RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

10651-00-QAC-PD-0003

PAGE 1 OF 162

REV.: 01

QUALITY REQUIREMENTS FOR SUBCONTRATORS

REVISION CONTROL PAGE

REV. DATE

ISSUE CODE DESCRIPTION

PARAGRAPH

00

01

11-27-23

12-22-23

IFI

IFI

Issue For Information

Issue for Information

4.2.2

PREPARED

REVIEWED

APPROVED

CHECKED

J. García

Construction QC Leader

A. Ferrer

Deputy Quality Manager

H. Sahabi

J. L. Holgado

Project Director

Quality Manager

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

10651-00-QAC-PD-0003

PAGE 2 OF 162

REV.: 01

INDEX

  1. PURPOSE AND SCOPE … 6

  2. DEFINITIONS … 7

  3. REFERENCES … 13

COMPANY DOCUMENTS … 13 PROJECT DOCUMENTS … 15 INTERNATIONAL STANDARDS … 16

  1. DEVELOPMENT … 16

QUALITY REQUIREMENTS … 16 General … 16 Quality Management System (QMS) … 18 Software Requirements … 18 Documentation Requirements … 19 Internal Audits … 24 QA/QC Training … 27 QA/QC Weekly Meeting … 27 Monitoring and Measurement - Quality indicators … 28 Preparation of Quality Record Books … 30 QA/QC PERSONNEL AND RESOURCES … 31 General … 31 QA/QC Resources Management … 32 Organization … 49 Personnel Mobilization and Demobilization … 50 CONTROL OF CONSTRUCTION ACTIVITIES … 51 Kick-Off Meeting … 51 Inspection and Test Plans. SAUDI ARAMCO Inspection and Test Plans (SATIPs) and Inspection Procedures. … 51 Management of Non-Conformances… 57 QUALITY VERIFICATION OF CONSTRUCTION ACTIVITIES … 59 Initial verification … 59 In-process verification … 59 Final verification … 60 THIRD PARTY INSPECTION (TPI) Verification … 61 Verification by CONTRACTOR … 61 QA/QC COORDINATION … 61 QA/QC Two-Week Look Ahead Schedule … 61 Request for Inspection (RFI) … 61 Inspection and test status … 65 CONTROL OF CONSTRUCTION PROCESSES … 65 Field Engineering Control of Design Changes … 65

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

10651-00-QAC-PD-0003

PAGE 3 OF 162

REV.: 01

Special processes … 65 Identification and traceability … 67 Storage and handling of CONTRACTOR supplied material and equipment … 67 Control of monitoring and measuring devices … 68 ON SITE CIVIL MINIMUM REQUIREMENTS … 70 Material Certificates … 70 Excavation and Backfilling … 71 Concrete Work and Formwork … 72 Concrete … 74 STEEL STRUCTURE FABRICATION MINIMUM REQUIREMENTS … 82 Materials Certificates … 82 Steel Structure Fabrication … 82 Welding Consumables … 83 Welder Qualification … 84 Welding Procedures … 84 Welding Operations … 85 Post Weld Heat Treatment … 86 Inspection Access … 86 Non-Destructive Testing … 86 Repairs … 89 Steel Structure Storage … 89 Calibration … 90 Structural Bolts … 90 Reception at Site … 90 Steel Structure Erection … 90 Field Corrections … 91 Site Inspection and Testing … 91 ON SITE PIPING FABRICATION & WELDING MINIMUM REQUIREMENTS … 92 Piping Material … 92 Piping fabrication … 93 Welding Consumables … 95 Welder Qualification … 97 Welding Procedures … 99 Welding Operations … 100 Post Weld Heat Treatment … 105 PRODUCTION WELD HARDNESS TESTING … 106 Inspection Access … 107 Non-Destructive Testing … 107 VISUAL EXAMINATION … 112

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

10651-00-QAC-PD-0003

PAGE 4 OF 162

REV.: 01

RADIOGRAPHY … 112 MAGNETIC PARTICLE … 113 LIQUID PENETRANT … 114 ULTRASONIC … 114 POSITIVE MATERIAL IDENTIFICATION … 114 NDT COVERAGE … 114 VISUAL EXAMINATION … 115 RADIOGRAPHY … 115 MAGNETIC PARTICLE TESTING AND LIQUID PENETRANT TESTING. 115 ULTRASONIC TESTING … 116 POSITIVE MATERIAL IDENTIFICATION (PMI) … 116 REPAIRS … 116 PIPING HANDLING, STORAGE AND ERECTION … 117 CALIBRATION … 118 PRESSURE TESTING … 118 Protection from Overpressure … 120 Testing … 122 Tie-ins / Hot Taps … 125 On Stream Inspection Study … 126 FLANGE MANAGEMENT … 127 Flange Management System. … 127 Material Certificates … 128 Flange Management Team organization … 129 Flange Management Data Base … 130 Tools and Machinery- Bolt Tightening. … 130 Preservation … 131 PAINTING/COATING MINIMUN REQUIREMENTS … 132 Internal and external coating minimum requirements … 132 Abrasive materials … 132 Requirements before abrasive blasting … 133 Requirements after abrasive blasting … 134 Coating application … 135 Defect repair … 138 Installation externally FBE, 3LPE and 3LPP coated line pipe and piping general requirements … 139 Coating equipment … 139 Coating/Blasting personnel qualifications … 140 Coating materials … 140 Approved Protected Coating Systems … 141 Colours and Identification for Piping and Equipment … 141 INSULATION … 141

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

10651-00-QAC-PD-0003

PAGE 5 OF 162

REV.: 01

General requirements … 141 Insulation materials … 142 Personnel protection insulation … 143 Insulation accessories … 143 Insulation installers qualification … 144 ON SITE E&I MINIMUM REQUIREMENTS … 144 Instrumentation Requirements … 144 Electrical Requirements … 144 TEST PACKAGE … 145 Piping Test Package … 146 Pipeline Test Package … 147 Piping Tie-Ins Test Package … 149 Static Equipment Box-Up / Final Inspection Package … 150 Rotary Final Inspection Package … 151 Skid / Miscellaneous Final Inspection Package … 152 API / Field Tank Box-Up Package … 153 Motor Test Package … 154 Loop Test Package … 155 Relief Valve Test Package … 156 Test Package – Document Control … 156 QUALITY PENALTIES … 159

  1. ATTACHMENTS AND TEMPLATES … 160

10651-00-QAC-PD-0003-TMP01- INSPECTION AND TEST PLAN FORM … 161 10651-00-QAC-PD-0003-TMP02- REQUEST FOR INSPECTION FORM … 162

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

10651-00-QAC-PD-0003

PAGE 6 OF 162

REV.: 01

PURPOSE AND SCOPE

The object of this document is to describe CONTRACTOR´s minimum quality requirements

for SUBCONTRACTOR´s Quality System, which shall be implemented and fulfilled during

fabrication, construction, pre-commissioning activities and services by the scope of work

defined in the Subcontract of RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2.

Compliance with the requirements stated in this procedure does not exclude the

SUBCONTRACTOR’s compliance with the COMPANY Standards applicable to the WORK,

and with the rest of the requirements contained in the Subcontract or in some of its annexes

or attachments.

If a conflict arises between or within any of:

•

this procedure, or any CONTRACTOR Procedures or Plans;

• COMPANY Standards applicable to the WORK;

•

the Subcontract, or in some of its annexes or attachments,

The SUBCONTRACTOR shall promptly notify and

request

the CONTRACTOR

Representative in writing for resolution within thirty (30) days from the Subcontract effective

date.

In respect of any conflict discovered and notified by SUBCONTRACTOR more than thirty

(30) days after the Subcontract effective date, the CONTRACTOR Representative shall be

entitled to issue an instruction to SUBCONTRACTOR to implement a resolution to the

conflict. SUBCONTRACTOR shall comply with all instructions given by the CONTRACTOR

Representative without by reason of such instruction, becoming entitled to any extension of

time, any Change, any additional payment or any other relief.

The SUBCONTRACTOR will compile all conflicts sent in a log, each conflict will have a

unique number, and the log must reflect the individual conflict status (Unique number,

description, date sent, replied, status, comments…etc.) and also the general conflict status

as % and number clarified against % and number pending to clarify. The log form has to be

prepared by SUBCONTRACTOR and send in advance for approval to the CONTRACTOR

before to start or use it.

This Q.R.F.S. document neither abrogates nor modifies the contractual agreements between

the parties but provides the mechanism for carrying out the normal working relationship

between the parties during the Project execution.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

10651-00-QAC-PD-0003

PAGE 7 OF 162

REV.: 01

The guidelines contained in this document apply to all parties involved in the project.

DEFINITIONS

COMPANY:

Aramco Overseas Company B.V. (OOK)

Saudi Arabian Oil Company (Saudi Aramco) (IK)

UTE Jafurah (OOK)

CONTRACTOR:

Consortium of Técnicas Reunidas Saudia for Services and

Contracting Co Ltd. and SINOPEC Engineering (Group) Co.,

Ltd. Saudia (IK)

PROJECT:

Riyas NGL Fractionation Facilities PKG. 1 (NGL Fractionation

Trains ) & PKG. 2 (NGL Utilities, Storage & Export Facilities).

SUBCONTRACTOR:

firm, partnership, company, corporation or Any person, combination thereof with whom CONTRACTOR has sent the REQUEST FOR QUOTATION or signed the SUBCONTRACT.

Approval (A):

An activity that requires a document subject to be approved by the

CONTRACTOR and/or Client and/or Third party. No formal

inspection notification is required.

Backlog:

An accumulation of uncompleted work or matters needing to be

dealt with.

Calibration:

Comparison of a measurement and test equipment with a reference

standard or with another one provided with better tolerance in order

to detect or to measure possible inaccuracies and to document or

eliminate them.

Facilities:

Means the structure or items being designed, procured or fabricated

by SUBCONTRACTOR pursuant to the Subcontract.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

10651-00-QAC-PD-0003

PAGE 8 OF 162

REV.: 01

Hold Point (H):

An inspection activity that requires the CONTRACTOR and/or

COMPANY and/or Third party be notified by the Manufacturer/

Vendor/ SUBCONTRACTOR of a specific time and place for the

activity to be attended. This notification shall be carried out by a

Formal information process and the activity shall not be developed

without the CONTRACTOR and/or COMPANY and/or Third party

presence and written approval or a signed waiver.

Inspection:

Determination of conformity to specified requirements, such as

Inspection and

Test Plan (ITP):

measuring, examining,

testing or gauging one or more

characteristics of an entity and comparing the results with specified

requirements in order to establish whether conformity is achieved

for each characteristic.

Document that defines a list of chronological Inspections and

Test that shall be carried out before, during and after the execution

of Work in

the Construction phase and occasionally

in

the

Precommissioning phase. In this document are also mentioned the

Control Forms required to verify the inspections and Tests.

Inspection

A set of documents

that

include details of purchased

Assignment Package

material/equipment and their quality requirements needed to

(IAP):

perform full inspection at the vendor/sub-vendor facility.

Inspection Waiver:

Written confirmation if the CONTRACTOR elects not to visit the

SUBCONTRACTOR to perform an inspection activity.

IWE:

KPI:

International Welding Engineer

Key Performance Indicator

Loader:

Templates with specific data and format those are imported to the

different corporate tools. These Loaders must be delivered by

SUBCONTRACTOR to CONTRACTOR.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

10651-00-QAC-PD-0003

PAGE 9 OF 162

REV.: 01

Log:

Control Forms which list different documents, certificates, accreditations needed to ensure the required traceability during applicable works. Applicable documents, certificates and /or accreditations will be available and checked by CONTRACTOR before the activities commencement.

Lot/Batch:

A lot of piping (or designated lot of piping) is the quantity of piping

to be considered in applying the requirements for examination in the

Code.

May

It expresses a possibility

Monitoring:

The observation, verification and recording of specific design,

procurement, construction and inspection activities while in process

to ensure that work is performed in accordance with the applicable

standards and specifications.

Non-Conformity

COMPANY, CONTRACTOR or SUBCONTRACTOR document that

Report (NCR):

highlights any non-conformance discovered during the execution of

the subcontract.

Non-Conformance:

The non-fulfilment of specified requirements.

NDT:

PCA:

Non-Destructive Testing.

Piping Control Application; the PCA is a system owned and developed by TR for piping production control, providing information of isometrics, spools and welds, including NDT and Test Package performance. And generates reports that can be used for several Departments (construction, quality control, planning…).

Pre-commissioning:

Testing of system components for continuity, operability and in the case of the process plants, their ability to withstand operating pressure prior to the introduction of feedstock or other final products into the facility.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 10 OF 162

10651-00-QAC-PD-0003

REV.: 01

Quality Assessment: Generally, replaces the term ‘Quality Audit’. A systematic and

independent examination to determine whether quality activities and

related results comply with planned arrangements and whether

these arrangements are implemented effectively and are suitable to

achieve objectives.

Quality Assurance (QA):

Part of quality management focused on providing confidence that quality requirements will be fulfilled.

Quality Control (QC): Part of quality management

focused on

fulfilling quality

requirements.

QForms:

It is a mobile app developed by TR that allows all Project Teams

accessing and downloading RFIs, complete the associated scope

of Control Forms and the sign off workflows digitally, as well as

providing access to RFI attachments such as drawings, reports or

photos.

Quality Management

Part of the organization’s management system, procedures,

System (QMS):

process and resources, that focuses on achievement of results, in

relation to the quality objectives, to satisfy the needs, expectations

and requirements of CONTRACTOR and of any other interested

parties, as appropriate.

Quality Manual:

Is a document setting out the SUBCONTRACTOR´s quality policies,

systems, procedures and practices and including a listing of

procedures.

Quality Plan:

Is the SUBCONTRACTOR document specifying which procedures

and associated resources shall be applied by whom and when

during the execution of the Subcontract.

QRFS:

Quality Requirements For SUBCONTRACTOR.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 11 OF 162

10651-00-QAC-PD-0003

REV.: 01

Quality Record Book

A compilation of documents which provide a record of Quality

or

Final Quality

checks performed by the SUBCONTRACTOR under the scope of

Dossier:

the Subcontract.

Request

for

Document that is issued by SUBCONTRACTOR to CONTRACTOR

Inspection (RFI):

and CONTRACTOR in turn to the COMPANY for notification and

subsequent confirmation of inspections and tests requiring in

accordance with

the ITP approved by CONTRACTOR and

COMPANY.

Review (R):

An activity designated by the CONTRACTOR and/or Client and/or

Third party that requires the review and acceptance of the

Manufacturer/ Vendor/ SUBCONTRACTOR’s documentation. No

formal inspection notification is required

Aramco

Saudi Inspection Checklists (SAIC):

Saudi Aramco pre-approved Inspection Checklists form part of the

SATIPs that identify the lists of PASS/FAIL Inspection Criteria,

reference standards, re-inspection date and other pertinent

Saudi Typical and (SATIP):

Aramco inspection Plan

Test

inspection details that are used for inspection of activities. The use

of SAIC(s) is mandatory.

Saudi Aramco pre-approved Inspection and Test Plans (ITPs) that

are generated by Saudi Aramco Inspection Department customized

for use in Saudi Aramco-managed construction projects. The use

of SATIP(s) is mandatory.

Shall:

It indicates a mandatory requirement.

Should:

It expresses a recommendation among other possibilities

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 12 OF 162

10651-00-QAC-PD-0003

REV.: 01

Site

Quality

Site Quality Management System: it is an in-house web-based

Management System

software developed by TR, which is used to plan and monitor the

(SQMS):

Project’s scope of site tests and inspections based on the Inspection

and Test Plans (ITPs) and Test Packages requirements, and

associated QC Forms. SQMS is also the platform that orchestrate

all the inspection workflows: from the notification, or request for

inspection (RFI), up

to

its completion. SQMS provides a

collaborative platform where all the Teams work together, with

access to the same information at any time. It is the software

developed by TR used

to monitor

the Pre-commissioning,

Commissioning activities and the Punch Lists to assure the correct

transference of Operating Subsystems/Systems. This software will

be also used to control some of the activities developed prior the

transference of Subsystems, activities such as the Test Packages

and its related Control Forms.

Subcontract:

Means any tier of contract for the performance of any portion of the

Work entered into by a SUBCONTRACTOR.

SUBCONTRACTOR

Technical and specific Construction Procedures in accordance with

Procedures:

the requirements of their Subcontract, which are developed by the

SUBCONTRACTOR

for CONTRACTOR approval.

ITPs are

included in the scope of SUBCONTRACTOR Procedures.

Surveillance (S):

A monitoring activity

in which

the CONTRACTOR and/or

COMPANY and/or Third party verify by random attendance whether

materials, items or works meet the specified requirements. No

formal inspection notification is required.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 13 OF 162

10651-00-QAC-PD-0003

REV.: 01

Third

Party

Someone other than COMPANY or CONTRACTOR, directly

Inspection Agency

involved in a service of inspection, supervision or agreement. Third

(TPIA):

party is not a directly involved in the WORKS or agreement or

contract, but they may be present as a part of the CONTRACT or

someone affected by the CONTRACT.

