR6S-5

• Bridge linked Tie-in to RP6S

Production from existing wellheads (WHP6S & WHP10S) and new wellhead (WHP14S) are routed via riser platform RP6S to compression platform CP6S to boost pressure and export to onshore via two export lines through the existing WHP6S pipeline and a new 38” carbon steel looping trunkline from RP6S (installed by EPCOL). CP6S is bridge-linked to RP6S.

• CP7S Compression Complex

• Compression Platform CP7S, Living Quarters LQ7S, Flare FL7S

• Bridges BR7S-2, BR7S-3, BR7S-4, BR7S-5

• Bridge linked Tie-in to RP7S

Company No._Rev. 200-51-IN-SPC-00021_00

5 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

CP7S shall receive production from existing wellheads (WHP5S & WHP7S) and new wellhead (WHP13S). There is only one export line for CP7S through the existing export pipeline from WHP7S. CP7S is bridge-linked to RP7S.

RGA Complex Destressing

Migration of the Electrical power source, Telecoms, Instrumentation and Control systems from WHPs and RPs hosted by RGA to the respective Compression Complexes listed below:

• WHP6S, WHP10S, WHP14S, RP6S and RP10S to CP6S Compression Complex

• WHP5S, WHP7S, WHP13S and RP7S to CP7S Compression Complex

Destressing of Telecoms, Instrumentation and Control system in RGA Complex Control Room, which would include decommissioning and removal of telecom system devices and equipment that would no longer be required post migration and destressing activity.

Onshore

An Onshore Collaborative Center (OCC) will be built under EPC-9, which will enable onshore based engineering teams to conduct full engineering surveillance of all the offshore facilities. The OCC Building will be located in Ras Laffan Industrial City (RLIC) within the Qatar Gas South Plot. MICC & Telecommunication, ELICS related scope will be performed in the OCC building.

Figure 1.2.1: NFPS Compression Project COMP2 Scope

Company No._Rev. 200-51-IN-SPC-00021_00

6 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

2 DEFINITIONS AND ABBREVIATIONS

2.1 Definitions

Definition

Description

COMPANY

Qatargas Operating Company Limited.

CONTRACTOR

Saipem S.p.A.

DELIVERABLES

FACILITIES

All products (drawings, equipment, services) which must be submitted by CONTRACTOR to COMPANY at times specified in the contract. All machinery, apparatus, materials, articles, components, systems and items of all kinds to be designed, engineered, procured, manufactured, constructed, supplied, tested and permanently installed by CONTRACTOR at SITE in connection with the NFPS Project as further described in Exhibit 6.

fabricated,

MILESTONE

A reference event splitting a PROJECT activity for progress measurement purpose.

PROJECT

NFPS Offshore Compression Complexes Project EPC 2

SITE

(i) any area where Engineering, Procurement, Fabrication of the FACILITIES related to the CP6S and CP7S Compression Complexes are being carried out and (ii) the area offshore required for installation of the FACILITIES in the State of Qatar.

SUBCONTRACT

Contract signed by SUBCONTRACTOR and CONTRACTOR for the performance of a certain portion of the WORK within the Project.

SUBCONTRACTOR

Any organization selected and awarded by CONTRACTOR to supply a certain Project materials or equipment or whom a part of the WORK has been Subcontracted.

WORK

Scope of Work defined in the CONTRACT.

WORK PACKAGE

The lowest manageable and convenient level in each WBS subdivision.

VENDOR

The person, group, or organization responsible for the design, manufacture, the Equipment/Material.

load-out/shipping

testing,

and

of

Company No._Rev. 200-51-IN-SPC-00021_00

7 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

2.2 Abbreviations

Code

Definition

AC

ACS

ADAS

ALMS

ANSI

API

ASME

ASTM

ATEX

BDV

CCR

Alternating Current

Anti-surge Control System

Analyzer Data Acquisition System

Alarm Management System

American National Standards Institute

American Petroleum Institute

American Society of Mechanical Engineers

American Society for Testing and Materials

Atmospheres Explosible

Blowdown Valve

Central Control Room

PEMS

Predictive Emissions Monitoring System

CFIHOS

Capital Facilities Information Handover Specification

CPMS

Condition and Performance Monitoring System

C&E

DC

DCS

DFT

DIFFS

ELICS

EMC

EN

ENMCS

EPC

Cause and Effect

Direct Current

Distributed Control System

Dry Film Thickness

Deck Integrated Firefighting System

Electrical Integrated Control System

Electromagnetic Compatibility

European Norms

Electrical Network and Monitoring Control System

Engineering, Procurement and Construction

Company No._Rev. 200-51-IN-SPC-00021_00

8 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

Code

Definition

EPCOL

Engineering, Procurement and Construction Offshore Looping

EPU

ESD

Ex d

Ex e

Ex i

FAT

Electrical Power Unit

Emergency Shutdown System

Hazardous Area Protection Technique – Flameproof

Hazardous Area Protection Technique – Increased Safety

Hazardous Area Protection Technique – Intrinsically Safe

Factory Acceptance Test

FEED

Front End Engineering Design

FGS

F&G

FRP

GRP

GTC

GTG

Fire and Gas System

Fire and Gas

Fiber Reinforced Plastic

Glass Reinforced Plastic

Gas Turbine Compressor

Gas Turbine Generator

HART

Highway Addressable Remote Transducer

HMI

HPU

HVAC

IAMS

ICSS

IEC

IECEx

IEEE

I/O

Human Machine Interface

Hydraulic Power Unit

Heating Ventilation and Air Conditioning

Instrument Asset Management System

Integrated Control and Safety System

International Electrotechnical Commission

International Electrotechnical Commission System for Certification to Standards Relating to Equipment for Use in Explosive Atmospheres

Institute of Electrical and Electronics Engineers

Input Output

Company No._Rev. 200-51-IN-SPC-00021_00

9 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

Code

Definition

IP

IR

IRP

IS

ISA

ISO

I/O

JB

LER

LQ

MAC

MICC

MMS

NACE

NFA

NFB

Ingress Protection

Infra-Red

Interposing Relay Panel

Intrinsically Safe

International Society of Automation

International Organisation for Standardisation

Input / Output

Junction Box

Local Equipment Room

Living Quarters

Manual Alarm Call Point

Main Instrument and Control Contractor

Machine Monitoring System

National Association of Corrosion Engineers

North Fields Alpha

North Fields Bravo

NFPS

North Field Production Sustainability

NPT

OCC

PCB

PE

PLC

POIS

QA

QG

National Pipe Thread

Onshore Collaborative Center

Printed Circuit Board

Protective Earth

Programable Logic Controller

Plant Operating Information System

Quality Assurance

Qatargas

Company No._Rev. 200-51-IN-SPC-00021_00

10 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

Code

Definition

Qatargas Block 1

Qatargas Block 2

Qatargas North

Qatargas South

Request for Quotation

RasGas Alpha

RasGas Expansion (LNG Train 3,4,5,6,7 and AKG-1,2) - Wet Gas System

Ras Laffan

Riser Platform

Resistance Temperature Detector

Supervisory Control and Data Acquisition

Shutdown Valve

Safety Instrumented Function

Safety Integrity Level

SmartPlant for Instrumentation

Stainless Steel

Thermocouple

QG1

QG2

QG-N

QG-S

RFQ

RGA

RGE

RL

RP

RTD

SCADA

SDV

SIF

SIL

SPI

SS

TC

TCP/IP

Transmission Control Protocol/Internet Protocol

UCP

UPS

WHP

Unit Control Panel

Uninterruptable Power Supply

Wellhead Platform

Company No._Rev. 200-51-IN-SPC-00021_00

11 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

3 REFERENCE, RULES, CODES AND STANDARDS

The following codes, standards and specification are referenced within the document shall be considered as part of this specification. Conflict among applicable specification and / or codes shall be brought to the attention of the COMPANY for resolution COMPANY decision shall be final and shall be implemented. The latest editions of codes and specification effective as on date of contract shall be followed.

In general, the order of precedence shall be followed:

a) Qatari Governmental and Regulatory Requirements

b) COMPANY Procedures, Policies and Standards (Exhibit 5 Appendix I)

c) Project Specifications.

d) Industry Codes and Standards

e) COMPANY and CONTRACTOR’s Lessons Learned

If CONTRACTOR/SUBCONTRACTOR deems any deviations from the specifications will result in significant project cost and schedule saving, proposal to such deviations shall be submitted to COMPANY for review and approval. CONTRACTOR/SUBCONTRACTOR shall not proceed with any deviation to the specifications without prior COMPANY approval. In general, all design activities shall conform to legal and statutory regulations, and recognized industry best practices.

3.1 Company Documents

S. No

Document Number

Title

PRJ-PJL-PRC-004_07

PRJ-PJL-PRC-005_21

PRJ-PJL-PRC-006_01

PRJ-PJL-PRC-007_01

Facilities Engineering and VENDOR Document Numbering Procedure Facilities, System and Unit Number Codes and Descriptions Procedure Project Information Handover Procedure

SmartPlant Engineering Applications & Drafting (CAD) Standard

PRJ-PJL-PRC-008_16

Equipment Numbering Philosophy

PRJ-PJL-PRC-048_11

PRJ-PJL-PRC-049_01

TCH-AIG-PRC-044 Rev 01

GDL-UF-06 Rev 2.0

Metadata

Documentation

Facilities Requirements Procedure Project Information Handover, Verification and Acceptance Procedure Industrial Control System Security Engineering Specification Procedure Qatar Measurement of Hydrocarbon Fluids

Petroleum Guidelines

the

for

OGO-OPS-OVR-006 Rev 02

Alarm Management Philosophy

3.2 Project Documents

S. No

Document Number

Title

200-51-IN-DEC-00002

Alarm Philosophy Complexes

for CP6S and CP7S

Company No._Rev. 200-51-IN-SPC-00021_00

12 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

S. No

Document Number

Title

200-51-IC-DEC-00004

200-51-IN-DEC-00003

200-51-IN-DEC-00004

200-51-IN-DEC-00006

200-20-CE-SPC-00015

200-51-IN-SPC-00025

200-51-IN-SPC-00026

200-51-IN-SPC-00019

200-51-IN-SPC-00028

200-93-IN-SPC-00001

200-51-IN-SPC-00022

200-51-IN-SPC-00029

200-51-IN-SPC-00023

200-51-IN-SPC-00031

200-51-IN-SPC-00032

200-51-IN-SPC-00020

200-20-PR-DEC-00021

560-51-IN-DWG-00001

Cyber Security Assessments and Control Report Instrument and Control Systems Design Basis for CP6S and CP7s Complexes Electrical and Instrument Interface Philosophy for CP6S and CP7s Complexes Integrated Control and Safety Systems (ICSS) Philosophy for CP6S and CP7s Complexes Painting Specification for CP6S and CP7S Complexes Specification for Alarm Management System (ALMS) for CP6S and CP7s Complexes Specification for Analyzers and PEMS for CP6S and CP7s Complexes Specification for Field Instrumentation (incl. Flow, Level, Pressure and Temperature Instrumentation and F&G Detectors) for CP6S and CP7S Complexes Specification for Instrument Asset Management System (IAMS) for CP6S and CP7S Complexes Specification for Fuel Gas Metering for CP6S and CP7S Complexes Specification for Instrument Cables and Cable Glands for CP6S and CP7S Complexes Specification for Integrated Control and Safety System (ICSS) for CP6S and CP7s Complexes Protection, Specification Condition and Performance Monitoring System Specification for Panels and Control Consoles for CP6S and CP7S Complexes Specification for Plant Operating Information System for CP6S and CP7S Complexes Specification (Control Valves, Pneumatically/Motor Actuated/ On-Off Valves, Pressure Relief Valves) for CP6S and CP7S Complexes Utilities Design Basis for CP6S and CP7S Complexes Instrument Grounding Details Complex

for Machinery

for Valves

for CP6S

3.3 Contractor Documents

S. No

Document Number

Title

Not Applicable

Not Applicable

Company No._Rev. 200-51-IN-SPC-00021_00

13 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

3.4

International Codes and Standards

S. No

Code/Standard

Title

ASME B1.20.1

Pipe Threads, General Purpose (Inch)

ASME B16.5

ASME B16.20

Pipe Flanges and Flanged Fittings NPS 1/2 Through NPS 24 Metric/Inch Standard Metallic Gaskets for Pipe Flanges

ASME B16.36

Orifice Flanges

ASME B16.47

Large Diameter Steel Flanges

ASME B31.3

Process Piping

ASME B40.100

Pressure Gauges and Gauge Attachments

ASME B46.1

Surface Texture (Surface Roughness, Waviness, and Lay)

ASME PTC 19.3 TW

Thermowell - Performance Test Codes

ASME Section IX

ASME VIII

API RP 551

Qualification Standard FOR Welding, Brazing, And Fuzing Procedures; Welders; Brazers; And Welding, Brazing, And Fusing Operators - Welding, Brazing And Fusing Qualifications Boiler and Pressure Vessel Code - Rules for Construction of Pressure Vessels Process Measurement

EN 10204

Metallic Products – Types of Inspection Documents

IEC 60079 series

Explosive Atmospheres (all relevant parts)

IEC 60068-2-27

IEC 60529

Environmental Testing – Part 2-27: Tests – Test Ea and Guidance: Shock Degrees of Protection Provided by Enclosures (IP Code)

IEC 60584

Thermocouples

IEC 60751

IEC 60770-1

IEC 61000-4 Series

IEC 61140

Industrial Platinum Resistance Thermometers and Platinum Temperature Sensors Transmitters for Use in Industrial-Process Control Systems – Part 1: Methods for Performance Evaluation Electromagnetic Compatibility (EMC): Testing and Measurement Techniques Protection Against Electric Shock – Common Aspects for Installations and Equipment

Company No._Rev. 200-51-IN-SPC-00021_00

14 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

S. No

Code/Standard

Title

IEC 62305

Protection Against Lightning

IEC 62443 Series

Security for Industrial Automation and Control Systems

ISA 18.1

Annunciator Sequences and Specifications

ANSI/ISA 18.2

Management of Alarm Systems for the Process Industries

ANSI/ISA-71.04

ISO 5167

ISO 5168

MR0175/ISO 15156

NFPA 72

NE 043

Environmental Conditions for Process Measurement and Control Systems: Airborne Contaminants Measurement of Fluid Flow by Means of Pressure Differential Devices Inserted in Circular Cross-section Conduits Running Full Measurement of Fluid Flow – Procedures for the Evaluation of Uncertainties Petroleum and Natural Gas Industries – Materials for use in H2S - Containing Environments in Oil and Gas Production National Fire Alarm and Signaling Code

Standardisation of the Signal Level for the Failure Information of Digital Transmitters

Company No._Rev. 200-51-IN-SPC-00021_00

15 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

4 PURPOSE

The purpose of this document is to define the minimum technical requirements for instrumentation design, engineering, prefabrication and installation of the equipment supplied on the packaged units for NFPS Offshore Compression Complexes Project COMP2.

Compliance with this specification does not relieve the package VENDOR from the responsibility to handover fit for purpose equipment in accordance with codes and standards, project specifications, COMPANY specifications and good engineering practice.

This document should be read in conjunction with other design philosophies, specifications and referenced document specified in Section 3.

5 SCOPE

This specification along with all the specifications and standards referenced in this document, defines the minimum technical requirements for the selection, engineering, design, manufacture, inspection, testing and installation of all instrumentation, control and safety systems for the PROJECT. As defined in Section 1.2.

6 GENERAL TECHNICAL DESIGN CRITERIA

6.1 Design Life

In general, the design life of the new facilities shall be for an operational life of 30 years. Any specific deviation shall be subject to COMPANY approval.

To minimise the disruption of the platform operations, equipment shall have full replacement or spare parts/component replacement in case of malfunction. All equipment must have at least two (2) years proven field experience. Prototype equipment and components shall not be used.

VENDOR shall provide technical support and provision of all supplied components throughout PROJECT design life (30 years). For any components becoming obsolete, VENDOR shall suggest and provide alternative component fit for the intended purpose.

6.2 Environmental Condition and Weather Protection

All field mounted instruments, junction boxes, local control panel/unit control panel and instrument accessories installed outdoor shall be suitable for installation in saliferous, marine and corrosive environment for offshore locations and at onshore locations.

