NFPS Offshore Compression Complexes Project COMP2

COMPANY Contract No.: LTC/C/NFP/5128/20

CONTRACTOR Project No.: 033734

Document Title

:

DATA SHEET FOR LIFE JACKETS WITH CABINET FOR CP6S COMPLEX

COMPANY Document No.

: 560-20-SH-DTS-00012

Saipem Document No.

: 033734-B-D-30-SPM-LP-B-10013

Discipline

: HSE&Q

Document Type

: DATA SHEET

Document Category/Class

: 2

Document Classification

: INTERNAL

00

20-Dec-2023

26-Sep-2023

B

A

Approved for Construction Issued for Approval

Azran Shariman

Rama Krishna K

Luminita Oprescu

Maria Fransisca

Rama Krishna K

Luminita Oprescu Vijayakumar Rajaram

09-Aug-2023

Issued for Review

Maria Fransisca

Rama Krishna K

REV.

DATE

DESCRIPTION OF REVISION

PREPARED BY

CHECKED BY

APPROVED BY

Saipem S.p.A.

THIS DOCUMENT IS PROPERTY OF QATARGAS. THIS DRAWING OR MATERIAL DESCRIBED THEREON MAY NOT BE COPIED OR DISCLOSED IN ANY FORM OR MEDIUM TO THIRD PARTIES, OR USED FOR OTHER THAN THE PURPOSE FOR WHICH IT HAS BEEN PROVIDED, IN WHOLE OR IN PART IN ANY MANNER EXCEPT AS EXPRESSLY PERMITTED BY QATARGAS.

Company No._Rev. 560-20-SH-DTS-00012_00

1 of 13

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFE JACKETS WITH CABINET FOR CP6S COMPLEX

REVISION HISTORY

Revision

Date of Revision

Revision Description

A1

A

B

00

20-Jul-2023

Issued for Inter-Discipline Check

09-Aug-2023

26-Sep-2023

20-Dec-2023

Issued for Review

Issued for Approval

Approved for Construction

HOLDS LIST

Hold No

Hold Description

Company No._Rev. 560-20-SH-DTS-00012_00

2 of 13

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFE JACKETS WITH CABINET FOR CP6S COMPLEX

TABLE OF CONTENTS

1

2

3

4

5

INTRODUCTION … 4

1.1 PROJECT OBJECTIVE … 4 1.2 PROJECT SCOPE … 4

DEFINITIONS AND ABBREVIATIONS … 6

2.1 DEFINITIONS … 6 2.2 ABBREVIATIONS … 7

REGULATIONS, CODES AND STANDARDS … 9

3.1 COMPANY DOCUMENTS … 9 3.2 PROJECT DOCUMENTS … 9 INTERNATIONAL CODES AND STANDARDS … 10 3.3

PURPOSE … 11

DATA SHEET … 12

Company No._Rev. 560-20-SH-DTS-00012_00

3 of 13

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFE JACKETS WITH CABINET FOR CP6S COMPLEX

1

INTRODUCTION

The North Field is the world’s largest natural gas field and accounts for nearly all of the state of Qatar’s gas production. The reservoir pressure in the North Field has been declining due to continuous production since the early 1990s. The principal objective of the NFPS Project is to sustain the plateau from existing QG South Operation (RL Dry Gas, RGE Wet gas) and existing QG North Operation (QG1 & QG2) production areas by implementing an integrated and optimum investment program consisting of subsurface development, pressure drop reduction steps and compression. Refer to the figure below for a schematic of the North Field.

Qatargas Operating Company Limited is leading the development of the North Field Production Sustainability (NFPS) Project.

1.1 Project Objective

The objective of this Project includes:

• Sustain the Qatargas North Field Production Plateau by installing new Compression Complex facilities CP6S & CP7S in QG south with integration to the existing facilities under Investment #3 program.

• Facility development shall be safe, high quality, reliable, maintainable, accessible, operable,

and efficient throughout their required life.