Traceability:

Capacity or ability to trace at any moment, the history, application or

location for the quantity and characteristics of the materials.

Will:

It expresses a declaration of purpose or intent by one party.

Witness Point (W):

An inspection activity that requires the CONTRACTOR and/or

COMPANY and/or Third party be notified by the Manufacturer/

Vendor/ SUBCONTRACTOR of a specific time and place for the

activity to be attended. This notification shall be carried out by a

Formal information process and the activity shall be developed with

or without the CONTRACTOR and/or COMPANY and/or Third-party

presence with no signed waiver required

Means all the works and services and other obligations to be carried out by SUBCONTRACTOR under the Subcontract.

Welder Performance Qualification.

Welding Procedure Specification.

Work:

WPQ:

WPS:

Any other terms related to quality and not listed above shall conform to section 3 “Term and

Definition” of ISO 9000:2005 “Quality Management System – Fundamentals and vocabulary.

REFERENCES

COMPANY DOCUMENTS

Contract IK (6600051791) & Contract OOK (6600051792)

PKG. No 1 Riyas NGL Fractionation Facilities- NGL Fractionation Trains

Contract IK (6600051793) & Contract OOK (6600051794)

PKG. No 2 Riyas NGL Fractionation Facilities- NGL Utilities, Storage & Export Facilities

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 14 OF 162

10651-00-QAC-PD-0003

REV.: 01

As defined in Schedule Q Attachment II, “SUBCONTRACTORS shall comply with all applicable SAUDI ARAMCO Mandatory Engineering Requirements (MSAER’s) as defined under SAEP-301; Material System Specifications (SAMSS), Engineering Standards”.

As a minimum the SUBCONTRACTOR shall comply with the following COMPANY standards/specifications:

Schedule Q

Quality Requirements

Schedule B

Job Specification

SAEP-122

Project Records

SAEP-119

Materials System Specifications

SAEP-127

Security and Control of Saudi Aramco Engineering Data

SAEP-302

SAEP-303

Instructions for Obtaining a Waiver of a COMPANY Engineering Requirement

Engineering Reviews of Project Proposal and Detail Design Documentation

SAEP-316

Performance Qualification of Coating Personnel

SAEP-324

Certification Review and Registration of Project Welders and Brazers

SAEP-347

Supplying Material from Stockists

SAEP-352

Welding Procedures Review and Approval

SAEP-379

Quality Issues Notification

SAEP-380

Equipment Deficiency Report

SAEP-381

Project Quality Issues Escalation

SAEP-385

Preservation of Project Materials and Equipment

SAEP-1101 through 1117

SAEP-

Welding and Brazing Test Supplements for Welder Performance Qualification

SAEP-1131

Pressure Relief Device Authorization through SAP Workflow

SAEP-1133

Form 3750, Pressuring Relieving Device Test Report

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 15 OF 162

10651-00-QAC-PD-0003

REV.: 01

SAEP-1141

Radiation Protection for Industrial Radiography

SAEP-1142

Qualification of Non-COMPANY NDT Personnel

SAEP-1143

Radiographic Examination

SAEP-1144

Magnetic Particle Examination

SAEP-1145

Liquid Penetrant Examination

SAEP-1152

Approval Procedure for Ready-Mixed Concrete Mix Design

SAEP-1154

Guidelines for CONTRACTOR´s Quality Plan

SAEP-1160

Tracking and Reporting of Welding, NDT and Pressure Testing for Capital Projects

SAEP-1636

Installation and Checkout Plan

SAEP-1638

Site Acceptance Test Plan

SAEP-1151

Inspection Requirements for CONTRACTOR procured materials, equipment

SAEP-35

Valves Handling, Hauling, Receipt Tests and Storage

SAEP-351

Bolted Flange Joints Assembly

PROJECT DOCUMENTS

10651-00-PRM-PD-0001

Project Execution Plan

10651-00-PRM-PD-0002

Coordination Plan

10651-00-QAC-PD-0001

Engineering & Procurement Quality Plan

10651-00-QAC-PD-0003

Quality Requirements for SUBCONTRACTORs

10651-00-DOC-PD-0001

Document Management Plan

10651-00-QAC-PD-0005

Verification and Validation Procedure

10651-00-PRC-PD-0004

Project Risk Management Plan

10651-00-PRM-PD-0003

Organization Procedure

10651-00-PRC-PD-0001

Planning and Scheduling Plan

10651-00-PRC-PD-0002

Progress Control Procedure

10651-00-PRC-PD-0003

Project Reporting Procedure

10651-00-PRM-PD-0004

Change Order Management Procedure

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 16 OF 162

10651-00-QAC-PD-0003

REV.: 01

10651-00-DOC-PD-0002

Comments Control Procedure

10651-00-PRE-PD-000

Engineering Plan

10651-00-PRM-PD-0011

Coordination with Licensor Procedure

10651-00-PPC-PD-0002

Inspection Plan

10651-00-PPC-PD-0003

QA/QC, Inspection and Expediting Requirements for Vendors

10651-00-PRE-PD-0002

Numbering Procedure

10651-00-PPC-PD-0001

Procurement Plan

10651-00-CON-PD-0004

Field Materials Management Plan

10651-00-PPC-PD-0004

Traffic and Logistics Plan

10651-00-QAC-PD-001

Non-Conformance Procedure

INTERNATIONAL STANDARDS

As a minimum the SUBCONTRACT shall to comply with the following international standards:

ISO 9001:2015

Quality Management Systems - Requirements

ISO 9000:2015

Quality Management Systems - Fundamentals and Vocabulary

ISO 10005:2018

Quality Management Systems - Guidelines for Quality Plans

ISO 10006:2017

Quality Management Systems – Guidelines for Quality Management in Projects

International Codes

International codes and Standards as per applicable scope of work (i.e. API, ASME, AWS, ASTM, etc.)

DEVELOPMENT

QUALITY REQUIREMENTS

General

This document describes the minimum requirements for SUBCONTRACTOR´s Quality

System.

SUBCONTRACTOR shall perform the WORK with the best engineering practice,

workmanship, and following the applicable project requirements within the Subcontract

scope.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 17 OF 162

10651-00-QAC-PD-0003

REV.: 01

SUBCONTRACTOR shall be totally responsible for the quality of their WORK and also the

works carry out for their own SUBCONTRACTORs required in the scope of work in this

Subcontract.

SUBCONTRACTOR shall inspect, test and accept all parts of the WORK as defined in the

scope of work of this Subcontract and the scope of work in the individual Purchase Order

where applicable, in conformance with all drawings, specifications and standards applicable

to the WORK.

CONTRACTOR shall be entitled to have the CONTRACTOR Representative or his nominee

present at all locations where SUBCONTRACTOR or its sub-SUBCONTRACTORs and

suppliers are engaged in the performance of the WORK, at any and all times, to review all

aspects of SUBCONTRACTOR’s Quality activities and to witness whatever inspection and

testing is required by this Subcontract. CONTRACTOR retains the right to conduct whatever

additional tests or inspections it deems necessary to assure itself that the materials meet the

requirements of the Contract. SUBCONTRACTOR shall not refuse access to technical or

other data which SUBCONTRACTOR considers proprietary or confidential, and which is

reasonably required to inspect SUBCONTRACTOR’s performance of the WORK; except

where the nominee of CONTRACTOR’s CONTRACTOR Representative is a competitor of

SUBCONTRACTOR in the sale, engineering, or installation of systems similar to the

FACILITIES or is related to or affiliated with such a firm, in which event the CONTRACTOR

Representative may nominate an alternate.

SUBCONTRACTOR must strictly

follow all applicable

local

laws and regulations,

specifications, and all instructions contained within this document and their annexes.

For any inspection or any test required by COMPANY/CONTRACTOR standards to be

witnessed, including any requirement included in the local applicable laws, rules and

regulations, SUBCONTRACTOR shall provide notice of said inspection or test as specified

in the approved Inspection and Test Plans (ITP’s) to enable the CONTRACTOR

Representative to attend. If any part of the WORK or the FACILITIES is closed or covered

before the required inspection or witnessing has been performed or without agreement by

CONTRACTOR, it must, if required by CONTRACTOR, be opened or uncovered for

inspection or witnessing and re-closed or recovered at SUBCONTRACTOR’s expense.

If any inspection or test directed or performed by CONTRACTOR, or by another party at the

direction of CONTRACTOR, reveals any defect in SUBCONTRACTOR-supplied materials or

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 18 OF 162

10651-00-QAC-PD-0003

REV.: 01

in the WORK, SUBCONTRACTOR shall bear the cost of such inspection and testing and

shall promptly correct such defect at SUBCONTRACTOR’s expense.

If SUBCONTRACTOR does not adhere to the Quality requirements of this Subcontract,

CONTRACTOR may, after two (2) weeks notification to SUBCONTRACTOR, supply

sufficient inspection and testing services to assure that the WORK is being done as required

by this Subcontract. SUBCONTRACTOR shall bear the cost of such inspection and testing.

CONTRACTOR may lower the requirements of this document at its own discretion, keeping

SUBCONTRACTOR informed.

Quality Management System (QMS)

SUBCONTRACTOR shall develop and operate a Quality Management System (QMS) based

on the ISO 9001-2015 Quality standard, or a suitable implemented and documented

alternative management system accepted by CONTRACTOR.

During the bid phase, the SUBCONTRACTOR shall submit to CONTRACTOR copy of the

Quality Manual and

the

ISO 9001 2015 certificate

issued by an accredited

National/International Certification Body, and any other certificate that demonstrate the

operation and/or installation activities according to International Standards (ASME, API, etc.).

If SUBCONTRACTOR Quality System has not been independently assessed against any

Standard and is not certified by an accredited National/International Certification Body,

SUBCONTRACTOR is required to demonstrate fulfillment with the QA/QC requirements

described in this document and ISO 9001-2015 requirements to the CONTRACTOR.

SUBCONTRACTOR shall conduct senior management reviews every six (6) months to the

Project Quality system to ensure that the system is suitable, adequate and effective.

According to Schedule Q Paragraph 4.1 Senior Management reviews as a minimum,

addressing the interactions of the items provided in Paragraph 7.1.1 of this Schedule “Q”

shall be scheduled events included in the quality audit schedule approved by the

Company Representative as provided in Paragraph 7.3.2 of this Schedule “Q”.

Software Requirements

SUBCONTRACTOR shall use a dedicated CONTRACTOR Software “Site Quality

Management System”-SQMS, in order to manage i.e. plan, notify (NOI / RFI), record and

track, all inspections and tests, according to the applicable ITPs and Test Packages.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 19 OF 162

10651-00-QAC-PD-0003

REV.: 01

Secondly, CONTRACTOR may

implement mobile

field

inspection plan

for

the

SUBCONTRACTOR scope of works by using a dedicated mobile application (usually

Qforms). If this was the case, then SUBCONTRACTOR shall adhere to this implementation

by carrying out the test and inspections in accordance with the ITPs and/or Test Packages

as per CONTRACTOR’s instructions using the mentioned mobile app and providing their own

devices.

SUBCONTRACTOR shall therefore provide the necessary hardware equipment (computers

and tablets) to utilize the dedicated desktop and mobile software mentioned above, and in

accordance with their latest hardware requirements.

Otherwise, if a Software is not provided by CONTRACTOR, SUBCONTRACTOR shall submit

for CONTRACTOR’s approval an alternative dedicated or alternative software, allowing

similar management of all the Quality Document Requirements here mentioned, no later than

thirty (30) calendar days after effective date of this Subcontract.

After the selection of the dedicated software described above, and during the execution of

the works, a different dedicated software may be required by COMPANY or CONTRACTOR.

In this case, the dedicated software will be substituted, and the SUBCONTRACTOR shall

adopt it.

SUBCONTRACTOR shall identify the required Inspections and Tests in accordance with the

applicable ITP and the SUBCONTRACTOR’s scope of work breakdown. As a result, each of

the portions of work defined will require a number of specific Inspections and Tests and all

this information shall be provided by SUBCONTRACTOR to CONTRACTOR for review and

approval, by filling out the templates provided by CONTRACTOR’s dedicated Software or its

alternative.

Documentation Requirements

SUBCONTRACTOR shall plan, organize, control and execute all WORK in accordance with

SUBCONTRACTOR’s Quality Plan(s), Inspection and Test Plans (ITPs) and documented

procedures. The Quality Plan(s) shall ensure that quality personnel and processes are

effective and that the WORK is completed in strict compliance with all provisions of the Job

Specification of the Subcontract and the Scope of Work in the individual Release P.O. where

applicable.

SUBCONTRACTOR shall prepare and maintain a narrative, specific Project Quality Plan

(PQP) including quality objectives, processes, resources, applicable COMPANY SATIPs

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 20 OF 162

10651-00-QAC-PD-0003

REV.: 01

(according to the scope of work) or approved Inspection & Test Plans (ITPs), SAICs, SATRs,

work instructions and quality procedures covering, as applicable, design, procurement,

construction and Pre-Commissioning quality activities and WORK in accordance with the

Subcontract, SAEP-1154, the 2018 version of ISO 10005 (Quality Management Systems -

Guidelines for Quality Plans) and the 2017 version of ISO 10006 (Quality Management

Systems - Guidelines for Quality Management in Projects).

SUBCONTRACTOR shall submit the PQP to the CONTRACTOR for review and approval (a)

within twenty-one (21) calendar days of the Effective Date of the Subcontract.

The SUBCONTRACTOR´s Project Quality Plan shall include as a minimum, but not limited to:

• Project quality policy and objectives.

• Scope of project´s Quality Management System, specifying whether engineering

and procurement is included.

• Project QA/QC organization and responsibilities. Organization chart

• List and status of the procedures to be used in the project.

• Document and record control on the project.

• Engineering quality control (if engineering is in the scope of work).

• QA/QC

requirements and control of SUB-SUBCONTRACTORS and

SUBCONTRACTOR vendors´ (if procurement and SUB-SUBCONTRACTS are in

the scope of work).

• Site Inspection Activities (ITPs and QCForms).

• Quality records management.

• Material control (traceability).

•

Internal audits and schedule for the project scope of work.

• Control of non-conformities and corrective actions.

SUBCONTRACTOR shall adopt the latest revision of Saudi Aramco Typical Inspection and

Test Plan (SATIP) and associated Saudi Aramco Inspection Check list (SAIC) in lieu of its

own ITPs and inspection procedures. SUBCONTRACTOR may customize the SATIP and

SAIC to suit the scope of work, with the approval of CONTRACTOR Representative.

SUBCONTRACTOR shall include a list of applicable SATIPs for execution of the scope of

the WORK in accordance with Subcontract. CONTRACTOR and/or COMPANY rejection to

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 21 OF 162

10651-00-QAC-PD-0003

REV.: 01

SUBCONTRACTOR ITPs shall mean the use and implementation of the latest revision of

Saudi Aramco ITPs (SATIP’s, SAIC’s and SATR’s) with no extra cost to CONTRACTOR.

When any part of the scope of WORK is not supported by SATIP(s), SAIC (s), SATRs,

CONTRACTOR shall prepare and submit, as part of the PQP, ITPs and supporting quality

documents to CONTRACTOR for approval a minimum of 30 calendar days prior to the start

the activity

SUBCONTRACTOR shall modify its Quality Plan(s) and ITPs, when applicable, to reflect any

significant

changes

identified

by

SUBCONTRACTOR

or CONTRACTOR.

SUBCONTRACTOR´s revised Quality Plan(s) or ITPs shall be then resubmitted for

CONTRACTOR´s approval within seven (7) calendar days after such significant changes

have been identified.

CONTRACTOR will complete its review of SUBCONTRACTOR’s Quality documents (Quality

Plan(s), procedures, ITPs) and personnel qualifications no more than thirty (30) calendar

days after submittal of a document or its subsequent modifications. CONTRACTOR will

approve or provisionally approve the submitted document or personnel qualification, or it will

reject the document with comments.

SUBCONTRACTOR shall not commence WORK prior to CONTRACTOR approval of the

SUBCONTRACTOR´s Quality Plan and applicable ITPs.

The latest revision of SUBCONTRACTOR’s Quality Manual(s) and all referenced

documentation shall be available for CONTRACTOR’s use at the SUBCONTRACTOR’s

design, procurement, fabrication and installation or construction locations. Reference

documents include all those contained in drawings, specifications and procedures, SAES,

SAEPs for the inspection of equipment and materials to be fabricated or constructed at the

applicable site.

