UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
PROJECT INFORMATION HANDOVER, VERIFICATION AND ACCEPTANCE PROCEDURE
APPROVAL
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01
Page 1 of 29
Criticality Level: Medium
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
REVISION HISTORY
Rev No.
Issue Date
Revision Description
00
14 JUN 2016
01
03 FEB 2019
First issue RG-DFO-004 Final Deliverables Handover to Operations, Verification and Acceptance Procedure
Document restructured The following documents have been combined into this procedure: RG-DFO-004: Final Deliverables Handover to Operations, Verification and Acceptance Procedure
Draft Projects Technical Information Procedure
(PTI), sections 9.0 and 10.0
Valid Until Date
31 DEC 2021
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 2 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
CONTENTS
GENERAL … 5
Purpose… 5 Scope … 5 Out of Scope … 5
Criticality… 5 Key Risks and Controls … 5 Compliance … 6 Roles and Responsibilities … 6 PROCESSES AND REQUIREMENTS FOR PIH SUBMISSION… 8
Early Deliverables … 8 Final Deliverables … 8 Deficiencies and Late Deliverables … 8 REVIEW PROCESS … 9
Completeness … 9 Hardcopy … 9 Error Management and Correction … 10 Format Checking … 10
Sampling of Hardcopy Documentation … 10
Electronic Documentation … 11 Error Management and Correction … 11
Format Checking … 11
Soft Copies Checking Percentage Criteria (Accuracy and completeness)… 11
Review of Technical Content … 12 PMT … 12
OED/OTS… 13
PIH PROGRESS AND COMPLIANCE ASSESSMENTS … 14
HANDOVER TO PROJECTS DOCUMENT SUPPORT … 15
VERIFICATION AND MEASUREMENT … 16
FEEDBACK AND CONTINUAL IMPROVEMENT … 17
APPENDICES … 18
Appendix 1 – References and Relevant Documents … 18 Appendix 2 – Glossary of Terms: Definitions, Acronyms and Abbreviations … 19 Appendix 3 – List of checklists … 20 A3.1 Facilities Description Manual (SAMPLE) … 21 A3.2 Operating Manual (SAMPLE) … 22 A3.3 Fabrication Record Book (SAMPLE) … 23
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 3 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
A3.4 Vendor Mechanical Catalog Contents (SAMPLE) … 24 A3.5 Supplier Installation, Operation and Maintenance (IOM) Manual (SAMPLE) … 25 A3.6 Manufacturer Record Book Content (SAMPLE) … 26 A3.7 Engineering Documentation Checklist (SAMPLE) … 27 A3.8 Hard Copy Files – CheckList (SAMPLE) … 28 A3.9 Tracking Register (SAMPLE)… 29
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 4 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
GENERAL
PURPOSE
This procedure establishes guidelines, and a standardized set of processes, by which Early and Final Deliverables handover shall be managed and controlled from Contractor to PMT and then to Receiving Qatargas Parties in accordance with the requirements of the specifications listed in this procedure. In addition, this procedure describes the processes for review, validation, and approval of hardcopy and electronic deliverables. To this end, checklists provided as attachments. Final Deliverables shall be handed over to the receiving Qatargas party in an efficient and timely manner as per described in PRJ-PJL-PRC-006 Project Information Handover (PIH) Procedure.
SCOPE
This document is applicable to all deliverables handed over from Contractor(s) to Project Management Team (PMT), and from PMT to the appropriate receiving Qatargas parties. This procedure aligned with the requirements of PIH Procedure PRJ-PJL-PRC-006 and with ONS- OTS-OVR-002 Operations Technical Support Process to Manage Projects Procedure.
The following topics covered in this procedure:
Project close out activities applicable to handover of hardcopy and electronic
deliverables.
The handover process, including the formal acknowledgement of receipt by the
designated receiving Qatargas parties.
OUT OF SCOPE
The process for handover of the remaining Project Management Deliverables (PMD) from PMT to the receiving Qatargas party is not covered by this procedure, but available in V08-X09-010 (Project Stewardship Transfer Guidelines).
CRITICALITY
This Procedure has been determined to be a Medium Criticality document.
Criticality Level : Medium
KEY RISKS AND CONTROLS
Key Risks
Key Controls
Non-compliance with Qatargas PIH requirements
Final Deliverables requirements are listed and aligned with PIH Procedure PRJ-PJL-PRC-006
Acceptance of PIH without verification
List of roles and responsibilities for all parties are involved in the verification process.