• Achieve standards of global excellence in Safety, Health, Environment, Security and Quality

performance.

1.2 Project Scope

The Project Scope includes detailed engineering, procurement, construction, transportation & installation, hook-up and commissioning, tie-in to EXISTING PROPERTY and provide support for start- up activities of the following facilities and provisions for future development. The WORK shall be following the specified regulations, codes, specifications and standards, achieves the specified performance, and is safe and fit

purpose in all respects.

for

Offshore

‐

‐

CP6S and CP7S Compression Complexes that are part of QG-S RGE facilities as follows:

• CP6S Compression Complex

• Compression Platform CP6S, Living Quarters LQ6S, Flare FL6S

• Bridges BR6S-2, BR6S-3, BR6S-4, BR6S-5

• Bridge linked Tie-in to RP6S

Production from existing wellheads (WHP6S & WHP10S) and new wellhead (WHP14S) are routed via riser platform RP6S to compression platform CP6S to boost pressure and export to onshore via two export lines through the existing WHP6S pipeline and a new 38” carbon steel looping trunkline from RP6S (installed by EPCOL). CP6S is bridge-linked to RP6S.

• CP7S Compression Complex

• Compression Platform CP7S, Living Quarters LQ7S, Flare FL7S

• Bridges BR7S-2, BR7S-3, BR7S-4, BR7S-5

• Bridge linked Tie-in to RP7S

Company No._Rev. 560-20-SH-DTS-00012_00

4 of 13

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFE JACKETS WITH CABINET FOR CP6S COMPLEX

CP7S shall receive production from existing wellheads (WHP5S & WHP7S) and new wellhead (WHP13S). There is only one export line for CP7S through the existing export pipeline from WHP7S. CP7S is bridge-linked to RP7S.

RGA Complex Destressing

Migration of the Electrical power source, Telecoms, Instrumentation and Control systems from WHPs and RPs hosted by RGA to the respective Compression Complexes listed below:

• WHP6S, WHP10S, WHP14S, RP6S and RP10S to CP6S Compression Complex

• WHP5S, WHP7S, WHP13S and RP7S to CP7S Compression Complex

Destressing of Telecoms, Instrumentation and Control system in RGA Complex Control Room, which would include decommissioning and removal of telecom system devices and equipment that would no longer be required post migration and destressing activity.

Onshore

An Onshore Collaborative Center (OCC) will be built under EPC-9, which will enable onshore based engineering teams to conduct full engineering surveillance of all the offshore facilities. The OCC Building will be located in Ras Laffan Industrial City (RLIC) within the Qatar Gas South Plot. MICC & Telecommunication, ELICS related scope will be performed in the OCC building.

Figure 1.2.1: NFPS Compression Project COMP2 Scope

Company No._Rev. 560-20-SH-DTS-00012_00

5 of 13

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFE JACKETS WITH CABINET FOR CP6S COMPLEX

2 DEFINITIONS AND ABBREVIATIONS

2.1 Definitions

Definition

Description

COMPANY

Qatargas Operating Company Limited.

CONTRACTOR

Saipem S.p.A.

DELIVERABLES

FACILITIES

All products (drawings, equipment, services) which must be submitted by CONTRACTOR to COMPANY at times specified in the contract. All machinery, apparatus, materials, articles, components, systems and items of all kinds to be designed, engineered, procured, manufactured, constructed, supplied, tested and permanently installed by CONTRACTOR at SITE in connection with the NFPS Project as further described in Exhibit 6.

fabricated,

MILESTONE

A reference event splitting a PROJECT activity for progress measurement purpose.

PROJECT

NFPS Offshore Compression Complexes Project COMP2

SITE

(i) any area where Engineering, Procurement, Fabrication of the FACILITIES related to the CP6S and CP7S Compression Complexes are being carried out and (ii) the area offshore required for installation of the FACILITIES in the State of Qatar.