The offshore environmental conditions on the respective offshore / onshore environmental data as given below:

6.2.1 Offshore Environmental Condition

• Ambient Temperature

o Expected maximum daily average o Expected maximum daily o Expected minimum daily o Expected yearly maximum temperature o Expected yearly minimum temperature

: 36°C : 41.1°C : 12.7°C : 45.6°C : 8.3°C

Company No._Rev. 200-51-IN-SPC-00021_00

16 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

o Air cooler design o Gas Turbine design o Black bulb temperature o Design temperature for equipment operating

: 45.6°C : 42°C : 84°C : 49°C

at ambient conditions

• Relative Humidity

o Minimum o Average o Maximum

• Atmospheric Pressure

o Minimum o Maximum

• Rainfall

o Once in 2 years minimum o Once in 10 years minimum o Once in 50 years minimum

• Sea Water Temperatures (°C):

: 37 % : 71 % : 100 %

: 998 mbar : 1020 mbar

: 12 mm/h : 27 mm/h : 41 mm/h

Table 6.1: Sea Water Temperature

Water Depth (m)

Min. Temperature

Max. Temperature Mean Temperature

0

15

30

45

60

75

15.8

15.8

15.6

15.2

16.3

17.1

34.7

34.5

33.4

33

31.8

27.5

24.1

22.9

23.2

22.7

22.1

21.6

6.2.2 Onshore Environmental Condition

• Barometric Pressure

o Design Barometric Pressure o Maximum Barometric Pressure o Minimum Barometric Pressure o Maximum Instantaneous Barometric Charge (for LNG tank pressure/vacuum protection design)

: 1013 mbar : 1020 mbar : 995 mbar : 25 mbar

• Ambient Temperature

o Annual Average Air Temperature (Dry Bulb)

: 29°C

Company No._Rev. 200-51-IN-SPC-00021_00

17 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

o Annual Average Air Temperature (Wet Bulb) o Yearly Maximum (Dry Bulb) o Yearly Minimum (Dry Bulb) o Extreme Dry Bulb Temperature

: 21°C : 49°C : 5°C : 49°C

• Relative Humidity

o Mean Daily o Mean Daily Maximum o Mean Daily Minimum

• Solar Radiation

: 59% : 80%(@4°C Dry Bulb) : 35%(@4°C Dry Bulb)

o Yearly Maximum Daily Measured o Design

: 8.03 kW/m2 : 0.90 kW/m2

Note: Equipment exposed to sunlight shall be designed for black bulb temperature.

Placing of Control Panels outdoors shall require Company’s approval and shall be in accordance with Specification for Packaged Equipment for CP6S And CP7S Complexes, document no. 200-51-IN-SPC- 0021.

Design rating of servers installed indoors shall in compliance with ETS 300 019-1-3 Class 3.1e, as a minimum. For other equipment installed indoor in environment-controlled location with HVAC, design rating of all electrical/ electronic equipment shall be +49 ºC.

As minimum, all equipment installed outdoor shall be with IP66 ingress protection as per IEC 60529. For instrument which are installed at splash zone area (impacted due to green water wave impact), ingress protection rating shall be IP67 or higher. In general, tubing shall not be routed in the vicinity of such areas to avoid impact / impingement due to waves. Consideration to be given for usage of instrument protective enclosures, where practical/available for the intended instrument, which act as a protective shield to the instruments which could be potentially exposed to the waves/splash. For cable routing in such exposed areas, consideration to be given for covered trays to protect cables from direct impact due to waves. In general, instruments, push buttons, cable, cable trays, tubing etc. shall not be installed in splash zone.

All control panels and other instrument enclosures installed in unclassified areas inside enclosed building shall be rated minimum IP42, except for IT cabinets (server and network) which shall be minimum IP20. Server cabinet doors are preferred to be mesh type (perforated) for maximum air flow.

All electronics shall be tropicalized, with measures such as anti-corrosion coatings on printed circuit boards and hermetical sealing of electronic circuitry, shall be incorporated within the instrument design to withstand the outdoor ambient conditions and function properly in the outdoor environment. Conformal coatings for PCBs, electronic modules, etc for control system equipment in indoor installation shall be provided to meet severity levels of ISA -71.04 Class G3.

Where equipment contained in enclosures may be subjected to temperatures exceeding 85°C due to solar, radiant or self-heating, the enclosure shall be provided with either a canopy type covering or a cooling system to maintain internal temperature below 85°C or equipment operating limit.

Canopy shall be provided for all electronic Instrumentation that are exposed to direct sunlight, as well as junction boxes when required. Canopy shall be UV resistant electrostatic free FRP / GRP material.

For environmental conditions which is to be met during equipment storage, it shall follow the storage temperature and conditions recommended by manufacturer of the equipment during storage of equipment during the execution phase.

Company No._Rev. 200-51-IN-SPC-00021_00

18 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

6.3

Instrumentation Standardization

Instrumentation (field Instrumentation, valves, ICSS, package control system and instrument bulk e.g. tubes and fittings) standardization requirements to be aligned with project contractual strategy including phased investments of the PROJECT involving different CONTRACTORS. Instrument standardization shall be considered for the PROJECT, including packaged units, to maximise the use of instrument with same technology, manufacturer and model for the same use, wherever possible.

6.4 Electrical Hazardous Area Protection

All instrument installed in outdoors shall be suitable for installation in Zone 1, Gas Group IIB and Temperature Class T3 as minimum. For instruments installed within battery rooms, it shall be certified for installation in a Zone 1, Gas Group IIC, and Temperature Class T3 as minimum. Equipment certification shall comply to IECEx standard.

Field instrument shall be Ex ‘d’ flameproof certified, unless otherwise specified. Intrinsically Safe Ex ‘i’ protection is acceptable (as per package VENDOR recommendation) for some of the machine monitoring signals, anti-surge control signals, etc.

6.5 Obsolescence Management

VENDOR shall submit an obsolescence plan and a support life cycle plan for both hardware and software supplied for technologies used for technologies used as part of the Services. The obsolescence should be managed according to IEC 62402 and aligned with COMPANY obsolescence plan.

All technologies shall be supported by the VENDOR for a minimum of 15 years from the placement of order or 10 years from end of warranty, whichever period ends last. These technologies include system hardware, firmware, and software with spare parts and services. This support shall not be contingent on the customer upgrading to later releases of software or hardware unless this upgrade is supplied at no additional cost.

System software upgrades to the latest revisions of vendor software and vendor approved underlying operating system shall be provided for, up to the end of the EPC warranty period. The obsolescence for backward compatibility to hardware and software shall be at least 10 years. Bid proposal shall cover this requirement explicitly.

6.6 Electromagnetic Compatibility

The equipment supplied shall function without introducing intolerable electromagnetic disturbances to other items of equipment or being susceptible to electromagnetic influences from other sources. The equipment shall include electromagnetic compatibility and electrostatic discharge protection in accordance with the requirements of the IEC 61000-4 standards.

6.7 Mechanical Shock and Vibration Compatibility

Mechanical shock and Vibration compatibility shall be in accordance with IEC 60068-2-27, IEC 62828- 1, and IEC 61131-2. Where no product specific standards exist, a continuous or repetitive vibration of 2.5 G, 5 -500 Hz shall not cause any damage or malfunction.

Company No._Rev. 200-51-IN-SPC-00021_00

19 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

6.8 Lightning Protection and Electrical Surge Protection

For lightning protection, all field transmitters which are installed outdoor and directly exposed to sunlight shall be equipped with inbuilt transient surge protection within the circuitry. Similarly, photo-optic isolators or inductive surge protection for the ICSS I/O cards and package control system I/O cards shall be integrated in the I/O card design for each channel.

Surge protection device/module shall be installed at the incoming power supply inside the ICSS power distribution panel. Surge protection device/module to be installed in package control panels installed in the field at the incoming power supply. Surge protection device shall be designed and tested in accordance to IEEE requirement.

6.9

Instrument Signal Definition

All electronic analogue transmitter signals connected to ICSS and package equipment control and safety systems shall be smart 4-20mA output superimposed with HART protocol (revision 7 or latest), 2 wire, 24VDC loop powered. Transmitters shall be supplied with integrated local digital indicators to display the measurement with associated engineering units. Separate remote local indicator shall be provided for transmitter installed on inaccessible location.

Transmitters with 4-20mA output shall comply with NAMUR NE043 enabling process under range and over range detection and sensor failure detection with upscale or downscale burnout selector switch. The fault detection configuration in ICSS shall match to the field equipment fault generation settings.

Smart transmitters shall have output analog signal operational between 3.8 mA to 20.5 mA, unless specified otherwise by COMPANY.

3-wire and 4-wire transmitters with external power supply are acceptable for special instruments like analyzers, Fire and Gas devices, magnetic flow meters, ultrasonic flare flow meters, coriolis flow meters etc. in situations where they are not available in standard 2-wire version, loop powered.

Discrete inputs and outputs shall be 24VDC rated system for process instrumentation signal exchange across systems with either dry or wet contacts. Hardwired signal exchange between Instrument and Electrical systems for MCC, heater related trip signals and control signals (e.g. VFD speed set point signals) will be via the Interposing relay panel (IRP) which will be installed in Electrical switchgear room. Interposing relay shall be 24VDC with maximum 3 watts power consumption. Refer to Electrical and Instrument Interface Philosophy for CP6S and CP7S Complexes, 200-51-IN-DEC-00004.

Actuated on-off valves (shutdown valves, blowdown valves and process on-off valves) and control valves position feedbacks shall be provided through SMART type position transmitter having 4-20mA output superimposed with HART protocol. Proximity switch shall be used for valves with critical logics and interlocks. Actuated Valves and Control Valves shall either use proximity switches or position transmitter for position feedback. Refer to Piping and Instrumentation Diagram Legend - Typical Details for Instrumentation (200-20-PR-PID-00035/36-0001).

MOVs shall be provided with integral position feedback signals/contacts for valves open and close indications. Provision shall be made in the design to provide a contactless position feedback transmitter which give a 4-20mA analog signal corresponding to valve travel for remote indication when required.

Outputs to solenoids valves shall be 24VDC supply powered by ICSS / UCP. Solenoids shall be low power type below 5 watts power consumption.

For ESD signal, normally energized (fail-safe) design shall be followed. For FGS, normally de-energized (non fail-safe) design shall be followed.

Company No._Rev. 200-51-IN-SPC-00021_00

20 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

For F&G input signal to FGS, all discrete input signal from F&G detectors shall be dry contact (volt-free) and shall be supervised to detect faults (open or short circuit) in the field wiring. For ESD, discrete input signals part of SIF shall be supervised to detect faults (open or short) in the field wiring.

Output signals from FGS to solenoids or alarm devices shall be energized to trip/alarm, with power fed from FGS. All output circuits shall be continuously line monitored for fault conditions (open or short circuit detection).

Thermocouple signals for flare tip applications shall be wired to flare local control panel for monitoring / alarm.

6.10 Material Requirement

For well fluid process/hydrocarbon services, wetted part material and pressure retaining parts including manifold shall be Inconel 625 / Hastelloy C276 as minimum.

Tubing and fittings material shall be minimum Inconel 625 for all services. Sea water service shall utilize monel as minimum.

For sour service application, material shall be fully in compliance with the ISO 15156/ NACE MR 01-75 requirements and material certificate to EN 10204 3.2 shall be provided.

In general, wetted parts materials for all instruments shall follow the associated piping class and shall as minimum have SS316 for non-hydrocarbon and non-sour services.

SS 316 instruments installed in exposed areas (under direct sunlight) where the ambient temperature / process temperature exceeds 60°C suitable alternate material shall be considered to avoid Chloride induced stress cracking). Stainless steel grade other than 316 are not allowed.

For seawater services, instrument wetted parts material shall be Monel 400 or equal.

Transmitter wetted parts, Instrument manifold, mounting bolts and nuts, tubing and and fittings shall be of same material of construction in order to avoid bi-metallic corrosion.

All materials including gaskets shall be free from hazardous substances such as Asbestos, mercury, halogen, ceramic fibre, radioactive materials etc.

6.11 Utilities and Power Supplies

6.11.1 Greenfield Compression Hubs, RPs and WHPs

In each of CP6S/CP7S compression hubs, instrument air will be available which shall be utilized for actuation of control valves, ESD valves, blowdown valves and general purpose on-off valves.

The supply condition for instrument air is given in the following table:

Table 6.11.1: Instrument Air Supply Conditions

Pressure (barg)

Temperature (°C)

Min Normal Max

Design Min Normal Max

Design

Instrument air

5.5

7.5

9.0

10

Amb. Amb.

40

85

Company No._Rev. 200-51-IN-SPC-00021_00

21 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

Type of valves actuation for Greenfield compression hubs shall be as per table below:

Table 6.11.2: Valves Actuation Type Based on Platforms for Greenfield

Facility

Scope w.r.t Compression

Valve type

Actuation type

Remarks

CP6S/7S

Greenfield

SDV, BDV, General purpose ON-OFF valve, Control valve, HIPSS Valve, Anti Surge Valve

Pneumatic (Instrument air)

CP6S/7S

Greenfield

MOV

Motorized

LQ6S/7S

Greenfield

SDV, BDV, General purpose ON-OFF valve, Control valve

Pneumatic (Instrument air)

The ICSS and all package UCPs (except Gas Turbine Compressor Package) shall be supplied with two 230VAC, 50 Hz from dual redundant UPS. UPS and Non-UPS supply shall be 230V, 1Phase+N + Earth for all new platforms in COMP2 PROJECT.

Power distribution panels shall be used to distribute UPS power for the ICSS cabinets/panels and other cabinets/panels inside the Local Equipment Room (LER) in CP platform, CCR and CCR Rack Rooms in LQ platform. The UPS power distribution panel shall be installed in the LER and CCR Rack Room and supplied by IMICC. For field instruments and packaged equipment instrumentation in field that need external 230 VAC UPS power supply, it shall be powered from the Instrument UPS power distribution panel.

Each cabinet, that requires power, shall be equipped with dual feeders from redundant UPS supply. UPS supplies shall be fed from independent buses. All the components inside cabinets (i.e. control system components (controllers, I/O modules etc) and panels fans shall be powered by the UPS supply. Each cabinet shall be provided with fans to ensure that HVAC failure does not expose electronics to more than 49°. Panel/cabinet lighting and utility sockets shall be powered by non-UPS supply.

Gas Turbine Generator (GTG) package panels (UCP, anti-surge panel, CPMS panel etc) which are supplied by the Machinery VENDOR, panels shall be powered by Platform UPS (110V DC). The lighting and utility sockets of these package panels shall be powered by Platform’s non-UPS supply.

Gas Turbine Compressor (GTC) package panels (UCP, anti-surge panel, CPMS panel etc) which are supplied by the Machinery VENDOR, panels shall be powered by the package VENDOR supplied UPS. The lighting and utility sockets of these package panels shall be powered by Platform’s non-UPS supply.

Automatic transfer switch or differential switch between the dual supplies shall be used for power supply to workstations and HMI. All the instruments shall be generally 24VDC loop powered from ICSS and package UCPs, as applicable. However, when external power supply to field instruments is required, it shall be powered from 230VAC, 50Hz UPS.

The power supply units installed in the ICSS cabinets and package UCP cabinets shall be Non-floating Power supply with the negative grounded to earth.

Solenoid valve commands, hardwired interface signals between ICSS and MCC / Package control shall be 24VDC, low power driven by ICSS I/O cards. Interface to MCC shall be through IRP. Refer to Instrument and Electrical Interface Philosophy for CP6S and CP7S Complexes, document no. 200-51- IN-DEC-0004.

Company No._Rev. 200-51-IN-SPC-00021_00

22 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

Electric motor operator for MOVs shall be provided with three phase power (400V, 50Hz, 3 wired + PE) supplied from Electrical distribution board.

6.11.2 Brownfield Tie-In & Modification

For brownfield tie-in and modification at existing RGE, RL and QG2 WHPs and RPs, the utilities and power supply requirement for the instrument shall be in accordance with existing facilities design conditions.

In general, on-off valves provided by EPCOL in RGE RP6S, RP4S, RP7S and RP8S are hydraulically actuated. Any new valves part of COMP2 to be installed on RP6S/RP7S which are bridge linked to CP shall be pneumatically operated with pneumatic supply from bridge linked CP. Remote RP and WHP valve actuation method shall be based on existing platform’s philosophy.

For brownfield tie-in related to riser platforms which are bridge linked to the compression hub such as RGE Riser Platforms (RP6S and RP7S), instrument air will be supplied from the adjacent CP. For the brownfield compression scope on these riser platforms, instrument air will be used for the new on/off valves, SDV / BDV and control valves actuation using instrument air supplied from the adjacent compression hub.

