UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
Spare Parts and Material Identification, Procurement, Delivery, Receipt and Payment-OTS-OED Supported Projects PROCEDURE APPROVAL
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 1 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
REVISION HISTORY
Rev No.
Issue Date
Revision Description
Valid Until Date
00
04 NOV 2019
First issue. This procedure has been developed by including projects scope content from the following procedures as part of OTS/OED harmonization: ONS-MNT-PLNG-004 – Rev.01 RG-DFO-003 – Rev.00
14 NOV 2024
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 2 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
CONTENTS
1 GENERAL … 5 1.1 Purpose … 5 1.2 Scope … 5 1.3 Criticality … 6 1.4 Key Risks and Controls … 6 2 DESCRIPTION OF THE PROCUREMENT PROCESS … 7 2.1 Capital Spares and Special Tools … 7 2.1.1 Identification … 7 2.1.2 Approval … 7 Entry into SAP System … 7 2.1.3 2.1.4 Shipping, Freight, and Markup Cost … 8 2.1.5 Warehouse Receipt … 8 2.1.6 Payment for Materials … 8 2.1.7 Reporting … 8 2.2 Materials Purchased by QG Supply … 8 2.3 Material Purchased by the Project Contractor and Delivered to QG Warehouse … 8 Identification of Materials … 8 2.3.1 2.3.2 Material Approval and PO Placement … 9 Entry of Material into the SAP System … 9 2.3.3 Shipping, Freight, and Markup Costs … 9 2.3.4 2.3.5 Warehouse Receipt … 9 2.3.6 Payment for Materials … 9 2.3.7 Reporting … 9 2.4 Commissioning Spares … 10 2.5 Operating Supplies List … 10 2.6 Loan Process … 10 3 DETAILED SPARE PARTS LIST COORDINATION … 11 3.1 Roles and Responsibilities … 11 3.1.1 QG Maintenance Project Focal Point (OTS/OED) … 11 3.1.2 QG Material Focal Point (OTS/OED) … 11 3.1.3 Project Spares Single Point of Contact (PMT) … 12 3.1.4 Warehouse Division … 12 3.1.5 QA/QC Engineering Division … 13 3.1.6 Process Engineering Division … 13 3.1.7 Reliability and Maintenance Engineering Support Division … 13 3.1.8 Qatargas Project Accounting … 13 3.1.9 Qatargas Financial Accounting … 13 3.1.10 Contractor … 14 3.1.11 Supplier Responsibilities … 15 3.2 Projects Communication … 16 3.3 Projects Spare Parts/Operating Supplies Schedules … 16 3.4 Spare Parts Review Process and Documentation Requirements … 16
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 3 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
A5.1 A5.2 A5.3 A5.4
3.4.1 Spare Parts Review Process … 16 3.4.2 Documentation Requirements and Numbering … 17 3.5 Receiving and Inspection … 18 3.5.1 Upon Arrival at the Contractor’s Warehouse… 18 3.5.2 HPO Creation … 18 3.6 Spare Parts and Materials Handover to QG Warehouse … 19 3.7 Activities at QG Warehouse … 19 APPENDICES … 21 Appendix 1 – References and Relevant Documents … 22 Appendix 2 – Glossary of Terms: Definitions, Acronyms, and Abbreviations… 23 Appendix 3 – Projects Review Organization and Key Personnel … 25 Appendix 4 – RACI Chart for Projects … 26 Appendix 5 – Workflows … 27 Spare Parts Process Management Workflow … 27 Receiving/Inspection Spare Parts Workflow … 29 Loan Process Workflow … 30 Template (Loan process) … 31 Appendix 6 – Finance and Reporting … 32 A6.1 Milestone Payments (If applicable) … 32 Payment of Final Goods Invoice … 33 A6.2 Payment of invoices for Material Delivery Related Costs … 34 A6.3 A6.4 GR/IR Account Management … 35 A6.5 Management Reporting … 36 Appendix 7 – Spare Parts Template … 37 Cover Sheet Information … 37 Cover Sheet Template … 38 Equipment Detail Sheet Information … 41 Equipment Detail Sheet Template … 42 Spare Parts Sheet Header Information … 44 Spare Parts Sheet Template: … 47 Spare Parts Sheet Template … 50 Spare Parts List Review Report … 51 Appendix 8 – Qatargas Spare Parts: QA/QC Requirements … 53 Appendix 9 – Operating Supplies List (OSL) … 54 Lube Template … 54 Chemical Template … 55 Appendix 10 – Special Tools Template … 56 Appendix 11 – Blinds & Spacers Template … 58 Appendix 12 – Piping Gasket Template … 59 Appendix 13 – Manual Valve Guidelines … 60 Appendix 14 – SKID Sample for Contractor/Vendor Reference – Incomplete vs. Complete Data … 61
A7.1 A7.2 A7.3 A7.4 A7.5 A7.6 A7.7 A7.8
A9.1 A9.2
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 4 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
1 GENERAL
PURPOSE
1.1 This procedure describes processes and responsibilities for identifying materials and spare parts, including data and documentation requirements, for the development of Spare Parts Lists for all maintainable equipment (tagged and untagged), as well as creation, ordering, procurement, delivery, and payment for all projects under Qatargas (QG) Operations Technical Support (OTS) and Operations Expansion Department (OED).
SCOPE
1.2 This spare parts procedure applies to projects covered by OTS/OED (Onshore and Offshore facilities).
The main scope of the procedure includes:
Instruction for submission of Spare Parts List Dossiers
Methodology and workflows
Spare parts templates
Payment milestones
It is the responsibility of the Project Management Team to incorporate the intent of this procedure, as well as the overall spare parts process defined herein, within the Contractor scope of work.
As part of OTS/OED integration and harmonization, this procedure derives project-related content from the following:
QG procedure ONS-MNT-PLNG-004 Spare Parts and Material Identification, Procurement,
Delivery, Receipt and Payment
QG procedure RG-DFO-003 Instructions for Spare Parts Requirements and Documentation
QG procedure PGS-INV-PRC-010 Master Data Governance
Input from lessons learned
This procedure includes spare parts processes beginning with creation of the Spare Parts List by the Vendor in QG standardized templates through to handover of spare parts and acceptance certification provided by the QG Warehouse.
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 5 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
CRITICALITY
1.3 This procedure has been determined to be a Medium Criticality document.
Criticality Level: Medium
1.4
KEY RISKS AND CONTROLS
Key Risks
Key Controls
Unavailability of spare parts for safety and high/business critical equipment that has potential impact on SHE and production loss in QG Operations
Spare parts process is a key control element for
spare parts identification and availability
Failure to identify risks as a result of nonconformance to this procedure
Ensure that procedural requirements are
communicated to the relevant stakeholders
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 6 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
2 DESCRIPTION OF THE PROCUREMENT PROCESS
Capital Spares and Special Tools: Capital spares and special tools are to be identified and included in the lump-sum agreement of main equipment Purchase Orders (POs); ordered by the Contractor; preserved and stored in the Contractor’s Warehouse; and delivered to the QG Warehouse.
Pre-Commissioning and Commissioning Spares and Materials: Pre-commissioning and commissioning spares and materials are to be ordered by the Contractor and delivered to the Project Management Team or Contractor’s Warehouse (not to the QG Warehouse).
Startup Spares and Materials: Startup spares and materials are to be ordered by the Company (PMT) through the Contractor and delivered to the Project Management Team or Contractor’s Warehouse (not to the Qatargas Warehouse).
2-year Operating Spares (i.e., already in existence within the QG system): Spare Parts List are to be compiled by the Contractor/Vendor, and Reviewed and Identified by Company OTS/OED. Only additional quantities are to be purchased through Qatargas Supply Department.
2-year Operating Spares (i.e., newly created): Spare Parts Lists are to be compiled by the Contractor/Vendor; Reviewed, Identified and Approved by Company OTS/OED; ordered by PMT; and purchased and delivered to the Qatargas Warehouse by the Contractor.
Life Cycle Spares: Spare Parts List will be compiled by the Contractor/Vendor; Reviewed and Identified during the Project Spare Parts List review phase by Company OTS/OED; Ordered and purchased by QG OPCO through QG Supply after facility handover to the Operating Asset. Such spares are required to cover one (1) full maintenance cycle (i.e., one complete overhaul of the equipment).
