NFPS Offshore Compression Complexes Project COMP2

COMPANY Contract No.: LTC/C/NFP/5128/20

CONTRACTOR Project No.: 033734

Document Title

:

DATA SHEET FOR LIFEBUOY FOR CP6S COMPLEX

COMPANY Document No.

: 560-20-SH-DTS-00009

Saipem Document No.

: 033734-B-D-30-SPM-LP-B-10011

Discipline

: HSE&Q

Document Type

: DATA SHEET

Document Category/Class

: 2

Document Classification

: INTERNAL

00

06-Dec-2023

26-Sep-2023

B

A

Approved for Construction Issued for Approval

Azran Shariman

Rama Krishna K.

Luminita Oprescu

Maria Fransisca

Rama Krishna K.

Luminita Oprescu Vijayakumar Rajaram

09-Aug-2023

Issued for Review

Maria Fransisca

Rama Krishna K.

REV.

DATE

DESCRIPTION OF REVISION

PREPARED BY

CHECKED BY

APPROVED BY

Saipem S.p.A.

THIS DOCUMENT IS PROPERTY OF QATARGAS. THIS DRAWING OR MATERIAL DESCRIBED THEREON MAY NOT BE COPIED OR DISCLOSED IN ANY FORM OR MEDIUM TO THIRD PARTIES, OR USED FOR OTHER THAN THE PURPOSE FOR WHICH IT HAS BEEN PROVIDED, IN WHOLE OR IN PART IN ANY MANNER EXCEPT AS EXPRESSLY PERMITTED BY QATARGAS.

Company No._Rev. 560-20-SH-DTS-00009_00

1 of 12

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFEBUOY FOR CP6S COMPLEX

REVISION HISTORY

Revision

Date of Revision

Revision Description

A1

A

B

00

20-Jul-2023

Issued for Inter-Discipline Check

09-Aug-2023

26-Sep-2023

06-Dec-2023

Issued for Review

Issued for Approval

Approved for Construction

HOLDS LIST

Hold No

Hold Description

Company No._Rev. 560-20-SH-DTS-00009_00

2 of 12

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFEBUOY FOR CP6S COMPLEX

TABLE OF CONTENTS

1

2

3

4

5

INTRODUCTION … 4

1.1 PROJECT OBJECTIVE … 4 1.2 PROJECT SCOPE … 4

DEFINITIONS AND ABBREVIATIONS … 6

2.1 DEFINITIONS … 6 2.2 ABBREVIATIONS … 7

REGULATIONS, CODES AND STANDARDS … 8

3.1 COMPANY DOCUMENTS … 8 3.2 PROJECT DOCUMENTS … 8 INTERNATIONAL CODES AND STANDARDS … 9 3.3

PURPOSE … 10

DATA SHEET … 11

Company No._Rev. 560-20-SH-DTS-00009_00

3 of 12

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFEBUOY FOR CP6S COMPLEX

1

INTRODUCTION

The North Field is the world’s largest natural gas field and accounts for nearly all of the state of Qatar’s gas production. The reservoir pressure in the North Field has been declining due to continuous production since the early 1990s. The principal objective of the NFPS Project is to sustain the plateau from existing QG South Operation (RL Dry Gas, RGE Wet gas) and existing QG North Operation (QG1 & QG2) production areas by implementing an integrated and optimum investment program consisting of subsurface development, pressure drop reduction steps and compression. Refer to the figure below for a schematic of the North Field.

Qatargas Operating Company Limited is leading the development of the North Field Production Sustainability (NFPS) Project.

1.1 Project Objective

The objective of this Project includes:

• Sustain the Qatargas North Field Production Plateau by installing new Compression Complex facilities CP6S & CP7S in QG south with integration to the existing facilities under Investment #3 program.

• Facility development shall be safe, high quality, reliable, maintainable, accessible, operable,

and efficient throughout their required life.

• Achieve standards of global excellence in Safety, Health, Environment, Security and Quality

performance.