Table 6.11.3: Valves Actuation Type Based on Platforms / Onshore for Brownfield

Facility

Scope w.r.t Compression Valve type

Actuation type

Remarks

RP6S/ RP7S

Brownfield

SDV, BDV, General purpose ON-OFF valve, Control valve

Pneumatic (Instrument air)

6.12 Engineering Units

Engineering units of this project shall follow the engineering units as per PROJECT Basis of Design, as per below:

Table 6.4: Unit of Measurement

Parameter

Unit

Abbreviation

Absolute Viscosity

Centipoise

Area

square meter

СР

m²

Cathodic Current Density

Amp per square meter

A/m²

Conductivity

Micro Siemens per centimeter

μS/cm

Current

Elevation

Flow (mass)

Flow (molar)

Amp

meter

Kilogram per hour

A

m

kg/h

kilogram mole per hour

kgmol/h

Company No._Rev. 200-51-IN-SPC-00021_00

23 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

Parameter

Unit

Flow (volume)

Force

Barrel per day. Cubic meter per hour

kilo Newton

Heat / Energy

Kilocalorie. Kilojoule

Heat Transfer Coefficient

watts per square meter per degree C

Abbreviation

BPD, m3/h

kN

kcal, kJ

W/m²°C

Heating Value

megajoule per cubic meter megajoule per kilogram

MJ/m3 MJ/kg

Heat Radiation

watts per square centimeter

W/cm²

Kinematic Viscosity

Centistokes

cSt

Length

Level

Millimeter or Meter or Kilometer

Meter or millimeter Percentage

mm or m or km

m or mm %

Liquid Density

Kilogram per cubic meter

kg/ m3

Mass Enthalpy

kilojoule per kilogram

Mass

Pipe diameter

Potential

Power

Pressure

Pressure (close to atmosphere)

Pressure Differential

Resistance

Kilogram or metric tons

Inch

Volt

Kilowatt

Bar gauge, Bar absolute

barg, bara

millimeter water column

mmH2O

Bar

Ohm

Sound Pressure

Decibel

Specific Heat

Stress

kilojoule per kilogram per degree C Newton per square meter (Pascal)

Temperature

Degree Celsius

kJ/kg

kg ort

in

V

kW

bar

Ω

dBA

W/m°C

N/m²

°C

Thermal Conductivity

watt per meter per deg C

W/m°C

Company No._Rev. 200-51-IN-SPC-00021_00

24 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

Parameter

Unit

Abbreviation

Throughput of gas at standard conditions

Time

Vacuum

Velocity

Viscosity

Volume

Standard cubic feet per minute Million standard cubic feet per day

SCFM MMSCFD

Second / minute/ hour / day

s/min/h/d

millimeter water column

mmH2O

Meter per second

centipoise

Cubic meter

m/s

cP

m3

m/s

Wind Velocity

meter per second

6.13 Painting and Coating

Field instrument (including instrument stand) painting, shall be suitable for offshore corrosive environment and in accordance with Painting Specification, Doc. No: 200-20-CE-SPC-00015

Field instrument housing and instrument outdoor control panel with SS316/L material of construction shall be painted according to PROJECT’s Painting Specification, 3 coat system epoxy coating with minimum total DFT of 250micron.

Indoor cabinets and control console shall be finished using baked-on enamel paint or double pack epoxy paint. Interiors shall be white. The finish of cabinets and console shall be smooth and of approved VENDOR’s standard colour Light Grey (RAL 7035). One quart of finishing paint will be shipped with the system for field touch-up for each colour used.

For outdoor panels, material of construction shall be stainless steel. The panel installed outdoor shall be coated suitably (i.e. marine grade paint, etc.) or DFT 250micron for installation in saliferous, marine and corrosive environment for offshore locations.

For Firewater Panel, the coating colour shall be fully “Red”.

Refer Specification for Panels and Control Consoles for CP6S and CP7S Complexes, document no. 200-51-SPC-00031 for cabinet painting and coating information.

6.14 Nameplate and Identification

Instruments shall have the following information on a permanently fastened 316 stainless steel nameplates in accordance with the project tagging philosophy.

a) Equipment identification number, which shall be supplied by Purchaser.

b) Manufacturer’s name, model, and serial number.

As applicable, nameplates shall also state service, pressure rating of pressure holding parts, operating range, certifications, voltage, frequency, and materials of construction for parts exposed to process fluids.

In addition to any package VENDOR supplied nameplate, each installed instrument shall be provided with an identification nameplate containing the tag number and the process service description. These nameplates shall be fabricated from a corrosion resistant material (16 U.S. gauge stainless steel or

Company No._Rev. 200-51-IN-SPC-00021_00

25 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

equivalent is preferred) and shall be permanently and securely fastened to the instrument by either stainless steel wire or drive screws. The identification nameplate shall be readable from grade or the associated maintenance platform. If any process connection is not viewable from its associated instrument, then a separate tag nameplate is required at each such process connection.

Refer Appendix 1 for detail of Instrument identification nameplate.

Instrument nameplate shall have tag number with service description.

6.15 Instrument Identification and Numbering

Instrument identification and numbering, including package instruments shall be in accordance with COMPANY’s Equipment Numbering Philosophy.

As part of the development of digitalisation solution initiative, CONTRACTOR shall develop and implement a Master Tag Register, listing all the tagged items and its tag attributes, as well as its Tag Document association in the PROJECT. This register shall be developed by consolidating all tagged items in the project, including VENDOR supplied packages.

CONTRACTOR shall classify all tag items and its attributes per CFIHOS functional tag classification and submit Master Tag Register in a data delivery templates to be provided by COMPANY during Detail Engineering. CONTRACTOR shall progressively submit Master Tag Register and Data Quality & Consistency Check Report at periodic submission timeline to be agreed with COMPANY.

6.16 Instrument Engineering Database

SmartPlant Instrumentation (SPI) version 13.1 (13.01.00.3927 HF 28) shall be used as instrument engineering database for this PROJECT. Instrument deliverables (i.e. Datasheets, Index, I/O lists, etc) shall be generated as part of SPI in accordance with Instrument Database Specification, 200-51-IN- SPC-00010 and SmartPlant Engineering Applications & Drafting Procedure by COMPANY, Document no PRJ-PJL-PRC-007 Rev 00.

For brownfield scope where existing instrument SPI database may not be available, Microsoft® Excel spreadsheet will be used for instrument deliverables (e.g. Instrument Index, I/O list, datasheets and etc).

6.17 Instrument QR Code

Package VENDOR shall provide for each item in its scope of supply a permanent mounting bracket (or equivalent) that is most visible to individuals standing in front of the equipment to place the QR code shall be as per QR code specifications submitted by DSI (Digital System Integrator). Size of the QR code will be determined by DSI (Digital System Integrator) however but it shall not exceed 10x5 cm.

7 PACKAGE TYPE DEFINITION AND CONTROL PHILOSOPHY

7.1 General

Equipment packages shall be categorized into four types, P1, P2, P3 and P4 as defined in the following sections.

Packages shall only be classed as P3 type where the UCP is based on a package VENDOR standard design and configuration, with only minimal project specific customization requirements, i.e., tag numbers & service descriptions.

Company No._Rev. 200-51-IN-SPC-00021_00

26 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

Where the package controls are not based on a standard design and configuration the package shall be classed as a P2 or P1 type with the control and safety functionality fully integrated into the Platform’s ICSS.

Instrumentation and associated instrument equipment shall be selected from the COMPANY’s approved VENDOR list. Any deviation to project specification must be approved by the COMPANY and fully documented.

Refer Appendix 1 for Package Type P1, P2, P3 and P4 scope of supply battery limits.

7.2 P1 Type Package

This package is delivered with all skids mounted instruments installed and connected to process line and/or pneumatic sub-header/line inside package, without cables, cable trays and junction boxes. The skid Instrument shall be wired to nearest junction boxes according to the type of signal. All cable, cable trays and junction boxes including their termination, routing and testing shall be by CONTRACTOR.

This package has minimal instrumentation and is fully controlled by the Platform’s ICSS according to functional description given by VENDOR.

A functional description of the package’s operational requirements which includes I/O list, logic diagram, control narrative, control, alarm and trip set point list, C&E matrix etc. shall be provided by VENDOR for the development of the ICSS configuration for the package

The package regulatory control and safety algorithms shall be validated during the ICSS FAT.

Fire and gas detectors shall be supplied by CONTRACTOR.

7.3 P2 Type Package

This is a prefabricated equipment skid with all skid mounted instruments are already installed and connected to process line and/or pneumatic sub-header/line inside package. The Instrument shall already be pre-wired via cable trays to skid edge junction boxes or local control panel. All the Instrument, hook up material and cabling within skid shall be supplied and installed by VENDOR.

P2 packages are fully controlled by the Platform’s ICSS according to functional description supplied by Equipment VENDOR. The corresponding machine vibration and temperature monitoring and protection will be integrated into Platform MMS (supplied by CONTRACTOR). MMS will be interfaced with CPMS supplied by GTC VENDOR. Refer to Specification for Machinery Protection, Condition and Performance Monitoring System for detail of MMS specification.

Cabling from the skid edge junction boxes to Platform’s ICSS installed in the Local Equipment Room (LER) shall be routed, supplied and installed by CONTRACTOR.

A functional description of the package’s operational requirements which includes I/O list, logic diagram, control narrative, control, alarm and trip set point list, C&E matrix, wiring diagram etc. shall be provided by VENDOR for the development of the ICSS configuration for the package.

Small compressors, pumps and simple process skids are example of P2 Packages. This is to be evaluated in detail with VENDOR during bid clarification to ensure proper implementation of Package Controls.

Cabling and junction boxes shall be segregated by system and signal type (DCS, ESD, FGS, MMS and Analog, IS, etc) as per Instrument and Control Systems Design Basis.

Universal IOs for DCS, FGS and ESD system shall be utilized at CP6S and CP7S. Cables for related instrument connected to DCS (AI, AO, DO (signal) and DI) will have individual shield and overall shield.

Company No._Rev. 200-51-IN-SPC-00021_00

27 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

Cables for related instrument connected to ESD and FGS (AI, AO and DI) required individual shield and overall shield. ESD and FGS DO type required only overall shield.

Below table shall be adhered to for individual shield and overall shield of cables.

Table 7.3: Screen segregation for Universal IO

UNIVERSAL I/O FOR P1/P2 AND OTHER INSTRUMENT

I/O TYPE AI AO DI DO (Signal) DO (Powered)

DCS IS/OS IS/OS IS/OS IS/OS Not Required

ESD IS/OS IS/OS IS/OS OS Not Required

FGS IS/OS IS/OS IS/OS OS Not Required

Fire and gas detectors shall be supplied by CONTRACTOR.

7.4 P3 Type Package

Similar to P2 Type Packages, this is a prefabricated equipment skid with all skid mounted instruments are already installed and connected to process line and/or pneumatic sub-header/line inside package. The Instrument shall already be pre-wired via cable trays to skid edge junction boxes or local control panel. All the Instrument, hook up material and cabling within skid shall be supplied and installed by VENDOR.

However, the control functions within this type of package are implemented in a dedicated UCP as part of the package scope of supply, including all relevant control equipment. For project standardization purposes, the UCP shall be based on the standard PLC make and model selected as for the project according to the Project VENDOR List. Control actions shall be fully independent and shall have no common mode failure.

The corresponding machine vibration and temperature monitoring and protection will be integrated into Platform’s MMS (supplied by GTC VENDOR). However, specific for GTC and GTG package, independent MMS same make with Platform’s MMS shall be supplied for the packages. MMS shall be supplied in accordance with Specification for Machinery Protection, Condition and Performance Monitoring System.

Cabling from the skid edge junction boxes to the UCP installed in the Local Equipment Room (LER) shall be routed, supplied and installed by CONTRACTOR.

For shutdown function, independent protective systems on a package are normally not required and that the package would be isolated and shut down by the platform ESD. However, if independent ESD required for the Package, it shall comply with ESD specification depicted in Specification for Integrated Control and Safety Systems (ICSS). The package ESD shall be segregated from the control function of the package.

All shut down alarms shall be included in first-up sequence and the first-up alarm shall be identified and transmitted to the DCS. During the maintenance of Instrument, selected ESD initiator shall be provided at the DCS with MOS for maintenance purposes during normal operation.

All safety and control executive actions between the package UCP and the Platform’s ICSS shall be hardwired. The package UCP shall be interfaced to the Platform’s DCS for monitoring.

Fire and gas detectors shall be supplied by CONTRACTOR except for machinery enclosure. Fire and gas detectors within enclosure, air intake and vent shall be supplied by VENDOR and connected to

Company No._Rev. 200-51-IN-SPC-00021_00

28 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

FGS supplied by VENDOR. All fire and gas detection and executive actions shall be executed by this Package FGS.

Every Safety Instrumented Function (SIF) shall be reviewed and assigned a SIL in accordance to IEC 61508/61511. The design and implementation of every safety loop shall satisfy the SIL requirements of the associated SIF.

For the motors within the package unit which are controlled by UCP, the control and safety signals exchange between the Package Unit and Platform’s MCC shall be hardwired through Interposing Relay Panels.

Packages HMI shall have all necessary resources for operation, control, configuration, and programming.

Cabling and junction boxes shall be segregated by system and signal type (DCS, ESD, FGS, MMS and Analog, IS, etc) as per Instrument and Control Systems Design Basis.

7.5 P4 Type Package

Similar to P3 type packages, however the dedicated control panel will be a stand-alone local control panel (LCP) located within skid with minimum interface to ICSS. There is no serial link interface between the LCP and ICSS.

If required, Package specific alarms like failure or abnormal alarm between the package UCP and the Platform’s ICSS shall be hardwired. Cabling from the LCP to the Platform’s ICSS installed in the Local Equipment Room (LER) shall be routed, supplied and installed by CONTRACTOR.

Fire and gas detectors shall be supplied by CONTRACTOR.

7.6 Facilities Control Philosophy

Operation and control of the RGE CP6S, and CP7S compression hubs are detailed in ICSS Philosophy.

In general, for RGE CP6S and CP7S compression hubs, the base case design shall be hub wise control where each compression hubs will have its own control room in LQ for hub based operation, control and monitoring.

In addition to the base case design of hub wise satellite control for QG-S compression hubs, as an additional case, centralized control of the RGE offshore compression hubs from the CP6S control room is considered. For QG-S RGE hubs, CP6S will be the centralized hub for other satellite hubs (i.e. CP7S).

In any case, it shall also be possible to perform individual and independent hub wise controls locally from each hub.

The control and operation of the facilities shall be designed to be in-line with COMPANY Operation and Maintenance Philosophy.

Company No._Rev. 200-51-IN-SPC-00021_00

29 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

8 SCOPE OF WORK AND SUPPLY

VENDOR is responsible for the engineering, design and supply of instrument systems to control and protect equipment within packaged unit. All Instrument, valves and accessories supplied shall be from COMPANY Approved VENDOR List (AVL).

8.1 Design Basis Requirements for Instrumentation

Package instrumentation shall be selected and designed according to project requirements including environment and process conditions, and comply with following specifications:

  1. By the time the package unit is delivered, VENDOR shall guarantee that the equipment provided shall not be obsolete. The instrumentation and controls shall be proven in use, no prototype or beta test instrumentation is allowed. Warranty and spare parts policies are described in the respective Material Requisition/RFQ, Purchase Order or Contract.

  2. P3 package VENDOR shall provide an obsolescence road map for each of the components used within their network/equipment for 30 years product life cycle. Obsolescence roadmap/plan shall include but not limited to:

a. Hardware platform used on servers, workstations, firewalls, switches, HMI’s, routers etc.

b. Software platforms and associated patches installed on servers, workstations, firewalls,

switches, HMI’s, routers etc.

  1. All applicable software platforms and patches / hardware platforms, applications and patches, firmware and operating system shall be at the latest level / revision supported and approved by the respective P3 package VENDOR during site acceptance.

  2. Each instrument shall be calibrated and certified by the package VENDOR. Before delivery, a copy of the factory calibration certificate and the calibration/validation report sheet shall be delivered to the CONTRACTOR; these shall be included within the technical documentation requested in the requisition.

8.2 Requirements for Instrument Installation and Earthing

Installation of all field Instrument, local panel, junction boxes, cables, mounting support & accessories and earthing shall be as per following reference documents:

• Process and Pneumatic/Hydraulic Hookup Drawings

•

Instrument Installation Details

• Earthing scheme/philosophy for field instrument shall be as per Instrument Grounding Details

for CP6S Complex, Drawing No: 560-51-IN-DWG-00001 for earthing details.

9 PACKAGE DESIGN CRITERIA

9.1 Power Supply Network

For CP6S and CP7S Compression Hub, the following power supplies will be available for each package unit (except Gas Turbine Compressor) as required:

• 230V AC UPS, 50Hz, 1 phase + N, 2 wire + PE (from UPS) (Unearthed/ IT)

Company No._Rev. 200-51-IN-SPC-00021_00

30 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

• 230V AC, 50 Hz, 1 phase + N, 2 wire + PE, non-UPS (Solidly earthed / TN-S): For normal power

supply for lighting, power socket, etc.

• 400V AC, 50Hz, 3 phase + N, 3 wires + N + PE (Solidly earthed / TN-S)

For P3 type package, the power used for UCP shall be taken from 230 VAC UPS feeders, distributed by PDB and converted by internal power supply unit installed inside the UCP. Internal power supply shall be redundant in configuration. The loss of power shall be alarmed to the operator workstation located at the control room.

Internal power supply shall meet the following minimum requirements:

•

Incorporate a fully redundant design such that loss of any component or single power source will not affect system operation.

• Provide full fault diagnostics with an external alarm to indicate any internal power supply

equipment malfunction or abnormal operating mode.

• Permit safe maintenance/removal/replacement of any power supply module on-line without

affecting system operation.

• For DC power supplies, blocking diodes shall be employed to provide reverse polarity protection.

Use of batteries for supply of DC power is not acceptable except for GTC and GTG package in which the battery shall be the back-up in case

9.2

Instrument Air Network

Platform instrument air will be available for each package unit skid, through one single connection tapping point.

For offshore greenfield compression hubs, the instrument air supply pressure conditions as per Table 6.1: Instrument Air Supply Conditions.

From that taping point, VENDOR shall supply reducer / filter and instrument air header for distribution inside package. Size of header will be defined according to the instrument installation specification. VENDOR shall provide instrument air consumption requirements to CONTRACTOR.