Operating Supplies: Operating supplies are to be compiled by the Contractor/Vendor and reviewed by OTS/OED. The initial fill and consumption is a project scope and shall last until an Operational Acceptance Certificate (OAC) is granted (for details on OAC, refer to OGO- OTS-OVR-002 Project System Completion and Handover Procedure), typically 1 month for Offshore and 2 months for Onshore.
2.1
CAPITAL SPARES AND SPECIAL TOOLS
2.1.1
IDENTIFICATION
Capital spares and special tools are usually included in the Lump Sum Agreement of main equipment Purchase Orders.
2.1.2 APPROVAL
The Project PMT shall consult the Maintenance Projects Focal Point (MPFP) prior to PO placement, and RCS tools shall be used to identify Capital Spares requirements wherever applicable.
2.1.3 ENTRY INTO SAP SYSTEM
The Project (PMT) Material Single Point of Contact (SPOC) provides the Capital Spares and Special tools lists to the QG Material Focal Point (MFP) in QG’s dedicated template format for Material Creation in the MDG system (refer to PGS-INV-PRC-010 Master Data Governance (MDG) For Materials and PGS-INV-PRC-013 Material Control procedure).
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 7 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
2.1.4 SHIPPING, FREIGHT, AND MARKUP COST
The Project Contractor handles and pays for all costs associated with delivering materials to the QG Supply Warehouse.
The Cost of shipping shall be included in the lump-sum agreement or in the main equipment PO.
2.1.5 WAREHOUSE RECEIPT
The Project PMT shall coordinate with the QG warehouse for Historical Purchase Order
(HPO) creation
The Warehouse will create a Historical Purchase Order (HPO) in SAP to allow posting of
Goods Receipts (GRs)
The Contractor will ensure that items being handed over to the Warehouse are correctly
marked with Qatargas SAP Material numbers for easy identification
Material without quarantine – the Warehouse shall accept and create a Goods Receipt in
SAP for such inventory
Material with quarantine/shortage/damaged etc. – the Warehouse will inform the
PMT/Contractor to resolve all discrepancies
For detailed Warehouse Receiving and Inspection process, refer to Section 3.5.
2.1.6 PAYMENT FOR MATERIALS
The Project will pay for materials through the lump-sum agreement, or through Contractor Purchase Orders (PO) for the main equipment.
QG Warehouse Supply/Operations will not pay for capital spares and special tools, as providing these materials is an obligation of the project. Materials will be entered as “Full Value” in SAP
2.1.7 REPORTING
The QG Warehouse will provide status reporting to the Project Spares SPOC and QG MFP. Reporting will contain material delivered, material inspected, materials Quarantined, and handover status, against respective HPOs.
2.2 MATERIALS PURCHASED BY QG SUPPLY Operating spares (i.e., existing stock) and Operating Supplies are purchased by QG Supply. This does not include newly created 2-year operating spares, as they are purchased by the Project unless approved by the Supply Manager under special requirements.
2.3 MATERIAL PURCHASED BY THE PROJECT CONTRACTOR AND DELIVERED TO QG
WAREHOUSE
Materials covered under this section include all spare part types (i.e., Capital, Start up, 2-year, Special tools, and Piping/Insulation gaskets).
2.3.1
IDENTIFICATION OF MATERIALS
Approved Spare Parts against each PO are purchased by the Project Contractor and
delivered to the QG Warehouse
Refer to Appendix A5.1 Spare Parts Process Management Workflow
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 8 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
2.3.2 MATERIAL APPROVAL AND PO PLACEMENT
Reliability and Maintenance Engineering Support (RMES) review the material and recommend 2-year Operating spares quantities to be purchased by the Contractor, PO-wise
QG Material focal point submits the recommended quantity to the PMT Single Point of
Contact for purchase, PO-wise
The PMT approves placement of the order with the Contractor
The Contractor places the order with the Vendor(s) and provides PO copies to the PMT
SPOC
2.3.3 ENTRY OF MATERIAL INTO THE SAP SYSTEM
The QG OTS/OED Material team raises Change Requests (CRs) in MDG and submits for
approvals
Pricing for items entered into MDG will be according to the Spare Parts List
The Product Specialist (e.g., QA/QC Engineering, Hygienist, etc.) will review item
specification and its document/certificate
RMES will provide the recommended quantity to purchase
The QG Warehouse (i.e., Integrity and Material Control team) will review and create stock
codes, stock levels, etc., in the MDG SAP system
QG OTS/OED will receive MDG notification once material codes are created in the MDG
SAP system
2.3.4 SHIPPING, FREIGHT, AND MARKUP COSTS
The Project Contractor handles and pays for all costs associated with delivering the
materials to the Warehouse
The Project Contractor will instruct the Vendors that partial shipments are not permitted without advance written approval by the Company; thus, each shipment will complete the Vendor scope of supply under a given PO
2.3.5 WAREHOUSE RECEIPT
Refer to Section 3.5, Receiving and Inspection
2.3.6 PAYMENT FOR MATERIALS
After acceptance of materials, the Warehouse creates a GR entry in the SAP system for
inventory and payment purpose
The Project will be invoiced by the Contractor, and payments will be made as applicable
(refer to Section 3.1.10 for the Contractor Responsibilities Milestone table)
2.3.7 REPORTING
The Contractor will provide all status reporting to the PMT SPOC from issuance of the
Spare Parts List - PO wise, until acceptance of materials by the Warehouse
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 9 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
The PMT SPOC will distribute reports monthly to the Project Management Team (PMT),
Project Maintenance Focal Point and QG MFP
COMMISSIONING SPARES
2.4 Commissioning spares are ordered by the Contractor and delivered directly to the Contractor’s Warehouse site.
Project Engineers will be responsible for the identification of commissioning spares (i.e., items and quantities) to be purchased, including required delivery dates.
Commissioning material that is not consumed by the Project (i.e., surplus material of critical/high value, with relevant supporting documents, certificates, preservations, etc.) shall be reviewed by the respective Asset Maintenance Focal Point in consultation with the PMT Project focal point, with final approval by the Maintenance Manager, for acceptance in the QG Warehouse.
2.5 OPERATING SUPPLIES LIST An Operating Supplies List (OSL) is arranged by the EPC Contractor in a QG-approved format, and shall include Lubes/Oils, Greases, Solvents, Buffer Solutions, Chemicals, etc.
Project scope is only Initial fill and shall last until Operational Acceptance Certificate (OAC is granted.
Lubes/Oils purchase recommendations are provided by RMES Engineering, and Chemicals purchase recommendations are provided by the QG Process Engineer, and all these items are purchased through the QG Supply Department by the receiving entity.
LOAN PROCESS
2.6 The loan process shall be used to support a project when there is an emergency or unavoidable circumstanceduring the commissioning and startup phase.
For Spares and Materials, the PMT shall take approval from the Project Maintenance focal point in the agreed-upon format.
For the Loan process workflow and Template, refer to Appendix A5.3 and Appendix A5.4, respectively.
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 10 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
3 DETAILED SPARE PARTS LIST COORDINATION The Spare Parts Template shall list all tagged/untagged equipment and its spare parts that make up each piece of equipment covered by a Vendor’s Purchase Order or subcontract scope of supply.
NOTE: The Vendor must list all parts that are applicable for the subassemblies, assemblies of Equipment/Instruments (e.g., Complete Bills of Material) required for Life Cycle Maintenance).
Spare Parts and Operating Supplies are early deliverable documents by Vendors through contractor/licensors to Company, and are critical to plant Start-up and Operations.
The intent is to have a Complete List of Equipment and its parts for the equipment that can be loaded into the Company’s SAP Maintenance Management and Material Master Modules.