1.2 Project Scope

The Project Scope includes detailed engineering, procurement, construction, transportation & installation, hook-up and commissioning, tie-in to EXISTING PROPERTY and provide support for start- up activities of the following facilities and provisions for future development. The WORK shall be following the specified regulations, codes, specifications and standards, achieves the specified performance, and is safe and fit

purpose in all respects.

for

Offshore

‐

‐

CP6S and CP7S Compression Complexes that are part of QG-S RGE facilities as follows:

• CP6S Compression Complex

• Compression Platform CP6S, Living Quarters LQ6S, Flare FL6S

• Bridges BR6S-2, BR6S-3, BR6S-4, BR6S-5

• Bridge linked Tie-in to RP6S

Production from existing wellheads (WHP6S & WHP10S) and new wellhead (WHP14S) are routed via riser platform RP6S to compression platform CP6S to boost pressure and export to onshore via two export lines through the existing WHP6S pipeline and a new 38” carbon steel looping trunkline from RP6S (installed by EPCOL). CP6S is bridge-linked to RP6S.

• CP7S Compression Complex

• Compression Platform CP7S, Living Quarters LQ7S, Flare FL7S

• Bridges BR7S-2, BR7S-3, BR7S-4, BR7S-5

• Bridge linked Tie-in to RP7S

Company No._Rev. 560-20-SH-DTS-00009_00

4 of 12

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFEBUOY FOR CP6S COMPLEX

CP7S shall receive production from existing wellheads (WHP5S & WHP7S) and new wellhead (WHP13S). There is only one export line for CP7S through the existing export pipeline from WHP7S. CP7S is bridge-linked to RP7S.

RGA Complex Destressing

Migration of the Electrical power source, Telecoms, Instrumentation and Control systems from WHPs and RPs hosted by RGA to the respective Compression Complexes listed below:

• WHP6S, WHP10S, WHP14S, RP6S and RP10S to CP6S Compression Complex

• WHP5S, WHP7S, WHP13S and RP7S to CP7S Compression Complex

Destressing of Telecoms, Instrumentation and Control system in RGA Complex Control Room, which would include decommissioning and removal of telecom system devices and equipment that would no longer be required post migration and destressing activity.

Onshore

An Onshore Collaborative Center (OCC) will be built under EPC-9, which will enable onshore based engineering teams to conduct full engineering surveillance of all the offshore facilities. The OCC Building will be located in Ras Laffan Industrial City (RLIC) within the Qatar Gas South Plot. MICC & Telecommunication, ELICS related scope will be performed in the OCC building.

Figure 1.2.1: NFPS Compression Project COMP2 Scope

Company No._Rev. 560-20-SH-DTS-00009_00

5 of 12

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFEBUOY FOR CP6S COMPLEX

2 DEFINITIONS AND ABBREVIATIONS

2.1 Definitions

Definition

Description

COMPANY

Qatargas Operating Company Limited.

CONTRACTOR

Saipem S.p.A.

DELIVERABLES

FACILITIES

MILESTONE

All products (drawings, equipment, services) which must be submitted by CONTRACTOR to COMPANY at times specified in the contract. All machinery, apparatus, materials, articles, components, systems and items of all kinds to be designed, engineered, procured, tested and manufactured, constructed, supplied, permanently installed by CONTRACTOR at SITE in connection with the NFPS Project as further described in Exhibit 6.

fabricated,

A reference event splitting a PROJECT activity for progress measurement purpose.

PROJECT

NFPS Offshore Compression Complexes Project COMP2

SITE

(i) any area where Engineering, Procurement, Fabrication of the FACILITIES related to the CP6S and CP7S Compression Complexes are being carried out and (ii) the area offshore required for installation of the FACILITIES in the State of Qatar.

SUBCONTRACT

Contract signed by SUBCONTRACTOR and CONTRACTOR for the performance of a certain portion of the WORK within the Project.

SUBCONTRACTOR

Any organization selected and awarded by CONTRACTOR to supply a certain Project materials or equipment or whom a part of the WORK has been Subcontracted.

WORK

Scope of Work defined in the CONTRACT.

WORK PACKAGE

The lowest manageable and convenient level in each WBS subdivision.

VENDOR

The person, group, or organization responsible for the design, manufacture, testing, and load-out/shipping of the Equipment/ Material.