Table 1: Key Risks and Controls
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 5 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
COMPLIANCE
All projects shall comply with the applicable deliverables as defined in this procedure for the effective handover verification and acceptance to Qatargas to ensure safe and reliable operation and maintenance of the plant / facility throughout its entire operational life cycle.
ROLES AND RESPONSIBILITIES
Position or Role
Projects Document Support (PDS) Representatives
PMT Representatives
Operations Expansion Department (OED)/ Operations Technical Support (OTS) Representatives
Engineering & Projects (E&P) Group Representatives
PMT Information Management Representatives
Responsibilities
Check, verify and accept Final Deliverables
Review Project Information Deliverables from Contractor prior handover to PDS representatives
Review Early Deliverables technical content and accept
on behalf of Operations
Review and approval of Recommended Spare Parts List
(RSPL) and Operating Supply List (OSL)
Note: Applicable for CAT I, II and III projects
Review Early Deliverables technical content and accept
on behalf of Operations
Review and approval of Recommended Spare Parts List
(RSPL) and Operating Supply List (OSL)
Note: Applicable for CAT III (less than $200 M), IV, V and VI projects Facilitation of PIH meetings with Contractor and Qatargas
parties
Timely and orderly handover of Final Deliverables as per
requirements
PIH Progress reporting
PMT QA/QC Lead
Review and approval of Manufacturer Records Book (MRB) & Fabrication Records Book (FRB)
PMT Document Control
Check final electronic deliverables against hardcopy deliverables.
PMT Completions Engineer
Major Projects Group Representatives
Check and verify completion dossiers and software registers
Monitor and verify Final Deliverables are handed over in
accordance with Qatargas requirements
Coordination and meeting attendance with PMT and PDS Auditing the PIH process
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 6 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
PDS Drafting
Review and approval of engineering database deliverables
Reliability Engineering Representatives
Review and approval of Reliability, Availability & Maintainability (RAM) model
Table 2: Roles and Responsibilities
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 7 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
PROCESSES AND REQUIREMENTS FOR PIH SUBMISSION
The Project Information Handover procedure shall be implemented for each project.
EARLY DELIVERABLES
Certain personnel representing the Operations Group shall be granted ‘full read’ access to the CONTRACTOR’s Enterprise Document Management System (EDMS) or the Major Projects group’s Project Document Management System (PDMS), in order that Early Deliverables are accessible. Early Deliverables are subject to quality checking for completeness and correctness as an integral feature of each project’s documented review and approval cycle, which includes input from PMT and Operations personnel as described in ONS-OTS-OVR-002 Operations Technical Support Process to Manage Projects Procedure. As the Early Deliverables process is designed to provide an ‘as is’ view, there is no separate or independent formalized checking process for this activity.
FINAL DELIVERABLES
It represents the Final Deliverables as described in PIH Procedure PRJ-PJL-PRC-006.
The contractor progressively hands over Final Deliverables during the project to PMT. The appointed representatives from PMT and Operations shall review Final Deliverables in accordance with the discipline to which the Information deliverables belong. The PMT Document Distribution Matrix will capture the responsibilities for this review and approval process.
DEFICIENCIES AND LATE DELIVERABLES
Deficiencies identified during PMT checks shall be notified to CONTRACTOR on formal transmittal. Issues requiring further resolution shall be escalated through the designated PMT representative.
Where deliverables fail to meet the milestone date (late deliverables), the designated PMT representative will initially agree amended target dates for submission with Contractor. The amended target date shall not supersede the agreed milestone date for reporting purposes.
Where late deliverables fail to meet an amended target date, the designated PMT representative shall escalate to Project Manager. Following handover a process may be established under the Stewardship of Projects Document Support and Quality teams to manage rectification of any deficiencies.
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 8 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
REVIEW PROCESS
Each category of submitted information will be subject to a defined review process described in PIH Procedure PRJ-PJL-PRC-006 “Appendix 10”, using the appropriate checklists (see attached appendices), to reflect the differing in formats and structures. Criteria for checking activity established in the individual line items set out in each checklist.