The SUBCONTRACTOR documented QMS shall be adapted to the contractual scope of

work and requirement in order to ensure full compliance with specific project quality

procedures, expectations and needs including but not limited to:

• Planning of product realization including details of the organization structure,

qualifications, roles and responsibilities, lines of authority and interfaces of

management and staff personnel implementing QA/QC activities;

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 22 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Document control procedures to control status and ensure that only the latest

approved revision of documents are available for the work;

• Procedure to control all changes or modifications to design documents and as

built documentation;

• Procedure for verification of construction purchased material including Material

Approval Request (MAR) work process, inspection services, surveillance and

quality auditing of suppliers as applicable to the contractual scope;

• Procedure for material receiving inspections, for the control of handling, storage and preservation of material and equipment including those supplied by CONTRACTOR, as per SAEP-385 requirements;

• Procedure for identification and traceability of material and equipment from

receiving through installation and handover.

• Procedure for special processes qualification. This shall include specific

qualification and tests for any special process and related personnel;

• Procedure for controlling the production and the implementation of Inspection and

Test Plans, including the control of construction special processes;

• Method for tracking and maintaining status of field inspection and testing;

• Method for controlling calibration of monitoring and measuring devices;

• Procedure and plan

for

internal audits and external audits of

SUBCONTRACTORs;

• Procedure

for

identification,

reporting,

tracking and resolution of non-

conformances at the construction site;

• Procedure for identifying, performing and documenting training in the field;

• Procedure verifying compliance and quality records to support mechanical

completion of system/plant as required.

• Mechanical Completion Procedures.

• Procedures for a Non-Destructive Examinations, for Hardness and for Post Weld

Heat Treatment according to requirements of standards and codes applicable for

the Project.

SUBCONTRACTOR must issue to CONTRACTOR logs book taken into account their scope

of work. The normal logbook will contain the following information, but not limited to:

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 23 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Log book for concrete works including test performed, fabrication and site

(Weekly basis)

• Log book for backfilling and paving works including test performed, fabrication

and site (updated in a weekly basis)

• Log book for electrical and instrumentation works including test performed,

calibration status, etc. (updated in a weekly basis)

• Log book for NCRs with the status (updated in a weekly basis)

• Log book for CAR / PARs

• Log book for OBSERVATIONs with the status (updated in a weekly basis)

• Log book of QA/QC documentation: ITPs, NDE procedures (LP, PH, UT, RT, HT,

PWHT, etc.) (updated in a weekly basis)

• Welding book, including backlog status (updated in a weekly basis)

• Log for WPS and PQR (updated in a weekly basis)

• Log for welder qualification (updated in a weekly basis)

• Log of personnel qualification (updated in a weekly basis)

• Log of purchase orders/ SUB-SUBCONTRACTS (updated in a weekly basis)

• Log for material/equipment reception including documented information such as

quality certificates, data sheets, brochures, manuals, etc. (updated in a weekly

basis)

• Log of preservation and maintenance (updated in a weekly basis)

• Log for calibrate equipment (calibration date, next calibration and mentioned

calibration certificate) (updated in a weekly basis)

• Authorized signature register, every time that the SUBCONTRACTOR performs

changes in their organization or in the internal duties and responsibilities, in this

case, SUBCONTRACTOR must issue the updated organization chart.

• Log book for inspection performed (Approved/Rejected Status), delivery control

of partial or complete System/Sub-System/Area and even for Inspection and Test

Plan activities. Per discipline and delivered by all

interested parties

(SUBCONTRACTOR/ CONTRACTOR/ TPI/ OWNER) when required (updated in

a weekly basis).

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 24 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Log book for Punch Items/Lists information and status (updated in a weekly basis)

• Log book for Equipment Erection.

• Log Book for Hydrostatic Test Package (updated in a weekly basis)

• Log Book for the Construction Handover dossier, information and status of the

works successfully achieved and documented including approval of interested

parties when required (updated in a weekly basis)

All type of logs mentioned must be in native files to facilitate the cross check.

The issue of new logs or changes in existing ones shall be under CONTRACTOR’s

criterion.

When required, schemes/drawings shall be attached to ensure traceability to above

mentioned documents.

The intellectual property of all documents generated at this stage shall be held by the

CONTRACTOR who retains the right to use them freely.

Internal Audits

SUBCNTRACTOR shall plan and conduct Internal Audits in accordance with ISO 19011

guidelines; covering all WORK Phases, and Sub-Subcontracts for design, procurement or

construction with a duration of three (3) calendar months or longer. Internal Audits shall fully

address SUBCONTRACTOR QMS; implementation, maintenance and compliance with

quality processes and

requirements specified

in

the CONTRACTOR approved

SUBCONTRACTOR PQP, the Subcontract and the 2015 version of ISO 9001. Internal

Audits shall be planned and conducted on each Sub-SUBCONTRACTOR or Supplier QMS

and PQP that is adopted by reference or attachment to the CONTRACTOR approved

SUBCONTRACTOR PQP.

SUBCONTRACTOR shall submit an Internal Audit schedule to the CONTRACTOR

Representative for review and Approval within twenty-one (21) calendar days from the

Effective Date of the Subcontract.

Internal Audits shall be annually (Full System) until completion of the Construction phase.

All internal audits shall be executed by objective and impartial internal Quality System

Auditors (qualified in accordance with Schedule Q Attachment I) not directly responsible for

the area being audited or by an approved third-party agency.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 25 OF 162

10651-00-QAC-PD-0003

REV.: 01

SUBCONTRACTOR Quality Manager shall investigate root causes and initiate corrective

actions for items identified in each audit and shall verify implementation and closeout of

corrective actions prior to the next scheduled audit.

SUBCONTRACTOR Quality Manager shall submit to CONTRACTOR a copy of each audit

report within twenty-one (21) calendar days of the audit closing meeting date.

Internal Audit Process will include:

• Planning of quality audits.

• Selecting qualified Quality System auditors.

• Preparing the audit checklist.

• Notifying the audited organization/activity.

• Conducting the pre-audit meeting.

• Performing the audit.

• Conducting the post-audit meeting to present the audit findings and clarify possible

misunderstandings.

• Preparing the audit report and Non-Conformity Reports (NCR), completed by

corrections/ corrective actions or preventive actions.

• Processing corrective action requests.

• Follow-up (as required).

All Quality System Auditors for internal and external audits on this Project shall be approved

by the COMPANY prior to conduct the audits, qualified, as minimum, as follows:

• Shall have 5 years Quality System experience in auditing activities in the discipline

he is working in.

• Auditors shall be qualified as stated in ISO-19011 and competent in the discipline

being audited.

• Familiar with Quality System standards and be able to exercise judgment against the

criteria of the standards.

• Auditors must be able to communicate clearly in writing and orally.

• Auditors shall have satisfactorily completed a training course and passed the course

examination.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 26 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Auditors shall have participated in a minimum of four audits for a total of at least 20

days including documentation review, actual audit activities and audit reporting during

the past three years.

Quality audits scope must be relevant but not limited to:

• SUBCONTRACTOR implementation of the QMS (full or partial);

• Compliance to contractual QA/QC requirements;

• Performance of inspections, examinations and testing as per approved ITPs;

• Conformity of the Works or part thereof completed;

• Review of the SUBCONTRACTOR activities and QA/QC related documentation;

• Verification of NCR disposition and corrective action follow-up and close-out;

• Any other QA/QC verification as deemed necessary to provide confidence that

SUBCONTRACTOR is in conformance with all QA/QC requirements.

Audit notifications and agendas must be submitted to the CONTRACTOR fourteen (14) days

in advance of the planned audit. CONTRACTOR Representative or nominee shall be invited

to participate in all SUBCONTRACTOR internal audits as auditor.

SUBCONTRACTOR must submit to the CONTRACTOR a copy of each audit report within

fourteen (14) days of its completion.

Any deficiencies noted during the audit shall be immediately rectified by SUBCONTRACTOR.

If CONTRACTOR´s follow up audits are necessary to confirm rectification, all costs related

to such CONTRACTOR´s follow up audits will be borne by SUBCONTRACTOR until

acceptable compliance is achieved.

CONTRACTOR or its appointed representative, reserves the right to carry out Quality Audits,

Reviews and Surveillances at the SUBCONTRACTOR / Lower Tier SUBCONTRACTOR

offices and workshops, to verify that the Quality System is being implemented satisfactorily.

The SUBCONTRACTOR shall provide CONTRACTOR and/or Third-Party Auditors all

necessary documentation, free access, working space and other facilities, necessary to

satisfactorily accomplish Quality Audits.

CONTRACTOR shall communicate the quality audit schedule to SUBCONTRACTOR at least

seven (7) days prior to the audit. This notification is not necessary to perform Reviews and

Surveillances at the SUBCONTRACTOR offices and workshops.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 27 OF 162

10651-00-QAC-PD-0003

REV.: 01

CONTRACTOR reserves the right to pre-qualify each SUB-SUBCONTRACTOR and its

specific site prior to placement of the Sub-Subcontract.

The SUBCONTRACTOR shall establish and control quality requirements in their SUB-

SUBCONTRACTORS to ensure that the specified quality requirements are met.

QA/QC Training

CONTRACTOR will implement an ongoing training program to introduce and familiarize

SUBCONTRACTOR Key personnel with the project QA/QC project requirements for their

area of responsibility;

SUBCONTRACTOR will implement a training program to ensure all his employees know the

project QA/QC requirement for their area of responsibility, all personnel involved shall attend

the training course. CONTRACTOR will be invited as a witness in the trainings.

QA/QC Weekly Meeting

SUBCONTRACTOR shall participate to QA/QC meetings as directed by CONTRACTOR. Meetings, in general, shall be held weekly and/or otherwise agreed at site.

Scope and agenda of the meeting shall be agreed by participants according to the quality issues arising during construction work. As a minimum quality meeting agenda shall include the following topics:

• Previous meeting outstanding items;

• Description of the activities on going;

• Construction quality issues per construction disciplines;

•

ITP planning, issuing and approval status;

• Construction quality procedures planning, issuing and approval status;

• Updated QA/QC Personnel Organization chart with names and working location per

disciplines;

• QA/QC personnel qualification approval status per disciplines;

• Direct manpower/inspectors ratio per disciplines;

• RFI issuing per week per discipline;

•

•

Inspection and test failures;

Inspection and tests status log summary;

• Welding qualifications status, welding rejection rate and repair % ratio;

• List of approved monitoring and measuring devices;

• NCR status.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 28 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Needs of quality improvements and improvements activities.

• NDT Backlogs/Action Plan –The NDT backlog provide by SUBCONTRACTOR must

be compared with the PCA data.

Monitoring and Measurement - Quality indicators

SUBCONTRACTOR shall continually monitor and measure construction activities, inspection

activities and critical processes throughout the Work. The Quality Manual or Quality Plan

shall include suitable measurement methods to evaluate the ability of the process to achieve

planned results.

SUBCONTRACTOR shall plan and implement applicable methods for monitoring and

measurement analysis including statistical techniques to demonstrate conformity of the work

performed, such as but not limited to:

•

Internal Lessons Learned – Implementation / Collection

• External Lessons Learned – Implementation / Collection

• Design Office Notices / Field Requests

• Material Receiving

• Preservation of Materials

• Concrete Operations

• Equipment Installation

• Welding Operations

• Coating Operations

• Non-destructive Testing of Welding and Materials

• Hydrostatic and Pneumatic Pressure Testing

• Construction and Pre-Commissioning QA / QC

• Mechanical Completion and Safe Energization

Measurement of quality shall be in the amount of repair or re-work required during the

construction phase. Evaluation of these quality indicators shall be repair % of production or

re-work %.

SUBCONTRACTOR shall keep accurate logs of non-conformances, inspection and test

failures, repair, and re-works rates and their reasons in order to document and support the

indicator final scoring.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 29 OF 162

10651-00-QAC-PD-0003

REV.: 01

SUBCONTRACTOR shall monitor and measure all activities related to its operations that can

have a significant quality impact and progress towards the organization’s quality objectives,

using indicators (KPI).

SUBCONTRACTOR shall include in its Quality Plan and shall monitor, as minimum, the same

Quality indicators and Objectives than the measured by CONTRACTOR.

SUBCONTRACTOR shall monitor and analyse Key performance indicators (KPI’s) whose

results will be issued weekly, as a minimum but not limited as per CONTRACTOR request:

• First inspection rejected/total inspections performed

• Non-Conformities/Site Observations.

• RFI cancelled or postponed/Total RFI issued

• Rejected series of concrete cube test/total series performed

• Rejected compacted soil batch (Dry density test) /Total batch tested

• Number of repaired weld joints/Number of weld joints with NDE carried out) x 100

(Regarding welding

repair

rates,

in addition

to above generic KPI,

SUBCONTRACTOR shall provide indicators as welding repair rates (total and per

each welder, per each welding process based on repaired weld length and repaired

weld joint), evaluation of welding quality in prefabrication and in erection, in general

for SUBCONTRACTOR and/or unit, and also for every welder). CONTRACTOR can

disqualify for the Project any welder with rejections in the visual inspection of welds,

additionally, any welder with a high rejection rate.

• Number of RT films rejected / Number of RT films taken

• Rejected PMI test / Total PMI performed

• Failed first pass pressure test/ total pressure test performed with CONTRACTOR

(Internal pressure test can be performed prior to formal pressure test with

CONTRACTOR).

• Backlogs of delivery of documentation expressed as documents delivered within 24

hours after its completion versus the total of documents

• Backlogs of NDE or/and Post Weld Heat Treatment.

SUBCONTRACTOR shall prepare in a monthly basis, a Quality Report including at least,

previous information.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 30 OF 162

10651-00-QAC-PD-0003

REV.: 01

Preparation of Quality Record Books

SUBCONTRACTOR shall prepare a procedure describing how quality documentation and

records will be handed over to CONTRACTOR. The procedure shall ensure compliance with

the requirements stated

in SAEP-122 “Project Record Books” and shall enable

CONTRACTOR to hand over the same to the COMPANY.

In any case, the Quality Records shall be under CONTRACTOR custody all the time.

SUBCONTRACTOR shall propose the quality documentation procedure, which shall include

but not be limited to:

• List of documents to be included in the Site QA/QC Record Book;

• Filing system;

• Binder (size, colour, material, holes, separator…etc)

• File box type suitable for long preservation;

• Volumes numbering;

• Cover labels;

•

Indexing volumes/files/records;

• Number of copies;

• Quality of reproduction;

• Type of formats;

• Retrievability of documents.

All documentation and signed test records shall be provided in paper and electronic form

(Acrobat Adobe PDF file with searchable version – (OCR). The documents shall be properly

indexed, hyperlinked, and searchable. SUBCONTRACTOR shall submit the number of

copies of the Site Final Quality Dossiers indicated in Subcontract to CONTRACTOR.

SUBCONTRACTOR shall issue to CONTRACTOR the above procedure for review and

approval during the initial phase of construction, no later than sixty (60) days after the

Subcontract award.

SUBCONTRACTOR shall issue to CONTRACTOR a Site QA/QC Record Book Index for

CONTRACTOR review and approval no later than sixty (60) days after the Subcontract

award.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 31 OF 162

10651-00-QAC-PD-0003

REV.: 01

The SUBCONTRACTOR will provide to the CONTRACTOR enough, competent, and

qualified personnel to carry out the archiving and storing of documentation related to welding

non-destructive examinations and post weld heat treatment and any associated testing shall

ensure suitable storing and long preservation of documents such as radiographs, PWHT-

charts etc. The archiving and storing methods shall be approved by CONTRACTOR Welding

Supervisor, the SUBCONTRACTOR will supply to the CONTRACTOR enough, competent

and qualified personnel to support the activities such RT Film scanner and RT film storage

The SUBCONTRACTOR will provide enough : Small Cardboard boxes (for 100 Films), Big

plastic boxes (8 small boxes =800 films).The submittal and storing of the original films will be

in daily basis.

NOTE.- All the documentation submitted by SUBCONTRACTOR to CONTRACTOR in order

to comply with the documentation requirements defined along this procedure do not exclude

SUBCONTRACTOR to include all of these documents, already submitted to CONTRACTOR,

into the Final Quality Dossier and submitted again to CONTRACTOR at the end of the Work.

Prefabrication Quality Record Books

In case the Subcontract includes fabrication activities, a specific Prefabrication Final Quality

Record Books shall be prepared by SUBCONTRACTOR with all the documentation related

to the prefabrication. The PRB must be completed 15 days after completing the

prefabrication. in the Site Final Quality Record Books will be mentioned the Name-Numbering

and location related to the Prefabrication Quality Record Books.

NOTE: SUBCONTRACTOR to send to CONTRACTOR a delivery plan of Quality Record

Books for approval, with all chapters, items and files (physical file and electronic)

QA/QC PERSONNEL AND RESOURCES

General

The SUBCONTRACTOR shall have an independent Quality Control organization with

sufficient resources to oversee the Works (i.e. Quality Control personnel shall be independent

of any related production or construction function).