3.1
ROLES AND RESPONSIBILITIES
3.1.1 QG MAINTENANCE PROJECT FOCAL POINT (OTS/OED)
Serves as custodian of spare parts process management
Ensures ORP spares deliverables are achieved in a timely manner
Ensures that required resources are in place
Liaises with the PMT to ensure capital spares are identified
Reviews final quantities to proceed for purchase, wherever applicable
Communicates between QG OPCO and projects
Approves QG materials that are requested by projects on a loan basis
3.1.2 QG MATERIAL FOCAL POINT (OTS/OED)
Manages the day-to-day process of the QG Project (OTS/OED) Project Material Team
Ensures timely loading of all electronic PO-wise spare parts lists to the allocated share
drive
Manages, reviews, and approves by specified due dates, and ensures review reports
include all observations/queries forward to the PMT SPOC
Manages MDG SAP processes for Material Master creation
Liaises with RMES Engineering for quantity recommendations (i.e., new and existing
material)
Submits approved PO-wise Spare Parts Lists to the Project Spares SPOC for purchase
Coordinates with the PMT to expedite spares to ensure a timely delivery to the
QG Warehouse
Manages and ensures Bill of Materials (BOMs) are created and uploaded in MDG/SAP
Liaises with other responsible parties (e.g., meeting/reports)
Follows up and closes out all Spare Parts action items after facility handover to the Asset,
if any are pending
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 11 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
3.1.3 PROJECT SPARES SINGLE POINT OF CONTACT (PMT)
Manages the day-to-day spare parts process for the project, which includes the management of all spare categories (refer to Appendix 2, Glossary of Terms: Definitions and Abbreviations)
Reviews the scope of supply in the Contractor’s Unpriced Purchase Orders, Sub-Contracts, subsequent amendments, and related Vendor documents, to ensure that all Equipment and Parts are included in the Spare Parts List and OSL prior to official submission
Ensures the Contractor is delivering an accurate and fully populated Spare Parts List, OSLs, Capital Spares, and/or Special tools lists in terms of specification and data integrity, along with all supporting documents (refer to Sections 3.1.11 and 3.4.1)
Loads electronic Spare Parts Lists, OSLs, and Special tool lists, with supporting documents,
to the relevant project share drives (location and name of folder to be advised)
Follows up with the Contractor/Vendors and resolves all clarifications submitted by the
QG Material Focal Point
Ensures that all Project Design Change Notifications (DCNs), Field Change Notifications (FCNs), deviations/modifications, etc., in the plant are reviewed, and coordinates with the Contractor/Vendor to submit revised Spare Parts Lists
Ensures that all tagged and maintainable equipment and its spares are covered in the
Project Spare Parts List
Ensures that spare parts lists are provided with necessary supporting document for all
zero-recommended equipment spares
Provides spare parts volume for Warehouse storage requirements
Liaises with other responsible parties (e.g., meeting, HPO creation, etc.)
Reports late submission of Spare Parts Lists, OSLs, and Special tools lists to the QG
Material Focal Point
Follows up for delivery with the Contractor and submits reports to the QG Material Focal
Point
Ensures that all Ordered Spares are purchased and delivered to the QG Warehouse
Submits reports to the Project Maintenance Focal Point and QG Material Focal Point
Follows up and closes out all Spare Parts action items after facility handed over to the
Asset, if any are pending
3.1.4 WAREHOUSE DIVISION
Creates stock numbers for newly added items
Update Stock levels (i.e., new and existing material)
Creates Purchase Requisitions for spares to be ordered by Supply (i.e., existing material)
Creates a Historical Purchase Orders (HPO) for new spare parts purchased by the
Contractors
Receives spare parts at the QG Warehouse
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 12 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
Creates a GR in SAP for payment purposes after acceptance of the material into inventory,
and acknowledge the HPO certificate
3.1.5 QA/QC ENGINEERING DIVISION
Reviews pressure-containing and lifting equipment spares and documents/certificates
(e.g., CRs)
Inspects received pressure-containing and lifting equipment spares with relevant certificates
3.1.6 PROCESS ENGINEERING DIVISION
Reviews Operating Supplies Lists (OSLs)
Provides required volume of Operating Supplies for operations
3.1.7 RELIABILITY AND MAINTENANCE ENGINEERING SUPPORT DIVISION
The Discipline Engineer should refer to the criticality rating of the equipment, while
reviewing the Spare Parts
Determines spare parts criticality for all disciplines (including firefighting and telecom)
Recommends quantities (e.g., Demand Max) for purchase of new spares (i.e., 2-year
operation)
Optimizes stock levels for existing materials
Recommends storage conditions
Recommends Lifecycle spares quantities for future requirements that are to be purchased
by the Asset through QG Supply after project handover to the receiving entity
3.1.8 QATARGAS PROJECT ACCOUNTING
Determines if a new SAP vendor master is required and, if so, raises a request
If applicable, ensures that required HPO “Header Conditions” and markup accounts are in place and communicated to the impacted stakeholders
Codes milestone invoicing
Submits milestone invoices for payment
Codes final goods invoices with reference to the HPO
Submits final goods invoices for payment
Codes invoices for material delivery related costs
Reviews balances in the markup account
Provides GR/IR accounts management
3.1.9 QATARGAS FINANCIAL ACCOUNTING
Updates the “Cut-back” report to include new storage locations (if required), and
communicate to the impacted parties
Arranges for payments of milestone invoices by QG OPCO
Arranges for payment of final goods invoices by QG OPCO
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 13 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
Provides GR/IR accounts management
3.1.10 CONTRACTOR
The Contractor shall include instructions for completing and submitting Spare Parts List, OSLs and Special tools within the “Call for Tender”, and then within the relevant purchase orders.
The Contractor shall include clauses explicitly in the equipment purchase orders and subcontractor scope, to ensure that Suppliers do not neglect their responsibilities regarding spare parts and materials, as follows
Spare Parts List shall be classified for approval by the Company
Milestone Payment associated with Spare Parts acceptance, as illustrated in the table
below:
Milestone Steps
Milestone Description
M1
M2
M3
M4
M5
Receipt of Spare Parts List and OSL from VENDOR
COMPANY approval to proceed for purchase (Approved with Comments)
COMPANY approval for receipt of As-Built PO PO-wise Spare Parts Lists and Supporting document (Approved with No Comments)
CONTRACTOR Purchase and delivery of spares to QG WH (HPO) Wise)
HPO-wise Acceptance Certificate
Cumulative Progress
20%
50%
60%
75%
100%
Engage CONTRACTOR’s person in charge post-Contract Award to achieve the following:
Fully compliant Spare Parts List, OSL, Capital Spares, and Special Tools provided by the
Vendor/Supplier
The Contractor shall ensure a forecast plan is provided for the Spare Parts List , OSL,
Capital Spares and Special Tools
Ensure all maintainable equipment are covered in the project Spare Parts PO
Each PO Spare Parts Dossiers are to be reviewed by the Contractor (relevant engineering discipline-wise, e.g., Mechanical, Electrical, Instrumentation, etc.) for completeness, including all relevant supporting documents (i.e., all required information is provided, such as Scope of Supply covered, Tag references are shown in P&IDs and the Equipment Database, relevant Drawings/document numbers for all Equipment and Parts). Vendor-recommended quantities for Commissioning and Operating Spares are to be reviewed by the Contractor, with recommendations updated as appropriate.
Check that interchangeability lists for parts that are listed in Spare Parts List, OSLs and
Special Tools List are furnished.
Contractor shall prepare Spare Parts List, OSLs, and Special Tools lists in cases where the
Supplier has failed to submit such documents.
The Contractor shall review the Spare Parts List and OSL Review Report comments and ensure that the Supplier clarifies all queries, and submit the revised Spare Parts List and, Supporting documents, and reply underneath each company comment in the Spare Parts Review Report as required (refer to Appendix 7.8).
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 14 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
The Contractor shall schedule/manage issuance of Spare Parts List POs based on lead-time sequence and issue to the Company for review and approval within 15 weeks after issuance of the equipment purchase order, or at a given date specified in the PO.
This will allow sufficient time for the Company to review and approve the Purchase quantity PO-wise, and the Contractor can thereby place the Purchase Order and ensure the delivery of spares prior to “Ready for Startup” (RFSU).
The Contractor shall issue a Spare Parts List/OSL Status Report to the Company (PO-wise)
that confirms the following:
Received, Submitted, Reviewed and Approved or Clarification Status
Re-scheduled Status of Under Clarifications Spare Parts List
PO placement and ETA Status
The report should reflect the benchmark(s) against contractual requirements, to
be issued on a weekly basis and/or as per Company requirements
Meeting shall be in place as agreed between the PMT, Contractor, and QG Focal Point.
3.1.11 SUPPLIER
Submission of Spare Parts List, Operating Supplies List, and Special Tool List:
All requirements specified hereunder are for Suppliers and Sub-vendors under their responsibility. However, the Contractor shall ensure that Equipment and Material Data is fully populated and accurate, utilizing Vendor documentation.