COMPLETENESS
Each Information Management (IM) deliverable within PIH procedure will be checked against the Master Document Register (MDR), Vendor Document Register (VDR), purchase order register or software registers to identify any misalignment between the scope of the registers and the deliverables submitted. Where missing documents are identified, this will be escalated through direct interface between the PMT and Contractor in the first instance. The relevant registers for each PIH Information Management (IM) deliverable are listed as following:
Information Deliverables
IM group
Description
IM-01
IM-02
IM-03
IM-04
IM-05
IM-06
IM-07
IM-08
Facility Process Description Manual
Operating Manual and Training Material
Engineering Documentation
Databases & Software
Vendor Documentation
Fabrication Record Book
Marine Transportation and Installation Manual
Ready for Commissioning (RFC) and Ready for Start-up (RFSU) Dossiers
Table 3: Information Management Deliverables
HARDCOPY
Review of Hardcopy will include:
Format checking (including legibility)
Technical content checking
Electronic copy cross-checking for consistency
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 9 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
Referential integrity checking, including validity and currency of all external
references (document numbers, tag numbers, etc.)
ERROR MANAGEMENT AND CORRECTION
Where formatting or technical errors found, a deficiencies sheet detailing the errors should be returned to the contractor by transmittal. The Contractor will ensure the deliverable corrected and resubmitted to the PMT by transmittal.
FORMAT CHECKING
The format checking of dossiers undertaken to ensure that each dossier complies with the Qatargas requirements, which include (but are not be limited to):
Binder
Front Cover
Spine
Index
Presentation
Legibility
Dividers
SAMPLING OF HARDCOPY DOCUMENTATION
Unless otherwise agreed with Projects Document Support, the PMT will conduct 100% review of Final Deliverables. Should this not possible, PMT shall contact Project Document Support to resolve the matter. Projects Document Support shall conduct a predefined percentage of reviews (sampling) according to PIH group.
The table below shows the percentage reviews that will be carried out by each responsible party. Acceptance criteria for review defined in the Hardcopy Files Checklist (Appendix A3.8).
Documentation/ Data
PMT
PDS
IM-01 IM-02 IM-03 IM-04 IM-05 IM-06 IM-07
IM-08
100% 100% 100% NA 100% 100% 100%
100%
10% 10% 100% NA 100% 30% 100% 10%; in addition all Mechanical and Systems Completions Original certificates
Table 4: Hardcopies Documentation QA/QC
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 10 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
ELECTRONIC DOCUMENTATION
Electronic documentation review includes (but not limited to):
Format checking
Technical content Checking
Hard copy Cross-Checking for consistency
Referential Integrity checking, including validity and currency of all external
references (document numbers, tag numbers, etc.)
Metadata verification
ERROR MANAGEMENT AND CORRECTION
Where formatting or technical errors found, a deficiency sheet detailing the errors shall be returned to the contractor by transmittal. The Contractor shall ensure the electronic file(s) is corrected and resubmitted to PMT by a transmittal and new hardcopy versions generated.
FORMAT CHECKING
The format checking of electronic documentation is undertaken to ensure compliance with Qatargas requirements, which include (but are not be limited to):
Electronic Format
o Refer to PIH Procedure PRJ-PJL-PRC-006.
File integrity
o File opens and displays correctly in its entirety.
Internal format layout o Front Cover, Spine, Indices and Dividers meet requirements and are fully aligned
with hardcopy
Bookmarks
o Bookmarks are comprehensive (complete) and fully functional
Searchable text: Optical Character Recognition (OCR)
o Text is complete and accurate
Legibility
o All text is legible
SOFT COPIES CHECKING PERCENTAGE CRITERIA (ACCURACY AND COMPLETENESS)
Information Management group
PMT
IM-01
IM-02
100% 100%
100% 100%
PDS
OTS/OED Design Drafting
N/A
N/A
N/A
N/A
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 11 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
IM-03
IM-04
100% 100%
N/A
N/A
Engineering Indices
100% N/A
RSPL (Note1)
100% N/A
EDMS
Smart-Plant databases (Note2)
100% 100%
N/A
N/A
Other software
100% N/A
RAM Model
100% N/A
IM-05
IM-06
IM-07
IM-08
100% 100%
100% 30%
100% 100%
100% 10%; in addition all
Mechanical and Systems Completions Original certificates
N/A
N/A
N/A
N/A
100%
100%
N/A
N/A
N/A
N/A
100%
N/A
N/A
100%
N/A
N/A
N/A
N/A
N/A
N/A
Table 5: Softcopies Documentation QA/QC
An acceptance criterion for review defined in the PIH deliverables Checklists (Appendix-3).