SUBCONTRACTOR shall ensure at any time adequate number of competent and qualified

personnel to perform the work.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 32 OF 162

10651-00-QAC-PD-0003

REV.: 01

SUBCONTRACTOR QA/QC team shall be provided with sufficient clerical personnel to

accomplish a timely submittal of inspection notifications, inspection and test reports, status

and summary necessary to control completion of the Work and to ensure the availability of

the required documentation.

The definition of the QA/QC Key personnel needs to be agreeing between CONTRACT and

SUBCONTRACTOR.

QA/QC Resources Management

SUBCONTRACTOR shall provide qualified resources to implement, maintain and improve

the QMS as set forth in the Subcontract and the approved PQP. For all activities under the

scope of work of the Subcontract, sufficient SUBCONTRACTOR Quality personnel prior to

the start of applicable WORK. At minimum, SUBCONTRACTOR shall deploy the

SUBCONTRACTOR Quality Personnel specified in TABLE 1 of this document. Selection of

SUBCONTRACTOR Quality Personnel shall be subject

to

the Approval of

the

CONTRACTOR representative

SUBCONTRACTOR Quality personnel for review and approval at least thirty (30) days in

advance to each individual starting work.

As a minimum, SUBCONTRACTOR shall assign CONTRACTOR approved quality personnel

to the WORK in accordance with the following TABLE 1

TABLE 1 – Quality Personnel Requirements

Position

SUBCONTRACTOR(s)

Quality Control Manager

One (1) full time for each SUBCONTRACTOR

Quality Control Supervisor

One (1) full time per discipline for each eight (8) inspectors

Procurement Quality Control Supervisor

One (1) full time if the SUBCONTRACTOR is involved in procurement

Materials/Equipment Receiving Inspection

One (1) Inspector per discipline

Quality Record Controller

One (1) full time per SUBCONTRACTOR

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 33 OF 162

10651-00-QAC-PD-0003

REV.: 01

Construction Discipline

Primary Inspectors (SUBCONTRACTOR)

Pre-Commissioning Inspectors (SUBCONTRACTOR)

Inspection Discipline: Civil / Structural

Bridges/ Buildings

One (1) full time Inspector per twenty- five (25) Carpenters and Ironworkers*

N/A

Interior Design:

One (1) full time Inspector per twenty- five (25) workers*

N/A

Landscaping System

One (1) full time Inspector per twenty- five (25) workers*

N/A

Earth Work / Paving / Fencing / Thrust Boring

One (1) full time Inspector per fifteen (15) earthwork machines or one full time Inspector per fifty (50) laborers*

N/A

Foundation / Concrete

One (1) full time Inspector per twenty- five (25) Carpenters and Ironworkers*

One (1) part time inspector

Steel Structure

One (1) full time Inspector per twenty- five (25) Installers*

One (1) Inspector to be available for every walkthrough package

Batch Plant (Concrete & Asphalt)

One (1) full time Inspector per Batch plant

N/A

U/G Piping (RTR/PVC/ CPVC)

One (1) full time Inspector per fifteen (15) Installers*

One (1) Inspector to be available for each system hydrostatic test.

Plumbing

HVAC

One (1) full time Inspector per twenty- five (25) Installers/ Craftsmen*

One (1) full time Inspector

One (1) full time Inspector per fifteen (15) Installers*

One (1) full time Inspector

Inspection Discipline: Mechanical / Piping

Equipment/ Mechanical

One (1) full time Inspector per fifteen (15) workers*

(1)

One Commissioning

Inspector

during

Piping

One (1) full time Inspector per fifteen (15) workers*

One (1) full time Inspector per 25 (10) hydrostatic workers or packages*

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 34 OF 162

10651-00-QAC-PD-0003

REV.: 01

Construction Discipline

Primary Inspectors (SUBCONTRACTOR)

Pre-Commissioning Inspectors (SUBCONTRACTOR)

Valves Testing

(1)

One full Hydrostatic testing location

time

Inspector per

One (1) full time Inspector

Coatings / Insulations/ Testing

One (1) full time Inspector per three (3) crews per site*

One (1) full time Inspector

Padding/ Lowering/ Bedding and Backfilling

Package Units & Other Mechanical

One (1) full time inspector per site*

N/A

Multidiscipline inspectors as needed* One (1) Lead inspector

Inspection Discipline: Welding

Shop Welding

Field Welding

PMI

One (1) full time Inspector per fifteen (15) Welders*

N/A

One (1) full time Inspector per ten (10) welders *

One (1) Inspector per twenty-five (25) workers

One (1) analysis unit

full

time

technician per

N/A

Heat Treatment

One (1) full time Inspector per ten (10) Heat Treatment technicians*

One (1) part time inspector

NDT Coordinator

One (1) full time NDT coordinator per site and/or fabrication shop

N/A

RTFI

One (1) full time COMPANY certified RTFI

One (1) COMPANY certified RTFI

Inspection Discipline: Electrical/Instrumentation/Communication

Electrical/ Protection

Cathodic

One (1) full time Inspector for every twenty (20) labours/ technicians per site*

One (1) full time Inspector per twenty-five (25) workers*

Instrumentation

One (1) full time Inspector per twenty- five (25) labours and/or three (3) crews*

One (1) full time Inspector per twenty (20) workers*

Safety Relief Valves

One (1) full time inspector per crew

One (1) full time inspector

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 35 OF 162

10651-00-QAC-PD-0003

REV.: 01

Construction Discipline

Primary Inspectors (SUBCONTRACTOR)

Pre-Commissioning Inspectors (SUBCONTRACTOR)

Communication

One (1) full time Inspector per site

One (1) full time Inspector

Notes to the above (Table 1):

  1. If the personnel ratio in Table 1 cannot be met, changes will be submitted to CONTRACTOR for approval.

  2. One (1) Primary Inspector can conduct Earthwork, Foundation, Steel Structure and Thrust Boring inspections when approved by CONTRACTOR.

  3. One (1) Primary Inspector can conduct multiple welding inspections within the same wellhead area when approved by CONTRACTOR

When required by CONTRACTOR, SUBCONTRACTOR shall designate the CONTRACTOR

approved Quality Assurance Coordinator for this Subcontract seven (7) calendar days of the

effective date of the Subcontract. The Quality Assurance Coordinator shall be assigned to

the WORK through Project Completion.

When required by the TABLE 1, SUBCONTRACTOR shall designate the CONTRACTOR

approved Quality Control Manager at

least

thirty

(30) calendar days prior

to

SUBCONTRACTOR’s request to CONTRACTOR to issue the Notice to Proceed or the start

of fabrication (whichever date is earliest). The Approved QC Manager shall be assigned to

the WORK through Project Completion

When required by the TABLE 1, SUBCONTRACTOR shall deploy the CONTRACTOR

Approved Procurement QC Supervisor for the Subcontract within thirty (30) calendar days of

the Effective Date. The Approved Procurement QC Supervision shall be assigned to the

WORK through Project Completion.

CONTRACTOR may assign Quality personnel to multiple Work Authorizations under the

same contract. For the primary contract, CONTRACTOR’s Quality personnel shall be

dedicated to perform quality functions as described in this Schedule “Q” and shall perform no

other function on this Contract.

SUBCONTRACTOR Quality Personnel shall be professionally certified and currently licensed

to practice their assigned occupation, discipline, duties and responsibilities in accordance

with their assigned occupation, discipline, duties and responsibilities in accordance with (a)

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 36 OF 162

10651-00-QAC-PD-0003

REV.: 01

the Subcontract, (b) Mandatory COMPANY Engineering Requirements under SAEP-301, (c)

Saudi Council of Engineers (SCE) registration of accredited engineers and technicians, and

(d) the applicable laws, rules and regulations of Saudi Arabia.

SUBCONTRACTOR candidate knowledge and determination of equivalency of candidate

qualifications, certification and years of related work experience to requirements specified in

this document will be evaluated by CONTRACTOR.

All SUBCONTRACTORS Quality Personnel assigned to the WORK, including, without

limitation, third party agencies and NDT service provider personnel, shall meet the minimum

qualification requirements specified as follows in this document and shall be fully competent

to perform their duties:

Quality Control Manager:

The Site Quality Control Manager is integrated in the Project and has the overall responsibility

for the quality control and inspections of the Construction and Pre-Commissioning Phases,

and reports to the Project Director functionally although hierarchically reports to the Home

Office Quality Assurance Manager and to the Corporate Quality Assurance Manager to

ensure sufficient independency and authority to carry out all quality assurance tasks, and is

responsible for the overall management of the quality functions and quality activities on the

project.

Site Quality Control Manager shall have a university degree or equivalent and a total of seven

(7) years inspection experience or a high school diploma with a total of ten (10) years

inspection experience. As minimum, he shall have five (5) years directly relating to

supervision of construction activities in the Contract Scope of WORK

He has sufficient authority, access to work areas, and organizational freedom, to identify

quality problems, initiate, recommend or provide solutions, and verify the implementation of

the solutions.

Passed an internationally accredited (i.e., IRCA or ASQ) Quality Auditor training course and

examination, or approved equivalent, for the 2015 version of ISO 9001.

Ability to interpret, audit, apply and exercise judgment on capital project construction & Pre-

Commissioning QMS requirements and engineering standards.

Fluent in reading, writing and speaking the English language.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 37 OF 162

10651-00-QAC-PD-0003

REV.: 01

Quality Assurance Coordinator:

Site Quality Assurance Coordinator shall demonstrate knowledge in IS0-9001 or equivalent

and shall be able to exercise judgment against the criteria of the standards. Shall have a high

school graduate or equivalent with a minimum of three (3) years of direct experience in

Quality Management system activities relating to the Contract Scope of WORK.

The Site Quality Assurance Coordinator has sufficient authority, access to work areas, and

organizational freedom, to identify quality problems, initiate, recommend or provide

solutions, and verify the implementation.

Ability to interpret, audit, apply and exercise judgment on capital project QMS requirements

and engineering standards.

Fluent in reading, writing and speaking the English language.

Main work responsabilities are:

• Monitor and report Project Quality KPI’s through each phase

• Quality reports preparation.

• Follow and monitoring the Project Quality Assurance processes including audits,

reviews, etc., in order to ensure that project objectives are met.

• Ensure follow up for an appropriate close out of all Quality action items.

• Ensure quality documentation and quality procedures is compiled and completed in a

timely matter and meeting deadlines.

• Follow up the implementarion of corrective actions from NCRs to ensure the closure

of the NCRs before the approved completion date.

• Follow up of the implementation of the surveillance and training programs to ensure

quality processes are well implemented.

• Coordinate the project internal audits to ensure their performance according to the

Project Requirements.

• Ensure the correct progression of final Quality project records books.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 38 OF 162

10651-00-QAC-PD-0003

REV.: 01

Nondestructive Testing (NDT) Personnel:

All SUBCONTRACTOR, Sub-SUBCONTRACTOR, Vendor personnel responsible for (a)

performing NDT operations, (b) interpreting or reviewing test results, and (c) otherwise

ensuring or auditing NDT operations shall be evaluated, certified and qualified to

requirements specified in COMPANY specification SAEP-1142. All NDT personnel shall hold

current COMPANY recognized NDT certificates as specified below:

NDT Level III Personnel under SAEP-1142:

Currently certified to Level III by either ASNT or an equivalent, internationally recognized,

COMPANY approved certification program in the NDT method(s) required by the Subcontract

scope of WORK.

Currently certified by the Employer to Level II techniques in accordance with ANSI/ASNT CP-

189 and SAEP-1142, if the Level III employee will directly perform any test or interpret any

NDT results (see Paragraph 1.4.5).

Evaluated and approved to perform Level III responsibilities including, but not limited to:

NDT method application;

Interpretation of NDT results if he fulfills the requirements described in this document;

Interpretation of codes and standards;

Preparation and approval of NDT procedures prior to submittal to CONTRACTOR for

approval;

Establish and approve contactor NDT certification program and,

Training of Level I and Level II NDT personnel.

SUBCONTRACTOR, Third-Party and Vendor NDT Level III personnel shall be currently

certified in NDT methods required by the relevant scope of WORK, such as Visual and Optical

Testing (VT), Radiographic Testing (RT), Ultrasonic Testing (UT), Magnetic Particle Testing

(MT), and Liquid Penetrant Testing (PT).

SUBCONTRACTOR shall ensure NDT Level III personnel (employees and consultants) have

no direct or indirect affiliation or relationship with Sub-SUBCONTRACTOR, specifically

including Sub-SUBCONTRACTORs, Third-Parties, Inspection and Testing Agencies and

NDT Service Providers deployed on the Project.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 39 OF 162

10651-00-QAC-PD-0003

REV.: 01

SUBCONTRACTORS with two or more CONTRACTOR approved NDT Level III personnel

assigned to the WORK shall designate one SUBCONTRACTOR employee or consultant as

the Principal NDT Level III in accordance with SAEP-1142.

SUBCONTRACTOR, including NDT Service Provider and Vendor NDT personnel performing

NDT or evaluating NDT results shall be examined by CONTRACTOR in the NDT methods

and techniques required by the relevant scope of WORK.

SUBCONTRACTOR, NDT Service Provider and Vendor NDT personnel working in-Kingdom,

and performing, interpreting or influencing the results of RT Film Interpretation (RTFI), MUT

or AUT under the Subcontract, shall be tested, approved and certified by CONTRACTOR

under SAEP-1142.

SUBCONTRACTOR, NDT Service Provider and Vendor NDT personnel working out-of-

Kingdom, and performing, interpreting or influencing the results of NDT under the

Subcontract, shall be certified by an internationally recognized scheme with a minimum of

five years of experience in the method and technique.

SUBCONTRACTOR NDT Coordinator:

Currently certified by the candidate’s Employer to Level II, under ANSI/ASNT CP-189 and

SAEP-1142, in two or more of the NDT methods and techniques required by the relevant

scope of WORK.

Twelve (12) or more years of direct work experience in NDT and welding inspection of

industrial capital projects quality.

Documented recent experience in the coordination of two or more NDT Service Providers on

industrial construction jobsites.

Third-Party Civil Engineering Testing Laboratories, Geotechnical Design Offices, Concrete

Batch Plants and Precast Concrete Manufacturing Plants under SAEP-383: All Third-Party

organization engineers and technicians responsible for (a) performing civil and geotechnical

testing, (b) interpreting or reviewing test results, and (c) otherwise ensuring or auditing civil

and geotechnical testing shall be evaluated, certified and qualified to CONTRACTOR

requirements specified in this document and SAEP-383. All Third-Party engineers and

technicians shall hold current, COMPANY issued credentials where specified in SAEP-383.

SUBCONTRACTOR must designate an NDT Coordinator (if apply) a minimum of thirty (30)

days prior to the start of welding. NDT Coordinator position is considered as Key personnel,

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 40 OF 162

10651-00-QAC-PD-0003

REV.: 01

CONTRACTOR reserve the right to request to the SUBCONTRACTOR to replace the NDT

Coordinator if the NDT backlog is not controlled after to apply an NDT action plan. The new

NDT coordinator needs also the CONTRACTOR approval.

QC Supervisor:

Internationally recognized university, four (4) or five (5) year Bachelor degree in an

engineering discipline, with seven (7) or more years of direct work experience in inspection

of capital projects quality, ISO 9001 QMS requirements, activities and resources for

construction & pre-commissioning of materials and equipment or high school diploma with

twelve (12) or more years of direct work experience in inspection of capital projects quality,

ISO 9001 QMS requirements, activities and resources for construction & Pre-Commissioning

of materials and equipment.

Three (3) or more years of direct work experience in QC supervision of capital project

construction & Pre-Commissioning quality related to the engineering discipline and scope of

WORK (e.g., industrial oil and gas production or petrochemical projects).

Passed an internationally accredited (i.e., IRCA or ASQ) Quality Auditor training course and

examination, or approved equivalent, for the 2015 version of ISO 9001.

Proficient in reading, writing and speaking the English language.

Demonstrated mastery of ISO 9001 QMS requirements, engineering and design documents,

engineering standards, material specifications, construction methods and QC inspection and

test procedures in one or more inspection disciplines as specified in this section.

Procurement Quality Control Supervisor:

University degree or equivalent and seven (7) years inspection experience or a high

school diploma with ten years inspection experience with a minimum of three (3) years

directly relating to supervision of vendor inspection activities in the Contract Scope of

WORK (e.g.; oil, gas and petrochemical projects, Infrastructure, communication).

Senior QC Inspectors:

High school diploma with ten (10) or more years of direct work experience in a specific

inspection discipline, performing QC inspection and testing of industrial project materials,

equipment, systems and facilities under construction and pre-commissioning.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 41 OF 162

10651-00-QAC-PD-0003

REV.: 01

Five (5) or more years of direct work experience performing QC inspection and testing related

to the scope of WORK (e.g., industrial oil and gas production or petrochemical projects).