SUBCONTRACT

Contract signed by SUBCONTRACTOR and CONTRACTOR for the performance of a certain portion of the WORK within the Project.

SUBCONTRACTOR

Any organization selected and awarded by CONTRACTOR to supply a certain Project materials or equipment or whom a part of the WORK has been Subcontracted.

WORK

Scope of Work defined in the CONTRACT.

WORK PACKAGE

The lowest manageable and convenient level in each WBS subdivision.

VENDOR

The person, group, or organization responsible for the design, manufacture, testing, and load-out/shipping of the Equipment/ Material.

Company No._Rev. 560-20-SH-DTS-00012_00

6 of 13

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFE JACKETS WITH CABINET FOR CP6S COMPLEX

2.2 Abbreviations

Code

Definition

BR

CFR

CP

EEBD

ELICS

EPC

EPCOL

FEED

FL

GRP

HFE

IMO

IP

LQ

LSA

MED

NFPS

OCC

QG

RGA

RGE

RL

RLIC

Bridge

Code of Federal Regulations

Compression Platform

Emergency Escape Breathing Device

Electrical Integrated Control System

Engineering, Procurement and Construction

Offshore and Pipelines Project

Front End Engineering Design

Flare Platform

Glass Reinforced Plastic

Human Factors Engineering

International Maritime Organization

Ingress Protection

Living Quarter Platform

Life Saving Appliances

Marine Equipment Directive

North Field Production Sustainability

Onshore Collaborative Center

Qatargas Operating Company Limited

Ras Gas Alfa

Ras Gas Expansion

Ras Laffan

Ras Laffan Industrial City

Company No._Rev. 560-20-SH-DTS-00012_00

7 of 13

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFE JACKETS WITH CABINET FOR CP6S COMPLEX

Code

Definition

RP

SOLAS

UV

WBS

WHP

Riser Platform

Safety of Life at Sea

Ultraviolet

Work Breakdown Structure

Wellhead Platform

Company No._Rev. 560-20-SH-DTS-00012_00

8 of 13

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFE JACKETS WITH CABINET FOR CP6S COMPLEX

3 REGULATIONS, CODES AND STANDARDS

In general, all design activities shall confirm to legal and statutory regulations and recognized industry best practices. Conflict among applicable specification and / or codes shall be brought to the attention of the COMPANY for resolution COMPANY decision shall be final and shall be implemented. The latest editions of codes and specification effective as on date of contract shall be followed.

In general, the order of precedence shall be followed:

a) Qatari Governmental and Regulatory Requirements

b) COMPANY Procedures, Policies and Standards (Exhibit 5 Appendix I)

c) Project Specifications.

d) Industry Codes and Standards

e) COMPANY and CONTRACTOR’s Lessons Learned

If CONTRACTOR/SUBCONTRACTOR deems any deviations from the specifications will result in significant project cost and schedule saving, proposal to such deviations shall be submitted to COMPANY for review and approval. CONTRACTOR/SUBCONTRACTOR shall not proceed with any deviation to the specifications without prior COMPANY approval.

The following is a list of relevant regulations, codes, standards, specification, Company documents that shall be considered for the Project in the order of precedence listed above.

3.1 Company Documents

S. No

Document Number

Title

PRT-PRS-PRC-014

Offshore Loss Prevention Philosophy

COMP-QG-PR-REP- 00008

North Field Production Sustainability Compression Project: EPC-2 – Basis of Design EPC2

(NFPS), NFPS

PRT-ENV-PRC-013

Environmental Aspects and Impacts Procedure

3.2 Project Documents

S. No

Document Number

Title

200-20-SH-DEC-00005

200-20-SH-DEC-00008

200-20-SH-SPC-00006

200-20-ME-DEC-00003

200-20-PI-SPC-00015

200-20-SH-SPC-00011

200-20-CE-DEC-00003

Technical Safety and Loss Prevention Design Philosophy for CP6S and CP7S Complexes Escape, Evacuation & Rescue Design Philosophy for CP6S and CP7S Complexes Specification for Safety & Life Saving Equipment for CP6S and CP7S Complexes Material Handling Philosophy Complexes Piping Material Specification Complexes HFE Workplace Design Specification for CP6S and CP7S Complexes Material Selection Philosophy Complexes

for CP6S and CP7S

for CP6S and CP7S

for CP6S and CP7S

Company No._Rev. 560-20-SH-DTS-00012_00

9 of 13

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFE JACKETS WITH CABINET FOR CP6S COMPLEX