Note1: Recommended Spare Parts List (RSPL) is subject to ongoing review and approval during project execution.
Note2: Smart-Plant output data is subject to review and approval during project execution either through 3D models reviews or the approval of extracted deliverables such as P&ID’s, instrument indices, line lists by PMT. The PDS Drafting representative shall review from the initialization and on an ongoing basis along with the final review and acceptance of IM-04.
REVIEW OF TECHNICAL CONTENT
PMT
The responsible PMT shall undertake technical content checking, such as Quality or Engineering, dependent on the type of information or data and at the discretion of the project.
During the reviewing process, if any errors found, a deficiency sheet will be completed and returned to the contractor for corrective action. If necessary, copies of marked-up incorrect pages or dossiers(s) will be attached to the deficiency sheet and returned to the contractor where necessary check sheets defining technical content requirements for each type of dossier will be developed.
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 12 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
OED/OTS
The OED/OTS departments’ representatives will review the technical content of IM Early Deliverables as provided by PMT during project execution and return deficiencies to the PMT.
OED/OTS will also check and approve the technical content of the IM Early Deliverables.
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 13 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
PIH PROGRESS AND COMPLIANCE ASSESSMENTS
Information Management representative for the project will develop an assessment plan together with representatives from the receiving parties. The assessment plan shall take in account handover milestones for Early and Final Deliverables. It is mandatory to execute an assessment three months prior to RFSU and another three months after RFSU.
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 14 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
HANDOVER TO PROJECTS DOCUMENT SUPPORT
After all checks been completed, errors rectified and Final Deliverables provided, the Final Deliverables are ready for handover to PDS.
Projects Document Support will accept handover progressively if the submittals are undertaken in logical sets of volumes (i.e. VMC/MRB by Purchase Orders), or full sets of one IM group. If, following handover, PDS representatives detect any problems; they will communicate it to the project Information Management representative for resolution.
Hardcopy and electronic versions of Final Deliverables dossiers shall be submitted at the same time, together with the required EDMS Load list and Document-Tag Correlation List (DTCL).
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 15 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
VERIFICATION AND MEASUREMENT
The Project Management Team (PMT) and CONTRACTOR shall implement document processes to verify that all Information Deliverables are in compliance with the PIH requirements. These processes shall be auditable by Qatargas.
The Specification Deviation Request (SDR) process or equivalent is described in PRJ- CHG-PRC-001 Waiver Request Procedure, which defines the overall process for reviewing and approving proposed deviations to Qatargas specifications. This includes the PIH specification in PRJ-PJL-PRC-006. Interface points with Operation’s subject matter experts are implemented to provide recommendations for final disposition.
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 16 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
FEEDBACK AND CONTINUAL IMPROVEMENT
Feedback and continual improvement implemented through the following activities:
PDS SME involvement in project PIH Workshops in conjunction with the EPC
Contractor.
Early interfacing with Operations at the point of delivery of PIH Early Deliverables.
Interface coordination with defined focal points from Operations for identified disciplines and/or data types.
Joint reporting and tracking of PIH deliverable progress during a final handover stage.
Regular progress updates meetings with attendance of PIH stakeholders.