Instrument air distribution within package shall use Instrument air manifold if there is a sizeable amount of consumers within the Package. Otherwise, isolation valve shall be provided on the Instrument air header for distribution to dedicated consumers.

9.3 Field Instrumentation and Valves

All field Instrumentation and valves installed in packaged unit shall be supplied as per following specification:

• Specification for Field Instrumentation (Incl. Flow, Level, Pressure and Temperature and Fire &

Gas Devices), Document No.: 200-51-IN-SPC-00019

• Specification for Analyzers and PEMS for CP6S And CP7S Complexes, Document No.: 200-51-

IN-SPC-00026

• Specification for Instrument Cables and Cable Glands for CP6S And CP7S Complexes,

Document No.: 200-51-IN-SPC-00022

• Specification for Valves (Control Valves, Pneumatically/Motor Actuated On-Off Valves, Pressure

Relief Valves) Document No.: 200-51-IN-SPC-00020

Company No._Rev. 200-51-IN-SPC-00021_00

31 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

10 UNIT CONTROL PANEL

10.1 UCP Construction and Design

Construction and specification for Unit Control Panel (UCP) shall comply with Specification for Panels and Control Consoles.

Control and marshalling section of UCP shall be segregated into dedicated cabinets.

Basic design principle shall be as follows:

• Marshalling section: for interface between I/O’s and the PLC

• Control section which contained all electronic equipment (PLC, HMI, MMS, ACS, Over speed protection system, etc.). Combined Cabinet System / Marshalling is accepted providing all the spares required in Section 14 below are compiled by VENDOR.

10.2 UCP Location

UCP shall be installed inside pressurised air-conditioned either in Electrical Room (ER), Instrument Rack Room or Local Equipment Room (LER). Local Control Panel if required shall require approval from COMPANY.

In case of field installation, the following additional requirements shall be fulfilled (i.e. LCP if required and applicable):

• Panel supplied by VENDOR shall be suitable for the installation in the classified hazardous area

mentioned in the datasheet.

• Certification for the hazardous zone where it is installed (as required), certified by an approved

certifying authority

• Cabinets shall be provided with anti-vibration strip installed between plinths in order to minimise

any vibration

• Construction from mild steel suitably painted for protection according to project’s Painting

Specification.

• With a canopy required by environmental conditions (i.e: direct sunlight…)

• Shall be suitable for operation at maximum ambient temperature and blackbody metal temperature without the need for cooling system. VENDOR shall advise cooling system if required (e.g. HVAC unit).

•

IEC Ex / ATEX certified

Prior to manufacturing, VENDOR shall submit to CONTRACTOR, for approval, the layout and internal arrangement drawings.

10.3 UCP Control Philosophy

10.3.1 Offshore UCP Control Philosophy

The packaged UCP shall have final regulatory control over the equipment in the Third-Party Equipment Package. However, manual manipulation from DCS shall be provided (e.g. manual opening of package’s control valve from DCS via Package UCP). The packaged unit controls shall accept remote supervisory direction from the DCS. Remote control from the DCS shall be in the form of start / stop commands, set points, and permissive.

Company No._Rev. 200-51-IN-SPC-00021_00

32 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

Remote set points and start/stops shall not override any packaged unit control logic permissives.

Inputs and/or outputs for independent equipment items (pumps, compressors, etc.) should utilize separate modules where practical to minimize the impact of a single module failure.

For P3 package, Packaged equipment electric motors driven from the platform switchboards / MCC shall be able to be controlled by both UCP and DCS. These controlled signals shall be hardwired from MCC to UCP. For controlled from DCS, hardwired interface shall be provided between DCS and UCP. Other monitoring and status signals shall be sent through serial link connected from MCC to DCS. From DCS, these statuses shall be sent to UCP through serial link.

The packaged unit controls shall be designed such that a unit can be started or stopped from the Platform’s DCS via hardwired 24 VDC digital signal.

ESD shall be to trip the package equipment and bypasses the packaged unit PLC or logic solver and trips the necessary valves, and other devices to safely shutdown the facility. ESD shall also be used to trip the Packaged equipment electric motors driven from platform switchboards / MCC. Trip shall be hardwired from ESD to MCC.

Fire and gas detection and suppression shall normally be executed by platform FGS. VENDOR shall advise on the fire and gas detection and suppression requirement and if required within skid boundary, the detectors or suppression devices / piping shall be designed and supplied by VENDOR package (e.g. gas detection at air intake of compressor enclosure etc). Alternatively, the fire and gas detection for the packaged unit can be performed by the dedicated FGS system supplied by VENDOR. The FGS supplied by package VENDOR shall be the same make of the main FGS system as used by platform. Otherwise, exception shall be approved by COMPANY.

Fire and gas detectors within machinery enclosure, enclosure air intake and vent shall be supplied by VENDOR and connected to FGS supplied by package VENDOR. All fire and gas detection and executive actions shall be executed by this Package FGS.

10.4 PLC Features

10.4.1 General

PLC and other non-proprietary computer network equipment types (e.g. cable, network routers, switches, hub, fiber converters etc) make and model shall be as per COMPANY’s Approved VENDOR List (AVL).

Programmable systems shall be configured for remote access by VENDOR for maintenance purposes, including diagnostics access, fault finding, and configuration.

In general, shutdown of the package PLC will be handled by the platform ESD except for critical packages i.e. turbomachinery where control and safety logic is integrated into a dedicated package control and protection system. For PLCs executing SIF, TUV certification to SIL3 rating shall be provided.

All the firmware and software supplied with the PLC shall include licenses for design life and shall be the latest version at the time of supply.

All the electronic cards must count on protection against severe levels of G3 polluting agents according to ISA S71.04 or equivalent.

The PLC shall provide the following redundancy facilities for:

• Power supply

• CPU

Company No._Rev. 200-51-IN-SPC-00021_00

33 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

•

Internal communication buses

• Peer to peer communication

•

I/O modules, with exception for non – critical annunciator and indicative IO

10.4.2 Controller

Controller design shall ensure that processor and memory loading, including data storage, shall not exceed 50% of system capacity during actual operation. CPU loading shall be demonstrated prior to concluding the FAT.

The Controller program logic and configuration settings (e.g., tuning parameters and alarm limits) shall be preserved during power failures.

Control modules shall be provided with the capability (such as battery back-up) to store volatile data during power loss. This capacity should be sufficient to maintain that data for a minimum of ninety days.

The Controller shall be resistant to radio frequency interference according to IEC 61000-4-3 and the use of hand-held radios in the immediate vicinity of the control panel (i.e., use of radio while operating the panel) shall not interfere in any way with the control system functionality. This shall be demonstrated during the factory acceptance test (FAT) of the control panel.

Redundant controller configuration shall be provided for the package control. Written approval from COMPANY shall be obtained when simplex controller is proposed.

A watchdog timer shall be incorporated into the controller design that generates an alarm when the controller stops or when controller loading exceeds 100%. A 24 VDC hardwired dry contact shall be provided by UCP to alarm upon a controller watchdog timer alarm. Watchdog timer for communication failure shall also be provided.

System throughput (including measurement, logic processing, output change, final element movement) shall meet the response time requirements of the process (machinery speed, pressure, etc.) for control and protective functions.

Automatic self-testing and system diagnostics shall be incorporated into the Controller configuration and require no additional application logic. All testing and system diagnostics shall be a proven integral part of the standard system and shall be completely transparent to the user when the application is implemented. The diagnostics and tests shall run periodically (preferably every scan cycle), shall maximize diagnostic coverage, and shall include the following as a minimum:

a) Error detection in serial and parallel communications.

b) An internal watchdog timer to detect halted or looping processor execution.

c) A set of instructions executed at each functional cycle to exercise active system components,

including the processor.

d) A periodic memory check.

e) A check of each signal line of a parallel bus before a “read” or “write” operation to an input or

output component.

f) Detection of the removal of, or any defect in, any logic unit, communication module, processor,

I/O module, or power supply.

g) Check of the logic-solving ability including a test that exercises active system components

including the processor(s). This test shall be run prior to each logic cycle.

h) A set of power-up initialization and communications checks.

Company No._Rev. 200-51-IN-SPC-00021_00

34 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

Modification to software:

a) Modifications to software shall be restricted by a password.

b) It shall be possible to download changes in software from the engineering workstation to the Controller while it is on-line without disturbing the operation of the controlled or protected equipment. Adequate testing procedures shall be available to verify the new logic prior to activating it in the on-line program. VENDOR shall specify any restrictions regarding downloading changes while on-line.

c) PLC mode selection switch during normal operating shall be at “RUN MODE” position. The PLC logics shall be coded in such a way that the remote write from Platform’s DCS is possible (e.g. remote set point/ by pass/ remote start-stop etc) during RUN MODE.

10.4.3 Power Supply Modules

230 VAC power to the control system power modules shall be provided by redundant UPS power systems from Power Distribution Board (PDB) supply by CONTRACTOR (Gas Turbine Compressor Package shall have its own UPS system). Each power supply shall incorporate over-current protection for connected loads (rated at 125% of maximum possible connected loads). Conversion of the 230V AC power to any other voltages within the equipment shall be VENDOR responsibility including 24 VDC power supply for external input and output loads.

All control system power supply modules shall be redundant. Upon power supply failure, alarm shall be sent to DCS via the hardwired common alarm signal.

Power supply (e.g. 230 VAC) wiring shall run in separate duct from the panel termination wiring, low voltage wiring and communication wiring. The 230 VAC terminals shall be covered with protective plastic covers with warning signs

10.5 Time Synchronization

Time synchronization between master clock (DCS) shall be done to ensure package PLC, HMI, workstation and server have the same time reference to the platform DCS. This can be achieved as follows and will be defined in a case basis during Detail Engineering according to Package supply:

• Via GPS NTP time server on Package L3 network connected with platform’s common GPS.

Common GPS shall be by Telecom.

•

If above is not possible, a simple methodology of sending a pulse hardwired at pre-configured time will enable synchronizing its clock with that of DCS system, which is continuously synchronized with the GPS NTP server.

• Other option is by using the Modbus TCP/ IP communication between DCS and the package PLC. VENDOR shall ensure and address any impact to the time sync accuracy due to communication delay within the Modbus signal.

Package shall be provided with one number of time synchronisation signal form the selected method. The PLC shall then synchronise all other equipment as applicable.

Company No._Rev. 200-51-IN-SPC-00021_00

35 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

10.6 Human Machine Interface (HMI)

10.6.1 Hardware Requirement

P3 package type shall be provided with HMI. Package HMI shall be replicated in the DCS graphics by DCS VENDOR.

The following HMI to be considered.

• GTC PLC- workstation HMIs – 1 no. of PCS7 OWS and 1 no. of CPMS OWS/EWS shall be provided for GTC at CP LER., 1 no. of PCS7 EWS, 1 no. of CPMS OWS/EWS and 1 no. of PEMS OWS shall be provided for GTC at CCR Engineering Room. HMI on panel is also required for each compressor train. A common portable laptop shall be provided to serve all trains.

• GTC PLC – 1 no. of CP6S PCS7 OWS and 1 no. of PEMS OWS in OCC CCR. 1 no. of PCS7

EWS, 1 no. of CP6S PEMS and 1 no. of CPMS OWS/ EWS in OCC Engineering Room.

• GTC Anti Surge / Load Sharing - workstation HMI – 1 no. of EWS shall be provided for anti surge / load sharing at CP LER and 1 no. of EWS in LQ Engineering Room. HMI on panel is also required for each compressor train. 1 no. of EWS shall be provided in OCC Engineering Room.

• GTG - 1 workstation HMI (EWS / OWS) shall be provided for GTG in each ER, and CCR Engineering Room. HMI on panel is also required for each GTG. A common portable laptop shall be provided to serve all trains.

• A common machinery HMI (supplied by GTC package VENDOR) shall be provided on each Operator Console at CCR to access and display GTC and GTG graphics for all trains. GTC / GTG package VENDOR shall work with IMICC for the connectivity of GTC / GTG system to the HMI. Based on final selected VENDOR for GTG, this common machinery HMI will be optimized as part of value engineering wherever applicable.

• Other miscellaneous P3 packages (with own UCP) - shall have the panel mounted HMI only. Where there are multiple machines, one of the HMI shall be used as master HMI which can access the other HMIs. Engineering Maintenance Laptop supplied by VENDOR.

The UCP panel mounted HMI shall be housed on front face of UCP and shall be composed of:

• An industrial computer with colour touch screen (17” minimum)

• An operator pointing device such as touch-screen or trackball

• An industrial keyboard

The HMI shall use latest generation and proven software and hardware and shall be manufactured for an industrial environment.

HMI located outdoor shall be avoided.

HMI displays and keypad/keyboards should operate trouble - and maintenance - free for a minimum of 5 years.

10.6.2 HMI Data Display

Graphic symbols on process displays shall comply with ISA 5.5 unless otherwise approved by COMPANY.

HMI display shall be developed and customised based on guideline that will be provided during Detail Engineering to ensure a common graphic philosophy provided to Operator. Colours used for all valve

Company No._Rev. 200-51-IN-SPC-00021_00

36 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

operation and pump/motor running status shall be consistent throughout the facility to avoid operator misinterpretation. COMPANY shall approve all graphics.

Graphics on HMI shall be provided to display key operating data for the complete package and the associated auxiliary systems.

Following shall be the minimum graphic to be displayed in the HMI:

Start-up Sequence Graphic

All start-up sequence steps with permissive status shall be shown on an HMI graphic to allow the Operator to prepare for and take any required manual actions and quickly determine the reason for delays in completing the start-up sequence or failure of the start-up sequence.

In the event of a start sequence failure, the control system shall annunciate the failed start and indicate the device or condition preventing progression of the start sequence. Unless necessary for the protection of the equipment, start sequence failure shall not automatically trip the unit.

The progress of the start-up of auxiliaries and the full starting sequence shall be time-stamped and indicated on the control system HMI, showing a clear description of each step of the start-up sequence.

A graphic shall be provided that allows PID tuning parameters to be viewed and changed, where allowed by VENDOR. Access to change PID tuning parameters shall be password-protected.

Alarm and Trip Graphics

Graphics shall be provided that display all alarm and trip messages generated in the control system.

If the alarm condition has cleared, the alarm message shall remain on the graphic until acknowledged by the Operator.

A graphic shall be provided that allows alarm and trip set points to be viewed. Access to change alarm and trip set points shall be password-protected and provided according to UCP’s standard configuration tool.

Trend displays shall be provided to display real-time and historical trend data.

HMIs shall be capable of providing trip logs that archive defined analog values, discrete events, and alarms, for a predetermined time period before and after the trip.

Overview and Process Graphic

A single overview graphic shall be provided to display key operating data for the complete machinery package and the associated critical auxiliary systems.

All machinery process variables, including flows, temperatures, pressures, speeds, differential pressures, and vibration, shall be displayed.

Graphics for sequencing and control of associated equipment, including yard valves, cooling fans, fuel and starter Shutdown Valves (SDVs), seal gas, etc., shall be provided.

Graphics shall be developed for the main compression system process, including compressor map with surge control line, and all auxiliary systems (e.g., lube oil, gas fuel, liquid fuel, starting systems, dry gas seal systems, etc.).

Colors used for all valve operation and pump/motor running status shall be consistent throughout the facility to avoid operator misinterpretation. COMPANY shall approve all colors.

Company No._Rev. 200-51-IN-SPC-00021_00

37 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

RATIONALE: If motor and valve status colors vary by unit, there is a potential for operator confusion, which can cause incorrect action, potentially resulting in a trip or an unsafe condition. Power generation systems are understood to use different color schemes for motor status and valve position.

A graphic shall be provided that allows PID tuning parameters to be viewed and changed, where allowed by VENDOR. Access to change PID tuning parameters shall be password-protected.

Trend displays shall be provided to display realtime and historical trend data.

F&G Detectors

A detail graphic display for fire and gas detection and suppression system within skid limit shall be provided as applicable. The display shall consist of a simplified unit layout showing the approximate physical locations of the individual sensors and suppression system. When a detector is in alarm, the symbol shall turn colour according to platform standard. COMPANY shall approve all colours.

Trip Logic Status

Graphic display for trip logic and trip status shall be provided to display individual package’s trip status and override facilities (e.g. MOS, OOS, automatic overrides) that are grouped for each equipment or process unit.

Acknowledgement of IPF alarms and the resetting of IPFs shall be allowed within this graphic.

10.6.3 HMI Data Storage and Retrieval

HMIs shall be capable of providing trip logs that archive defined analog values, discrete events, and alarms, for a predetermined time period before and after the trip.

HMIs shall be capable of storing and displaying alarm and trip messages for at least 30 days.

An HMI archival application shall be provided for storing all historical alarm, event, and trend data to external archival media. The archival application shall provide a method of uploading and displaying historical data from archival media in the original display format.

10.7 CPU / Engineering Workstation Requirements

Engineering / Operator workstation shall be provided by package VENDOR for programming and maintenance of package control system, complete with all required software, hardware and all accessories inclusive of cables, adapters, carrying case, etc to permit up-loading and down-loading of data and programs to the PLC.

Engineering / Operator workstation shall be either using laptop to be connected locally at UCP or desktop to be provided at control room located in the LQ. Additional engineering workstation shall be provided also in Onshore Collaborative Center (OCC) for remote monitoring from onshore location.