Proficient in reading, writing and speaking the English language.

Demonstrated mastery of the 2015 version of ISO 9001 QMS requirements, engineering and

design documents, engineering standards, material specifications, construction methods and

QC inspection and test procedures in one or more inspection disciplines as specified in

Paragraph 3.6 of this Attachment I.

With minimal supervision, performed a variety of document review, inspection and testing

functions to verify SUBCONTRACTOR compliance with Subcontract requirements.

QC Inspectors:

High school diploma with six (6) or more years of direct work experience, in the specific

engineering discipline(s), performing QC inspection and testing of industrial project materials,

equipment, systems and facilities under construction and Pre-Commissioning.

Three (3) or more years of direct work experience performing QC inspection and testing

related to the scope of WORK (e.g., industrial oil and gas production or petrochemical

projects).

Proficient in reading, writing and speaking the English language.

Demonstrated thorough knowledge and understanding of the 2015 version of ISO 9001 QMS

requirements, engineering discipline drawings, standards, material specifications,

construction methods and QC inspection and test procedures in one or more inspection

disciplines as specified in this document.

With minimal supervision, performed a variety of document review, inspection and testing

functions to verify SUBCONTRACTOR compliance with Subcontract requirements.

Assistant QC Inspectors:

Citizen of Saudi Arabia with an internationally recognized university, four (4) or five (5) year

Bachelor degree in an engineering discipline, and no work experience or citizen of Saudi

Arabia with a COMPANY approved vocational college or technical school, two (2) or three

(3) year diploma or associate degree in an engineering or inspection discipline and two (2)

or more years of direct work experience in a specific inspection discipline, performing QC

inspection and testing of industrial project materials, equipment, systems and facilities under

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 42 OF 162

10651-00-QAC-PD-0003

REV.: 01

construction and Pre-Commissioning or citizen of Saudi Arabia with a high school diploma

and three (3) or more years of direct work experience in a specific inspection discipline,

performing QC inspection and testing of industrial project materials, equipment, systems and

facilities under construction and Pre-Commissioning.

Proficient in reading, writing and speaking the English language.

Demonstrated fundamental awareness and basic understanding of the 2015 version of ISO

9001 QMS requirements, engineering discipline standards, material specifications,

construction methods and QC inspection and test procedures in an inspection discipline as

specified in Paragraph 3.6 of this Attachment I.

With training, development and close supervision, performed a variety of document review,

inspection and testing functions to identify deviations from Contract requirements.

QC Supervisors and Inspectors shall be evaluated, certified and qualified to all minimum

requirements in one or more inspection disciplines, as follows:

Welding QC and Non-Destructive Testing (NDT) Inspector:

Currently certified by either (1) AWS as a CWI, or (2) TWI CL as a CSWIP 3.1 WI, or (3) an

approved equivalent certification level and scheme.

Direct work experience and demonstrated thorough knowledge of engineering codes and

standards with welding and testing requirements required for the WORK, such as

ANSI/ASME B31.3, B31.4 & B31.8; ASME BPVC (Sections V and IX); API 620, API 650 and

AWS D1.1.

Where NDT forms part of the WORK, currently certified by the Employer to a minimum of

Level II under ASNT SNT-TC-1A and ANSI/ASNT CP-189 in the relevant test methods and

techniques to be performed, reviewed or assured (i.e., VT, MT, PT, RT and/or UT).

Where NDT forms part of the WORK, certified by COMPANY under SAEP-1142 to perform,

review or otherwise ensure RTFI.

Mechanical QC Inspector:

Currently certified by API to API 653 and API 510.

Direct work experience and thorough knowledge of static and rotating mechanical equipment,

commodities, materials construction, Pre-Commissioning and quality activities required for

the WORK.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 43 OF 162

10651-00-QAC-PD-0003

REV.: 01

Demonstrated thorough knowledge of Work-related engineering codes and standards, such

as ASTM, API, IEC, NEMA, UL, FM, NFPA, ASME BPVC (Sections I, V, VIII and IX);

ANSI/ASME B31.3, B31.4, B31.8 and B73; NACE SPs, API 620, API 650 and AWS D1.1.

Demonstrated thorough knowledge of mechanical process systems inspection and testing;

procedures, tools and test equipment used in receiving, storage, fabrication, erection,

construction and Pre-Commissioning of steam & combustion turbines, diesel engines,

pumps, compressors, motors & generators, mixers & agitators, fans, gearboxes, firewater

pumps & motors, auxiliary cooling & lubrication systems, packaged process equipment, pipe,

pipe fittings, valves, pressure vessels, fired heaters, tanks, structural steel, hot/cold insulation

and other equipment and commodities as required for the WORK.

Heat Treatment QC Inspector:

Direct work experience and full knowledge of all aspects of heat treatment; methods,

techniques, tools and quality activities required for the WORK.

Demonstrated thorough knowledge of WORK-related engineering codes and standards with

heat treatment requirements, such as ANSI/ASME B31.3 and ASME BPVC (Section VIII,

Division 1).

Direct experience in the review and verification of heat treatment work procedures and

parameters.

Positive Materials Identification (PMI) QC Inspector:

Direct work experience and demonstrated full knowledge of all aspects of PMI testing;

methods, techniques and operation of test equipment required for the WORK.

Trained and certified by the manufacturer(s) of PMI test equipment to be operated.

Civil QC Inspector:

Direct work experience and thorough knowledge of all aspects of civil, structural and

architectural (C/S/A) engineering systems, equipment, commodities, materials and quality

activities required for construction and Pre-Commissioning of the WORK.

Demonstrated thorough knowledge of WORK-related engineering codes and standards with

C/S/A requirements, such as ICC IBC, API, NFPA, ACI, AASHTO, ASTM, ASCE 7, BS 4550,

BS 1744-1, SASO, AISI, AISC and AWS D1.1.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 44 OF 162

10651-00-QAC-PD-0003

REV.: 01

Demonstrated thorough knowledge of C/S/A inspection and testing; procedures, tools and

test equipment used in soil preparation & earthwork; pile foundations; Portland cement

concrete foundations, structures & retaining walls; structural steel; building masonry,

interiors, finishes & roofing systems; asphalt concrete roadways and other materials and

commodities as required for the WORK.

Interior Design Inspector

Inspector shall be graduate of BS Architecture or Interior Design major in field of Interior

Designing and shall have eight (8) years of documented experience in the field of interior

design inspection for the required specific application. He shall be able to demonstrate a

thorough working knowledge of standards codes, such as IBC, ASTM, ACI, American

Architectural Manufacturers Association

(AAMA), National Structural Steelwork

Specification for Building Construction (NSSSBC), American National Standards Institute

(ANSI) as required by the scope of the contract related to inspection of interior design

and its components, such as material finishing and installation methods to include marble

work, tile work, woodwork, wall coverings, paints and special coatings, fixtures and

fittings installation (kitchens and bathrooms), hardware, lighting fixtures, furniture and

electrical fittings, curtain and etc. He shall be able to interpret and assess interior design

packages to ensure compliance with the contractual requirements.

Landscaping System:Inspector

Inspector shall be graduate of BS Architecture major in field of Landscaping Systems

and shall have eight (8) years of documented experience in the field of Landscaping

System inspection for the required specific application. He shall be able to demonstrate

a thorough working knowledge of international codes such as Time- Saver Standards for

Landscape Architecture, IBC, ASTM, ACI, American Architectural Manufacturers

Association

(AAMA), National Structural Steelwork Specification

for Building

Construction (NSSSBC), American National Standards

Institute (ANSI), ASTM

International Standards on Sustainability in Buildings and standards related to inspecting

Landscaping System and its components, involving irrigation systems, planting, and

playground equipment, He shall be able to interpret and assess Landscaping System

packages to ensure compliance with the contractual requirements.

Batch Plant, & Precast / Prestressed Concrete Plant QA/QC Inspector:

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 45 OF 162

10651-00-QAC-PD-0003

REV.: 01

Currently certified by ACI as a Concrete Field Testing Technician - Grade I.

Direct work experience and thorough knowledge of all aspects of asphalt and Portland

cement concrete; design, materials, mixing, manufacture, delivery and quality required for

construction and Pre-Commissioning of the WORK.

Demonstrated thorough knowledge of WORK related engineering codes and standards with

plant and QC laboratory requirements, such as ISO 17025, ICC IBC, ACI, PCI, AASHTO and

ASTM.

Demonstrated thorough knowledge of review, inspection and testing; procedures, tools and

test equipment used in the selection, testing & weighing of mix materials; mixing, product

reinforcement, casting & curing, transport, delivery & placement of concrete required for the

WORK.

Qualified to assess plant QC equipment, personnel (both inspectors and lab technicians),

procedures, techniques, records and results for compliance with applicable standards.

Qualified to evaluate plant capacity, capability and safety against CONTRACTOR

requirements.

Coating QC Inspector:

Currently certified to SAEP-316 Level II by (1) NACE as CIP, or (2) SSPC as PCI, or (3) TWI

CL as BGAS-CSWIP, or (4) an Approved equivalent certification scheme required for the

WORK.

Training, direct work experience and demonstrated thorough working knowledge of coating

materials, application methods, quality activities and recognized engineering codes and

standards required for the WORK, such as ASTM, ISO, NACE SPs and SSPC SPs.

Plumbing/Fire Protection QC Inspector:

Direct work experience and full knowledge of all aspects of industrial plumbing and fire

protection systems; equipment, materials and quality activities required for construction and

Pre-Commissioning of the WORK.

Demonstrated thorough knowledge of WORK related engineering codes and standards with

plumbing and fire protection requirements, such as ASTM, IAPMO UPC; ICC IBC & IFC;

NFPA 13, 14, 15, 20, 22, 24, 25 & 291; UL, API, AWWA and ANSI/ASME B31.9.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 46 OF 162

10651-00-QAC-PD-0003

REV.: 01

Demonstrated thorough knowledge of plumbing and fire protection systems inspection and

testing; procedures, tools and test equipment used in receiving, storage, fabrication,

construction and Pre-Commissioning of industrial plant and building potable water, oily

wastewater, sanitary sewer, storm water, firewater and other systems, equipment and piping

as required for the WORK.

HVAC QC Inspector:

Direct work experience and full knowledge of all aspects of HVAC systems; design,

equipment, materials and quality activities required for construction and Pre-Commissioning

of the WORK

Demonstrated thorough knowledge of WORK related engineering codes and standards with

HVAC requirements, such as IAPMO UMC, NFPA 90A, ASHRAE, SMACNA, NEBB, AMCA

99, ACGIH IVM; ANSI/ASME B31.5, B31.9 & B73.1; and UL 181A/B.

Demonstrated thorough knowledge of HVAC systems inspection, testing and balancing;

procedures, tools and test equipment used in receiving, storage, fabrication, construction and

Pre-Commissioning of industrial process and building heating, ventilation, exhaust,

refrigeration air conditioning, hydronics, insulation, fuel gas and other systems, equipment

and piping as required for the WORK.

Lifting Equipment & Crane QC Inspector:

Direct work experience and full knowledge of all aspects of lifting equipment, cranes and

elevators; equipment, materials, quality and safety activities required for construction and

Pre-Commissioning of the WORK.

Demonstrated thorough knowledge of WORK related engineering codes and standards with

crane and lifting requirements, such as CMAA, ANSI/ASME A17.1 & 17.2; and ANSI B30.1

through B30.16.

Demonstrated thorough knowledge of lifting systems inspection and testing; procedures,

tools and test equipment used in receiving, storage, fabrication, construction and Pre-

Commissioning of industrial plant and building hoists, overhead cranes (monorail, bridge,

gantry, etc.), elevators (equipment and personnel) and other systems and equipment as

required for the WORK.

Electrical QC Inspector:

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 47 OF 162

10651-00-QAC-PD-0003

REV.: 01

Currently certified by COMPANY Industrial Training Department as a Power Cable Splicer

for inspection of WORK under GI 2.705 scope.

Direct work experience and full knowledge of electrical equipment, materials and quality

activities required for construction and Pre-Commissioning of the WORK.

Demonstrated thorough knowledge of WORK related engineering codes and standards, such

as ANSI/IEEE, ANSI/NEMA, SBC 401 (IEC 60364), IEC 60079 (IECEx scheme); API RP 500

& 505; ANSI/NFPA 30, 59, 70 (NEC), 70E, 496, 497 & 780; SASO/IEC, UL, ASTM, IESNA

and NACE.

Demonstrated full knowledge of inspection and testing; procedures, tools and test equipment

used in receiving, storage, fabrication, construction and Pre-Commissioning of substations,

transformers, switchgear, controlgear, power electronics, motors, generators, insulated

cable, raceway, lighting, lightning protection, cathodic protection, power protection relays and

other equipment and commodities as required for the WORK.

Communications QC Inspector:

Direct work experience and full knowledge of communications and data systems, equipment,

materials and quality activities required for construction and Pre-Commissioning of the

WORK.

Demonstrated thorough knowledge of WORK related engineering codes and standards, such

as BICSI TDMM & OSPDRM; ANSI/NFPA 70 (NEC), 70E & 496; ITU-T, EIA/TIA, ANSI/IEEE,

ANSI/NEMA, SBC 401 (IEC 60364), IEC 60079 (IECEx scheme); API RP 500 & 505;

SASO/IEC, UL and ASTM.

Demonstrated full knowledge of quality inspection and testing; procedures, tools and test

equipment used in receiving, storage, fabrication, construction and Pre-Commissioning of

electronic equipment, outside plant (OSP) systems, premises distribution systems (PDS), RF

antenna, RF waveguide, fiber optic cable, insulated copper cable, raceway, lightning

protection, grounding, DC power and other equipment and commodities as required for the

WORK.

Instrumentation QC Inspector:

Direct work experience and full knowledge of industrial process instrumentation and control

systems and quality activities required for acceptance, construction and Pre-Commissioning

of the WORK.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 48 OF 162

10651-00-QAC-PD-0003

REV.: 01

Demonstrated thorough knowledge of WORK related engineering codes and standards, such

as ASTM, AGA, API, ANSI/ASME B16, ANSI/ISA, ANSI/FCI, SAMA, ISO/NACE, SBC 401

(IEC 60364), IEC 60079 (IECEx scheme), ANSI/NFPA 30, 59, 70 (NEC), 70E, 72 (NFAC),

496, 497 & 780, ANSI/IEEE 1100, ANSI/NEMA, SASO/IEC, UL, ITU-T, EIA/TIA EIA/RS-455

and BICSI TDMM & OSPDRM.

Demonstrated full knowledge of inspection and testing; procedures, tools and test equipment

used in acceptance, receiving, storage, fabrication, construction and Pre-Commissioning of

process instruments & analyzers, control valves & actuators, safety relief valves; intrinsically

safe systems; data display, meters, annunciation & recording devices; process control

systems such as ESD, DCS, PLC & SCADA/RTU; fire detection and alarm systems, tubing

and tube fittings, fiber-optic cable; metallic control, signal and data cable; IECEx cable fittings,

cabinets, raceway and other equipment and commodities as required for the WORK.

Cathodic Protection QC Inspector:

Currently certified by NACE as a Level 2 Cathodic Protection Technician.

Direct work experience and full knowledge of Cathodic Protection (CP) equipment, materials

and quality activities required for construction and Pre-Commissioning of the WORK.

Demonstrated thorough knowledge of WORK related engineering codes and standards, such

as NACE; ANSI/NFPA 70 (NEC), 70E, 496 & 497; ANSI/IEEE, ANSI/NEMA, SBC 401 (IEC

60364), IEC 60079 (IECEx scheme); API RP 500 & 505; SASO/IEC, UL and ASTM.

Demonstrated full knowledge of CP inspection and testing; procedures, tools and test

equipment used in receiving, storage, fabrication, construction and Pre-Commissioning of

impressed current and galvanic CP systems for marine structures, pipelines, tanks, pressure

vessels, plant foundations and facilities as required for the WORK. CONTRACTOR shall

review, verify and submit legible resumes, certificates and credentials for all proposed

SUBCONTRACTOR Quality Personnel to CONTRACTOR, for review and approval at least

thirty (30) calendar days prior to the start of WORK for each individual. CONTRACTOR has

the right to interview and/or test all proposed personnel. CONTRACTOR shall have the right

to reject SUBCONTRACTOR quality Personnel that do not comply with the requirements in

section 4.5.7. of this document or if CONTRACTOR has had prior poor experience with such

candidates.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 49 OF 162

10651-00-QAC-PD-0003

REV.: 01

SUBCONTRACTOR may subcontract inspection services, subject to CONTRACTOR review

and approval.

Personnel performing work affecting quality shall be familiar with SUBCONTRACTOR Quality

Manual or Quality Plan and in particular with quality system procedures, working procedures,

inspection and tests methods and related applicable acceptance criteria.