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 17 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
APPENDICES
APPENDIX 1 – REFERENCES AND RELEVANT DOCUMENTS
Document Number
PRJ-PJL-PRC-006 PRJ-CHG-PBK-001 PRJ-PJL-PRC-007
PRJ-CHG-PRC-001 ONS-OTS-OVR-002
V08-X09-010
Document Title
Project Information Handover Manage Change requests & Studies Smart Plant Engineering Applications And Drafting (CAD) Standard Procedure Waiver Request Procedure Operations Technical Support Process to Manage Projects Procedure Venture Project Stewardship Transfer process
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 18 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
APPENDIX 2 – GLOSSARY OF TERMS: DEFINITIONS, ACRONYMS AND ABBREVIATIONS
Term
Definition
COMPANY
Qatargas Operating Company Ltd
CONTRACTOR
Provider of services for Engineering (E), Procurement (P), and Construction (C)
DTCL
EDMS E&P EQDB FRB IM LIMC MCC MDR MRB OED OTS OSL PAC PDS PIH PMD PMT QG RAM RFC RFSU RSPL VDR VMC
Document-Tag Correlation List
Enterprise Documents Management System Engineering and Projects Equipment Database Fabrication Records Book Information Management Lead Information Management Coordinator Mechanical Completion Certificate Master Document Register Manufacturer Records Book Operations Expansion Department Operations Technical Support Operating Supply List Provisional Acceptance Certificate Projects Document Support Project Information Handover Project Management Documentation Project Management Team Qatargas Operating Company Ltd Reliability, Availability & Maintainability Ready for Commissioning Ready for Start-up Recommended Spare Parts List Vendor Document Register Vendor Mechanical Catalogue
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 19 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
APPENDIX 3 – LIST OF CHECKLISTS
Term
Definition
A3.1
A3.2 A3.3 A3.4 A3.5 A3.6 A3.7 A3.8 A3.9
Facilities Description Manual (Sample)
Operating Manual (Sample) Fabrication Record Book (Sample) Vendor Mechanical Catalogue (Sample) Supplier/Vendor IOM Manual (Sample) Manufacturer Records Book (Sample) Engineering Documentation (Sample) Hard Copy Files – Checklist (Sample) Tracking Register (Sample)
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 20 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
A3.1 FACILITIES DESCRIPTION MANUAL (SAMPLE)
Document No.
Vendor Name
Equipment Description
A
R
Approved
Rejected - (Incorporate Comments and Resubmit for Approval)
PO Number
Tag Number
Total No. of Volume
OPCO Review
Engineering Review
QA/QC Review
DCC Review
Name, Signature & Date
Name, Signature & Date
Name, Signature & Date
Name, Signature & Date
Requirements
Yes
No
N/A
Comments
Follow-Up
Signature
Date
FACILITY OVERVIEW
DESIGN INTENT AND PHILOSOPHY
T L U S E R
No .
1
2
3a
FACILITY DESCRIPTION (ONSHORE)
3b
SYSTEM DESCRIPTION (OFFSHORE)
4a
FACILITY CONTROL (ONSHORE)
4b
SYSTEMCONTROL (OFFSHORE)
5
6
7
8
9
PROCESS TECHNOLOGY
PROCESS DESCRIPTION (ONSHORE ONLY)
NORMAL OPERATING PARAMETERS
EQUIPMENT SPECIFICATION (HIGH LEVEL DESCRIPTIONS OF MAJOR EQUIPMENT)
PROCESS CONTROL (ONSHORE ONLY)
10
SHUTDOWN AND SAFETY SYSTEMS
11 HARDZS,RISKS AND PRECAUTIONS
12 ALTERNATE OPERATING MODES
13
SYSTEM BOUNDARY DRAWINGS (ONSHORE ONLY)
14
SYSTEM SPECIFICATION CONSIDERATIONS
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 21 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
A3.2 OPERATING MANUAL (SAMPLE)
Document No.
Vendor Name
Equipment Description
PO Number
Tag Number
Total No. of Volume
OPCO Review
T L U S E R
A
R
Approved
Name, Signature & Date
Rejected - (Incorporate Comments and Resubmit for Approval)
QA/QC Review
Engineering Review
Name, Signature & Date
DCC Review
Name, Signature & Date
Name, Signature & Date
No.
Requirements
Yes
No
N/A
Comments
Follow-Up
Signature
Date
1
Presentation by Hard Copy Files
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
Is the FOLDER - A4 size, hard, durable & loose-leaf folder(s)
Does the thickness of contents in each file exceed 80mm
Is the front page caption and first cover sheet in accordance with the approved format
Is the Spine Sheet layout in accordance with the approved format
Is the Vendor Document Number format in accordance with the Project Specification
Is the language used English or English translation?
Is the Index titled Operating Manual List of Contents?
Is Cardboard Sheet used to separate relevant sections, with proper label section letter and title?
Are irrelevant sections in the Operating Manual List of Contents indicated as N/A and is it printed on the title sheet
1.10
Are page numbers indicated at the right corner of each sheet?
Please Indicate Your Answer “N/A” If The Section Is Irrelevant To The Book
2
OVERVIEW
2.1
2.2
2.3
2.4
Purpose
Integrity Critical statement (IC procedure only)
Plant Turndown
Major Equipment Turndown Capacity
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 22 of 29
PO Number
Tag Number
Total No. of Volume
OPCO Review
Engineering Review
QA/QC Review
DCC Review
Name, Signature & Date
Name, Signature & Date
Name, Signature & Date
Name, Signature & Date
Yes
No
N /A
Comment s
Follow-Up
Signature
Date
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
A3.3 FABRICATION RECORD BOOK (SAMPLE)
Document No.