S. No

Document Number

Title

200-20-CE-SPC-00015

Painting Specification for CP6S and CP7S Complexes

200-21-ST-DEC-00001

560-20-SH-PLN-00008

560-20-SH-PLN-00007

560-20-SH-PLN-00009

562-83-SH-PLN-00001

562-83-SH-PLN-00002

562-83-SH-PLN-00003

562-20-SH-PLN-00002

562-20-SH-PLN-00001

Greenfield Structural Design Basis for Substructure of CP6S and CP7S Complexes Escape Route, Life Saving and Fire Fighting Equipment Layout – PSV Service Platform for Compression Platform CP6S Escape Route, Life Saving and Fire Fighting Equipment Layout – Production Deck for Compression Platform CP6S Escape Route, Life Saving and Fire Fighting Equipment Layout – Sump Deck for Compression Platform CP6S Escape Route, Life Saving and Fire Fighting Equipment Layout – Level 1 for LQ6S Escape Route, Life Saving and Fire Fighting Equipment Layout – Level 2 for LQ6S Escape Route, Life Saving and Fire Fighting Equipment Layout – Level 3 for LQ6S Escape Route, Life Saving and Fire Fighting Equipment Layout – Roof Deck for LQ6S Escape Route, Life Saving and Fire Fighting Equipment Layout – Cellar Deck for LQ6S

560-20-SH-DTS-00010

Data Sheet for Common Safety Cabinet for CP6S Complex

560-20-SH-LIS-00001

Safety Equipment List for CP6S Complex

3.3

International Codes and Standards

S. No

Document Number

Title

IMO IE110E

International Convention for the Safety of Life at Sea (SOLAS)

IMO ID982E

Life Saving Appliances (LSA) Code

OSHA 1910

Occupational Safety and Health Standard

46 CFR Part 161 Subpart 161.012 46 CFR Part 164 Subpart 164.018

Code of Federal Regulations - Personal Flotation Device Lights Code of Federal Regulations - Retroreflective Material for Lifesaving Equipment

Company No._Rev. 560-20-SH-DTS-00012_00

10 of 13

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFE JACKETS WITH CABINET FOR CP6S COMPLEX

4 PURPOSE

The purpose of this data sheet is to cover the technical requirements for the Life Jackets with Cabinet for CP6S Complex in the NFPS Offshore Compression Complexes Project, COMP2. This data sheet shall be read in conjunction with Specification for Safety & Life Saving Equipment for CP6S And CP7S Complexes [Ref. 6]. VENDOR’s scope of supply shall include, but not be limited to, the requirements listed in this data sheet and referred specifications.

Company No._Rev. 560-20-SH-DTS-00012_00

11 of 13

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFE JACKETS WITH CABINET FOR CP6S COMPLEX

5 DATA SHEET

LIFE JACKETS & CABINET

A

1

B

1

2

DATA SHEET IDENTIFICATIONS

DOCUMENT NO

560-20-SH-DTS-00012

ADMINISTRATIVE IDENTIFICATIONS

PROJECT NUMBER

033734

PROJECT

NFPS OFFSHORE COMPRESSION COMPLEXES PROJECT COMP2

TOTAL LIFE JACKETS AT CP6S: 148 (INSIDE CABINET AS BELOW) + 2 (AT CRANE CABINS) LIFE JACKET CABINETS CP:

• 4 NOS OF CABINETS FOR 25 LIFE JACKETS • 2 NOS OF CABINETS FOR 24 LIFE JACKETS • CABINETS INSIDE CRANE CABIN (REFER TO DATA SHEET FOR COMMON SAFETY CABINET [REF. 21])

3

QUANTITY & LOCATION

TOTAL LIFE JACKETS AT LQ6S: 176 (INSIDE CABINET AS BELOW) +105 (ONE FOR EACH BED CABIN) + 1 (AT CRANE CABIN) LIFE JACKET CABINETS LQ:

• 2 NOS OF CABINETS FOR 55 LIFE JACKETS • 2 NOS OF CABINETS FOR 25 LIFE JACKETS • 1 NO OF CABINET FOR 16 LIFE JACKETS • CABINET INSIDE CRANE CABIN (REFER TO DATA SHEET FOR COMMON SAFETY CABINET [REF. 21]) • CABINET INSIDE BED SPACE (REFER TO DATA SHEET FOR COMMON SAFETY CABINET [REF. 21])

C

EQUIPMENT IDENTIFICATION

AT CP6S: LIFE JACKET CABINETS CP:

• 4 NOS OF CABINETS FOR 25 LIFE JACKETS: 560-XZ2051 ~ 560-XZ2054 • 2 NOS OF CABINETS FOR 24 LIFE JACKETS: 560-XZ2055, 560-XZ2026 • CABINETS INSIDE CRANE CABIN (REFER TO DATA SHEET FOR COMMON SAFETY CABINET [REF. 21]

1

TAG NUMBER

AT LQ6S: LIFE JACKET CABINETS LQ:

• 2 NOS OF CABINETS FOR 55 LIFE JACKETS: 562-XZ2031, 562-XZ2032 • 2 NOS OF CABINETS FOR 25 LIFE JACKETS: 562-XZ2034, 562-XZ2035 • 1 NO OF CABINET FOR 16 LIFE JACKETS: 562-XZ2033 • CABINET INSIDE CRANE CABIN (REFER TO DATA SHEET FOR COMMON SAFETY CABINET [REF. 21]) • CABINET INSIDE BED SPACE (REFER TO DATA SHEET FOR COMMON SAFETY CABINET [REF. 21])

2

SERVICE

LIFE SAVING

OPERATION DATA

ENVIRONMENTAL / SITE CONDITIONS (NOTE 3 & 4)

D

1

2

3

E

1

ENVIRONMENTAL / SITE CONDITIONS

MINIMUM

NORMAL

MAXIMUM

BLACK BULB

UNITS

AMBIENT TEMPERATURE

RELATIVE HUMIDITY DAILY AVERAGE

8.3

37.0

45.6

100.0

84

°C

%

ATMOSPHERE

HUMID, SALIFEROUS, SALT LADEN, AND MARINE ATMOSPHERE, POSSIBLE H2S PRESENCE

TECHNICAL SPECIFICATION

EQUIPMENT DESIGN CRITERIA

LIFEJACKET CRITERIA:

1.1

SOLAS/MED LIFE JACKETS.

REQUIRED

1.2

TYPE-I LIFE JACKET (ADULT SIZE).

REQUIRED

1.8

1.9

HIGH BUOYANCY (190N BOUYANCY), INHERENTLY BOUYANT AND SELF- RIGHTING TYPE.

REQUIRED

NOT SUSTAIN BURNING AFTER BEING ENVELOPED IN A FIRE FOR A PERIOD OF 2 SECONDS.

REQUIRED

1.3

UNICELLULAR, WITH PLASTIC PANEL AND SYNTHETIC FOAM FILLED.

REQUIRED

1.10

SPLASH GUARD

REQUIRED

1.4

1.5

1.6

REVERSIBLE AND MADE OF HEAVY- DUTY MARINE GRADE FABRIC, POLYPROPYLENE OR NYLON WEBBING AND MARINE HARDWARE.