CONTRACTOR shall be the final authority for the determination of equivalency for all

SUBCONTRACTOR qualifications, certifications, or experience of SUBCONTRACTOR

QA/QC proposed personnel.

Organization

SUBCONTRACTOR shall assign or

require

its SUBCONTRACTOR

to assign,

CONTRACTOR approved quality personnel to the WORK, in accordance with contract

requirements and the established above it in this document.4.2.1 Table 1

SUBCONTRACTOR´s inspectors shall be able to write, speak and be fluent in the official

language of the Project. They shall be able to understand and follow the specifications and

codes of the project.

Sufficient number of QC personnel for adequate coverage of QC activities shall be ensured

by the SUBCONTRACTOR. The SUBCONTRACTOR shall have an independent QC

organization within its overall company organization with sufficient resources to verify,

perform tests and inspections of the works. The SUBCONTRACTOR shall provide details of

organization, including the ratios of QC staff to construction staff for each discipline together

with all QC personnel resumes for CONTRACTOR’s approval before commencement of

construction.

Upon written approval of the CONTRACTOR representative, inspectors may be qualified to

inspect more than one discipline; in this case, however, he may not fulfil more than one full

time position at any time.

Each workplace must have competent personnel to supervise the work. Welding inspectors,

paint experts, non-destructive testing personnel, and others will be defined in advance and

proposed for CONTRACTOR’s approval. In case of not having competent personnel for these

functions, these personnel will be supplied by the CONTRACTOR discounting the

corresponding amount of the SUBCONTRACT.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 50 OF 162

10651-00-QAC-PD-0003

REV.: 01

With appropriate justification, CONTRACTOR reserves the right to order a replacement for

the assigned SUBCONTRACTOR personnel when the duties and responsibilities are not

partially/fully covered according to CONTRACTOR criterion. In no case will there be

discussions about a person’s replacement request.

IMPORTANT NOTE

If it is required by CONTRACTOR: a Quality Lead (provided by CONTRACTOR) will be

established at the SUBCONTRACTOR offices, in order to coordinate and expedite the

documentation relating to the Test Packages. SUBCONTRACTOR will facilitate a physical

place at his installations and the access to the necessary documentation related on the

Hydrostatic Test process.

In the same way, if it is required by CONTRACTOR a QC Workshop Prefabrication Lead

(provided also by CONTRACTOR) will be established at the SUBCONTRACTOR

Prefabrication Workshop, in order to coordinate and expedite the activities relating to the

Piping prefabrication. SUBCONTRACTOR will facilitate a physical place at his installations

and the access to the necessary documentation related on the prefabrication of piping.

Any QAQC SUBCONTRACTOR personnel can be mobilized/ established at

the

CONTRACTOR offices if the CONTRACTOR QAQC Manager considers beneficial for better

communication in the project, for instance SUBCONTRACTOR RT coordinator to have

access to the RT P.C.A. information in real time or Hydrotest Coordinator to reduce the time

to release the test packs.

CONTRACTOR shall be the final authority for the determination of equivalency for all

qualifications, certifications, or minimum number of years of experience as specified in this

document, upon successful completion of required examinations and/ or interviews.

Personnel Mobilization and Demobilization

SUBCONTRACTOR QA/QC personnel must be mobilized in a timely manner consistent with

the construction activities and to ensure the required coverage at all times.

Within thirty (30) days following the CONTRACTOR’s issuance of Notice to Proceed,

SUBCONTRACTOR shall submit to the CONTRACTOR Representative a roster of all

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 51 OF 162

10651-00-QAC-PD-0003

REV.: 01

SUBCONTRACTOR Quality Personnel, sorted by discipline and position, including personnel

identified to be:

• Mobilized in the next sixty (60) days.

• Demobilized in the next sixty (60) days.

The roster shall be routinely updated and resubmitted as an attachment to the monthly

Quality Management Reports.

CONTROL OF CONSTRUCTION ACTIVITIES

Kick-Off Meeting

Prior to start of any Work, CONTRACTOR will initiate a Kick-Off Meeting with all the

SUBCONTRACTORS to ensure the full understanding of the requirements and the execution

and control of the Work.

cInspection and Test Plans. SAUDI ARAMCO Inspection and Test Plans (SATIPs) and Inspection Procedures.

All stages of Construction shall be controlled using ITP/SATIPs detailing the quality

verification performed by SUBCONTRACTOR QA/QC Organization with allowance for

CONTRACTOR surveillances/witness interventions.

SUBCONTRACTOR adoption and use of COMPANY SATIPs and SAICs shall not release

SUBCONTRACTOR from any obligations under SAEP-301 standards and the Subcontract.

Prior to the commencement of any work, SUBCONTRACTOR shall ensure the availability of

required quality documentation, records, applicable procedures, ITPs/ SATIPs and relevant

documentation such as drawings, standards, codes, etc.

SUBCONTRACTOR will use the CONTRACTOR approved ITPs/ SATIPs. If there are other

SUBCONTRACTORS that will perform the same activities as this first SUBCONTRACTOR,

those new SUBCONTRACTORS will adhere to these ITPs by written.

In case that any ITP need to be developed by SUBCONTRACTOR, SUBCONTRACTOR

shall no commence WORK prior to CONTRACTOR approval of the applicable ITP.

At least thirty (30) days prior to the start of any construction activities, SUBCONTRACTOR

must submit to CONTRACTOR for review and approval a detailed ITP along with related

procedures/instructions for all constructions activities to be executed by SUBCONTRACTOR.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 52 OF 162

10651-00-QAC-PD-0003

REV.: 01

Each ITP shall include quality requirements and shall detail all review, witness and hold point

for SUBCONTRACTOR as specified in the Subcontract, CONTRACTORS Procedures and

in the COMPANY Standards.

As a minimum, each ITP must include the following information:

• Process description with phases for planning, material receiving / storage, fabrication

/ installation, Pre-Commissioning, Mechanical Completion and acceptance.

• QC requirements for each phase and quality activity.

• Notification requirements for SUBCONTRACTOR “Requests For Inspections” (RFI)

issued to CONTRACTOR (see section 4.5.2 Request for inspection).

• Roles and responsibilities for scheduled document review, inspection and testing.

• Applicable work instructions and quality procedures.

• Contract acceptance criteria (i.e., COMPANY and International Industry Standards).

• Percentage of construction and Pre-Commissioning activities to be reviewed,

witnessed, inspected and tested by SUBCONTRACTOR quality personnel (review,

witness and hold points; including increased levels when quality performance

requirements are not met.)

• Percentage of SUBCONTRACTOR inspection and testing activities to be performed

or witnessed by CONTRACTOR (classified as Review, Witness or Hold points).

• Quality records and verifying documents.

An example of ITP (when applicable) form is shown as template 01 of this document.

The numbering of the Inspection and Test Plans shall be defined by CONTRACTOR.

SUBCONTRACTOR shall prepare an Inspection and Tests Status Log. Status of all

inspection and testing shall be maintained throughout the Mechanical Completion activities.

Where CONTRACTOR has concerns over the quality of Works, it shall have the right to re-

test. Where Works are covered over, the re-test shall include removal of covering. No work

shall be covered up without the approved ITP intervention points being documented closed.

Use of SATIPs and SAICs does not relieve SUBCONTRACTOR from his obligation to meet

all COMPANY Engineering Standards and other requirements.

The Work is designed and will be completed per Systems. Before offering any System

Mechanical Completion the SUBCONTRACTOR shall ensure that construction of all parts,

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 53 OF 162

10651-00-QAC-PD-0003

REV.: 01

components and items of the system are completed, fully punched out, and that all require

QC Forms are issued and signed off in compliance with the applicable SATIPs (or approved

ITPs if applicable).

SATIPS or ITP Implementation

SUBCONTRACTOR shall ensure all works necessary for the preparation and performance

of inspections, examinations and tests, including equipment, tools (i.e., pressure gauges,

temperature measuring equipment, NDE equipment, measuring device, etc.), scaffolding and

protection to enable CONTRACTOR representatives to safely witness the activities.

SUBCONTRACTOR shall issue inspections, examinations and tests reports immediately

after the completion of each activity (see 4.5.2 Request for Inspection). All reports shall be

approved by the SUBCONTRACTOR QA/QC approved personnel prior submittal to

CONTRACTOR for review or approval. The signature of CONTRACTOR or other Parties on

the inspection, examination and test documents (certificates, records, etc.) does not release

the SUBCONTRACTOR from its responsibilities.

SUBCONTRACTOR shall make available to CONTRACTOR the applicable international

standards/codes and Project Standards, Specifications or Procedures required for the

execution and validation of inspection, examination and tests.

When local laws apply, SUBCONTRACTOR shall be responsible to comply with all

mandatory regulations and provide relevant certification to the full satisfaction of local

authorities.

Control Forms (QC Forms) or SAICs

SUBCONTRACTOR shall issue all control forms/inspection checklist Unless otherwise

agreed, the above reports shall be prepared using forms included in the approved ITP(s).

SUBCONTRACTOR shall submit to CONTRACTOR for approval all new control forms prior

to include them in ITP(s) or SATIPs for site implementation.

Control Forms or SAICs shall be filled up with all information required to record the details of

the activity performed and to ensure the required traceability. For this purpose Control Forms

shall contain all information indicated in the template title blocks, as well as traceability and

numbering information and data relevant to register, inspection or test performed such as but

not limited to:

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 54 OF 162

10651-00-QAC-PD-0003

REV.: 01

•

Inspection checklist;

• Test details and condition;

• Applicable parameters;

• Reference acceptance criteria;

• Tolerances;

• Test results and/or evaluation;

• Explanatory notes if necessary (e.g., reference to previous records in the case of

unsuccessful previous tests);

• Test date;

The numbering of the Inspection and Test Reports shall be defined by SUBCONTRACTOR

and CONTRACTOR

SUBCONTRACTOR completes the Control Forms in all its parts, marking with N/A any items

which are not applicable. SUBCONTRACTOR shall sign off and obtain CONTRACTOR

representatives signature on Control Forms when required.

SUBCONTRACTOR shall distribute copies of reports to all signatory and provide for an

orderly collection, filing and distribution of all reports and prepare quality records for final

documentation hand over.

Unless otherwise instructed by CONTRACTOR, the original copy of each Control Forms shall

be submitted to CONTRACTOR.

SUBCONTRACTOR shall provide detailed information of the all Control Forms in a proven

electronic database referencing the appropriate ITP and certification. The records retention

systems must enable the identification, retention and retrieval of all Control Forms at all times.

SUBCONTRACTOR shall provide detailed information of the proposed system.

SATIPs (or approved ITPs if applicable) List

The following list is only a preliminary example. The actual list will be updated, separately

from this list, during the execution of the project to include all project activities and works.

• Civil SATIPs or ITPs

o Piling Installation

o Excavation and Backfilling

o Reinforcement steel, embedded elements, anchor bolts and formwork

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 55 OF 162

10651-00-QAC-PD-0003

REV.: 01

o Structural Concrete & Grouting Works

o Steel Structure erection

o Underground piping installation (RTR Work)

o Building Works

o Painting on surface concrete

o Asphalt Paving

o Precast- Prestressed concrete

o Epoxy Grout for Machinery Support

o Fire proofing concrete

o Structural Steel for buildings

o HVAC installation and testing

o Emergency Eyewash Shower/Shower System

o Gravity Sewer Piping and Sewer Manhole

• Mechanical SATIPs or ITPs

o Piping Prefabrication

o Piping erection and installation

o Fire Piping System

o Tanks Assembly

o Static Equipment Installation

o Rotating Equipment Installation

o Coating and Lining

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 56 OF 162

10651-00-QAC-PD-0003

REV.: 01

o External & Internal FBE

o

Insulation

o Refractory Installation

o Welding Structural steel and miscellaneous steel supports

o Post Weld Heat Treatment & Associated Hardness Testing

o Gasket Installation

o Gap Control Verification

• Electrical SATIPs or ITPs

o Power Transformer Installation

o Cable tray installation

o

Installation of lighting System

o AC UPS system

o DC current system

o Cables installation (LV, MV, HV, VHV as applicable)

o Above / Bellow grade Conduits installation

o HVAC Equipment

o Electrical Heat Tracing

o Grounding/ Bonding

o Motors LV & HV

o Cranes, Hoists and Elevators

o Fire Water Pump / Motor / Controller

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 57 OF 162

10651-00-QAC-PD-0003

REV.: 01

o LV Panel boards

o Factory Assembled (Packaged) Auxiliary Electrical Equipment

o Cathodic protection

o Cable gland / seal & Conduit seal installation Procedure & ITP

o Electrical Power Energization

•

Instrumentation and Communications SATIPs or ITPs

o

Instrument installation (Flow, pressure, temperature, level)

o

Instrumentation piping and tubing

o Electronic control system – DCS, PLC, ESD

o Fire Detection and Alarm Systems

o

Instrument Control Loop Checking

o Fiber Optic Cable Installation

o

Instrumentation Racks and Panels (Open); Terminal Boxes and Instrument

Cabinets (Enclosed)

o Communications Systems

o Fire Detection and Alarm Systems

o Fiber Optic Communications Cable

Management of Non-Conformances

SUBCONTRACTOR is responsible for the identification of non-conforming material and/or

workmanship on Construction and Inspection activities during the Work and shall notify to

CONTRACTOR any deviation from applicable procedures, standards and any other

applicable contractual requirements.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 58 OF 162

10651-00-QAC-PD-0003

REV.: 01

SUBCONTRACTOR shall plan, issue and submit a Non-Conformance and Corrective Action

Procedure including the above documentation, to CONTRACTOR for review, comment and

approval within thirty (30) days after Subcontract award.

SUBCONTRACTOR procedures must describe the requirements for evaluating the need for

actions to prevent occurrence of potential non-conformances and for the implementation of

applicable lessons learned from previous projects.

SUBCONTRACTOR Quality Management shall be delegated the unequivocal authority and

have direct access to SUBCONTRACTOR Senior Management to stop any works that are

non-conforming.

SUBCONTRACTOR must record all non-conformances to Subcontract requirements, Quality

Plans,

ITPs, and procedures. SUBCONTRACTOR shall

forward

records of all

non-conformances to CONTRACTOR within twenty-four (24) hours of issue, including

proposed corrective action.

SUBCONTRACTOR shall

initiate corrective actions

to prevent

recurrence of

non-conformances a maximum of five (5) days from the issue date of the non-conformance.

SUBCONTRACTOR

shall

provide CONTRACTOR with

an

explanation

for

non-conformances that will require more than ten (10) days to resolve.

SUBCONTRACTOR shall maintain a summary of the status of all non-conformances. Shall

be issued to CONTRACTOR after the first non-conformance is issued, and weekly basis the

subsequent submittals to CONTRACTOR

Non-Conformances issued by CONTRACTOR

SUBCONTRACTOR shall respond in writing, including proposed corrective action, to all

non-conformances issued by CONTRACTOR within forty-eight (48) hours of receiving

notification of the non-conformance.

SUBCONTRACTOR shall, at SUBCONTRACTOR’s own expense, promptly rework or repair

and re-inspect all non-conforming items in accordance with Approved ITPs and procedures

and notify CONTRACTOR for verification prior to closure that such rework/repairs is

satisfactory.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 59 OF 162

10651-00-QAC-PD-0003

REV.: 01

QUALITY VERIFICATION OF CONSTRUCTION ACTIVITIES

Initial verification

Prior to the commencement of work the following verifications but not limited to shall be

performed:

• Applicable documentation, such as drawings specifications, standards codes, SAES,

SAEPs etc., to be used for construction shall be listed, available and controlled by

SUBCONTRACTOR;

•

ITPs, special process procedures and procedures qualifications shall be available in

reviewed and/or approved status and they shall be adequate to ensure that work is

performed under controlled conditions, with all parameters identified and monitored

in accordance with applicable standards and specifications;

• All personnel performing inspection and testing activity (special process and

construction activity requiring experience and qualification) shall be identified and

qualified. Such qualification shall be kept updated and recorded;

• All testing and measuring equipment shall be suitable to perform the required quality

control activities. Testing and measuring equipment shall be identified and instruction

for their use, calibration and storage shall be available;

• Calibration and setting shall be performed by SUBCONTRACTOR in accordance with

the approved procedure;

• Certification forms shall be approved and available prior to perform related inspection

and testing activities;

• Detailed receiving inspection on materials and equipment arriving on site is required

and must include inspection for shipping damage.

In-process verification

SUBCONTRACTOR shall ensure that the work is carried-out in accordance with the latest

approved construction drawings, specifications, standards, SAES, SAEPs, codes and or

statutory requirements as applicable, and shall perform all in-process inspections and

examinations necessary to verify quality and to obtain from CONTRACTOR authorization to

proceed prior to the covering up, burying and insulating any item, part, area or system of the

works.