Vendor Name
Equipment Description
A
R
T L U S E R
Approved
Rejected - (Incorporate Comments and Resubmit for Approval)
No.
Requirements
1
Presentation by Hard Copy Files
1.1
Is the FOLDER - A4 size, hard, durable & loose-leaf folder(s)?
1.2 Does the thickness of contents in each file exceed 80mm?
1.3
1.4
1.5
Is the front-page caption and first cover sheet in accordance with the approved format? Is the Spine Sheet layout in accordance with the approved format? Is the Vendor Document Number format in accordance with the Project Specification?
1.6
Is the language used English or English translation
1.7
Is the Index titled MDR List of Contents
Is Cardboard Sheet used to separate relevant sections, with proper label section letter and title?
Are irrelevant sections in the MDR List of Contents indicated as N/A and is it printed on the title sheet
Are page numbers indicated at the right corner of each sheet
1.8
1.9
1.1 0
Please Indicate Your Answer “N/A” If The Section Is Irrelevant To The Book
2 USER GUIDE
2.1
Index
2.2
1.2. Guideline
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 23 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
A3.4 VENDOR MECHANICAL CATALOG CONTENTS (SAMPLE)
Document No.
Vendor Name
Equipment Description
A
R
T L U S E R
No.
Approved
Rejected - (Incorporate Comments and Resubmit for Approval)
PO Number
Tag Number
Total No. of Volume
OPCO Review
Engineering Review
QA/QC Review
DCC Review
Name, Signature & Date
Name, Signature & Date
Name, Signature & Date
Name, Signature & Date
Requirements
Yes
No
N/A
Comments
Follow-Up
Signature
Date
1.0
Introduction (Section Break only)
Suppliers Information (General information including name, address, contact person, telephone and/or fax number, e-mail address, Purchase Order number, main equipment description, and Tag Numbers).
1.1
This information shall include Qatar representative office details or Middle East office contact details for all items (including sub vendors).
1.2 Main Sub-Supplier Information Similar to Item 1.1 above
1.3 Main index for all volumes
1.4
Detailed index for all volumes
1.5
Detailed index of Manufacturers Record Book
1.6
1.7
Cross-reference Index between Document Number and Tag Number Note: This Index shall list all the Supplier documents and/or drawings (as per the VDR), their document and/or drawing numbers, and cross-reference them to the applicable Tag Numbers. This shall be provided in electronic format (MS Excel).
Cross-reference Index between Tag Number and Document Number Note: This Index shall list all the Tag Numbers allocated on this package and cross reference them to the Supplier documentation. This shall also be provided in electronic format (MS Excel).
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 24 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
A3.5 SUPPLIER INSTALLATION, OPERATION AND MAINTENANCE (IOM) MANUAL
T L U S E R
N o.
1
2
3
(SAMPLE)
Document No.
Vendor Name
Equipment Description
A
R
Approved
Rejected - (Incorporate Comments and Resubmit for Approval)
PO Number
Tag Number
Total No. of Volume
OPCO Review
Engineering Review
QA/QC Review
DCC Review
Name, Signature & Date
Name, Signature & Date
Name, Signature & Date
Name, Signature & Date
Requirements
Yes
No
N/A
Comments
Follow-Up
Signature
Date
Table of Contents
Introduction
Specifications and General Data
3.1
3.2
3.3
Name Plate data
Design, rated and normal operating and turn down conditions
Critical speeds: Centrifugal and rotary compressors; steam, gas, and hydraulic turbines; expanders, agitators, centrifuges, motors related these equipment
3.4 Weights of components
3.5
Actual operating and test curves
Characteristic performance All curves to permit calculation of power at non-standard operating conditions (e.g., power vs. RPM against inlet air temperature, and exhaust air temperature for gas turbine drivers): centrifugal compressors, turbines (all types), expanders, fans, Ring pressure vs. steam consumption and power: steam turbines All composite speed - torque illustrating torque vs. load requirements for critical services: e.g. compressors, gas turbines, generators, fans
3.6
Drawings (plan, cross-sectional, outline) showing critical clearance dimensions, location of connections, removal space for maintenance
3.7
Utilities (e.g. quantities, pressure, temperature, flows)
3.8
Catalysts and chemicals: quantities and specifications for initial charge and replacement or make up rates and recommended intervals
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 25 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
A3.6 MANUFACTURER RECORD BOOK CONTENT (SAMPLE)
Document No.