The Supplier shall prepare a detailed Spare Parts List dossier (per equipment type) covering all types of Spares and Material in the Company format. The Spare Parts Dossier shall include Spare Part List (for Commissioning, Start-up, 2-year operation, and Life Cycle spares), Operating Supplies List, Special tools List and Capital Spares Lists. For definitions and templates, refer to Appendices 2, 7, 8, 9, 10, and for supporting documents refer to Section 3.4.2.
The Supplier shall ensure that a Spare Parts List dossier is submitted as outlined below:
The Spare Parts List shall be submitted in an electronic spreadsheet format.
The language used shall be English.
List all equipment (tagged/untagged) and its parts within their scope of supply, and this shall include all Priced Spare Parts, repairable and replaceable, whether recommended for stock or not.
All relevant datasheets, drawings, catalogues, and manuals shall be provided against each PO Spare Parts dossier. Highlight or otherwise mark so that the parts on the Spare Parts List can be easily found in the documentation.
Conduct a QA/QC check prior to submission in order to ensure all references datasheets, drawings, catalogues, and/or manuals are available against each PO Spare Parts dossier.
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 15 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
Ensure that all mandatory requirement are filled in the Spare Parts dossier, i.e., “Equipment Model Number”, “Part Description”, “Material Specification”, “EPC Contractor/Manufacturer Drawing Number”, “Part Quantity Per Equipment”, “OEM and OPM Part Number”, “OPM Name (i.e., real manufacturer name)” ” Unit of Measure (UOM)”, and “Unit Price”. These shall be indicated in the appropriate columns of the Spare Parts List dossier.
For the purchase of Bulk Piping Materials (e.g., Manual Valves/Non Return Valves/Strainers/Traps/etc.) for each PO release, a Spare Parts List dossier shall be issued utilizing the same part number across all PO releases for spare parts that are interchangeable. Supplier must also provide piping specifications and valve identification numbers assigned by the Company, total valve quantity, etc., as per Company template (refer to Appendix 7.4).
For the Spare Parts Review Report (refer to Appendix 7.8), and follow the instructions
given below when submitting revised documents:
A Clarification or Reply shall be given underneath each Company comment
Add a new line or change data in one (or more than one) cell of a line, highlight the line in yellow, and define the changes in the last column of the template
When submitting a revised Spare Parts List and/or OSL, ensure the revision
number is changed before submission
The Supplier shall define and complete the Spare Parts List, OSLs, and Special tools list no later than 3 months or 12 weeks after issuance of the equipment purchase order, or at a given date specified within the purchase order
PROJECTS COMMUNICATION
3.2 Official communication shall be between the projects Maintenance Focal Point and the project Spares SPOC for each project.
3.3
PROJECTS SPARE PARTS/OPERATING SUPPLIES SCHEDULES
An equipment database shall be available for the first Criticality Assessment, 24 months
prior to RFSU (based on best practices and QG experience)
Submission of the Spare Parts List and Operating Supplies is to start 18-24 months prior
to RFSU
Spares are to be delivered and accepted by the QG Warehouse 3 months prior to RFSU
3.4
SPARE PARTS REVIEW PROCESS AND DOCUMENTATION REQUIREMENTS
3.4.1 SPARE PARTS REVIEW PROCESS
Refer to Appendices 3, 4, and A 5.1 for project Spare Parts List/OSL organization and
workflow
The Spare Parts List and OSL review timeline:
Shall be a maximum of 15 working days/3 weeks for clarification and rejection
Shall be a maximum of 21 working days/1 month for approval with quantities
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 16 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
If no appropriate clarification is provided by the Vendor(s) within 30 calendar days, the QG MFP shall escalate the concern to the Projects Spares Focal Point. One solution is to arrange for a face-to-face/teleconference meeting or issue a letter to the contractor with the relevant Vendor(s).
For each Spare Parts List, POs shall be dealt with on a standalone basis and shall have an
assigned number for tracking.
3.4.2 DOCUMENTATION REQUIREMENTS AND NUMBERING
The Contractor shall apply the following document numbering convention in the cover sheet when making a submission:
As a mandatory requirement, the Contractor need to ensure to submit the following documents (not limited to) along with Spare Parts List (PO-wise):
For Spare Parts List
The following documents shall be arranged to each Spare Parts List, as applicable: Datasheets, Drawings, or equivalent showing the location of parts quoted and referenced in the Spare Parts List, Bill of Materials, Assembly drawings, Part List, product manuals/brochures, Vendor P&IDs for package units, Pipe Class documents, etc.
For Special Tools
Manufacturing assembly drawings along with parts number reference
For Blind and Spacers
Piping Class Document, Isometric drawing, and if any non-standard is followed for Blind and Standard the Manufacturing drawing
For Piping Gasket
For OSLs (Chemicals & Lubes)
Manufacturer documents for non-standard gaskets Arrange supporting documents for Insulation gasket kits
Product Datasheet/Specifications and Material Safety Datasheet (MSDS)
NOTE: The Contractor’s review shall not be considered as final until the Company has confirmed all documents against respective Spare Parts List (PO-wise) and OSL are provided. The Company reserves the right to withhold applicable contractor payment(s) until the Contractor provides complete documentation and hands over all spares to QG against each HPOs.
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 17 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
3.5
RECEIVING AND INSPECTION
3.5.1 UPON ARRIVAL AT THE CONTRACTOR’S WAREHOUSE
The Contractor shall be responsible for preservation of Capital Spares and Operating Spares, as per vendor specification, until it is completely handed over and accepted at the QG warehouse.
The Contractor shall carry out a visual inspection of the packaging for damage and general condition before off-loading. If damage is found, it shall be documented to assist in the resolution.
Unload the spare parts at the Contractor’s warehouse and conduct a visual inspection of
all delivered spare parts.
Ensure that all items are correctly marked/labeled with a QG stock number prior to
handover to the QG Warehouse.
If damages are found after the Contractor’s inspection, the Contractor shall act to replace the damaged or broken spare parts.
Any materials with discrepancies (i.e., OS&D) shall be resolved by the Contractor prior to
handover to the QG Warehouse.
The Contractor shall prepare an inspection report and this is the first stage of inspection
by the Contractor, prior to transfer of spares to the QG Warehouse.
Ensure that all documents related to delivery of spares/consignment shall be provided in proper correlation against each SAP code, including CoC/MTC/SAT/FAT Certificates, etc., where applicable.
All items that are delivered to the QG Warehouse shall meet project specifications listed
in the Spare Parts List.
3.5.2 HPO CREATION
In order for transfer of spares from the Contractor’s premises to the QG Warehouse to take place, a Historical Purchase Order (HPO is required to allow the QG Warehouse to receive the spares.
The PMT SPOC shall provide the following for the creation of the HPO:
Vendor’s Name (EPC Contractor): complete name, address and vendor reference number
Spare Parts List Template: in Excel format, with the approved quantities, SAP codes, and
Unit price and currency in USD
The following additional activities shall be arranged during HPO creation with Header
condition (ZMSC):
Transportation, warranty, and documentation charges
Customs duties, legalization, and clearance charges
5% Contractor handling fees
Reference: Spare Parts List, PO number
The Warehouses raises the GR with exact/all prices provided by the PMT SPOC in the Spare Parts List to avoid any discrepancy at the payment stage.
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 18 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
SPARE PARTS AND MATERIALS HANDOVER TO QG WAREHOUSE
3.6 Notice of Handover to QG Warehouse
To minimize congestion, the QG Warehouse must be notified by the Contractor 7 days in advance of delivery.
Notification email shall include the following:
HPO number
Number of Items
Package size and number of consignment wherever applicable
Delivery Location
QATARGAS OPERATING COMPANY LIMITED
Ras Laffan Industrial City
P.O. Box 22666, State of QATAR
Attention: Warehouse Receiving Officer, Warehouse Receiving Section
Upon confirmation of delivery date with the Company, the Contractor shall transfer the spare parts to the above location or to any other location designated at that time by the QG Warehouse.