Company No._Rev. 560-20-SH-DTS-00009_00

6 of 12

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFEBUOY FOR CP6S COMPLEX

2.2 Abbreviations

Code

Definition

BR

CP

ELICS

EPC

EPCOL

FL

HFE

LQ

NFPS

OCC

QG

RGA

RGE

RL

RLIC

RP

UV

WBS

WHP

Bridge

Compression Platform

Electrical Integrated Control System

Engineering, Procurement and Construction

Offshore and Pipelines Project

Flare Platform

Human Factors Engineering

Living Quarters

North Field Production Sustainability

Onshore Collaborative Center

Qatargas Operating Company Limited

Ras Gas Alfa

Ras Gas Expansion

Ras Laffan

Ras Laffan Industrial City

Riser Platform

Ultraviolet

Work Breakdown Structure

Wellhead Platform

Company No._Rev. 560-20-SH-DTS-00009_00

7 of 12

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFEBUOY FOR CP6S COMPLEX

3 REGULATIONS, CODES AND STANDARDS

In general, all design activities shall confirm to legal and statutory regulations and recognized industry best practices. Conflict among applicable specification and / or codes shall be brought to the attention of the COMPANY for resolution COMPANY decision shall be final and shall be implemented. The latest editions of codes and specification effective as on date of contract shall be followed.

In general, the order of precedence shall be followed:

a) Qatari Governmental and Regulatory Requirements

b) COMPANY Procedures, Policies and Standards (Exhibit 5 Appendix I)

c) Project Specifications.

d) Industry Codes and Standards

e) COMPANY and CONTRACTOR’s Lessons Learned

If CONTRACTOR/ SUBCONTRACTOR deems any deviations from the specifications will result in significant project cost and schedule saving, proposal to such deviations shall be submitted to COMPANY for review and approval. CONTRACTOR/ SUBCONTRACTOR shall not proceed with any deviation to the specifications without prior COMPANY approval.

The following is a list of relevant regulations, codes, standards, specification, Company documents that shall be considered for the Project in the order of precedence listed above.

3.1 Company Documents

S. No

Document Number

Title

PRT-PRS-PRC-014

Offshore Loss Prevention Philosophy

COMP-QG-PR-REP- 00008

North Field Production Sustainability (NFPS), NFPS Compression Project: EPC-2 – Basis of Design EPC2

PRT-ENV-PRC-013

Environmental Aspects and Impacts Procedure

3.2 Project Documents

S. No

Document Number

Title

200-20-SH-DEC-00005

200-20-SH-DEC-00008

200-20-SH-SPC-00006

200-20-ME-DEC-00003

200-20-PI-SPC-00015

200-20-SH-SPC-00011

200-20-CE-DEC-00003

Technical Safety and Loss Prevention Design Philosophy for CP6S and CP7S Complexes Escape, Evacuation & Rescue Design Philosophy for CP6S and CP7S Complexes Specification for Safety and Lifesaving Equipment for CP6S and CP7S Complexes Material Handling Philosophy for CP6S and CP7S Complexes Piping Material Specification for CP6S and CP7S Complexes HFE Workplace Design Specification for CP6S and CP7S Complexes Material Selection Philosophy for CP6S and CP7S Complexes