VENDOR shall provide all software licenses and list COMPANY (or its designee) as the license owner.

All process control, monitoring servers and workstations that use Microsoft Windows Operating System shall be using the latest version i.e. Windows 10 / Windows Server 2019 or newer.

Antivirus software shall be compatible and managed through the platform Antivirus Server to update virus definition, otherwise VENDOR to advise and supply their own software and corresponding procedure.

Company No._Rev. 200-51-IN-SPC-00021_00

38 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

10.8 Virtualization

In order to reduce server cabinet footprint as well as cost and weight of the system, GTC and GTG package VENDOR shall consider virtualization without compromising functionality and security of the control and safety systems of packaged equipment. Virtualization of servers for the same system shall be considered for each compression platforms and Onshore Collaborative Centre (OCC).

Virtualization of servers shall be designed with high availability. Horizontal redundancy and vertical redundancy shall be considered in the virtualization design:

• Vertical redundancy can be achieved by having 1 server chassis (Chassis-A) installed in 1 virtualized server cabinet (Cabinet-A), fitted with redundant blade servers. This cabinet is powered by a dual-redundant UPS power supply.

•

Increased availability is achieved with horizontal redundancy, where in a separate cabinet (Cabinet-B powered by a separate dual-redundant UPS power supply), a redundant server chassis (Chassis-B) is installed. This redundant chassis is also fitted with redundant blades)

• The virtualization server cabinets (Cabinet-A and Cabinet-B) can be installed in the same room.

Zero Clients shall be used to access the functionality of these virtualized server.

Virtualization for Other P3 packages is not envisaged.

10.9 Special Tools

VENDOR shall provide as a minimum all special tools required for correct operation and for maintenance and calibration.

11 ALARM MANAGEMENT

Any condition on the package requiring operator attention or action and all pre-trip and trip alarms shall be sent to the ICSS.

Alarm management shall be implemented in Package UCP in order to minimize and where necessary suppress standing alarms, nuisance alarms, repeating alarms and alarm floods. Alarm management on the UCP shall be designed in accordance with COMPANY “Alarm Management Philosophy” and in line with project “Alarm Management Philosophy” and “Specification for Alarm Management System (ALMS)”.

Alarms and events shall always be stored, time stamped and presented in chronological order (as per Alarm Management Philosophy). All alarms shall be designated a priority level. Levels of alarm priority shall be distinguished by colour coding and sound tone. Priority levels shall be utilised by the operators to select the information presented in the alarm summary list.

Alarms on P3 Package shall be generated on the respective UCP and duplicated to ICSS.

Alarm criticality rating shall be included in the assessment workshop and shall be in accordance with the project requirement. All alarms, upon activation shall describe the actions that the operator needs to take to bring the process out of the alarm state.

Company No._Rev. 200-51-IN-SPC-00021_00

39 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

12 COMMUNICATION INTERFACES

12.1 List of Package Interface

List of Packages interface are indicated as below. The list to be finalized based on updated equipment list.

Table 12.1: List of Packages and Their Interfaces

No.

Package

Facilities

Control Type

Plant’s DCS Interface

Plant’s ESD/FGS Interface

MMS

Remarks

1

Emergency Diesel Generator

QG-S: CP6S/ 7S

P3, UCP

Dual Redundant Modbus

Hardwired N/A

2

Gas Turbine Generator

QG-S: CP6S/ 7S

P3, UCP

Dual Redundant Modbus

Hardwired Yes

3

Export Compressor / Turbine

QG-S: CP6S/ 7S

P3, UCP

Dual Redundant Modbus

Hardwired Yes

  1. Critical control signals shall be hardwired to DCS.
  2. Critical control signals shall be hardwired to DCS.
  3. FGS devices within enclosure limit shall be by VENDOR and to be connected to Package FGS housed in UCP.
  4. Critical control signals shall be hardwired to DCS.
  5. FGS devices within the package limit supply by package and connect to FGS PLC housed in UCP.

Export Pumps and Export Booster Pumps

QG-S: CP6S/ 7S

Seawater Lift Pumps

QG-S: CP6S/ 7S

4

5

P2

P2

Control from ICSS

Control from ICSS

Hardwired Yes

Hardwired N/A

Company No._Rev. 200-51-IN-SPC-00021_00

40 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

No.

Package

Facilities

Control Type

Plant’s DCS Interface

Plant’s ESD/FGS Interface

MMS

Remarks

Cooling Medium Circulation Pump

QG-S: CP6S/ 7S

P2

Control from ICSS

Hardwired Yes

Pedestal Crane

QG-S: CP6S/ 7S

P2, P4, LCP

Control from ICSS

Hardwired N/A

6

7

8

9

10

11

12

Chemical Injection Package

QG-S: CP6S/ 7S

Seawater Filter Package

QG-S: CP6S/ 7S

P2

P2

Water Chlorination Package

QG-S: CP6S/ 7S

P2, LCP

Flare Ignition Package

QG-S: CP6S/ 7S

P2, LCP

Nitrogen Bottles Package

QG-S: CP6S/ 7S

P2

13

Fuel Gas Metering

QG-S: CP6S/ 7S

P3, UCP

14

15

16

17

HP Flare KO Drum Electric Heater LP Flare KO Drum Electric Heater

QG-S: CP6S/ 7S

QG-S: CP6S/ 7S

Fuel Gas Superheater

QG-S: CP6S/ 7S

Pumps Mechanical Seal (Typical)

QG-S: CP6S/ 7S

P2

P2

P2

P1

18

HVAC - CP

QG-S: CP6S/ 7S

P3, UCP

Control from ICSS

Control from ICSS

Control from ICSS

Control from ICSS

Control from ICSS

Dual Redundant Modbus

Control from ICSS

Control from ICSS

Control from ICSS

Control from ICSS

Dual Redundant Modbus

Hardwired N/A

Hardwired N/A

Hardwired N/A

Hardwired N/A

Hardwired N/A

Hardwired N/A

Hardwired N/A

Hardwired N/A

Hardwired N/A

N/A

N/A

Hardwired N/A

F&G detectors inside Operator cabin shall be connected to FGS.

Local push button for flare ignition.

  1. Allocation metering.
  2. Critical control signals shall be hardwired to DCS.

19

Deluge Valves

QG-S: CP6S/ 7S

P2

N/A

Hardwired N/A

Company No._Rev. 200-51-IN-SPC-00021_00

Hardwired to FGS only.

41 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

No.

Package

Facilities

Control Type

Plant’s DCS Interface

Plant’s ESD/FGS Interface

MMS

Remarks

20

21

22

Fire Water Pump

Fire Suppression System Emergency Diesel Generator - LQ

QG-S: CP6S/ 7S

QG-S: CP6S/ 7S

P4, LCP

N/A

Hardwired N/A

P2, LCP

N/A

Hardwired N/A

QG-S: LQ6S/ 7S

P3, UCP

Dual Redundant Modbus

Hardwired N/A

23

Pedestal Crane - LQ

QG-S: LQ6S/ 7S

P2, P4, LCP

Control from ICSS

Hardwired N/A

Hardwired to FGS only.

Hardwired to FGS only.

Critical control signals shall be hardwired to DCS. F&G detectors inside Operator cabin shall be connected to FGS.

24

25

26

27

28

29

30

31

32

33

P2

P2

P2

Control from ICSS

Control from ICSS

Control from ICSS

Hardwired N/A

Hardwired N/A

Hardwired N/A

Service Water Lift Pumps/ FW Jockey Pumps

QG-S: LQ6S/ 7S

Service Water Filter Package

QG-S: LQ6S/ 7S

QG-S: LQ6S/ 7S

Sewage Treatment Package Reverse Osmosis & Demineralized Water Package

QG-S: LQ6S/ 7S

P2, LCP

Control from ICSS

Hardwired N/A

UV Sterilisation

QG-S: LQ6S/ 7S

P2, LCP

Air Comp. Package

Air Drier Package

Breathing Air Compressor Package

Helifuel Package

Inert Gas Generation Package

QG-S: LQ6S/ 7S

QG-S: LQ6S/ 7S

QG-S: LQ6S/ 7S

QG-S: LQ6S/ 7S

QG-S: LQ6S/ 7S

P3, UCP

P3, UCP

P2, LCP

P4, LCP

P2, LCP

Control from ICSS

Dual Redundant Modbus Dual Redundant Modbus

Control from ICSS

Control from ICSS

Control from ICSS

Hardwired N/A

Hardwired N/A

Hardwired N/A

Hardwired N/A

Hardwired N/A

Hardwired N/A

Company No._Rev. 200-51-IN-SPC-00021_00

42 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

No.

Package

Facilities

34

35

Deluge valves

  • LQ

QG-S: LQ6S/ 7S

Fire Water Pump

QG-S: LQ6S/ 7S

Control Type

Plant’s DCS Interface

Plant’s ESD/FGS Interface

MMS

Remarks

P2

N/A

Hardwired N/A

P4, LCP

N/A

Hardwired N/A

36

HVAC - LQ

QG-S: LQ6S/ 7S

P3, UCP

Dual Redundant Modbus

Hardwired N/A

37

Helideck DIFF System

QG-S: LQ6S/ 7S

P2

N/A

Hardwired N/A

38

Fire Suppression System – Clean Agent System

QG-S: LQ6S/ 7S

P2, LCP

N/A

Hardwired N/A

Hardwired to FGS only.

Hardwired to FGS only.

Hardwired to FGS only.

Hardwired to FGS only.

12.2 Hardwired Interface Design

The platform ICSS and UCP hardwired interface shall be using method and scope demarcation as following:

• Digital inputs to ICSS shall be dry contacts at the UCP, hardwired to and powered by the ESD /

FGS system.

• Digital outputs from ICSS shall be powered by the ICSS and hardwired to the UCP. If UCP cannot accommodate 24 VDC discrete signals from the ESD/FGS system, then VENDOR shall furnish an interposing relay and installed at Package UCP. GTC interposing relay reside in GTC UCP will be supplied by GTC VENDOR. GTG interposing relay reside in GTG UCP shall be supplied by GTG VENDOR. MCC interface signals shall be via ICSS IRP Panel, supplied by IMICC.

• Analog inputs (4–20 mA) to the ICSS from transmitters and fire and gas detectors shall be loop

powered by the ICSS and hardwired to the UCP.

A list of signal type definitions shall be provided by CONTRACTOR to VENDOR for each packaged unit.

Where platform ESD is utilised as package protective safety system, communication between PLC and ESD/ FGS shall be hardwired. The safety relay when provided shall be SIL 3 certified safety relay.

Hardwired communication link between PLC and ICSS may also be considered when there is limited amount of interface signals.

The following table shall be applied for various interface signal types with ICSS. Each loop shall be powered at 24 VDC.

Company No._Rev. 200-51-IN-SPC-00021_00

43 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

Table 12.2: List of Packages and Their Interfaces

Type

Specification

Loop Powered From

Alarm from Package

Analog from Package

Volt-free contact, open to alarm Analog 4–20 mA

Analog to Package

Analog 4–20 mA

DCS

DCS

DCS

Interlock to Package

Powered (24VDC) 0 Volt = contact open = not permissive, 24 volt = contact closed = permissive

DCS/ESD

Status (condition or state, e.g.,“running”) from Package. (When required to be in hardwired)

Volt-free contact, closed = status is true (e.g., closed contact means package is running)

DCS

Trip Status from Package’s ESD / FGS to Platform’s ESD / FGS .

Trip/Shutdown to Package

Start to Package

Stop to Package

Volt-free contact, ESD: contact open = trip/Shutdown. Contact close = normal FGS: contact open = normal. Contact close = trip

Volt-free contact, ESD: contact open = trip/Shutdown. Contact close = normal FGS: contact open = normal. Contact close = trip Powered (24 VDC) pulse ON for 1 second = start

Powered (24 VDC) pulse OFF for 1 second = stop

ESD / FGS

ESD / FGS

DCS

DCS

Emergency Stop to Package

Open contact (24 VDC) = STOP

ESD or MCC

As minimum, following signals shall be hardwired between the UCP and DCS besides the Modbus link:

• All control signals

• Common alarm signal to DCS for cabinet general alarm or fault

• Power supply modules failure

Company No._Rev. 200-51-IN-SPC-00021_00

44 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

• Watch dog timer when controller stop or loading exceed 100%

• Start / stop command from DCS to UCP

12.3 System Interface

12.3.1 P3 Machinery Network

• GTG and GTC shall be provided with network extended from LER / ER to CCR and up to OCC.

Following dedicated network shall be provided for GTG and GTC:

o Package control and safety PLC and CPMS network

o Anti surge and load sharing network (not applicable for GTG)

o PEMS network

• Refer to Specification for Machinery Protection, Condition and Performance Monitoring System

for architecture diagram of these networks.

• Package EWS / OWS workstation will be located in CCR and OCC. The network is expected to

support patch management, antivirus updates, engineering update of PLC programming.

• The necessary hardware required for this network shall be provided by VENDOR. This is to ensure UCP supplied shall be provided with provision to support the different control operation philosophies as described in Section 7.6.

12.3.2 P3 UCP Internal Interfaces (PLC, MMS, ACS, VSD, HMI / Workstation):

• Monitoring: Redundant serial links. Any deviation shall be approved by COMPANY.

12.3.3 UCP and Plant SIS or FGS:

• All signals exchanged shall be hardwired.

12.3.4 UCP and MCC:

• For UCP and MCC interface, refer detail in Electrical and Instrument Interface Philosophy for

CP6S and CP7S Complexes, document no. 200-51-IN-DEC-00004.

• For typical interface with IRP, refer to Figure 12.1. Package VENDOR shall refer to Section 6 of Electrical and Instrument Interface Philosophy for CP6S and CP7S Complexes, document no. 200-51-IN-DEC-00004, Section 6 for Interface signals.

As minimum, signals shown in the figure below shall be hardwired. Other monitoring and alarm shall be via serial link connection. There shall be no direct serial link interface from MCC – UCP, instead, all the soft signals shall be interface via DCS which is connected to MCC.

Company No._Rev. 200-51-IN-SPC-00021_00

45 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

Figure 12.1: Typical Interface Motor with UCP

12.3.5 UCP and DCS:

• Data exchange for monitoring will be made through Modbus TCP/IP, dual redundant serial links.

The serial link interface shall be through firewall.

• A data signal exchanged table shall be provided by the package VENDOR.

•

In case of failure of network communication between package UCP and DCS, the package shall continue in operation (except otherwise specified). All hardwired safety signals between UCP and ICSS shall remain effective.

• Connection from Package Control System connector up to DCS will be by means of an intermediate terminal block inside package cabinet. Communication details (protocol, baud rate, parity, tables, etc) and UCP-DCS interface validation details will be defined with ICSS VENDOR.

• Hardwired links will be applied to control executive functions (i.e. Package start/stop, trip,

sequence start)

• DCS shall send the data receive from UCP to POIS. There is no direct interface between UCP and POIS. UCP data acquisition in POIS shall be as described in Specification for Plant Operating Information System.

12.3.6 UCP and IAMS:

• HART pass through I/O card shall be provided by the UCP to enable the instrument diagnostic data inside the packaged equipment to be transferred to Platform’s Instrument Asset Management System (IAMS).

Alternatively, HART Multiplexer shall be provided if HART pass through I/Os are not available or communication cannot be established between UCP HART pass through IO and IAMS. The use of multiplexer shall be approved by COMPANY. Refer to Specification for Instrument Asset Management System (IAMS) for IAMS details.

12.3.7 Package MMS and CPMS:

Company No._Rev. 200-51-IN-SPC-00021_00

46 of 76

RContact closes to startRContact opens to stopContact closed = RunningRContact opens to tripINTERFACE RELAY PANEL (IRP) - By othersVENDOR CONTROL PANEL - By Package vendor24V DC2 secsSTART = 124V DC2 secsSTOP = 024V DCRUNNING = 1MOTOR CONTROL CENTER (MCC) - By ElectricalRunning Status(if applicable)Dry contactMaintained24V DCMaintainedTRIP = 0(If any)EMERGENCY SHUTDOWN SYSTEM (ESD) - By othersMaintainedTRIP = 0 (If any)RContact opens to trip24V DC(If not used)(If not used)Start commandStop commandTrip command PackageTrip command ESDContact closed = Available24V DCAVAILABLE = 1AVAILABLE Status(if applicable)Dry contactMaintained

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

• MMS Manufacturer standard protocol, redundant link.

• MMS rack supplied by VENDOR shall have communication card for data transfer to CPMS.

• Refer detail in Specification for Machinery Protection, Condition and Performance Monitoring

System.

12.3.8 UCP and Digitalization Server

Provision to interface between UCP and Digitalization server (supplied by OTHERS) shall be provided Interface mode can be in OPC / RS 485 Modbus RTU mode. The network interface tie-in layer (L4) to be determined when more information on digitalization is available. VENDOR to inform the possible communication protocol.

13 REMOTE ACCESS AND CYBER SECURITY REQUIREMENT

For GTC’s and GTG’s Package control & safety PLC, CPMS, anti-surge & load sharing PLC and PEMS network shall be extended from offshore to onshore OCC. Hardware and HMI of these packages shall be provided based on various control philosophies implemented by few phases as described in Section 7.6 of this document.