3.7
ACTIVITIES AT QG WAREHOUSE
The Project Contractor and the QG Warehouse shall jointly verify all materials along with
a delivery note at the time of delivery to the QG Warehouse
Prior to delivery to the QG Warehouse, all items shall be correctly marked with a QG stock
number, HPO number, and HPO item number(s) for easy identification
Documents and Conditions shall be followed by PMT/EPC at all steps (i.e., Vendor site/EPC
site, etc.) until handover to the QG Warehouse, to include the following:
A packing list or delivery note referencing the HPO number, including the number
of packages containing the material delivered
The original inspection documents related to the receiving process
A first-pass inspection report conducted at the Contractor’s warehouse shall be
enclosed
A Material Test Certificate (MTC) for pressure-containing parts
MSDS sheets for chemical and dangerous goods
Shelf-life and expiry date (80% of shelf-life requirement should be available at the
receipt of item)
All Capital Spares shall be handed over in a suitable preservation container
All pressurized containers shall have purge/vent and gauges located at accessible
locations
A Certificate of Conformity (CoC)
Special storage requirements
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 19 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
Preservation procedures along with evidence shall be furnished to ensure materials are preserved in at the Vendor/Contractor site, as per manufacturer recommendation
Calibration certificates
Valve Test certificates, etc.
Material without quarantine – the QG Warehouse shall accept the material and create
Goods Receipt in SAP for inventory
Material with quarantine/shortage/damaged/etc. – the QG Warehouse will inform the
PMT/contractor to resolve all discrepancies
The Contractor shall resolve all discrepancy issues within 7 working days; otherwise, the
items shall be collected from the QG Warehouse by the Contractor
After acceptance of spare parts, the QG Warehouse raises the GR for accepted material
and stores the goods at specified locations
PMT/Contractor should resolve all items having Quarantine/Rejection/Damage/Shortage,
etc., until all HPO line items are accepted by the QG Warehouse
The following are the storage condition codes used at the QG Warehouse:
1
2
3
4
Air Conditioned Area
Non-Air Conditioned Area
Dehumidified Storage Area
Yard (Open)
5
6
7
8
Cylinder Storage
Inert Nitrogen
Air conditioned + Inert G. Purged
OTHER
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 20 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
APPENDICES
Appendix 1 – References and Relevant Documents Appendix 2 – Glossary of Terms: Definitions, Acronyms, and Abbreviations Appendix 3 – Projects Review Organization and Key Personnel Appendix 4 – RACI Chart for Projects Appendix 5 – Workflows
A5.1 A5.2 A5.3 A5.4
Spare Parts Process Management Workflow Receiving/Inspection Spare Parts Workflow Loan Process Workflow Template (Loan process) Appendix 6 – Finance and Reporting
Payment of Final Goods Invoice Payment of invoices for Material Delivery Related Costs
A6.1 Milestone Payments (If applicable) A6.2 A6.3 A6.4 GR/IR Account Management A6.5 Management Reporting Appendix 7 – Spare Parts Template
A7.1 A7.2 A7.3 A7.4 A7.5 A7.6 A7.7 A7.8
Cover Sheet Information Cover Sheet Template Equipment Detail Sheet Information Equipment Detail Sheet Template Spare Parts Sheet Header Information Spare Parts Sheet Template: Spare Parts Sheet Template Spare Parts List Review Report
Appendix 8 – Qatargas Spare Parts: QA/QC Requirements Appendix 9 – Operating Supplies List (OSL)
A9.1 A9.2
Lube Template Chemical Template
Appendix 10 – Special Tools Template Appendix 11 – Blinds & Spacers Template Appendix 12 – Piping Gasket Template Appendix 13 – Manual Valve Guidelines Appendix 14 – SKID Sample for Contractor/Vendor Reference – Incomplete vs. Complete Data
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 21 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
APPENDIX 1 – REFERENCES AND RELEVANT DOCUMENTS
Number
PRT-PRC-000-012
FIN-ACC-PRC-014
Title
SHE Handbook
Spare Parts & Capital Spares Accounting
PGS-MWO-PRC-004
Warehouse Management
PGS-INV-PRC-009
RSK-IMR-POL-001
PGS-INV-PRC-010
02.18.50.04
Lifecycle Spares Management Process
Delegation of Financial Authority
Master Data Governance (MDG) for Materials
QA/QC Requirements for Material Receiving Inspection
PGS-MWO-PRC-002
Preservation of Warehouse Stock
PGS-INV-PRC-013
OGO-OTS-OVR-001
OGO-OTS-OVR-002
Material Control Management and Stock Analysis
Defects Management Process during Project Startups
Projects System Completion and Handover
OGO-MNT-PLNG-001
Asset Register Procedure
TCH-ASV-PRC-036
TCH-REL-PRC-013
ONS-MNT-PLNG-004
Asset Criticality Assessment Process Procedure
Capital and Critical Spares Review and Reordering Process
Spare Parts and Material Identification, Procurement, Delivery, Receipt and Payment Procedure
OGO-OTS-OVR-002
Projects System Completion and Handover Procedure
RG-DFO-003
ONS-OTS-MNT-001
TCH-AIG-PRC-088
Instructions for Spare Parts Requirements and Documentation
Bill of Material Procedure for Projects
Lifting Lug Welding & Testing – for Spades, Spacers and Blind Flanges
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 22 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
APPENDIX 2 – GLOSSARY OF TERMS: DEFINITIONS, ACRONYMS, AND ABBREVIATIONS
Term
2-year Operating Spares
BOM
Capital Spare
Description
Parts required to safeguard the operation of equipment during the first 2 years of operation
Bill of Materials
Major individual items or sub-assemblies of the equipment (e.g., Compressor Rotor, Special Valves, etc.) that are required for replacement of items not subject to deterioration by normal use, but the failure of which is critical for continued safe operation of the plant/facilities. Generally, capital spares are items of Business/High Critical Equipment with high value (> US $250k) and/or long-lead time (> 1 year). Also known as Insurance Spares.
CoC
Certificate of Conformity
Commissioning Spares
Spare parts required for commissioning of new facilities, which may be consumed due to worn out, broken, plugged up or otherwise fail while the systems being commissioned (example: gaskets, seals, bearing, filters, miscellaneous instruments and various electrical items)
CR
DCN
DNR
EDL
EPCC
EPL
ETA
FAT
FCN
GR/IR
HPO
IR
kg
Change Request
Design Change Notification
Do Not Re-order
Equipment Detail List
Engineering, Procurement, and Construction Contractor
Equipment Part List
Estimated Time of Arrival
Factory Acceptance Test
Field Change Notification
Goods Receipt/Invoice Receipt
Historical Purchase Order
Invoice Receipt
Kilograms
Lifecycle Spares
For normal operation beyond the first 2 years of operation, these spares are required to cover one (1) full maintenance cycle (one complete overhaul of the equipment)
MDG
MDR
MM
MPFP
MRP
MSDS
MTC
NRV
OAC
Master Data Governance
Material Discrepancy Report
Material Master
Qatargas Maintenance Projects Focal Point (OTS/OED)
Material Requirement Planning
Material Safety Datasheet
Material Test Certificate
Non-return Valve
Operational Acceptance Certificate
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 23 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
Term
Description
Operations Expansion Department
Original Equipment Manufacturer
Operating Company
Original Part (Component) Manufacturer
Operations Readiness Plan
Overage/Shortage/Damage
Operating Supplies List (e.g., Project consumables such as chemicals, catalysts, lube oil, etc.)
Operations Technical Support
Product Datasheet
Project Information Management System
Project Management Team
Purchase Order
Purchase Requisition
OED
OEM
OPCO
OPM
ORP
OS&D
OSL
OTS
PDS
PIMS
PMT
PO
PR
Project SPOC
Project Spares Single Point of Contact (PMT)
QA/QC
QG
QG MFP
QG OPCO
RACI
RFSU
RMES
RSPL
SAP
SAT
SHE
Spare Parts List
Special Tools
Startup Spares
UOM
WH
Quality Assurance/Quality Control
Qatargas
Qatargas Material Focal Point – i.e., erson designated by the Company (OTS/OED)
Qatargas Operating Company
RACI defines persons or groups who are Responsible (R), Accountable (A), Consultation (C), Information (I)
Ready for Startup
Reliability and Maintenance Engineering Support
Recommended Spare Parts List
Systems, Applications, Products (in Data Processing)
Site Acceptance Test
Safety, Health, and Environment
A complete spare parts and interchangeability list from a Vendor containing all parts for a piece of equipment that are replaceable and repairable within their scope of Supply
Tools specifically designed and fabricated by an equipment manufacturer/vendor to be used for installation, onsite repair, and/or dismantling/maintenance purpose
Spare Parts required for efficient startup of the facility until normal operations i.e. from RFSU till OAC approved, .