At least during construction, the following verifications shall be performed:

• Materials used for construction are always identified and properly preserved;

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 60 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Personnel performing special processes are qualified and identified;

• Latest approved construction documents are used;

•

Inspection and tests are performed as planned;

• Special process equipment used are identified and correctly calibrated;

• Measurement and testing equipment are certified, identified and calibrated as per

procedure;

• Approved work procedures and plans are followed;

• Environmental condition are satisfactory, otherwise measures shall be implemented

to protect the work;

• Defects occurring systematically on the work performed by SUBCONTRACTOR are

identified and adequate corrective actions are implemented;

• All inspection examinations and tests to be performed are orderly and correctly

scheduled to meet project requirements.

Final verification

Upon completion of each work, SUBCONTRACTOR shall ensure that the required

inspections and testing have been performed as per relevant ITP(s) and the results confirm

that all specifications, standards and code requirements are met.

After construction or installation of any item, part, area or system of the Works, the following

verification shall be performed:

• Final inspections and test as specified in applicable ITP(s);

• All required quality records and summary according to ITP have been issued and

approved;

• Applicable documentation has been reviewed, red marked and issued as site revision

(as built);

• Check to ensure that all NCR’s have been closed out satisfactorily and all

documentation have been completed;

• Review final documentation and traceability of quality records of system, part or area

of the works to ensure satisfactory mechanical completion prior to submit the same

to CONTRACTOR.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 61 OF 162

10651-00-QAC-PD-0003

REV.: 01

THIRD PARTY INSPECTION (TPI) Verification

If required in contractual documentation or when deemed necessary, SUBCONTRACTOR

shall use a TPI organization approved by CONTRACTOR. However, SUBCONTRACTOR

shall bear final responsibility for the achievement the specified quality.

TPI shall have free access to the jobsite and documentation to ensure that proper inspections

or examinations can be performed.

Verification by CONTRACTOR

CONTRACTOR have the right to perform or appoint a representative to verify the

performance and/or the results of inspections, examinations and testing at any time during

project execution and as per approved ITP(s), and/or as deemed necessary to provide

confidence that SUBCONTRACTOR is performing the work in compliance with all quality

provisions.

QA/QC COORDINATION

QA/QC Two-Week Look Ahead Schedule

SUBCONTRACTOR shall submit each week (on Thursday) a two-week look-ahead schedule

of all planned quality activities to the CONTRACTOR Representative during construction and

pre-commissioning. The schedule shall be sent electronically in a format acceptable to

CONTRACTOR.

Sufficient planning is required in order to perform the required tasks with minimal interference

with other activities. However, SUBCONTRACTOR must allow sufficient time for all

inspections/ surveillance required to satisfy all Project requirements.

Request for Inspection (RFI)

In accordance with 4.1.3 in this document, if a dedicated software is provided by

CONTRACTOR the processes here described may vary and in case of discrepancy, the

processes required as per the dedicated software will prevail.

In case CONTRACTOR does not provide the RFI form, SUBCONTRACTOR will present for

CONTRACTOR approval an inspection communication protocol to be applied during

WORKS (Request for Inspection, RFI). Hard/soft copy of RFI will be forwarded as notification

to all parties involved and necessary documents will be made available at the location of

Inspection by SUBCONTRACTOR/CONTRACTOR QC personnel. In case SQMS is

implemented in the Project, SUBCONTRACTOR shall issue all RFIs using the Software.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 62 OF 162

10651-00-QAC-PD-0003

REV.: 01

Based on the RFI all parties will inspect the completed WORK for its compliance with Project

standards, SAES, SAEPs, and specifications and accept the WORK. All parties will sign the

checklist / inspection report on completion of inspection. In case SQMS is implemented in

the Project, SUBCONTRACTOR shall scan RFIs Dossiers (after QC forms signatures) and

shall upload them in SQMS. SUBCONTRACTOR will file these completed hard copies RFI

Dossiers in safe custody. RFI and Inspection Logbook may be combined in a database with

access for CONTRACTOR.The Request for Inspection system proposed need to have an

operative philosophy orientate to avoid notification delay and non-necessary (duplicated)

signs.

Prior the beginning of work all parties concerned shall agree the details and coordination of

inspection, examination and testing activities to be carried out in accordance with the

approved ITP. RFI to CONTRACTOR shall be issued when the inspection type is indicated

in the ITP either W or H.

An example of Electronic Request for Inspection template is shown as template 02 of this

document.

Unless otherwise agree, SUBCONTRACTOR shall issue the notification for inspection to

CONTRACTOR a minimum of twenty-four (24) hours advance for Inspection staffed Job

Sites, forty-eight (48) hours advance for unstaffed onshore Job Sites, and one (1) calendar

week advance for unstaffed offshore Job Sites and remote area locations. However, normal

working days

inspection notification

time should be agreed at site between

SUBCONTRACTOR and CONTRACTOR quality representative, to avoid delays during

construction process.

The following workflow describes how SUBCONTRACTOR shall issue RFI and coordinate

with CONTRACTOR the surveillance on inspections, examinations and tests as well as the

issuing and the distribution of relevant reports:

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 63 OF 162

10651-00-QAC-PD-0003

REV.: 01

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 64 OF 162

10651-00-QAC-PD-0003

REV.: 01

The SUBCONTRACTOR shall coordinate with CONTRACTOR the daily inspection,

examination and test in accordance with the RFI issued and the QA/QC Two-Week Look

Ahead Schedule.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 65 OF 162

10651-00-QAC-PD-0003

REV.: 01

In case a Mobil App is implemented in the Project (usually Qforms), RFIs Dossiers issued

from SQMS will be download in Mobil App device instead of printing them out and the QC

forms will signed directly in Mobil App.

RFIs must be identified according to CONTRACTOR indications. If it is not established other

procedure in the Project:

RFIs will be automatically numbered by the software where the sequence numbers from

000001 to 099999 will be reserved for RFIs issued before the software is fully implemented

at the earliest phases of the project, 100000 to 199999 will be reserved for RFIs imported

from the early phase into the software, and from 200000 up to 999999 will be assigned when

SQMS is used on daily basis for RFI management.

Inspection and test status

SUBCONTRACTOR shall maintain and update the status of all inspection and tests. The

purpose of this registration is to control what has been completed in terms of RFI, inspection

performed, reports issued and what is still outstanding for the completion of an item, system,

area or part of Works. This is required to ensure an effective managing of all inspection and

tests activities.

Therefore, SUBCONTRACTOR shall prepare a register listing all items versus inspection and

tests to be performed in accordance with the applicable with the SATIPs (or approved ITPs

if applicable) and chapter 4.3.2 of this document.

CONTROL OF CONSTRUCTION PROCESSES

Field Engineering Control of Design Changes

Any change to IFC drawings or any other CONTRACTORS documents used for construction

that may arise during construction activities shall be informed by CONTRACTOR to

SUBCONTRACTOR via Engineering Instruction as per “STQ and Engineering Instructions

procedure. Likewise, any change initiated by SUBCONTRACTOR shall be approved by

CONTRACTOR via STQ. All design changes shall be controlled as per Project procedure

“Field Engineering Change Control and As Built Procedure”. Changes made in the field will

be collected by the corresponding SUBCONTRACTOR on a marked-up red line copy of IFC

drawings, latest revision. All changes must be approved via STQ or EI.

Special processes

SUBCONTRACTOR must ensure that such special processes are:

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 66 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Submitted for review and/or Approval at least twenty-one (21) days prior to the start

of any Work.

• Accomplished under controlled conditions as specified in all applicable standards and

specifications.

•

Identified all process parameters, with acceptance criteria specified and monitored

Construction and Pre-Commissioning Special Processes

Special Process (SP) Name

Field Engineering Change Control

Concrete Finishing

Concrete and Asphalt Mix

Welding, Brazing

Non-destructive Testing (NDT)

Positive Material Identification (PMI) & Color-Code Verification

Heat treatment & associated Hardness Testing

Hydrostatic Pressure Testing

Valve Testing and Installation

Coatings & Linings

Gasket Installation & Bolt Tightening

Gap Control (socket welds, thread engagement, back welding of threaded joints)

Hot Tap – Calculations & Tie-ins

Refractory Installation

HVAC Testing & Balancing

RTR Pipe work

High/Medium Voltage (HV/MV) Cable Splicing/Termination

Electric Power Systems Energization

Fiber Optic Cable Installation, Termination

Cable Gland/Seal & Conduit Seal Installation

Work Procedure Approval (A) or Review (R) Required

Personnel Qualification Procedure Approval Required (No/Yes)

Personnel Qualification Approval Required (No/Yes)

A

A

A

A

A

A

A

A

A

A

A

A

A

R

A

A

R

R

R

R

N

Y

N

Y

Y (Note1)

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

N

Y

N

Y

Y

Y

N

N

N

Y

N

N

N

N

N

Y

Y

N

N

Y

Notes: (1) Not required when NDT work is subcontracted to an approved In-Kingdom NDT by SUBCONTRACTOR. NDT SUBCONTRACTOR on all projects.

be monitored

performance

technician

shall

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 67 OF 162

10651-00-QAC-PD-0003

REV.: 01

Identification and traceability

SUBCONTRACTOR shall prepare and submit to CONTRACTOR for review and approval

within thirty (30) days of the effective date of the Subcontract an identification procedure for

materials, parts and components, including partially fabricated assemblies. Identification shall

be addressed either by using tags, stamps, colour coding, stencils and labels. The location

and the method of identification shall not affect the function or quality of the item being

identified. The procedure shall require that verification of correct identification of material,

parts and components be made and documented prior to installation.

Traceability shall be maintained on equipment, materials, parts and components, as

specified in COMPANY standards and manufacturer’s specifications.

SUBCONTRACTOR shall maintain, control and record the unique identification of the origin

of materials and components throughout fabrication, erection, installation, repair, modification

as specified in COMPANY standards and manufacturer’s specifications. The procedure

shall require that verification of traceability of material and components be made prior to

installation.

Storage and handling of CONTRACTOR supplied material and equipment

SUBCONTRACTOR shall plan, issue and submit a Reception, Protection and Storage

Materials Procedure including the above documentation, to CONTRACTOR for review and

approval within thirty (30) days after the Subcontract effective date.

SUBCONTRACTOR shall address in a procedure all contractual provisions for storage and

handling of materials and equipment supplied by CONTRACTOR. The written procedure

shall provide for receiving inspection, proper storage, maintenance, handling of materials and

equipment and shall considers as a minimum also the following aspects:

• Equipment storage categories;

• Equipment maintenance categories;

• Corrosion protection;

• Required rigging and lifting drawings.

Materials and equipment maintenance and preservation logs shall summarize, as a minimum:

• Active maintenance requirements;

• Dates of servicing;

• Type of service performed;

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 68 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Personnel responsible;

• Lubricants used etc.

SUBCONTRACTOR shall plan, issue and submit a Reception, Protection and Storage

Special attention should be paid on the storage and handling of Pressure Safety Valves.

These pressure equipment shall be treat according data sheets and specifications.

SUBCONTRACTOR shall establish and maintain controls to restrict further processing or

installation of non-conforming or defective items, pending decisions on disposition.

SUBCONTRACTOR shall segregate all nonconforming SUBCONTRACTOR material and

equipment to a clearly designated quarantine area.

The systems to control and manage the Non-conforming or Defective Material shall be

included into the SUBCONTRACTOR Reception, Protection and Storage Material Procedure

Control of monitoring and measuring devices

SUBCONTRACTOR shall implement a procedure for the identification, maintenance, control

and calibration of tools, gauges, instruments and other measuring and testing devices to be

used in performing inspection and tests. The procedure shall ensure that measurements are

carried out in a manner consistent to provide evidence of conformity of product to determined

requirements.

SUBCONTRACTOR shall plan, issue and submit a Calibration Procedure including the above

documentation, to CONTRACTOR for review, comment and approval within thirty (30) days

after Subcontract award.

Calibration and setting shall be performed against certified equipment having a known valid

relationship to internationally or nationally recognized standards. Where no such standards

exist, the basis used for calibration shall be documented.

Calibration shall be checked before beginning of inspections and at established periods.

Calibration period shall comply with applicable standards and at least with the following table:

Calibration shall be performed at established periods as specified in the most stringent

of COMPANY standards, other applicable standards, or manufacturer recommendations;

if no standards apply,

the calibration cycle shall not exceed six months.

SUBCONTRACTOR shall provide backup equipment when the primary equipment is

being calibrated or tested.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 69 OF 162

10651-00-QAC-PD-0003

REV.: 01

CONTRACTOR shall maintain a log of all testing, measuring and inspection equipment

calibration status and expiry date.

SUBCONTRACTOR personnel performing tests and calibrations shall be trained per

applicable international or manufacturer requirements. SUBCONTRACTOR testing and

calibration personnel as well as testing facilities shall be subject to CONTRACTOR approval.

If SUBCONTRACTOR personnel do not perform tests and calibrations, SUBCONTRACTOR

shall request CONTRACTOR approval for the agencies, or the manufacturers selected to

perform tests and calibrations

SUBCONTRACTOR shall review and document the validity of previous inspection and

test results when inspection, measuring and test equipment is found to be out of

calibration. A copy of the report shall be submitted to CONTRACTOR.

All calibrated monitoring and measuring devices shall be provided with means (labels,

nameplate, tag, card, etc) of immediate visual confirmation of the calibration status by means

of and identification sticker conforming to the following example:

TAG No.:__________________

Calibration date:____________

Re-calibration: _____________

QC Name: ________________

Signature:_________________

The calibration records shall be easily traceable to the equipment and maintained at work

site by SUBCONTRACTOR.

Calibration certificates shall be available as well as calibration record shall be maintained for

each monitoring and measuring device. The Calibration Log shall include the equipment

description, serial number, identification tag number, calibration date, range, calibration

frequency, last calibration date, expiry calibration date, calibration certificate reference

number, calibration by, assignation/resignation date and any other pertinent information.

Prior to use any monitoring and measuring devices, SUBCONTRACTOR shall ensure that

the effective calibration date has not expired, and the equipment has not been visibly

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 70 OF 162

10651-00-QAC-PD-0003

REV.: 01

damaged. The SUBCONTRACTOR shall maintain the updated list of approved monitoring

and measuring devices and periodically submit the same to CONTRACTOR for review.

Tests undertaken shall identify the relevant calibration equipment used. Should the

monitoring and measuring device be found to be out of calibration at the time of test, the

validity of the results of previous inspection, and test carried out with the same measuring

device shall be demonstrated by SUBCONTRACTOR at his own care and cost. When validity

cannot be proven, SUBCONTRACTOR shall repeat all relevant tests with an approved

calibrated measuring device.

ON SITE CIVIL MINIMUM REQUIREMENTS

This is the minimum quality requirement, in compliance with the Design Codes and

International Standards, but not limited to, which SUBCONTRACTOR shall implement and

follow during the execution of the work under this Subcontract.

The Quality Project documentation shall be submitted by SUBCONTRACTOR as the work is

developed.

The Work Procedures and the Reparation Work Procedures shall be officially issued by

SUBCONTRACTOR and

they must be validated by CONTRACTOR Construction

Department. The signed documents shall be recorded by CONTRACTOR Quality

Department.

All certificates, delivery notes, tests, etc., about the different materials shall be submitted by

SUBCONTRACTOR to CONTRACTOR when received.

A qualified independent laboratory shall perform all control tests under SUBCONTRACTOR

´s cost.

All testing shall be performed in accordance with relevant Standards and Codes. Company’s

minimum requirements shall apply if they are stricter.

Material Certificates

SUBCONTRACTOR shall submit to CONTRACTOR the corresponding Material Approval

Request (MAR) for all the material delivery by SUBCONTRACTOR that are going to be

permanent at site. CONTRACTOR shall revise it and shall approve or not according to

Contract and applicable Standards/specifications and drawings.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 71 OF 162

10651-00-QAC-PD-0003

REV.: 01

CONTRACTOR Quality Department shall record the signed originals.

Material certificates shall be in compliance with relevant Standards.

MAR Log shall be fulfilled by SUBCONTRACTOR and submitted to CONTRACTOR in a

weekly basis in an excel format that need to be approved previously by CONTRACTOR.

Excavation and Backfilling

The excavation and backfilling work shall be according to Project Documents (such drawings,

Specification, Project Procedures, ITPs, etc.)

Selected excavated material may be used provided that this material is free from matter

harmful to other materials in the work and suitable for compacting.

Excavated materials suitable for filling shall be placed in convenient areas and may be reused

as fill materials as required.

No fill material shall be placed until the surface to receive fill has been cleaned and prepared,

and the area is free from water.

Layer execution and compaction by layers, including compaction tests, shall be according to

Project Documents.

A program of testing shall be developed and provided by SUBCONTRACTOR to verify

compliance of all fill materials.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 72 OF 162

10651-00-QAC-PD-0003

REV.: 01

Concrete Work and Formwork

Batch Plant approval

SUBCONTRACTOR shall perform a survey and evaluation of each Batch Plants prior to use

and submit the results to CONTRACTOR for approval.