Network from offshore shall be extended to Onshore Collaborative Centre (OCC), for remote supervision and monitoring.

The remote access experience and capabilities shall be identical irrespective as to whether they are performed on the offshore compression hub or remotely from onshore OCC.

Identified data servers in the machinery networks will be available to GTC and GTG VENDOR work place for remote monitoring and surveillance. This external access shall be through External Interface Server supplied by each GTC and GTG VENDOR which connected via leased line.

All hardware and software required to establish this secured connection shall be supplied by the VENDOR and it shall be clearly detailed in the VENDOR’s proposal.

Cybersecurity and access control requirement shall be provided by VENDOR in accordance with project cybersecurity requirement as specified in COMPANY’s Industrial Control System Security Engineering Specification Procedure and PROJECT’s Cyber Security Lifecycle Management Plan.

14 SPARE CAPACITIES (FOR P2 AND P3 TYPES PACKAGES)

The following sparing philosophy shall be applied for packages as per project requirements:

Table 14.1: Instrument Spare Capacity

Description

Minimum Spare capacity

a) Instrument multicore / multipair cables within skid

Spare pairs / core of multicore / pair cables.

20%

b) Junctions Boxes (P2 & P3 Types)

Company No._Rev. 200-51-IN-SPC-00021_00

47 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

Spare terminal blocks inside Junction boxes (to terminate all wires of multicables)

Spare cable entries with corresponding plugs (suitable for area classification)

20%

20%

c) Cable trays (P2 & P3 Type)

Spare space available on cable ways

20% (maximum of 3 layers)

d) Local Panels / Unit Control Panels (P2, P3 & P4)

Spare terminal blocks (for each terminal row, to terminate all wires of multicables)

20%

Spare capacity in cable ducts/trunks inside cabinets

20%

e) PLC (P3)

Redundant power supply loading over 100% sized so that each power supply will carry no more than 70% of capacity under maximum load.

Spare capacity to match with that requirement.

Spare breakers in each bus

PLC CPU loading spare capacity

10%

50%

(Requirement to be applied to ALL programs blocks as, OR, AND, Timers, Set/reset, etc…)

Racks free spaces for upgrading and extension purposes 33%

PLC I/O or control system I/O of each type

20% installed and wired

Those target values are to be understood at FAT completion stage. VENDOR is responsible to make necessary reservations to cover its own engineering studies. VENDOR/CONTRACTOR shall demonstrate the above spare capacity post SAT and before System acceptance by COMPANY.

15 SOFTWARE LICENSES

VENDOR shall provide all the required licenses including one for each PLC software’s, workstation monitor licenses and any other licenses as required to function for NFPS facilities.

All Licenses for the UCP shall also be provided considering sizing requirements (including sparing and expansion).

All proprietary software technology shall be delivered after signature of a license agreement between OWNER and software VENDOR. Such agreement shall define the right of use of the software technology.

All servers shall operate under the latest version of Servers field proven Operating system available.

Company No._Rev. 200-51-IN-SPC-00021_00

48 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

All workstation shall operate under latest release of the operating system, available at the time of functional design approval.

16 DOCUMENTATION

The VENDOR shall provide all the documentation related to the engineering, detailed study, installation, maintenance and pre-commissioning for the instrumentation supplied with the packaged unit.

All technical, operating and user documents or manuals shall use “ENGLISH” language.

Quantity and procedure are indicated in package equipment requisition (refer to Section 14.2 for minimum documentation requirements).

VENDOR shall provide List of software / license with details i.e Software Version, Released date, Obsolescence date etc.

16.1 Documentation Required with Quotation

The VENDOR shall submit the following documents, as a minimum, with his quotation. For list of documentation to be submitted, VENDOR shall refer to the requisition.

  • P&IDs scope of supply for instrumentation shall be clearly shown on this diagram (to be

according to project formats and standards).

Instrument List, including a brief material specification.

  • System architecture

  • Typical cabinet arrangement

I/O count.

JB and cable list

  • Description of operation of Control and Safety Systems.

  • General arrangement (with JB location) and interface tray location

Interconnection block diagram, showing all necessary internal and external connections.

  • Utilities consumption and heat dissipation.

  • A list of all software and licenses

16.2 Instrumentation and Control Documentation during Execution

The necessary instrumentation and control documents/drawings as listed in relevant package specification shall be submitted by the VENDOR after order placement. For specific list of documentations to be submitted VENDOR shall refer to the requisition. The exact timing of document submittal is defined in the requisition and shall be agreed with CONTRACTOR.

After award, the VENDOR shall update the I/O count as the design develops and advises the CONTRACTOR in timely manner. Each VENDOR shall include in his scope of supply a full specification for functional requirements and support / integration services required, in a timely manner, to the CONTRACTOR for the engineering of the ICSS VENDOR.

The below list of documents is considered as the minimum required information, and is not limited.

Company No._Rev. 200-51-IN-SPC-00021_00

49 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

Table 16.1: List of Minimum Instrument Spare Documentation

Note 1 Note 2 Note 3

Applicable for package

Instrument list I/O list Modbus and soft interface list Instrumentation specifications Cables list Interconnection diagrams Instrumentation loop diagram Junction box wiring P&ID Calculation sheets I.S. loops calculation Control system description, operating principles, functional design specification, control narrative

instrument air

Cause and effect charts Overall dimensions and weight Power supply and consumption UCP heat dissipation Instrument layout Instrument hookup Main routings and instruments supports realization Cabinet drawings (including local panels) Earthing connections diagrams Inspection and test plan Certificates and inspection documents Commissioning documents Alarm Management Documents Alarm and trip summary Cybersecurity Documents Manufacturer’s record data book

Notes:

X X X X X X X X X X X

X

X X X X X X X X X X X X X X X X

X X X

X X X X X X X

X

X X

X X

X X X X X X X X

X X X X X X X X X

X

X X

X

X X X X X X X X X

ALL ALL P3 ALL P2 / P3 / P4 P2 / P3 / P4 P3 / P4 P2 / P3 / P4 ALL ALL P2 / P3 / P4

P2 / P3 / P4

ALL ALL ALL P3 P2 / P3 ALL P2 / P3 P2 / P3 / P4 ALL ALL ALL ALL P3 / P4 ALL P3 / P4 ALL

  1. Documents by VENDOR to be submitted to CONTRACTOR agreement/ COMPANY

Review.

  1. Documents to be updated by VENDOR, after construction, or after package assembly.
  2. Documents to be updated (“As built”), by VENDOR, after FAT in manufacturer’s

workshop.

Following deliverable related to COMPANY CMMS shall be provided in COMPANY’s template and format:

Equipment Database (EQDB)

Company No._Rev. 200-51-IN-SPC-00021_00

50 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

Bill of material (BOM)

Spare Parts List (SPL)

Special Tools

  1. Operating Supplies (Lubes and Chemicals)

  2. Maintenance manual

Installation and Operating Manual

Preservation procedure

17

INSPECTION AND TEST REQUIREMENT

17.1 General

VENDORS approved ITP shall form a basis for the Instruments inspection and testing requirements.

VENDOR shall provide internal factory test reports and material test certificates for completeness and compliance to the relevant specifications. The test reports shall include the following as a minimum:

• Hydro test procedure and report

• Painting procedure and report

• NDT procedure and test report

• Mill test certificates for materials

• Calibration reports

•

•

Instrument weather proof certificates

Instrument explosion protection certificates

17.2 Factory Acceptance Test (FAT)

As a pre-requisite prior to start the FAT, the packaged unit will have been completely tested by VENDOR, and the package documentation shall be approved by CONTRACTOR / COMPANY.

VENDOR shall provide its own test records to CONTRACTOR / COMPANY prior to start the FAT 4 weeks prior to start of FAT.

The FAT procedure for the acceptance of the package in the factory or yard shall be prepared by the VENDOR and submitted for approval to CONTRACTOR and COMPANY agreements 3 weeks before FAT.

FAT shall be aimed at covering:

• Mechanical acceptance

• Arrangement acceptance

• HMI graphic displays, if any,

• PLC configuration, Cybersecurity and alarm management compliance (P3 Type packages)

• Full functional tests

• Exchanged data table with ICSS (P3 Type packages)

Company No._Rev. 200-51-IN-SPC-00021_00

51 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

In this respect, it shall mainly include the following requirements:

• A comprehensive review of package drawings and documents, at their latest issue

• A comprehensive inspection including locations, installation, tagging, painting checking of all

instruments, junction boxes, cabinets

• The accessibility of main elements

• The leak and pressure tests

• The energy consumption checking

• The wiring checking (continuity, earth network, connection as per drawings, etc.)

• The noise level checking

• The functional tests including controls and sequences

• The performance checking

• The calibration of all instruments

• The interface with other systems (ICSS, etc.) checking (To be defined with ICSS)

• The work procedure during FAT (Working hours, punch list, forms, etc.)

• The test schedule

• Spare parts and special tools as per applicable documents

VENDOR shall allocate suitable time, facilities and assistance to perform FAT as per the approved procedure requirements.

VENDOR shall provide all necessary equipment to test and check the performances of all instruments and control systems supplied with the packaged unit.

This equipment shall include all instruments, test leads, temporary wiring, simulation equipment, special tools, consumables, utilities, as required to perform all FAT.

The package, including the PLC if any, shall be fully commissioned and tested in the VENDOR factory prior to delivery.

In case of failure, the VENDOR shall immediately carry out the necessary repairs, or replace the faulty equipment.

For package types P1 & P2, when required, VENDOR shall attend the ICSS VENDOR Factory Acceptance Tests of the Platform Control System in order to check the software development relevant to Supplier’s package.

17.3 Integrated Factory Acceptance Test (IFAT)

For P3 Type package, the testing will be performed as per one of below situations:

a. Packages will be tested using a suitable package VENDOR’s simulator kit at IMICC facility,

b. A portable ICSS simulator test kit (provided by IMICC) will be used and shipped to VENDOR’s facility.

Alternatively with COMPANY approval, the Package Control System shall be transported to ICSS VENDOR works for the IFAT.

Company No._Rev. 200-51-IN-SPC-00021_00

52 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

IFAT includes connection of the Package Control System to the ICSS and testing of the serial communication and functionality with the DCS. This will involve:

• Communication and response times.

• 100% test of functionality, e.g. alarm handling, controller tracking, transmitter validation,

• operator station commands and interactions

• 100% test of analogue signals transmitted to the DCS / ESD / FGS.

• 100% test of digital signals transmitted to DCS / ESD / FGS.

IFAT shall also include the remote access functionality check when implemented.

After successful IFAT, the Package Control Systems shall be released for shipment.

17.4 FAT / IFAT Report and Acceptance

After acceptance, a comprehensive test report shall be written and issued by the VENDOR.

The final approval of test dossier by CONTRACTOR and COMPANY shall be considered as the final acceptance of FAT / IFAT.

17.5 Site Activities (Installation, Pre-Commissioning/Commissioning and Start-Up)

The VENDOR shall provide assistance for the Site Acceptance Test, pre-commissioning and commissioning operations, and start-up activities as defined in the specific Package Material Requisition and specification.

The Site Acceptance Tests (SAT) procedures shall be prepared by the VENDOR and submitted to CONTRACTOR and COMPANY approval.

Further to SAT, VENDOR shall issue SAT report to CONTRACTOR.

Company No._Rev. 200-51-IN-SPC-00021_00

53 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

18 PACKING, SHIPMENT AND PRESERVATION

The requirements for packing and preservation of equipment package, including loose shipped items, are detailed in the protection, packing and marking instructions provided as part of contract documentation.

FAT final approval and closure of all punch items shall allow shipment of the equipment.

When Instruments arrive at site and kept in store for several days prior to installation, care shall be taken for protecting the necessary parts of the instruments from getting exposed to the adverse environmental conditions. Electronic parts shall be kept in air-conditioned room.

A preservation procedure and packing list shall be submitted to COMPANY for review before the shipment take place.

19 SPARE PARTS AND SPECIAL TOOLS

19.1 Spare Parts

The VENDOR shall recommend the number, type and storage conditions required for initial and operation spare parts and shall supply insurance and commissioning spare parts, as per project requirements.

The spares shall be managed via Spare Parts and Interchangeability Record (SPIR) process.

19.2 Special Tools

As part of the scope, VENDOR shall provide any special tools, which are necessary for assembly, dismantling, testing of the instruments during erection, pre-commissioning, operation and maintenance.

In addition to the software provided to run the PLC and HMI, VENDOR shall provide all software and licences to be used to develop application and/or operator interface (if any), this also applies to simple field local operator interface.

20 SERVICES

20.1 Training

The VENDOR is requested to perform training sessions relevant to its scope of supply as per defined in specific Package Specification. The VENDOR shall indicate within his offer, the training that can be provided at Supplier’s facilities and on site.

20.2 Attendance to Specific Reviews:

Requirement for attendance to the following specific reviews will be indicated in the Package Material Requisition.

• Package HAZOP

• Package SIL classification and assessment reviews

• Package Alarm Rationalization Workshop (via remote online)

Company No._Rev. 200-51-IN-SPC-00021_00

54 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

VENDOR shall provide assistance during SIL reviews in order to define required SIL level for each safety loop included in its package.

All data required for SIL calculation shall be provided by VENDOR for instruments or equipment provided with the package.

Upon the SIL results, any changes that are required to be made by VENDOR to meet the SIL shall be executed by VENDOR without additional cost.

Company No._Rev. 200-51-IN-SPC-00021_00

55 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

21 APPENDICES

Appendix 1

Package Scope of Supply Battery Limits

Appendix 2

Package Equipment Compliance List

Appendix 3

GTC Architecture Diagram, GTG Architecture Diagram and Anti Surge/ Load

                    Sharing

Company No._Rev. 200-51-IN-SPC-00021_00

56 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

21.1 Appendix 1

Package Scope of Supply Battery Limits

Package Definition:

P1 - Loose supplied instrument by packaged VENDOR and package control from Plant’s ICSS

P2 - Skid mounted instrument with JBs installed at the skid edge and package control from Plant’s ICSS. FGS devices are supplied by Plant CONTRACTOR.

P3 - Skid mounted instrument with JBs at the skid edge and package control by UCP supplied by Package VENDOR. Some package VENDOR may supply the FGS devices and connect to package FGS PLC (e.g. GTG and GTC package). Fire and Gas monitoring for other P3 packages will be connected to Plant’s FGS system.

P4 - Skid mounted instrument with JBs and local control panel (LCP) installed within the skid. Package is fully controlled by LCP with minimum hardwired interface to Plant’s ICSS.

Company No._Rev. 200-51-IN-SPC-00021_00

57 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

I. P1” Package Type Supply Battery Limits

Notes:

Electric Cable from / to Package Equipment up to MCC or Power Distribution Cabinets. Supplied by CONTRACTOR. Instrumentation Cable from / to instrument up to junction box or System Panel. Supplied by CONTRACTOR. Instrumentation Cable from / to junction box up to System Panel. Supplied by CONTRACTOR. Special Instrumentation Cable from / to instrument up to Systems. Supplied by CONTRACTOR. F&G detectors if required within skid shall be provided by CONTRACTOR including their cabling and connection to Platform FGS JB.

Company No._Rev. 200-51-IN-SPC-00021_00

58 of 76

Instrument Air SupplyPackage Battery LimitsPTP/IMLocal StopPackage Limit of SupplyIAF&G DetectorPackage SD Push ButtonFT225411333GBSxJB.(DCS)GBSx22PT22JB.(ESD)JB.(FGS)212345

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

II. “P1” Services Battery Limits

V: Equipment VENDOR

C: CONTRACTOR

ITEM 1

2

3

4

5

6

7

8

9

TASK DESCRIPTION

Field Instruments Data sheets Specifications Instrument accessories Impulse lines / pneumatic lines Labels on supports Cable glands Supports Junction boxes / local panel Terminals All cable glands (including multi cables) Labels Supports Cables: From Instruments to JB From JB to ICSS cabinet Special cables (to be specified by Equipment VENDOR) Cables trays: From instruments to JB From JB to skid battery limits From skid battery limits up to ICSS cabinet Cable trays supports (within battery limits) Cable trays fittings (within battery limits) PLC (NOT APPLICABLE) Application software (programming, configuration) Configuration tools Platform Control and Safety Systems / ICSS Hardware Functional description Application software (programming, configuration) Other Fire and Gas detectors Shut down PB Supports Electrical/Instrumentation cables and wiring to MCC and to ICSS Documentation

Design V C X X X X X X X X

X X X X X

X X

X X X X X

X

X

X X X X

X

X

 Supply

C

V X

Installation C

V X

X X X X X

X

X X X X X

X

X

V

X X X X X

X X

X X X X X

X

X

X X

X

X X X X X

X X X

X X X X X

X

X

X X

X

Company No._Rev. 200-51-IN-SPC-00021_00

59 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

III. “P2” Package Type Supply Battery Limits

Electric Cable from / to Package Equipment up to MCC or Power Distribution Cabinets. Supplied by CONTRACTOR. Instrumentation Cable from / to instrument up to skid edge junction box. Cable and junction boxes shall be supplied by Equipment VENDOR. Instrumentation Cable from / to skid edge junction boxes to System Panel. Supplied by CONTRACTOR. Special Instrumentation Cable from / to instrument up to Systems or System Panel. Supplied by Equipment VENDOR. F&G detectors if required within skid shall be provided by CONTRACTOR including their cabling and connection to Platform FGS JB.