Unit of Measure
Warehouse
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 24 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
APPENDIX 3 – PROJECTS REVIEW ORGANIZATION AND KEY PERSONNEL
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 25 of 62
Project Manager (QG)Project Maintenance Focal Point (QG)Material Focal Point (MFP)(QG)Reliability Maintenance Engineering Support TeamProcess EngineeringQA/QC Engineer QG Warehouse - Material Integrity Section - Material Control Section - Warehouse OperationsPMT (SPOC) Spares Coordinator
ONS-OTS-MNT-003
UNCONTROLLED IF PRINTED
Procedure
APPENDIX 4 – RACI CHART FOR PROJECTS
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 26 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
APPENDIX 5 – WORKFLOWS
A5.1 SPARE PARTS PROCESS MANAGEMENT WORKFLOW
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 27 of 62
Project Manager (PMT) discuss spares parts strategy with QG MPFP and agrees on ownership and schedule Contractor provides Spare Parts List / OSL to PMT Spares SPOC based on QG Spare Parts ProcedurePMT Spares SPOC reviews and Submit Spare Parts List / OSL to QG MFPQG MFP reviews Spare Parts List / OSL data fields for Completeness Satisfactory Review?QG MFP carries out detailed review of Spare Parts List / OSL items with given documents for completenessSatisfactory Review?QG MFP compares Spare Parts List / OSL items against existing SAP MM to avoid DuplicationQG MFP generates query and submit to PMT to obtains clarification from ContractorNOYESNO YESContinued on next Page
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
Note for OSL:
Project scope is only Initial fill and it shall last until the Operational Acceptance Certificate (OAC) is granted. OSLs requirements after OAC shall be handled by the receiving entity with QG Supply.
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 28 of 62
Continued from Previous PageQG MFP raise Change Request (CR) in MDG for 2 years and above 2 years Operating spares and OSLsProduct Specialist (QA/QC Engineering, Hygienist & etc.) review specification, document / certificate requirements RMES review and update Demand max (Quantity recommendation), Storage Condition, and Spares Criticality in MDG Note: Chemicals consumption requirements are provided by Process Engineer QG Warehouse carryout Quality check and create New Stock codes in MDG SAP QG MFP update Spare Parts List with Recommended Quantities and SAP stock codes and submit to PMT Spares SPOC for Purchase PMT Spares SPOC inform Contractor to place PO, follow up delivery process and handover to QG WH HPO wise for inspection and acceptanceQG MFP develop Bill of Materials for all equipment covered in the Project Spare Parts List
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
A5.2 RECEIVING/INSPECTION SPARE PARTS WORKFLOW
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 29 of 62
Vendor Delivers Goods FOB to Contractor site – PO wiseContractor Inform PMT to initiate HPO creation thru QG WH Material Control Section Contractor conduct Visual & First phase inspection and generate report HPO wiseContractor resolve clarifications with vendor, if any prior delivering to QG WH (with reference to Contractor PO)Contractor transfer Goods to QG WH Receiving Section with all documents, certificates, first pass inspection report & etc.- HPO wiseConduct Material Inspection (QG Warehouse, QA/QC, end user)Inspection Ok?QG Warehouse accept material into inventory and post GRContractor to resolve DiscrepanciesQG Warehouse will inform PMT/Contractor for items having quarantine, shortage, rejection etc. YESNO
ONS-OTS-MNT-003
UNCONTROLLED IF PRINTED
Procedure
A5.3
LOAN PROCESS WORKFLOW
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 30 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
A5.4 TEMPLATE (LOAN PROCESS)
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 31 of 62
ONS-OTS-MNT-003
UNCONTROLLED IF PRINTED
Procedure
APPENDIX 6 – FINANCE AND REPORTING
A6.1 MILESTONE PAYMENTS (IF APPLICABLE)
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 32 of 62
ONS-OTS-MNT-003
UNCONTROLLED IF PRINTED
Procedure
A6.2 PAYMENT OF FINAL GOODS INVOICE
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 33 of 62
ONS-OTS-MNT-003
UNCONTROLLED IF PRINTED
Procedure
A6.3 PAYMENT OF INVOICES FOR MATERIAL DELIVERY RELATED COSTS
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 34 of 62
ONS-OTS-MNT-003
UNCONTROLLED IF PRINTED
Procedure
A6.4 GR/IR ACCOUNT MANAGEMENT
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 35 of 62
ONS-OTS-MNT-003
UNCONTROLLED IF PRINTED
Procedure
A6.5 MANAGEMENT REPORTING
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 36 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
APPENDIX 7 – SPARE PARTS TEMPLATE
A7.1 COVER SHEET INFORMATION
Details on information required for the cover sheet are described below:
Item
Heading
Required Information
COVER SHEET
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Tracking Number
Single tracking number to be agreed at the beginning of each project
Equipment Purchase Order Number
PO Date
Ordered Item(s)
Vendor Reference
Contractor assigned Doc. No. (CTEP Doc. No. Assigned to Spare Parts List)
Vendor’s Spare Parts List Revision Designation
Number on the contractor Purchase Order for the equipment
Date shown on the Purchase Order
Short description of equipment on order, e.g., Centrifugal Pumps in recycle service
Vendor reference number required to be mentioned in correspondence. This will facilitate future communications
Number assigned by the contractor
Initial issue is Rev 0. Thereafter use Rev 1, Rev 2, etc.
Vendor Name
COMPANY named as vendor or seller on the Purchase Order
Vendor Address
Address shown on the Purchase Order and contacts
Original Equipment Manufacturer (OEM)
Companies whose items are listed on each Spare Parts List
OEM Address
Original manufacturer OEM address
Qatar Agent (if any)
If a Qatar Agent is representing the Vendor or OEM, include the Agent’s address and contact
Price Validity per EPC PO
Indicate date of expiration as stated in the Purchase Order
Comments
Any other information that the Vendor wants to provide
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 37 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
A7.2 COVER SHEET TEMPLATE
COVER SHEET
1
2
3
4
5
6
7
8
9
10
Equipment PO No.
PO Date
Ordered Item(s)
Vendor Reference
CTEP Doc. No. Assigned to Spare Parts List
Vendor’s Spare Parts List Revision Designation
Vendor Name
Vendor Address
Street
City
ZIP Code
Country
Company
Dept.
Contact Person
Phone (include Country Code)
Email Address
FAX (include Country Code)
Original Equipment Manufacturer
OEM Address
Street
City
ZIP Code
Country
Company
Dept.
Contact Person
COVER SHEET
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 38 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
Phone (Include Country Code)
Email Address
FAX (Include Country Code)
11
Qatar Agent (if any)
Street
City
ZIP Code (not applicable for State of Qatar)
Sample
Company
Dept.
Person
Phone
Email Address
Fax
12
Spare Parts Price Validity as per Contractor Purchase Order
13
Comments
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 39 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
Sample:
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 40 of 62
ONS-OTS-MNT-003
UNCONTROLLED IF PRINTED
Procedure
A7.3 EQUIPMENT DETAIL SHEET INFORMATION
EQUIPMENT DETAIL LIST
Col.
Heading
Description
Comment
A
B
C
D
E
F
G
Seq. No.
Sequential number. Fill in as required.
Equipment Model Number
Equipment Model Number associated with Equipment Tag. No. on the Equipment Detail Sheet. The same Equipment Model Number may be listed more than once if it has more than one Equipment Tag No/Equipment Model Number must also appear on Spare Parts List Templates.
Must also match with Purchase Order information.
Serial No.
Serial Number of the equipment assigned to Equipment Tag No. on the Equipment Detail Sheet.
Serial Number must only appear once.
Equipment Tag No. Provided by EPC CONTRACTOR. This is only one number. (Functional Location is SAP term for Equipment Tag No.) All Equipment Tag Nos. within the PO scope of supply shall be listed. Each applicable Tag Number/Functional Location should be listed in an individual
row (e.g., if three Functional Locations are applicable for the same Model Number, they should be listed in three different rows in the EDL). For guidance on untagged items, consult the Qatargas focal point.