Company No._Rev. 560-20-SH-DTS-00009_00

8 of 12

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFEBUOY FOR CP6S COMPLEX

S. No

Document Number

Title

200-20-CE-SPC-00015

Painting Specification for CP6S and CP7S Complexes

200-21-ST-DEC-00001

560-20-SH-PLN-00006- 0001

560-20-SH-PLN-00007

560-20-SH-PLN-00009

562-83-SH-PLN-00001

562-83-SH-PLN-00002

562-83-SH-PLN-00003

562-20-SH-PLN-00001

562-20-SH-PLN-00003

564-20-SH-PLN-00001

561-20-SH-PLN-00001

563-20-SH-PLN-00001

560-20-SH-LIS-00001

Greenfield Structural Design Basis for Substructure of CP6S and CP7S Complexes Escape Route, Life Saving and Fire Fighting Equipment Layout – Main Deck for Compression Platform CP6S Escape Route, Life Saving and Fire Fighting Equipment Layout – Production Deck for Compression Platform CP6S Escape Route, Life Saving and Fire Fighting Equipment Layout – Sump Deck for Compression Platform CP6S Escape Route, Life Saving and Fire Fighting Equipment Layout – Level 1 for LQ6S Escape Route, Life Saving and Fire Fighting Equipment Layout – Level 2 for LQ6S Escape Route, Life Saving and Fire Fighting Equipment Layout – Level 3 for LQ6S Escape Route, Life Saving and Fire Fighting Equipment Layout – Cellar Deck for LQ6S Escape Route, Life Saving and Fire Fighting Equipment Layout – Sub Cellar Deck for LQ6S Escape Route, Life Saving and Fire Fighting Equipment Layout Drawing – Flare Platform FL6S (CP6S Complex) Escape Route, Life Saving and Fire Fighting Equipment Layout Drawing – CP – LQ Bridge (CP6S Complex) Escape Route, Life Saving and Fire Fighting Equipment Layout Drawing – CP – FP Bridge (CP6S Complex) Safety Equipment List for CP6S Complex

3.3

International Codes and Standards

S. No

Document Number

Title

IMO IE110E

International Convention for the Safety of Life at Sea

IMO ID982E

Life Saving Appliances Code

Company No._Rev. 560-20-SH-DTS-00009_00

9 of 12

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFEBUOY FOR CP6S COMPLEX

4 PURPOSE

The purpose of this data sheet is to cover the technical requirements for Lifebuoy of CP6S Complex in the NFPS Offshore Compression Complexes Project, COMP2. This data sheet shall be read in conjunction with Specification for Safety & Life Saving Equipment for CP6S And CP7S Complexes [Ref.6]. VENDOR’s scope of supply shall include, but not be limited to, the requirements listed in this data sheet and referred specifications.

Company No._Rev. 560-20-SH-DTS-00009_00

10 of 12

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFEBUOY FOR CP6S COMPLEX

5 DATA SHEET

DATA SHEET IDENTIFICATIONS

DOCUMENT NO

560-20-SH-DTS-00009

ADMINISTRATIVE IDENTIFICATIONS

PROJECT NUMBER

033734

LIFEBUOY

PROJECT

NFPS OFFSHORE COMPRESSION COMPLEXES PROJECT COMP2

A

1

B

1

2

3

QUANTITY

C

EQUIPMENT IDENTIFICATION

1

TAG NUMBER

LIFEBUOY WITH LIFELINE

-CP6S PLATFORM : 22 NOS. -LQ6S PLATFORM: 16 NOS. -FL6S PLATFORM: 2 NOS. -BRIDGE CP6S-FL6S: 3 NOS. -BRIDGE CP6S-LQ6S: 6 NOS. -BRIDGE CP6S-RP6S: 3 NOS.

LIFEBUOY WITH LIFELINE, SMOKE SIGNAL AND LIGHT

-LQ6S PLATFORM: 4 NOS.

LIFEBUOY WITH LIFELINE

-CP6S PLATFORM: 560-XZ2021 ~ 560-XZ2042 -LQ6S PLATFORM: 562-XZ2001 ~ 562-XZ2016 -FL6S PLATFORM: 564-XZ2001 ~ 564-XZ2002 -BRIDGE CP6S-FL6S: 563-XZ2001 ~ 563-XZ2003 -BRIDGE CP6S-LQ6S: 561-XZ2001 ~ 561-XZ2006 -BRIDGE CP6S-RP6S: 565-XZ2001 ~ 565-XZ2003

LIFEBUOY WITH LIFELINE, SMOKE SIGNAL AND LIGHT

-LQ6S PLATFORM: 562-XZ2021 ~ 562-XZ2024

2

D

1

2

3

E

1

SERVICE

LIFE SAVING

OPERATION DATA

ENVIRONMENTAL / SITE CONDITIONS (NOTE 5 & 6)

ENVIRONMENTAL / SITE CONDITIONS

MINIMUM

NORMAL

MAXIMUM

BLACK BULB

UNITS

AMBIENT TEMPERATURE

RELATIVE HUMIDITY DAILY AVERAGE

8.3

37.0

45.6

100.0

84

°C

%

ATMOSPHERE

HUMID, SALIFEROUS, SALT LADEN, AND MARINE ATMOSPHERE, POSSIBLE H2S PRESENCE

TECHNICAL SPECIFICATION

EQUIPMENT DESIGN CRITERIA

LIFEBUOY CRITERIA:

1.1

TYPE

PERRYBUOY LIFEBUOYS

1.2

COLOUR

INTERNATIONAL ORANGE

1.6

1.7

SHALL HAVE COVER MADE OF ROTATIONALLY MOULDED HIGH DENSITY POLYETHYLENE SKIN.