REQUIRED

1.11

DESIGNED TO TURN AN UNCONSCIOUS PERSON FROM FACE DOWN IN THE WATER TO A VERTICAL OR SLIGHTLY BACKWARD (FACE-UP) POSITION

REQUIRED

HAVE AT LEAST 0.02 M2 OF RETRO- REFLECTIVE MATERIAL ATTACHED TO EACH FRONT SIDE, BACK SIDE, AND REVERSIBLE SIDES.

REQUIRED

1.12

SEWN WITH MILDEW RESISTANT, ROT RESISTANT THREAD.

REQUIRED

THE MATERIAL ATTACHED ON EACH SIDE OF THE JACKET MUST BE DIVIDED EQUALLY BETWEEN THE UPPER QUADRANTS OF THE SIDE, AND THE MATERIAL IN EACH QUADRANT MUST BE ATTACHED AS CLOSELY AS POSSIBLE TO THE SHOULDER AREA OF THE JACKET.

REQUIRED

1.13

FACILITY/ PLATFORM IDENTIFICATION MARKING

REQUIRED

1.7

COLOUR

INTERNATIONAL ORANGE

Company No._Rev. 560-20-SH-DTS-00012_00

12 of 13

1.2

1.3

1.4

2

2.1

2.2

2.3

G

1

4

5

6

7

NFPS Offshore Compression Complexes Project COMP2 DATA SHEET FOR LIFE JACKETS WITH CABINET FOR CP6S COMPLEX

F

1

EQUIPMENT ACCESSORIES

EACH LIFE JACKET SHALL HAVE THE FOLLOWING ACCESSORIES:

LIFE JACKETS & CABINET

1.1 WHISTLE AND LANYARD

REQUIRED

1.5

BATTERY FOR LIGHTS

REQUIRED

SEAWATER ACTIVATED ILLUMINATING LIGHT

REQUIRED

1.6

LIFTING STRAPS

REQUIRED

BODY STRAP (SHALL BE FULLY ADJUSTABLE WITH BUCKLE)

REQUIRED

1.7

SUITABLE FOR FASTENING WITH EEBD

REQUIRED

REFLECTIVE STRIPS (RETRO REFLECTIVE TAPE)

REQUIRED

1.8

STAINLESS STEEL FOR SNAP HOOK AND D-RING

REQUIRED

LIFEJACKET LIGHT CRITERIA:

HAVE A LUMINOUS INTENSITY OF NOT LESS THAN 0.75 CD IN ALL DIRECTIONS OF THE UPPER HEMISPHERE.

REQUIRED

2.4 WHITE COLOUR.

REQUIRED

HAVE A SOURCE OF ENERGY CAPABLE OF PROVIDING A LUMINOUS INTENSITY OF 0.75 CD FOR A PERIOD OF AT LEAST 8 HOURS

REQUIRED

VISIBLE OVER AS GREAT A SEGMENT OF THE UPPER HEMISPHERE AS IS PRACTICABLE WHEN ATTACHED TO A LIFEJACKET.

REQUIRED

2.5

HAZARDOUS AREA CLASSIFICATION REQUIREMENT: ZONE 1, GAS GROUP IIB, TEMPERATURE CLASS T3.

REQUIRED

CABINET DESIGN CRITERIA

SIZED FOR

2

CABINET TYPE

3

MOUNTING / INSTALLATION (NOTE 8)

CABINET MATERIAL

VARIOUS QUANTITY AS SPECIFIED IN SECTION B.3

SIDE OPEN DOOR / EASY REACHING TYPE

8

9

COUNTRY OF ORIGIN

VENDOR TO ADVISE

FITTINGS MATERIAL (HINGES, HANDLES, LATCHES, BOLTS, ETC.)

STAINLESS STEEL SS316

FREE STANDING, WITH PROVISION OF ADEQUATE BOTTOM AND BACK FRAMES TO PERMIT DECK OR BULKHEAD MOUNTING (VENDOR TO PROVIDE MOUNTING ACCESSORIES)

UV RESISTANT GRP AND FIRE RETARDANT.