Notes 1.

Junction Boxes segregation shall be according to Instrument and Control Systems Design Basis.

Company No._Rev. 200-51-IN-SPC-00021_00

60 of 76

Instrument Air SupplyPackage Battery LimitsPTP/IMLocal StopPackage Limit of SupplyIAF&G DetectorPackage SD Push ButtonFT22541133GBSxJB.(DCS)(Note 1)GBSx22PT22JB.(ESD)(Note 1)JB.(FGS)223JB.(MMS)(Note 1)MMS Detector12345

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

IV. “P2” Services Battery Limits

V: Equipment VENDOR

C: CONTRACTOR

ITEM 1

2

3

4

5

6

7

8

9

TASK DESCRIPTION

Field Instruments (within skid) Field Instruments (loose supply to CONTRACTOR) Data sheets Specifications Instrument accessories Impulse lines / pneumatic lines Labels on supports Cable glands Supports Junction boxes / local panel / skid edge JB Terminals All cable glands (including multi cables) Labels Supports Cables: From Instruments to skid edge JB From skid edge JB to ICSS cabinet Special cables (to be specified by Equipment VENDOR ) Cables trays: From Instruments to Skid edge JB From skid edge JB up to skid battery limits From skid battery limits up to ICSS cabinet Cable trays supports (within battery limits) Cable trays fittings (within battery limits) PLC (NOT APPLICABLE) Application software (programming, configuration) Configuration tools Platform Control and Safety Systems / ICSS Hardware Functional description Application software (programming, configuration) Other Fire and Gas detectors Shut down PB Supports Electrical/Instrumentation cables and wiring to MCC and to ICSS Documentation

Design V C X X X X X X X X X X X X X X

X

X

X X

X X

X

X

X

X

X

X X X X

Supply V C X X

Installation C

V X

X

X X X X X X X X X X

X

X X

X X

X

X X X X X X X X X X

X

X

X X

X X

X

X

X

X

X X X X

V

X X

X

X

X

X

X

Company No._Rev. 200-51-IN-SPC-00021_00

61 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

V. “P3” Package Type Supply Battery Limits

(Note 3)

Electrical Cables from / to Package equipment up to MCC or Power Distribution Cabinets (MCC out of package scope) – Supplied by CONTRACTOR.

Instrumentation Cables from / to instrument up to skid edge JB or Unit Control Panel. Supplied by VENDOR.

Instrumentation Cables from / to skid edge JB up to Systems or UCP. Supplied by CONTRACTOR.

Special Instrumentation Cable from / to instrument up to Systems or Unit Control Panel. Supplied by VENDOR.

Network interface cable between Unit Control Panel and Platform’s Control System. Supplied by CONTRACTOR.

Hardwired interface cable between Unit Control Panel and IRP/MCC. Supplied by CONTRACTOR.

Network interface cable between Unit Control Panel and Package CPMS. Supplied by CONTRACTOR. Applicable for GTC and GTG VENDOR.

Notes 1.

Junction Boxes segregation shall be according to Instrument and Control Systems Design Basis. Independent FGS shall be provided for GTG and GTC package. All detection and protection within skid shall be executed by this FGS. For offshore metering system, the metering UCP shall interface with platform’s DCS. For metering related details, refer to Specification for Fuel Gas Metering for CP6S and CP7S, 200-93-IN-SPC-00001.

Company No._Rev. 200-51-IN-SPC-00021_00

62 of 76

Power supplyPackage Limit of supplyInstrument Air SupplyPackage Battery Limits1PLC or Logic RelayUnit Control Panel MMS(vibration,…)ControlPanel000000000000000000000000000000000000000000000000000000000000000000000000000000000000000000000000000000000Hardwired Interfaces with Plant s ICSSLERPTP/IMLocal StopFieldIAF&G DetectorPackage SD Push ButtonFT2224113333JB Discr.(control)(Note 1)JB Discr.(safety) (Note 1)JB Discr.(safety) (Note 1)JB An.(F&G) (Note 1)3GBSxJB An.(control)(Note 1)GBSx232JB An.(safety)(Note 1)PT222Serial link to DCSMCC/IRPJB(MMS)(if any)MMS Detector2FGS(Note 2)CPMS373561234567

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

VI. “P3” Services Battery Limits

V: Equipment VENDOR

C: CONTRACTOR

ITEM 1

2

3

4

5

6

7

8

9

TASK DESCRIPTION

Field Instruments (within skid) Field Instruments (loose supply to CONTRACTOR) Data sheets Specifications Instrument accessories Impulse lines / pneumatic lines Labels on supports Cable glands Supports Junction boxes / local panel Terminals All cable glands (including multi cables) Labels Supports Cables: (copper or Fiber optic) From Instruments to junction boxes From PDB to UCP From junction boxes to marshalling cabinet/UCP From local panel (at skid edge, if any to UCP) Special cables (to be specified by VENDOR) Cables trays: From Instruments to junction boxes From junction boxes up to skid battery limits From skid battery limits up to marshalling cabinet Cable trays supports (within battery limits) Cable trays fittings (within battery limits) Unit Control Panel (if any) Fiber optic converters) Application software (programming, configuration) Configuration tools Platform Control and Safety System / ICSS Hardware Functional description Application software (programming, configuration) Other Fire and Gas detectors Shut down PB Supports Electrical/Instrumentation cables and wiring to MCC and to ICSS Documentation

interface hardware (i.e. patch panels,

Design V C X X X X X X X X X X X X X X

X

X

X X

X X X X X X

X

X

X X

X

X

X

X

X X X

Supply V C X X

X X X X X X X X X X

X

X X

X X X X X X

X

X

X X X X

X

X

X

X

V

Installation

V X

X X X X X X X X X X

X

X X

X X

X

X X X

C

X

X X X X

X

X

X

X

X

Company No._Rev. 200-51-IN-SPC-00021_00

63 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

VII. “P4” Package Type Supply Battery Limits

Local Control Panel

Electrical Cables from / to Package equipment up to MCC or Power Distribution Cabinets (MCC out of package scope) – Supplied by CONTRACTOR. Instrumentation Cables from / to instrument up to JB or Unit Control Panel. Supplied by VENDOR. Instrumentation Cables from / to JB up to Systems or Unit Control Panel. Supplied by CONTRACTOR. Special Instrumentation Cable from / to instrument up to Systems or Unit Control Panel. Supplied by VENDOR.

Notes 1.

Junction Boxes segregation shall be according to Instrument Design and Installation requirement.

Company No._Rev. 200-51-IN-SPC-00021_00

64 of 76

Power supplyPackage Limit of supplyInstrument Air SupplyPackage Battery Limits1PLC or Logic RelayUnit Control Panel MonitoringUnit(vibration,…)ControlPanel0000000000000000000000000000000000000000000000000000000000000000000000000000000000000000000000000000000003Hardwired Interfaces with Plant’s Safety System(if any)LOCAL UNITPITP/IMLocal StopFieldIAF&G DetectorPackage SD Push ButtonFIT2224113333JB Discr.(control)(Note 1)JB Discr.(safety) (Note 1)JB Discr.(safety) (Note 1)JB An.(F&G) (Note 1)3xZHxZLJB An.(control)(Note 1)xZHxZL232JB An.(safety)(Note 1)PZT2221234

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

VIII.

“P4” Services Battery Limits

V: Equipment VENDOR

C: CONTRACTOR

ITEM 1

2

3

4

5

6

7

8

9

TASK DESCRIPTION

Field Instruments Data sheets Specifications Instrument accessories Impulse lines / pneumatic lines Labels on supports Cable glands Supports Junction boxes / local panel Terminals All cable glands (including multi cables) Labels Supports Cables: (copper or Fiber optic) From Instruments to junction boxes From PDB to Local Control Panel (LCP) From junction boxes to Local Control Panel (LCP) Special cables (to be specified by VENDOR) Cables trays: From Instruments to junction boxes From junction boxes up to skid battery limits From skid battery limits up to marshalling cabinet Cable trays supports (within battery limits) Cable trays fittings (within battery limits) Local Control Panel (LCP) Fiber optic converters) Application software (programming, configuration) Configuration tools Plant Control and Safety System / ICSS – Limited to package alarm Hardware Functional description (Not applicable) Application software (programming, configuration) Other Fire and Gas detectors Shut down PB Supports Documentation

interface hardware (i.e. patch panels,

Design V C X X X X X X X X X X X X X

X

X X

X X X X X X

X

X X X

X

X

X

X

Supply V C X

Installation

V X

X X X X X X X X X X

X

X X

X X

X

C

X X

X

X

X

X

X

X

X X

X

X

X

X X X X X X X X X X

X

X X

X X X X X X

X X

X X X

X

X

X

V

Company No._Rev. 200-51-IN-SPC-00021_00

65 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

21.2 Appendix 2

Package Equipment Compliance List

The objectives of this check list is to highlight the requirements for instruments, control systems and accessories for package units, prior to the placing of a purchase order. It shall be completed by the VENDOR and evaluated by the CONTRACTOR during the technical bid tabulation stage and in the event of a purchase order being placed it will become binding on the VENDOR. Where no derogation or modification to the instrumentation requirements is stated or requested by the VENDOR , it will be understood that the VENDOR complies with the requirements in their entirety.

The CONTRACTOR’s Instrument Engineer in charge of packages will indicate in the document’s (Project requirements column) the requirements specific to the project where several alternatives are given. The VENDOR will indicate in the “Compliance with Requirements” column his agreement or not with the project requirements in the following manner:

 Y = YES, N = NO, NA = NOT APPLICABLE

If the VENDOR is not in compliance with a specific requirement, he shall indicate this in the “Reasons for non-compliance columns” and propose a suitable alternative.

The specific requirements are referred to the Package type as defined in APPENDIX A of this document.

Where the Package type is not indicated, the requirement is considered as Applicable for ALL types of package equipment.

This table shall be completed by VENDOR with corresponding Package bid offer.

Company No._Rev. 200-51-IN-SPC-00021_00

66 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

SPECIFICATION

PROJECT REQUIREMENTS (By CONTRACTOR)

COMPLIANCE WITH REQUIREMENTS (By VENDOR)

REASONS FOR NON- COMPLIANCE AND REMARKS (By VENDOR)

I 0 Package Type Definition:

I – GENERAL

◼P1: Pre-fabricated equipment skid with instruments and air sub-headers without cables, cable trays. CONTRACTOR connects skid instruments by field wiring to ICSS, to perform all monitoring, control and protection functions.

◼P2: Pre-fabricated equipment skid with instruments pre-wired by the supplier to JB via cable trays. CONTRACTOR connects from JB to ICSS, to perform all monitoring, control and protection functions.

◼P3: Pre-fabricated equipment skid with instruments pre-wired by the supplier via cable trays to interface j/boxes or local control panel, provided with UCP in LER. CONTRACTOR connects j/boxes or local control panel by field wiring to the UCP. Package is monitored, controlled and protected by its own control system, including package / networked printer, with hardwired and serial data interfaces with ICSS.

◼P4: Pre-fabricated equipment skid with instruments pre-wired by the supplier via cable trays to interface j/boxes or local control panel, provided with standalone LCP with minimum interface with ICSS. CONTRACTOR connects j/boxes or local control panel by field wiring to the LCP.

Yes/ NA

Yes/ NA

Yes/ NA

Yes/ NA

I 1 All instrumentation to comply with:

reference

documents/codes

and

Yes

◼All standards.

I 2 Formats for specifications, standards, instrument list, typical hook-ups, loop drawings, P&IDs, etc. will be:

◼The same as those used for the project: ◼VENDOR ‘s Standard: I 3 All instrument sub-VENDORs to be:

◼ Of the same type and model number as those purchased by CONTRACTOR for the main platform: ◼ Subject to CONTRACTOR approval from preferred VENDOR list:

Yes No

Yes

Yes (special instrumentation)

I 4 All instrument electrical connections to be:

◼The same size and type as main Platform standard sizes: ◼ VENDOR ‘s Standard:

Yes

No

Company No._Rev. 200-51-IN-SPC-00021_00

67 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

SPECIFICATION

PROJECT REQUIREMENTS (By CONTRACTOR)

COMPLIANCE WITH REQUIREMENTS (By VENDOR)

REASONS FOR NON- COMPLIANCE AND REMARKS (By VENDOR)

I 5

Instrument, JB, Cables, numbering and tagging to be:

cabinets,

etc…

(P2, P3, P4)

◼In accordance with that used for the main Platform (the project instrument identification designation table will be supplied to VENDOR and specific range of serial numbers will be allocated to VENDOR):

◼ VENDOR standard:

I 6 Environmental conditions:

-Outdoors Instrumentation & Systems will be designed for following conditions

◼ Equipment exposed to sunlight: ◼ Relative humidity: 100% ◼ Hazardous area classification: Zone, Gas Group, Temperature Class ◼ Tropicalised

◼ NACE classification:

I 7

I 8

◼ Other specific environmental conditions:

  • Marine environment
  • Indoors Instrumentation and Electronic Systems will be design according to the “Airbone Contaminant Class per ISA 71.04 “, and project specification (i.e. G3)

classification

defined

in

Electronic Instruments Codes & Standards:

◼ IEC: ◼ NEC: ◼ FM or UL listed: (certification organism)

Instrumentation Classification (in hazardous area only):

◼Instruments: Ex”i”, Ex”d”, Ex”e”, Ex”n”, other ◼Solenoid valves: Ex”i”, Ex”d”, Ex”e”, Ex”n”, Ex”m”, other ◼Junction Boxes/ Local panels: Ex”d”, Ex”e”, Ex”n”, other ◼Cable glands: Ex”d”, Ex”e”, Ex”n”, other (note : Barrier gland shall be used for Ex”d” enclosure)

Yes

No

Yes Yes Zone 1, IIB, T3 for all Packages except Zone 1, IIC, T3 for Water Chlorination Package due to Hydrogen presence

Yes If required See Mechanical Spec;

Yes Yes

Yes No No

Ex”d”

Ex”d”

Ex “e” (P2,P3, P4)

Ex “de” (P2,P3, P4)

Company No._Rev. 200-51-IN-SPC-00021_00

68 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

SPECIFICATION

PROJECT REQUIREMENTS (By CONTRACTOR)

COMPLIANCE WITH REQUIREMENTS (By VENDOR)

REASONS FOR NON- COMPLIANCE AND REMARKS (By VENDOR)

I 9

&

junction

Instruments classification (IP): ◼Instruments: ◼Junction boxes/ Cable Glands / Local

box

protection

panel without electronics:

◼Field Local panel with electronics (if any): ◼Panels in non-classified air-conditioned

buildings:

IP 66 IP 66 (P2, P3, P4)

IP 66 (P2, P3, P4) IP 42 (P3)

I 10 Painting of local package instrumentation: ◼CONTRACTOR project standards: ◼VENDOR standards: ◼Other:

Yes Yes (if approved by CONTRACTOR)

II - CONTROL PHILOSOPHY

II 1 Type of instrumentation:

◼Smart electronic 2 wire 4-20mA with Hart protocol ◼Conventional transmitters/positioners:

◼Fieldbus Foundation device:

Yes

If fast response time required (to be listed in proposal) No

II 2 Package unit panels for start-up: ◼Located locally: ◼Located in LER:

(P3, P4) Yes/No Yes/No

VENDOR will indicate if there are any cable length limitations for equipment supplied.

II 3 Start-up condition initiated from:

◼Remote- From DCS in main control room:

Yes

VENDOR to ensure that signals for start-up, permissive and shutdown are made available to DCS

◼Remote - From UCP in LER:

◼Locally - From VENDOR’s local gauge board:

Yes/ NA (P3)

Yes/NA (P2, P3, P4)

II 4 Control, Monitoring and Safeguarding of

(P3, P4)

Package unit and Auxiliaries:

◼Control & monitoring Functions: - Package PLC

◼Safety Functions: - Package PLC supplied by Supplier

  • Platform ESD:

Yes

Yes/No/NA Yes/NA

Company No._Rev. 200-51-IN-SPC-00021_00

69 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

SPECIFICATION

PROJECT REQUIREMENTS (By CONTRACTOR)

COMPLIANCE WITH REQUIREMENTS (By VENDOR)

REASONS FOR NON- COMPLIANCE AND REMARKS (By VENDOR)

II.5 Fire & Gas Systems:

(P2, P3, P4)

◼Detectors and FGS by VENDOR supplied as a complete system with repeat contacts for external use:

Yes (P3 GTG / GTC) (Note)

Yes (P2, P3, P4)

◼Integrated in the main Platform Fire and Gas system: (Supplier to specify requirements)

Note: GTG and GTC shall advise on requirement to have independent / dedicated FGS for package. Preferably to be integrated with platform’s FGS.