REQUIRED

LIFEBUOY LOCATED AT CELLAR DECK SHALL BE FITTED WITH SMOKE SIGNAL AND SELF-IGNITING LIGHTS

REQUIRED

1.3

SHALL BE FITTED WITH RETRO- REFLECTIVE MATERIAL TO ASSIST IN DETECTION.

REQUIRED

1.8

SHALL BE PROVIDED WITH LIFELINE REQUIRED

SHALL BE COMPLETE WITH GALVANIZED “Y” MOUNTING BRACKET(S) FOR MOUNTING ON HANDRAILS, MATERIALS OF BRACKET(S) SHALL BE CORROSION RESISTANT AND SUITABLE FOR THE SALIFEROUS ENVIRONMENT.

REQUIRED

1.9

SHALL BE FITTED WITH A GRABLINE REQUIRED

SHALL HAVE INNER CORE MADE OF POLYURETHANE FOAM.

REQUIRED

EQUIPMENT ACCESSORIES

LIFELINE CRITERIA:

POLYETHYLENE LIFELINE WITH ORANGE COLOR.

REQUIRED

ONE END OF LIFELINE SHALL BE ATTACHED TO THE LIFEBUOY AND OTHER END SECURELY FASTENED TO THE PLATFORM.

REQUIRED

1.10

ALL ACCESSORIES SHALL BE MADE UV AND MARINE RESISTANT MATERIAL.

REQUIRED

1.4

MADE OF SYNTHETIC ROPE WITH INHERENT UV RESISTANCE.

REQUIRED

1.5

ENCAPSULATED IN A PLASTIC HOLDER.

REQUIRED

1.4

1.5

F

1

1.1

1.2

1.3

LENGTH AND SIZE

MIN. 40 METERS AND 8 MM

2

WHISTLE CRITERIA:

2.1 MADE OF PLASTIC.

REQUIRED

2.3

THE LANYARD SHALL BE FREE OF HOOKS, SNAPS OR CLIPS.

REQUIRED

Company No._Rev. 560-20-SH-DTS-00009_00

11 of 12

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFEBUOY FOR CP6S COMPLEX

LIFEBUOY

2.2

WHISTLE COILED WITH 1 ft LENGTH OF LANYARD (NOT EASILY TANGLED) AND ATTACHED TO THE LIFE BUOY.

REQUIRED

3

SMOKE SIGNAL CRITERIA:

3.1

3.2

EMIT SMOKE OF A HIGHLY VISIBLE COLOUR (ORANGE) AT UNIFORM RATE FOR A PERIOD OF AT LEAST 15 MIN WHEN FLOATING IN WATER.

REQUIRED

PROVIDED WITH A QUICK RELEASE ARRANGEMENT THAT WILL AUTOMATICALLY RELEASE AND ACTIVATE THE SIGNAL.

REQUIRED

4 WATER ACTIVATED LIGHT CRITERIA:

4.1

SHALL BE SOLAS APPROVED.

REQUIRED

4.2

SHALL BE TAMPER, IMPACT AND CORROSION RESISTANT.

REQUIRED

4.3

4.4

4.5

4.6

SHALL BE SEALED TO PROTECT AND PROVIDE ITS BATTERY COMPARTMENT LONG TERM STORAGE PROPERTIES.

REQUIRED

SHALL OPERATE ON LITHIUM BATTERY.

REQUIRED

SHALL BE WATER-ACTIVATED AND INEXTINGUISHABLE BY WATER.

REQUIRED

HAZARDOUS AREA CLASSIFICATION REQUIREMENT: ZONE 1, GAS GROUP IIB, TEMPERATURE CLASS T3.

REQUIRED

G

SPECIAL REQUIREMENT

3.3

3.4

4.7

4.8

4.9

SMOKE SIGNAL SHALL BE PROVIDED WITH MOUNTING BRACKET & ALL FIXING ACCESSORIES AND ATTACHED TO THE LIFEBUOY WITH LANYARD.

REQUIRED

DO NOT IGNITE EXPLOSIVELY OR EMIT ANY FLAME DURING THE ENTIRE SMOKE EMISSION TIME OF THE SIGNAL.