10

DONNING INSTUCTIONS

LABELLING (NOTE 1)

11

12

IN ENGLISH, CONTAINED IN A WEATHER- PROOF COVER AND PERMANENTLY ATTACHED TO THE INSIDE OF CABINET LID/DOOR AT HEIGHT WHERE READABLE BY PERSON STANDING IN FRONT

“LIFE JACKETS” IN ENGLISH AND CABINET TAG NUMBER

IP RATING

IP56

MANUFACTURE NAME

VENDOR TO ADVISE

CABINET PAINT FINISH

INTERNATIONAL ORANGE

13

MODEL

VENDOR TO ADVISE

VENTILATION / DRAINAGE

REQUIRED

H

SPECIAL REQUIREMENTS

COMPLIANCE STANDARD

SOLAS / USCG

INTERNATIONAL LIFE SAVING APPLIANCES CODE

CERTIFICATION

MED / SOLAS / USCG

ENVIRONMENTAL REQUIREMENT

ALL MATERIALS SHALL BE SUITABLE FOR OFFSHORE SALINE CONDITION

PHYSICAL DATA

WEIGHT OF FILLED CABINET

VENDOR TO ADVISE

3

DIMENSION OF CABINET

VENDOR TO ADVISE

WEIGHT OF EMPTY CABINET

VENDOR TO ADVISE

EQUIPMENT IDENTIFICATIONS

EQUIPMENT TYPE

VENDOR TO ADVISE

MANUFACTURER NAME

VENDOR TO ADVISE

3

4

MODEL NUMBER

VENDOR TO ADVISE

MANUFACTURER COUNTRY

VENDOR TO ADVISE

1

2

3

I

1

2

J

1

2

K

NOTES

1

2

3

4

5

6

7

8

9

THE DESIGNATED CABINET SHALL BE LABELLED “LIFE JACKETS” IN ENGLISH AND PLATFORM NAME IN BOLD BLACK LETTERS AND CABINET TAG NUMBER. TYPE AND SIZE AND PRINTING ON THE LIFEJACKET CABINET SHALL FULFIL THE REQUIREMENT OF LSA/SOLAS.

FOR LIFE JACKETS WITH CABINET SHALL BE PROVIDED AT CORRESPONDING AREA. REFER ESCAPE ROUTE, LIFE SAVING AND FIRE FIGHTING EQUIPMENT LAYOUTS.

THIS DATASHEET SHALL BE READ IN CONJUCTION WITH SPECIFICATION FOR SAFETY & LIFE SAVING EQUIPMENT FOR CP6S AND CP7S COMPLEXES [REF. 6].

SPECIFICATION FOR SAFETY & LIFE SAVING EQUIPMENT FOR CP6S AND CP7S COMPLEXES [REF. 6] SHALL BE THE GOVERNING GUIDELINE IN CASE OF DISCREPANCY WITH DATA SHEETS

ENVIRONMENTAL CONDITIONS SHALL BE AS PER PROJECT DESIGN SPECIFICATION [REF.2 ]

ALL MATERIALS SHALL BE SUITABLE FOR OUTDOOR OFFSHORE CONDITIONS.

COMPLIANCE CERTIFICATES, THIRD PARTY VERIFICATION CERTIFICATES, TESTS AND TEST CERTIFICATES SHOULD BE PROVIDED BY THE VENDOR.

VENDOR SHALL PROVIDE THE FIXING ASSESSORIES FOR MOUNTING CABINET TO PLATFORM DECK.

THIS DATASHEET SHALL BE UPDATED BY VENDOR WITH VENDOR/ MANUFACTURER’S DATA POST PURCHASING.

Company No._Rev. 560-20-SH-DTS-00012_00

13 of 13

Project: Q-21699 - Saipem COMP2 Folder: PDF


Loading authentication...

Graph View

Backlinks

  • 00 Index

Created with Infinity Constructor © 2025

  • Elynox | Go Further