Bulk Piping Materials purchased under a Blanket Agreement without tag numbers
(manual valve, strainers, NRVs, etc.) must list the piping specification, identification number and size in the Equipment Detail List
Equipment Service
Short description of equipment service.
Piping Class
Valve Piping Class Specification shall be arranged.
Installed Quantity
Valve Installed quantity shall be arranged.
See Purchase Order or contact the Contractor. Note for Manual Valves:
- With tag numbers the Contractor/Vendor need to arrange the Valve Identification code and Piping Class.
- Without tag numbers the Contractor/Vendor need to arrange the Valve Identification code, Piping Class, and Installed Quantity.
See Data Sheets or other sources.
This is applicable only for manual valves.
This is applicable only for manual valves. This installed Quantity is required to evaluate the recommended quantity of spare parts
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 41 of 62
ONS-OTS-MNT-003
UNCONTROLLED IF PRINTED
Procedure
A7.4 EQUIPMENT DETAIL SHEET TEMPLATE
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 42 of 62
ONS-OTS-MNT-003
Sample
UNCONTROLLED IF PRINTED
Procedure
Equipment Details Sheet Sample – Exclusively for Manual Valves
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 43 of 62
ONS-OTS-MNT-003
UNCONTROLLED IF PRINTED
Procedure
A7.5 SPARE PARTS SHEET HEADER INFORMATION
Heading
Description
Seq. No.
Sequential number. Complete as required.
Equipment Model Number
Part Description
Equipment Model Number associated with Parts Description on the same line. It must also exist on Equipment Details List.
Use the most complete description available. The cell wraps to fit the complete PO description. Follow the format of noun, noun modifier, type, size, class, grade, and standards authority (as applicable). Note: The PO description shall be in Characteristics and Value format (wherever applicable and especially for Valves, O-Rings, Gaskets, Stud Bolts, generalized items/Consumables. etc.). Example: Gasket, Type: Spiral wound, Size: 2”, Rating: 150#, Winding Material: SS316L, Filler Material: Graphite, Inner/Outer ring Material: SS316/CS, Thickness: 4.5mm, Flange Standard: ASME B16.5, Gasket Design Standard:B16.20.
Material and Dimensions
Required for all items, e.g., bag size, grade, etc.
Assembly/Cross Section Dwg. No.
Contractor number with reference to the Manufacturers Operating Supplies Document.
Pos. No./Item Reference No.
Reference on the drawing that identifies the part. If there are multiple identical parts on the drawing, then all Pos. Nos./Item Reference Nos. are listed.
Manufacturer Assembly/Cross Section Dwg. No.
Manufacturer Operating Supply document reference number.
Quantity of this Part Per Model
Number of times this part is used on this Equipment Model Number (the total installed quantity of that part)
OEM Part Number
OPM Part Number
OPM Name
Delivery
Effective 15 NOV 2019
Part Number used by manufacturer or supplier of equipment sold to buyer. Specifically, it is the Part Number that is used when purchasing the part from the company that sold the equipment or package.
Part Number used by the real manufacturer of the part, not the supplier’s Part Number for the equipment or package. OPM Part Number and OEM Part Number are same only if: OEM actually manufactured the part, or OEM incorporated OPM Part Number intact into its Part Number system.
Name of the company that manufactured the part. OPM Name and OEM Name are only the same if OEM actually manufactured the part.
Number of weeks for item to be ready to ship - ARO (After Receipt of Order). Do not include shipping.
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 44 of 62
ONS-OTS-MNT-003
UNCONTROLLED IF PRINTED
Procedure
Heading
Description
Shelf Life
Weight
Storage Dimension
Storage Code
This field is only required if the part deteriorates over time. Show in weeks after shipment. Default is blank. Plant location is subject to extremes of heat and humidity.
This field is only required if weight of part is over 20 kg. Show weight to nearest KG. Default is blank.
This field is only required if part cannot be placed in a parts bin or on a shelf. Default is blank.
Insert correct code: 1 Air Conditioned Area 2 Non-Air Conditioned Area 3 Dehumidified Storage Area 4 Yard (Open) 5 Cylinder Storage 6 Inert Nitrogen 7 AC+Inert G. Purged 8 OTHER
Hazardous Material
If the material is hazardous, insert the four-digit U.N. Number Code here, e.g. “UNxxxx”. The United Nations assigns this code to dangerous, hazardous, and harmful substances, and is available from the Material Safety Data Sheet (MSDS).
Capital Spares
Refer to Definitions of Spares Categories. (Refer to Section 2 and Appendix 2.)
Commissioning Spares
Refer to Definitions of Spares Categories (refer to Section 2 and Appendix 2) and update recommendation.
Start Up Spares
Refer to Definitions of Spares Categories (refer to Section 2 and Appendix 2) and update recommendation.
2 Years and Life Cycle spares
Repairable Y/N
Unit of Measure
Refer to Definitions of Spares Categories (refer to Section 2 and Appendix 2) and update recommendation. Note: Only 2-year spares recommendation shall be filled in OEM column and above 2-year spares (life cycle spares) recommendation shall be kept BLANK.
Is part/equipment repairable?
Total approved amount by the Company, which is automatically calculated and the value indicated in this column.
UNIT OF MEASURE DEFINITIONS
UOM in SAP DEFINITION
UOM in SAP
DEFINITION
UOM in SAP DEFINITION
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 45 of 62
ONS-OTS-MNT-003
UNCONTROLLED IF PRINTED
Procedure
Heading
ASSY
ASSEMBLY
BG
BL
BOX
BT
CAN
CAT
CYL
BAG
BALE
BOX
BOTTLE
CAN
CARTRIDGE
CYLINDER
DRM
DRUM
EA
FT
EACH
FOOT
KG
KIT
LEN
LOT
M
M2
M3
PC
PK
PL
PR
Description
KILOGRAM
ROL
KIT
LENGTH
LOT
METER
SET
SHT
SQF
T
SQUARE METER
TIN
CUBIC METER
TNK
TUB
PIECE
PACK
PAIL
PAIR
ROLL
SET
SHEET
SQUARE FEET
TON
TIN
TANK
TUBE
Pricing Per Agreement
Unit price and currency.
Total Approved Amount by Company
Total cost/value of each item.
SAP Stock No.
QG allocated material number in SAP MM.
QA/QC Requirements
For QA/QC spare parts requirements, refer to Appendix 8.
Item Previously Recommended PO Number and Item number
If the item was previously recommended for other POs, please provide the PO numbers in which this Item was recommended with item number
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 46 of 62
ONS-OTS-MNT-003
UNCONTROLLED IF PRINTED
Procedure
A7.6 SPARE PARTS SHEET TEMPLATE:
NOTE: The Spare Parts List shall be reviewed for Lifecycle spares, and purchase is only for 2-year Operating spares. The PMT will purchase
the OTS/OED-approved 2-years Operating spares and hand over to the QG Warehouse.