II.6 Fire & Gas Extinguishing Systems:

◼By VENDOR ◼Integrated in the main Platform Fire and Gas system:

(P2, P3, P4)

Yes/No/ NA Yes/No

II 7 Vibration & Temperature Monitoring:

◼ Make & model number of equipment

required:

◼ Integrated in control cabinet provided

by Supplier with marshalling:

Integrated

in MMS provided by

◼

CONTRACTOR:

TBC (P2, P3, P4)

Yes/NA (P3, P4)

Yes/NA (P2, P3, P4)

II 8 Condition monitoring system including

software and interface with MMS (By CONTRACTOR):

◼ Make & model number of specific

instrumentation required:

II 9

Surge, Load Sharing, Performance controllers:

◼ Incorporated in DCS: ◼ Dedicated controller: ◼ Make & model number of specific

instrumentation required:

II 10 Speed & Fuel Control:

◼ Integrated in the UCP (preferred): ◼ Over speed control

II 11

The PLC supplied by Supplier for the Package control & protection function shall have the following features in hot- standby redundant configuration:

  • CPUs:
  • Power Supplies:
  • Communication interface with DCS:

Serial Link:

TBC

(P2, P3, P4) Yes/NA (P2) Yes/NA (P3, P4) TBC (P3, P4)

(P2, P3, P4) Yes/NA Yes/NA

(P3, P4)

YES YES YES (Modbus TCP/IP)

  • Communication interface with ESD:

Hardwired

Company No._Rev. 200-51-IN-SPC-00021_00

70 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

SPECIFICATION

PROJECT REQUIREMENTS (By CONTRACTOR)

COMPLIANCE WITH REQUIREMENTS (By VENDOR)

REASONS FOR NON- COMPLIANCE AND REMARKS (By VENDOR)

II 12 PLC HMI to be provided:

◼ Locally (on a local control panel) ◼ Remotely (on UCP located in LER) ◼ Remotely as an operator workstation in platform control room ◼ Remotely as an operator workstation in Onshore OCC

II 13 Systems Generalities:

Integrated in the main Platform ESD

◼Alarms and Events Time Stamping (SOE)

  • Provided in Package PLC

system: ◼Time Synchronization

  • Through communication link
  • Hardwired

II 14 Alarm and Shutdown philosophy:

◼Alarm contacts on alarm: ◼ESD Pushbutton ◼Solenoid valves normally energised: ◼Solenoid valves normally de-energised:

II 15 Shutdown signals to be:

◼4 - 20mA signals from dedicated transmitters:

(P3, P4)

Yes/No Yes/No Yes/No

Yes/No

(P3, P4)

Yes/No/NA Yes/No

Yes/No Yes/No

Open Yes Yes No

Yes

◼Contacts from switches i.e. level switches,

pressure switches etc.:

Subject to approval by Contractor (to be listed in proposal)

II 16 ESD field devices configuration

◼2oo3 ◼1oo2 ◼1oo1 ◼Independent transmitter to DCS

II 17 Package PLC Interface with Other Systems

◼ DCS: Serial/ hardwired ◼ ESD: hardwired ◼ MCC:

Serial (redundant) Hardwired

  • IRP
  • Direct

Yes/No Yes/No Yes/No Yes

(P3) Yes Yes

No Yes Yes/NA No

III - ENCLOSURES AND JUNCTION BOXES

III 1 Electronic Instrument protection:

◼Sunshades: ◼Heating Boxes:

III 2 Skid Junction Box material: ◼Stainless Steel: 316L ◼Cast Aluminium: ◼Glass Reinforced Plastic:

III 3 Separate Junction Box and cables for signal

types:

Yes No

(P3, P4) Yes No No

(P2, P3, P4) Yes

Company No._Rev. 200-51-IN-SPC-00021_00

71 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

SPECIFICATION

◼ IS Analog input/output: ◼ Non IS Analog and Digital: ◼Thermocouple (if any): ◼RTD: ◼Vibration: ◼Non IS Solenoids: ◼Fire & Gas:

PROJECT REQUIREMENTS (By CONTRACTOR)

COMPLIANCE WITH REQUIREMENTS (By VENDOR)

REASONS FOR NON- COMPLIANCE AND REMARKS (By VENDOR)

Yes Yes Yes Yes Yes Yes

III 4 Spare cores/pairs/triples considered for terminals

in each Junction Box:

20% (P2, P3, P4)

III 5

Junction Box terminal type (for hazardous area only):

◼Ex (e) ◼ blue terminals for I. S. circuits (Ex ‘I’):

III 6 Grounding

 ◼Junction box (P3) /Remote I/O Panel (P2)
 ◼Cable glands

III 7

Cable entry via undrilled gland plate (multi cables) or cable glands (single cables):

◼Bottom entry for multicore and branch cables: ◼ Cable gland for multipair/ single pair minimum size: ISO M20 ◼ Spare entries plugged according certification ◼ Top entry is prohibited.

to

(P2, P3, P4)

Yes Yes

(P2, P3, P4) Yes Yes

(P2, P3, P4)

Yes Yes

Yes Yes

IV - CABLE AND WIRING

IV 1

Instrument cables will be in accordance with Contractor cable specifications and Flame retardant or Fire resistant when specified

Yes

IV 2

Installation of multi/ single cables on:

(P2, P3, P4)

◼316 SS steel tray with covers (for outdoor) / Carbon Steel with galvanized coating (for indoor): ◼Glass reinforced plastic tray: ◼Rigid steel conduit ◼Flexible metallic conduit: ◼Cable fixing to cable Tray

Yes

No No No (Note 1) Yes

IV 3 All skid & field instruments to be pre-wired to

junction boxes at edge of skid(s) by VENDOR.

Yes (P2, P3, P4)

IV 4 All spare wires

in multicore cables

to be

terminated in junction boxes, panels.

Yes (P2, P3, P4)

IV 5 All cables / wires to be tagged at both ends,

stranded wires to be crimped.

Yes (P2, P3, P4)

Company No._Rev. 200-51-IN-SPC-00021_00

72 of 76

NFPS Offshore Compression Complexes Project COMP2 INSTRUMENT SPECIFICATION FOR PACKAGED EQUIPMENT FOR CP6S AND CP7S COMPLEXES

21.3 Appendix 3

GTC Architecture Diagram, GTG Architecture Diagram And Anti Surge /

Load Sharing Architecture

Company No._Rev. 200-51-IN-SPC-00021_00

73 of 76

Notes:

  1. CPMS / MMS are considered as a single network. It is expected that both CPMS and MMS Engineering can be accessed from the same network.

  2. CCC are considered with L2 network extended to CP6S/OCC for engineering and maintenance.

  3. All the servers and machines are shown for functionality. However, all these machines shall be reviewed, optimised and virtualized after finalization of design requirement.

  4. GTC networks (L1 up to External Interface Network) shall be dedicated, segregated from ICSS network and to be supplied by GTC Vendor. All workstations, cabinets, HMI, network switches, data diode, firewalls, servers and associated interconnecting cabling within room as shown in the diagram shall be in GTC SUPPLIER scope of supply. Cabling between rooms and facilities shall be by CONTRACTOR.

  5. CCR in Future shall be provided with dedicated CP4S, CP7S and CP8S Complex Operator Console. A common machinery HMI GTC and GTG as shown for CP6S Complex and CP7S Complex shall be provided for each console by GTC SUPPLIER. This common machinery HMI will be optimized as part of value engineering wherever applicable, based on final selected VENDOR for GTG.

  6. Refer Anti-Surge Block Diagram for architecture details.

  7. Refer MMS / CPMS Block Diagram available in Specification for Machinery Protection, Condition and Performance Monitoring System for architecture details.

  8. GTC Vendor shall provide interface to digitalisation server through security layer. Both server and security layer shall be provided by Digitalisation System Integrator. Interface mode via TCP/IP or equal. GTC Vendor to advise the communication protocol and dashboard availability on the interface from the L4 server.

  9. Interface between GTC UCP and Plant DCS preferably in Modbus TCP/IP. If Modbus TCP/IP protocol is used industrial Firewall between the interface shall be supplied by IMICC.

  10. Redundant OPC communication supplied by IMICC.

  11. Detail Architecture shall be referred to Export Gas Compressors 560-K2301A/B/C/D/E Control System Overview - (CP6S), Document No: 5128_20-4500355799-00083.

GTC Architecture Diagram

DAS GTC Replicated External Interface Server (Note 8)

Secure Firewall / Gateway

GTC External Interface Network

GTC External Interface Network

L3.5: GTC DMZ

L3: GTC Information Network

File Server

Redundant Domain Controller

Backup Management

Data Diode

FW

FW

L3.5: GTC DMZ

GPS

L3: GTC Information Network

SIEM

Patch Management

Antivirus Management

Network Monitoring

OCC

Leased Line

GTC External Connection / user

Machinery HMI on each CP Operator Console at OCC-CCR

CP6S PCS7 (OWS Client)

CP7S PCS7 (OWS Client)

PCS7 EWS Multi Client

NOTE 2, 4

L2: GTC VLAN SW

L2: GTC VLAN SW

L2: GTC VLAN SW

CP6S / LQ6S LQ – CCR RACK ROOM

L2: GTC VLAN SW

LQ – CCR

CP7S Operator Console at LQ6S-CCR

CP6S Complex Operator Console (Note 5)

My connect RM & D dashboard all units

My connect RM & D dashboard all units

Common CP7S GTG / GTC Machinery HMI

Common CP6S GTG / GTC Machinery HMI

PCS 7 EWS Multi Client

Printer

LQ – ENGINEERING ROOM

(Note 5)

(Note 5)

L2: CP6S GTC VLAN SW & FW

LQ – CCR RACK ROOM

GTC L2 VLAN SW (from other hubs)

PCS7 - OWS Client

NOTE 4

L2: CP6S GTC VLAN SW & FW

CP - LER

HMI

PLC

Anti- Surge

(Note 6)

COMMON GTC PORTABLE ENGINEERING LAPTOP

DCS

(By IMICC) (Note 9)

THIS DOCUMENT IS PROPERTY OF QATARGAS. THIS DOCUMENT OR MATERIAL DESCRIBED THEREON MAY NOT BE COPIED OR DISCLOSED IN ANY FORM OR MEDIUM TO THIRD PARTIES, OR USED FOR OTHER THAN THE PURPOSE FOR WHICH IT HAS BEEN PROVIDED, IN WHOLE OR IN PART IN ANY MANNEREXCEPT AS EXPRESSLY PERMITTED BY QATARGAS.

Company No._Rev. 200-51-IN-SPC-00021_00

74 of 76

Anti Surge Architecture Diagram

OCC

GPS

Log Servers

Redundant Domain Controller

Backup Management

FW

Patch Management

CCC EWS Servers

Antivirus Management

L3: ANTI SURGE / LOAD SHARING INFORMATION NETWORK

Common Hubs GTC Anti Surge OWS / EWS

CCC EWS Client

Notes:

  1. All the servers and machines are shown for functionality. However, all these machines shall be reviewed, optimised and virtualized after finalization of design requirement.

  2. GTC Anti Surge / Load Sharing networks (L1 up to L3) shall be dedicated, segregated from ICSS network and to be supplied by GTC Vendor. All workstations, cabinets, HMI, network switches, firewalls, servers and associated interconnecting cabling as shown in the diagram shall be in GTC SUPPLIER scope of supply. Cabling between rooms and facilities shall be by CONTRACTOR.

  3. CCR in Future shall be provided with dedicated CP4S, CP7S and CP8S Complex Operator Console.

  4. One machinery HMI for GTC shall be provided on the CCR console for CP6S Complex which shall provide information on Anti Surge / Load Sharing details. This common machinery HMI will be optimized as part of value engineering wherever applicable, based on final selected VENDOR for GTG.

  5. Detail Architecture shall be referred to Export Gas Compressors 560-K2301A/B/C/D/E CCC Panel Architecture Diagram - (CP6S), Document No: 5128_20-4500355799-00261.

NOTE 2

GTC ANTI SURGE / LOAD SHARING L2 VLAN SW

(from other hubs)

LQ – CCR

CP6S Complex Operator Console (Note 3, 4)

Common CP6S GTC

Machinery HMI

CP6S / LQ6S LQ – CCR RACK ROOM

L2: GTC ANTI SURGE / LOAD SHARING VLAN SW

CCC EWS Multi Client

LQ – ENGINEERING ROOM

L2: GTC ANTI SURGE / LOAD SHARING VLAN SW

LQ – CCR RACK ROOM

L2: GTC ANTI SURGE / LOAD SHARING VLAN SW

CP - LER

CCC EWS Client

HMI

Anti Surge / Load Sharing

Anti Surge / Load Sharing Typical for 1 GTC Train (5 + 1 Future Trains)

DCS

(By IMICC)

NOTE 2

THIS DOCUMENT IS PROPERTY OF QATARGAS. THIS DOCUMENT OR MATERIAL DESCRIBED THEREON MAY NOT BE COPIED OR DISCLOSED IN ANY FORM OR MEDIUM TO THIRD PARTIES OR USED FOR OTHER THAN THE PURPOSE FOR WHICH IT HAS BEEN PROVIDED, IN WHOLE OR IN PART IN ANY MANNEREXCEPT AS EXPRESSLY PERMITTED BY QATARGAS.

Company No._Rev. 200-51-IN-SPC-00021_00

75 of 76

Notes:

  1. CPMS / MMS are considered as a single network. It is expected that both CPMS and MMS Engineering can be accessed from the same network.

  2. All the servers and machines are shown for functionality. However, all these machines shall be reviewed, optimised and virtualized after finalization of design requirement.

  3. GTG networks (L1 up to External Interface Network) shall be dedicated, segregated from ICSS network and to be supplied by GTG Vendor. All workstations, cabinets, HMI, network switches, data diode, firewalls, servers and associated interconnecting cabling within room as shown in the diagram shall be in GTG SUPPLIER scope of supply. Cabling between rooms and facilities shall be by CONTRACTOR.

  4. CCR in Future shall be provided with dedicated CP4S, CP7S and CP8S Complex Operator Console. A common machinery HMI GTC and GTG as shown for CP6S Complex shall be provided for each console by GTC VENDOR.

  5. Refer MMS / CPMS Block Diagram available in Specification for Machinery Protection, Condition and Performance Monitoring System for architecture details.

  6. GTG Vendor shall provide interface to digitalisation server through security layer. Both server and security layer shall be provided by Digitalisation System Integrator. Interface mode via TCP/IP or equal. GTG vendor to advise the communication protocol.

GTG vendor to clarify dashboard availability on the interface from the L3 server.

  1. Interface between GTG UCP and Plant DCS preferably in Modbus RS 485 (or) Modbus TCP/IP. If Modbus TCP/IP protocol is used industrial Firewall between the interface shall be supplied by IMICC.

  2. EWS / OWS / Servers are common for GTC & GTG.

  3. PEMS and this architecture diagram will be updated based on final vendor data information.

  4. Based on final selected VENDOR for GTG, This common machinery HMI will be optimized as part of value engineering wherever applicable.

GTG L2 VLAN SW (from other hubs)

GTG Architecture Diagram

GTG Replicated External Interface Server

Secure Firewall / Gateway

OCC

Public Internet

GTG External Connection / user

GTG External Interface Server

GTG External Interface Network

Data Diode

L3.5: GTG DMZ

FW

GPS

L3: GTG Information Network

FW

FW

Interface to Digitalisation Server (Note 6)

Log Server

Domain Controller

Backup Management

SIEM

Patch Management

EWS Servers

Antivirus Management

Common Hubs GTG PLC OWS / EWS

ECC EWS Client

CP6S PCS7 (OWS Client)

CP7S PCS7 (OWS Client)

PCS7 EWS Multi Client

NOTE 3

LQ – CCR

CP6S Complex Operator Console (Note 5)

L2: GTG VLAN SW

CP6S / LQ6S LQ – CCR RACK ROOM

L2: GTG VLAN SW

LQ – ENGINEERING ROOM

My connect RM & D dashboard all units

Common CP6S GTG / GTC Machinery HMI

Common CP6S GTC CPMS EWS

PCS 7 EWS Multi Client

Printer

CP - LER

L2: CP6S GTG VLAN SW & FW

CP - ER

L2: CP6S GTG VLAN SW & FW

LQ – CCR RACK ROOM

PCS7 - EWS OWS

DCS

(By IMICC) (Note 7)

NOTE 3

HMI

PLC

COMMON GTG PORTABLE ENGINEERING LAPTOP

Common GTG PLC OWS

THIS DOCUMENT IS PROPERTY OF QATARGAS. THIS DOCUMENT OR MATERIAL DESCRIBED THEREON MAY NOT BE COPIED OR DISCLOSED IN ANY FORM OR MEDIUM TO THIRD PARTIES OR USED FOR OTHER THAN THE PURPOSE FOR WHICH IT HAS BEEN PROVIDED, IN WHOLE OR IN PART IN ANY MANNEREXCEPT AS EXPRESSLY PERMITTED BY QATARGAS.

Company No._Rev. 200-51-IN-SPC-00021_00

76 of 76

Project: Q-21699 - Saipem COMP2 Folder: Instrumentation


Loading authentication...

Graph View

Backlinks

  • 00 Index

Created with Infinity Constructor © 2025

  • Elynox | Go Further