Vendor Name
Equipment Description
A
R
T L U S E R
Approved
Rejected - (Incorporate Comments and Resubmit for Approval)
PO Number
Tag Number
Total No. of Volume
OPCO Review
Engineering Review
QA/QC Review
DCC Review
Name, Signature & Date
Name, Signature & Date
Name, Signature & Date
Name, Signature & Date
No.
Section A
Section B
Section C
Section D
Requirements
Yes
No
N/A
Comments
Follow-Up
Signature
Date
Inspection Release Certificate
a)
A copy of the ‘Inspection Release Note’ signed by Contractor inspector shall be included
List of Approved Specification Deviations
a)
All approved SDR’s shall be listed and described. Documented evidence of approvals shall be provided and placed behind the list.
Non Conformance Reports
a)
All non-conformance reports with their approved dispositions and implementation verification shall be inserted in this section.
Material Certificates, Alloy Verification, and Material Test Reports
a)
b)
This section shall contain a list identifying material certificates or material test reports with their part, piece or item number. This section shall also include certificate or reports referred to on the list.
The list shall show the Vendor’s drawing number of each part or piece of equipment or bulk material item number identified with
c)
Certificate or report number, line item - page number
d)
Heat, charge, batch, lot. Plate number etc.
e) Name of mill
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 26 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
A3.7 ENGINEERING DOCUMENTATION CHECKLIST (SAMPLE)
Document No.
Vendor Name
Equipment Description
PO Number
Tag Number
Total No. of Volume
OPCO Review
A
R
T L U S E R
Approved
Rejected - (Incorporate Comments and Resubmit for Approval)
Engineering Review
QA/QC Review
DCC Review
Name, Signature & Date
Name, Signature & Date
Name, Signature & Date
Name, Signature & Date
No.
Requirements
Yes
No
N/A
Comments
Follow-Up
Signature
Date
1
Engineering Documentation
1.1
Is the document legible?
1.2
Is the file Format is acceptable?
1.3
Is the document number is as per the procedure?
1.4
Is the revision number matches EDMS LL and MDR?
1.5
Is all EPC documents except those extracted from CAD DB are in native format?
1.6
Is the document number in MDR is available?
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 27 of 29
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-049 Procedure
A3.8 HARD COPY FILES – CHECKLIST (SAMPLE)
Document No.
Vendor Name
Equipment Description
A
R
Approved
Rejected - (Incorporate Comments and Resubmit for Approval)
T L U S E R
PO Number
Tag Number
Total No. of Volume
OPCO Review
Engineering Review
QA/QC Review
DCC Review
Name, Signature & Date
Name, Signature & Date
Name, Signature & Date
Name, Signature & Date
No.
Requirements
Yes
No
N/A
Comments
Follow-Up
Signature
Date
1
Presentation by Hard Copy Files
1.1
Thickness of the binder is acceptable.
1.2
Print out of the document is acceptable.
1.3
1.4
Covers and Spine in accordance with the approved format Document number as per the agreed numbering procedure
1.5
Is the language used English or English translation?
1.6
1.7
Is Cardboard Sheet used to separate relevant sections, with proper label section letter and title? Are page numbers indicated for each sheet are consistent with e-files
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 28 of 29
Classification: Internal
UNCONTROLLED IF PRINTED PRJ-PJL-PRC-004 Procedure
A3.9 TRACKING REGISTER (SAMPLE)
Transmittal No.
Document Number
v e R
Reason
For Issue
Document Title
Issue Date
Acknowledge received Y/N
Date Acknowledge
Accepted/Rejected
Reason for Volume / Documents Rejection
PIH Comments
Date Returned to PMT
Date Returned to Contractor
Response to PDS
Close- out Status
Date Close- out
MRB
IOM
VMC
FRB
Engineering Documents
Remarks
Numbers
Effective 01 JAN 2019
Project Information Handover, Verification and Acceptance Procedure Rev 01 Criticality Level: Medium
Page 29 of 29
Project: Q-21699 - Saipem COMP2 Folder: RFQ Files