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 47 of 62
SPARE PARTS LIST1234Seq NO.EQUIP. MODEL NUMBER (Matches Equipment Details List)PART DESCRIPTION Noun, Noun Modifier, Type, Size, Class, Grade, Standards Authority MATERIAL & DIMENSIONSEPC CONTRACTOR’SASSY./CROSS SECTION DWG. NO.DELIVERY (Ready to Ship) Weeks ARO (After Receipt of Order)SHELF LIFE In Weeks, If PerishableASSY./CROSS SECTION DWG. NO.MANUFACTURER’SQTY. OF THIS PART PER MODELOriginal Equipment Mfr.’s “OEM” PART NUMBEROriginal Part Mfr.’s “OPM” (Real Manufacturer) PART NUMBER Original Part Mfr.’s “OPM” (Real Manufacturer) NAME POS. NO. / ITEM REF. NO. (List All)
ONS-OTS-MNT-003
Sample:
UNCONTROLLED IF PRINTED
Procedure
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 48 of 62
SPARE PARTS LIST112X16X21-3STG HSB(52-P0201A/B/C, 53-P0201A/B/C)ROTATING ELEMENTSUS329J1/SCS14AQCSR1A0107-A-0007009, 009-02, 009-03, 93, 167, 176, 201, 202, 203, 204, 205, 218, 249, 249-02, 251, 256, 257, 658, 676-1, 676-03, 676-04, 676-05, 676-06, 676-09PR050773201/905(ITEM No.009, 009-02, 009-03, 93, 167, 176, 201, 202, 203, 204, 205, 218, 249, 249-02, 251, 256, 257, 658, 676-1, 676-03, 676-04, 676-05, 676-06, 676-09)1R040945901-ROTR040945901-ROTEBARA CORP.64520212X16X21-3STG HSB(52-P0201A/B/C, 53-P0201A/B/C)VOLUTE-IN HALVESSUS316QCSR1A0107-A-0007 013, 013-01, 026, 060, 060-01PR050773201/905(ITEM No. 013, 013-01, 026, 060, 060-01)1R040945901-VOLUTER040945901-VOLUTEEBARA CORP.64520312X16X21-3STG HSB(52-P0201A/B/C, 53-P0201A/B/C)IMPELLERSCS14QCSR1A0107-A-0007176PR050773201/905(ITEM No. 176)1R040945901-176-1R040945901-176-1EBARA CORP.64520412X16X21-3STG HSB(52-P0201A/B/C, 53-P0201A/B/C)IMPELLER-2ND.STG.SCS14QCSR1A0107-A-0007176PR050773201/905(ITEM No. 176)1R040945901-176-02R040945901-176-02EBARA CORP.64520512X16X21-3STG HSB(52-P0201A/B/C, 53-P0201A/B/C)IMPELLER-3RD.STG.SCS14QCSR1A0107-A-0007176PR050773201/905(ITEM No. 176)1R040945901-176-03R040945901-176-03EBARA CORP.64520DELIVERY (Ready to Ship) Weeks ARO (After Receipt of Order)Seq NO.EQUIP. MODEL NUMBER (Matches Equipment Details List)PART DESCRIPTION Noun, Noun Modifier, Type, Size, Class, Grade, Standards Authority MATERIAL & DIMENSIONSEPC CONTRACTOR’SASSY./CROSS SECTION DWG. NO.POS. NO. / ITEM REF. NO. (List All)ASSY./CROSS SECTION DWG. NO.SHELF LIFE In Weeks, If PerishableMANUFACTURER’SQTY. OF THIS PART PER MODELOriginal Equipment Mfr.’s “OEM” PART NUMBEROriginal Part Mfr.’s “OPM” (Real Manufacturer) PART NUMBER Original Part Mfr.’s “OPM” (Real Manufacturer) NAME
ONS-OTS-MNT-003
UNCONTROLLED IF PRINTED
Procedure
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 49 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
A7.7 SPARE PARTS SHEET TEMPLATE
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 50 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
A7.8 SPARE PARTS LIST REVIEW REPORT
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 51 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 52 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
APPENDIX 8 – QATARGAS SPARE PARTS: QA/QC REQUIREMENTS
For QA/QC requirements for material receiving inspection, refer to procedure 02.18.50.04 QA/QC Requirements for Material Receiving Inspection.
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 53 of 62
ONS-OTS-MNT-003
UNCONTROLLED IF PRINTED
Procedure
APPENDIX 9 – OPERATING SUPPLIES LIST (OSL)
A9.1
LUBE TEMPLATE NOTE: The project shall arrange the Lubes list in this format, which includes Oil, Grease, Solvent, Solution, etc.
NOTE: Initial fill and consumption is project scope, and it shall last until the Operational Acceptance Certificate (OAC) is granted.
Sample:
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 54 of 62
ONS-OTS-MNT-003
UNCONTROLLED IF PRINTED
Procedure
A9.2 CHEMICAL TEMPLATE
NOTE: The Project shall arrange the Chemicals/Catalyst list in this format.
NOTE: Initial fill and consumption is project scope, and it shall last until the Operational Acceptance Certificate (OAC) is granted.
Sample:
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 55 of 62
ONS-OTS-MNT-003
UNCONTROLLED IF PRINTED
Procedure
APPENDIX 10 – SPECIAL TOOLS TEMPLATE
NOTE: The Project shall arrange the Special tools list in this format.
PMT to follow:
- All lifting tools shall have parent equipment load test certificates
- Arrange supporting documents for all special tools
- The Project shall handover all Tools identified and purchased with main Equipment PO to QG Warehouse for future maintenance
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 56 of 62
ONS-OTS-MNT-003
Sample:
UNCONTROLLED IF PRINTED
Procedure
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 57 of 62
ONS-OTS-MNT-003
UNCONTROLLED IF PRINTED
Procedure
APPENDIX 11 – BLINDS & SPACERS TEMPLATE
NOTE: The Project shall arrange the Blinds/Spacers list in this format.
PMT to follow:
- The Project shall ensure to manufacture all Blinds and Spacers in line with procedure TCH-AIG-PRC-088 Lifting Lug Welding and Testing
– for Spades, Spacers and Blind Flanges
- Blinds/spacers shall have lifting lugs and be load-tested as per procedure TCH-AIG-PRC-088 prior to handover to the QG Warehouse for
future maintenance
- All relevant Certificates shall be arranged during handover
Sample:
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 58 of 62
ItemTagPiping SpecTypeSizeRatingMaterialRemarksDimensional StandardHand over QtyItemTagPiping SpecTypeSizeRatingMaterialRemarksDimensional StandardHand over Qty08-PC811003C3AS1XBlind10”150#ASTM A515 GR 70FEMALE RING-JOINTASME B16.48108-PC811013C3AS1Xspacer3”900#ASTM A240 Gr 316LASME B16.48108-PC811023C3AS1XBlind20”600#ASTM A516 Gr 70N + S5 + NACE MR0175 + PWHTImpact test temperature -46°CASME B16.481
ONS-OTS-MNT-003
UNCONTROLLED IF PRINTED
Procedure
APPENDIX 12 – PIPING GASKET TEMPLATE
NOTE: The Project shall arrange the Piping Gaskets list in this format.
PMT to follow:
- The PMT shall purchase new Piping and insulation gaskets identified by OTS/OED and hand over to the QG Warehouse for future
maintenance
- All relevant Certificates shall be arranged during handover
Sample:
NOTE: Update installed quantity if item tag is not available.
NOTE: Insulations gasket kit shall be included in the Piping Gasket List.
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 59 of 62
ItemTagPiping SpecGasket TypeSizeRatingThicknessMaterialDimensional StandardInstalled QuantityItemTagPiping SpecGasket TypeSizeRatingThicknessMaterialDimensional StandardInstalled Quantity00-BD020013C3AS1XFlat6”150#3MMEPDMASME B16.2100-BD020023C3AS1XSpiral Wound3”150#4.5MMFiller: GraphiteInner Ring: 316SSOuter Ring:316SSWinding: 316SSASME B16.2000-BD020033C3AS1XRING JOINT-OVALR65600#316LSSASME B16.20
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
APPENDIX 13 – MANUAL VALVE GUIDELINES
Manual Valves Strategy
Equipment
Size
Requirements
Manual Valve For Cryogenic and Operational Critical Valves
Manual Valve For Non-Cryogenic and Non-Critical Valves
Less than 2 IN
Complete Valve and Repair Kit/Soft Goods
2 IN and above
All Spare Parts (Life Cycle Spares) including Actuated device (Example: Gear, etc.)
Less than 2 IN
Complete Valve and Repair kit/Soft Goods
2 IN and above
Packing, Gasket and required maintainable spares including Actuated device (Example: Gear, etc.)
NOTE: Process and Operational critical valves shall be identified during initial the EPC phase to follow
above guidelines in the Spare Parts List by EPC/Supplier.
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 60 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
APPENDIX 14 – SKID SAMPLE FOR CONTRACTOR/VENDOR REFERENCE – INCOMPLETE VS. COMPLETE DATA
Sample Pump Skid without Auxiliary Equipment – Incomplete Data
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 61 of 62
UNCONTROLLED IF PRINTED ONS-OTS-MNT-003 Procedure
Sample Pump Skid with Auxiliary Equipment – Complete Data
This document shows tagged (Functional Locations) equipment. If there is an Equipment that is not tagged, then that equipment and its Spares shall be listed in the Spare Parts List worksheet.
Effective 15 NOV 2019
Spare Parts and Material Procedure – OTS-OED Supported Projects Rev 00 Criticality Level: Medium
Page 62 of 62