REQUIRED

LIGHT SHALL BE PROVIDED WITH MOUNTING BRACKET & ALL FIXING ACCESSORIES AND ATTACHED TO THE LIFEBUOY WITH LANYARD.

REQUIRED

SHALL EMIT WHITE COLOUR LIGHT FOR AT LEAST TWO (2) HOURS.

REQUIRED

SHALL BE CAPABLE TO EITHER BURN CONTINUOSLY WITH INTENSITY NOT LESS THAN 2.0 Cd OR FLASHING WITH RATE NOT LESS THAN 50 FLASHES/MIN

REQUIRED

4.10

SHALL BE ATTACHED TO THE BUOY BY A TWELVE THREAD LANYARD BETWEEN 3 TO 6 FT.

REQUIRED

4.11

BATTERIES FOR EACH LIGHT SHALL BE PROVIDED.

REQUIRED

COMPLIANCE STANDARD

SOLAS

LIFE SAVING APPLIANCES (LSA) CODE

CERTIFICATION

SOLAS / EC/ MED

ENVIRONMENTAL REQUIREMENT

ALL MATERIALS SHALL BE SUITABLE FOR OFFSHORE SALINE CONDITION

PHYSICAL DATA

WEIGHT OF EQUIPMENT

VENDOR TO ADVISE

INNER DIAMETER

VENDOR TO ADVISE

3

4

OUTER DIAMETER

VENDOR TO ADVISE

WEIGHT OF EQUIPMENT

VENDOR TO ADVISE

EQUIPMENT IDENTIFICATIONS

MODEL NUMBER

VENDOR TO ADVISE

3

MANUFACTURER COUNTRY

VENDOR TO ADVISE

MANUFACTURER NAME

VENDOR TO ADVISE

LIFEBUOY MATERIAL

LIFEBUOY MATERIAL

VENDOR TO ADVISE

LIFEBUOY COATING

VENDOR TO ADVISE

3

4

LIFEBUOY INNER CORE MATERIAL

VENDOR TO ADVISE

LIFEBUOY COVER MATERIAL

VENDOR TO ADVISE

NOTES

WEIGHT OF EACH LIFEBUOY COMPLETE WITH ITS ACCESSORIES AS WELL AS WEIGHT OF THE MOUNTING BRACKET TO BE PROVIDED SEPARATELY.

RING LIFEBUOY HOUSING WITH ROTATIONALLY MOLDED POLYETHYLENE COVER SHALL BE PROVIDED TO EXTEND LIFE SPAN OF THE LIFEBUOY.

LIFEBUOY HOLDER SHALL BE PROVIDED AT EACH LOCATION. THE HOLDER SHALL BE PERMANENTLY ATTACHED TO THE INSIDE OF HANDRAILS ALONG THE PLATFORM OUTER PERIMETER.

THIS DATA SHEET SHALL BE READ IN CONJUCTION WITH SPECIFICATION FOR SAFETY & LIFE SAVING EQUIPMENT FOR CP6S AND CP7S COMPLEXES [REF. 6].

SPECIFICATION FOR SAFETY & LIFE SAVING EQUIPMENT FOR CP6S AND CP7S COMPLEXES [REF. 6] SHALL BE THE GOVERNING GUIDELINE IN CASE OF DISCREPANCY WITH DATA SHEETS.

ENVIRONMENTAL CONDITIONS SHALL BE AS PER PROJECT DESIGN SPECIFICATION [REF.2].

ALL MATERIALS SHALL BE SUITABLE FOR OUTDOOR OFFSHORE CONDITIONS.

COMPLIANCE CERTIFICATES, THIRD PARTY VERIFICATION CERTIFICATES, TESTS AND TEST CERTIFICATES SHOULD BE PROVIDED BY THE VENDOR.

THIS DATA SHEET SHALL BE UPDATED BY VENDOR WITH VENDOR/ MANUFACTURER’S DATA POST PURCHASING.

1

2

3

H

1

2

I

1

2

J

1

2

K

1

2

3

4

5

6

7

8

9

Company No._Rev. 560-20-SH-DTS-00009_00

12 of 12

Project: Q-21699 - Saipem COMP2 Folder: PDF


Loading authentication...

Graph View

Backlinks

  • 00 Index

Created with Infinity Constructor © 2025

  • Elynox | Go Further