Survey and evaluation of Batch Plants need to be performed to determine their capabilities

to provide quality products and services in accordance with Project Standards/Specifications

and applicable industry codes and standards.

The SUBCONTRACTOR shall notify CONTRACTOR in writing at least seven (7) working

days prior to conducting a Batch Plant survey and/or evaluation. Witnessing a Batch Plant

survey and/or evaluation is at the sole option of.

SUBCONTRACTOR shall provide CONTRACTOR with the following documents as

attachment to the assessment, as applicable:

• Quality Manual/Plan.

• Organization Chart for the specified Batch Plant.

• Proposed Qualified QC Personnel (QC Manager, Engineers and Field Technicians).

• Control List of all plant apparatus providing type, serial number and calibration status.

• Calibration certificates of Batch Plant equipment.

• Latest raw material test report.

• Concrete Mix Designs.

CONTRACTOR has the right to perform technical & quality assessments to the Batch Plant

in order to verify the compliance with Project Requirements.

CONTRACTOR has the right to place on hold or disapprove Batch Plants in the event of

nonconformance to Project Requirements such as but not limited to:

• Saudi Arabia government regulatory violations.

• Environmental, health, safety and/or security violations.

• Falsification of documents or test results.

• Missing or late response and/or lack of corrective action to identified NCRS.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 73 OF 162

10651-00-QAC-PD-0003

REV.: 01

New Mix Design

A new concrete mix design shall be submitted to CONTRACTOR for approval at least thirty

(30) working days prior to start the concrete work, using formats acceptable to

CONTRACTOR and the COMPANY SAEP-1152. Mix proportioning shall be in accordance

with the applicable American Concrete Institute Code.

A new mix design is required when a proposed mix has no established record indicating that

it meets all the requirements of applicable standards or specifications. It is also required if

there is a change in type, source or quantity of the constituent parts of a previously approved

mix design.

New mix design shall be supported by successful full-scale plant trials performed and certified

by a CONTRACTOR approved independent testing laboratory. The SUBCONTRACTOR

shall notify CONTRACTOR in writing at least seven (7) working days prior to conducting a

plant trial. Witnessing a plant trial is at the sole option of CONTRACTOR who reserves the

right to monitor any or all phases of work required to prepare concrete mix design.

All quality tests on raw materials shall be performed by a CONTRACTOR approved

independent laboratory. Blending and proportioning data including test records by the

independent testing laboratory shall be made available upon CONTRACTOR’s request.

The approved mix design shall be assigned a unique Mix Identification (ID) Number, which

shall be indicated in the “Concrete Mix Design Data Sheet”. An approved mix design ID

number that has become void or obsolete due to change of ingredient or any other reason

shall not be re-used.

In remote sites where the concrete batch plant and the concrete mix designs are approved on one-time basis for a specific project and CONTRACTOR, new review and approval are required for other CONTRACTORs.

Mix Design with established Mix ID Number

The concrete mix design with an established Mix ID Number, needs to be verified if the tests

on the constituent parts are not up-to date. If raw materials test reports are not updates based

on the frequency set forth the Project, the mix design will not be accepted.

Mix design with established Mix ID Number shall be submitted for CONTRACTOR approval,

at least seven (7) working days prior to start of Work, using formats acceptable to

CONTRACTOR and the COMPANY SAEP-1152. (Request for Approved and Copy of the

approved “Concrete Mix Design Data Sheet”).

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 74 OF 162

10651-00-QAC-PD-0003

REV.: 01

Formwork

The design and construction of the formwork shall be in accordance with ACI 347, Saudi

Aramco Construction Safety Manual, and shall be

the

responsibility of

the

SUBCONTRACTOR.

Concrete

General

Additives to concrete must be validated by CONTRACTOR.

It is forbidden to aggregate water to the concrete mixture.

Water in the foundations shall be removed before starting concrete activities. Foundation

shall be protected against raining if it is raining or rain is foreseen during pouring concrete.

Ambient conditions shall be respected according to Contract and applicable standards. As a

general rule, no concrete work is allowed if ambient temperature is not up to 0ºC during

pouring concrete or it is foreseen to reach during concrete activities.

All concrete foundations shall be fabricated and constructed to SAES-Q-001 and SAES-Q-

  1. Foundations furnished by precast vendors shall comply with SAES-Q-012.

Foundations shall be concreting in one (1) phase. If it is not possible, the phases shall be the

minimum and the surface preparation and product for resumption of concrete between the

different phases shall be always considered.

The location of joints shall be according to drawings. Joints shall be arranged in order to

minimize the effect of shrinkage of the concrete.

The authorization records for Concrete Pouring must be signed and submitted by

SUBCONTRACTOR to CONTRACTOR before each pouring concrete. Approval by

CONTRACTOR is required prior to starting concrete activities. Authorization of Pouring

Concrete Record shall be signed for CONTRACTOR Construction Department and after by

CONTRACTOR Quality Department, who shall record the signed document.

The authorization records for Concrete Pouring shall always be submitted with their

corresponding Topographic Protocol. Signature sequences for Topographic Protocols shall

be the same as the Authorization of Pouring Concrete Record: SUBCONTRACTOR –

CONTRACTOR Construction Department – CONTRACTOR Quality Department –

COMPANY (if required).

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 75 OF 162

10651-00-QAC-PD-0003

REV.: 01

A Topographic Protocol after concrete work shall always be considered. Otherwise concrete

work is not finished until this protocol has been filled, submitted, and the resultant measures

are consistent with Contract/Standards/Specifications and drawings tolerances. Finishing

must be properly done as per Specifications/Standards and CONTRACTOR criteria.

If necessary, Reparation Work Procedure and materials for reparations shall be submitted

for approval to CONTRACTOR prior to start any reparation work.

Concrete traceability and delivery notes shall be submitted by SUBCONTRACTOR to

CONTRACTOR Quality Department no later than three (3) days after pouring concrete.

Formats for recording the traceability results are included in the corresponding ITP for

Concrete Works and Framework. CONTRACTOR Quality Department shall revise and

approve/comment on it.

Concrete tests shall be carried out according to Contract/Standards and ITPs. Concrete test

reports shall be officially submitted by SUBCONTRACTOR to CONTRACTOR no later than

two (2) days after accomplishment date. For test at seven (7) days, SUBCONTRACTOR

must submit it at nine (9) days, maximum. For test at twenty-eight (28) days, results shall be

submitted not more than thirty (30) days after pouring concrete works.

If concrete tests show a lower concrete strength than expected, SUBCONTRACTOR shall

prepare a procedure for concrete coring where different possibilities shall be considered as

well as Corrective and Preventive Actions. Any cost due to the fact of these results shall be

assumed by the SUBCONTRACTOR. If the CONTRACTOR considers that it is necessary to

conduct a new test for validation of the concrete mixture or additional concrete tests, they

shall be assumed by the SUBCONTRACTOR.

Concrete cover to reinforcement for the bars, clips and wires shall be minimum/maximum as

per drawings and Contract/Specifications. No reduction shall be permitted in the cover to

reinforcement because of a specified negative tolerance in a concrete section.

Notes of calculus of framework shall be submitted to CONTRACTOR as well as type and

characteristics, and it must be approved by CONTRACTOR before starting work.

SUBCONTRACTOR shall keep the formwork properly, it shall be leak proof, clean and free

from windblown dust and rubbish. Scrupulous maintenance shall be developed by

SUBCONTRACTOR. If CONTRACTOR considers that it is necessary to change/renovate the

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 76 OF 162

10651-00-QAC-PD-0003

REV.: 01

formwork,

it shall be assumed by

the SUBCONTRACTOR without any cost for

CONTRACTOR.

Approved release agents shall always be applied on the surface against which the concrete

is to be deposited. Steel reinforcement must be free from this coating material.

When it has not been utilized, the formwork shall be store in a workshop or/and in proper

conditions.

After concreting, the formwork shall be kept a minimum of twenty-four (24) hours. Depending

on the ambient conditions, the minimum time can be increased.

Placing concrete by pumping methods shall also conform to the requirements of ACI 304.2R.

Slump and cylinder test samples shall be taken from the end of the mixture truck chute or at

the discharge point of the concrete placement hose when concrete pumps are used.

When hot weather conditions exist, SUBCONTRACTOR shall place concrete in compliance

with ACI 305R and ACI 301-05.

Testing and Inspection

The SUBCONTRACTOR shall employ an independent CONTRACTOR approved testing

agency to perform field and laboratory testing which shall include compressive tests of

moulded concrete cylinders, test for slump, unit weight, air content (where air-entrainment is

required) and fresh concrete temperature. All testing shall be in accordance with 09-SAMSS-

097, “Ready-Mix Portland Cement Concrete”.

Placing Concrete

Concrete shall be placed in accordance with ACI 301-05, Chapter 8, ACI 304R and this

standard. For Hot Weather Concreting requirements, see also ACI 305R, ACI 305.1.

Equipment made of aluminium alloys shall not be used for pump lines, tremies, or chutes

used to discharge concrete from a truck mixer.

Concrete shall not be placed prior to a recorded pre-placement inspection and authorization

to proceed by CONTRACTOR.

Raking shall not be used for movement of concrete after placement.

Vibrators shall not be used to move concrete inside forms.

Retempering of concrete after placement is prohibited.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 77 OF 162

10651-00-QAC-PD-0003

REV.: 01

Concrete shall not be dropped freely where reinforcing will cause segregation, nor shall it be

dropped freely more than one (1) meter.

Concrete shall be deposited as near as possible in its final position to avoid segregation due

to re-handling or flowing.

Placed concrete shall be consolidated by mechanical vibrating equipment supplemented by

hand spading, rodding or tamping. Equipment and procedure for consolidation of concrete

shall be in accordance with ACI 309R.

Concrete shall be placed on a clean surface. Standing water shall be removed prior to

placement of concrete.

The use of precast concrete or mortar blocks as bar supports and spacers discussed in ACI

301-05, shall be prohibited. However, the use of PVC Schedule 80 pipe as spacer is allowed.

The PVC pipe shall be notched at the bottom to allow the ingress of concrete. Typical samples

shall be submitted for Supervisor of Civil Engineering Unit/CSD for approval.

Finishing

The finishing of concrete shall be in accordance with ACI 301-05, and ACI 302.1R unless

otherwise specified in the construction drawings or job specification.

Curing

Structural concrete shall be continuously water cured in accordance with recommendations

of ACI 305R, ACI 308. To avoid self-desiccation of the concrete mix, only water curing method

shall be used to cure the structural concrete. Please refer to section 1.3.2 of ACI 308R.

Maximum total dissolved solids in water used for curing shall not exceed 1000 parts per

million.

Water curing shall be continuous until the compressive strength has reached 70% of the

specified strength, but not less than what is specified in Table 5.1.

The saturated burlaps shall be covered with a plasticized sheet vapour barrier, minimum 0.15

mm (6 mils) in thickness and shall be kept in contact with the concrete surface at all times.

Curing Compound shall be in accordance with ASTM C309 or equivalent and verified by

independent lab on monthly basis.

Joints

Joints shall be as specified on the design drawings or in accordance with SAES-Q-001.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 78 OF 162

10651-00-QAC-PD-0003

REV.: 01

Paving or slab construction joints not specified on the drawings shall be located at column

centrelines and intermediate intervals.

Water stops shall be provided in joints where watertight construction is required in

accordance with ACI 504R. Water stop type shall be specified and shown on the drawings

and shall satisfy the function and operation of the structure.

Joint filler strips for expansion joints shall be as noted on the design drawings. Joints sealer

shall conform to 09-SAMSS-075.

Grouting

The SUBCONTRACTOR will prepare an ITR denominated “Release for grouting” ,applicable

for Static, Rotary and Skid equipment , with the relevant documentation/certificates/survey

protocols/Type of Grouting proposed…etc. attached to ensure the element (For instance

foundation” is ready for grouting, the ITR proposal must be approved by CONTRACTOR

before to use, The Release will be signed by CONTRACTOR once the documentation has

been reviewed and the field inspection is completed.

• The crew personnel shall be trained specifically by the Grout manufacturer for pouring

grout underneath of Static, Rotary and Skid equipment.

• SUBCONTRACTOR will be issued and send for CONTRACTOR approval the

Individual Grouting Card Authorization based on the specific training received from

the grout manufacturer.

• Proper inspection during mixing the grout material to ensure quantities, and grout

material condition as per manufacturer data sheet.

• Ensure the proper fixing of foam material for expansion joint to avoid the floating

during the grout pouring.

• The time for grout pouring shall be early morning or at evening day, in order to take

advantages of less temperature.

FOSROC Grout material is NOT recommended to be used for this purpose, and it shall be

approved by CONTRACTOR.

Reinforcing Steel, Embedded Elements and Anchor Bolts

All sleeves, inserts, anchor bolts, water stops, and other embedded items shall be installed

in accordance with the design drawings and supported against displacement.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 79 OF 162

10651-00-QAC-PD-0003

REV.: 01

Projecting steel items (such as grating angles, slide plates, unistrut, steel plates, etc.) which

are attached to the formwork and cast at the concrete surface shall be hot dip galvanized in

accordance with ASTM A123 or coated with the zinc rich epoxy primer in APCS-1C of SAES-

H-101. Additionally, the steel attachment, which anchors these items to the concrete, shall

be similarly galvanized or coated.

Reinforcing steel bars, anchor bolts or other steel embedments shall not be used as the

means for grounding electrical equipment and shall not be tied to grounding neutral

conductors, or any part of the lightning protection system.

Reinforcing Steel Bars shall conform to SAES-Q-001 and ACI 318 requirements. Anchor

Bolts shall comply with Saudi Aramco Standard Drawing AA-036322-001

Conduits, pipes and other items made from aluminium shall not be embedded in structural

concrete unless effectively coated to prevent aluminium-concrete reaction.

The routine test for the armature shall be according to Contract/Specifications and applicable

Standards.

Material Approval Request shall be submitted by SUBCONTRACTOR according to CONTRACTOR procedure “Procurement QC Instructions for SUBCONTRACTOR’s” 10650- 00-QAC-PD-0004.

Welding between armature-armature and armature-anchor bolts is strictly forbidden except

written acceptance by CONTRACTOR or where shown on drawings. If authorized, qualified

welding procedures and welders are required.

Joint ligatures shall be placed in a sufficient quantity, as per Specifications, applicable

Standards and Project Documents.

The design of anchor bolts shall be in accordance to SAES-Q-005 and the materials shall

be in accordance to 12-SAMSS-007. Anchor bolts shall be located inside the reinforcement

frame.

Anchor bolts at surfaces in contact with atmospheric conditions shall be painted according to

Specifications and drawings.

Type of grout shall be chosen based on the specific conditions for the foundation and the

manufacture’s recommendation. Manufacture’s recommendations shall be strictly considered

to mix, apply and cured the grout.

The grout shall have, as a minimum, a compressive strength equal to the concrete.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 80 OF 162

10651-00-QAC-PD-0003

REV.: 01

Elements to be grouted shall be released by CONTRACTOR supervisor and the release

recorded in the grouting authorization and inspection form as per Civil/Mechanical SATIPS

or ITPs. Grouting activity shall be inspected and recorded and samples for testing shall be

taken as per approved SATIPS or ITPs

Sewers and Drainage

Materials for the sewer system shall be adapted to the conveyed wastewater.

Manholes shall be made of reinforced concrete. Concrete channels shall be reinforced.

Manholes and concrete channels in which corrosive chemicals are present shall be covered

on the inside with special mortar, tiles or coating resistant to the actual chemicals.

It shall be done according to Project Documents, as Contract, Specifications, Drawings,

Standards, ITPs, etc.

Each pipe shall be carefully inspected on arrival to Site. Defective pipes shall be marked and

separated.

Each pipe shall be cleaned internally, and SUBCONTRACTOR shall ensure that any foreign

material is excluded from each joint before it is laid. Pipe joints shall be executed as required

by manufacturer’s recommendation.

After the piping has been tested, granular material shall be carefully placed, and compacted,

around and over the pipe. Height of granular material shall be according to the project

documents. In areas of heavy traffic or road crossings, the pipe shall be protected to

withstand the requirements of traffic loads.

All necessary tests shall be carried out according to Contract/Specifications and Standards.

No pipes or parts of pipes shall be covered before all the tests have been successfully

completed. Air testing of non-pressure pipelines is not permitted except if a water test is

impracticable and/or with written authorization by CONTRACTOR.

Roads and Paved Areas

Roads shall be in accordance to Project Specifications, Drawings, Standards, SATIPs (or

approved ITPs if applicable), etc.

A polythene sheet between the subgrade and concrete paving shall be provided. Thickness

and characteristics shall be as per Project documents.

As a general rule, the following steps shall be considered for road construction:

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 81 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Sub-graded of sand or graved fill, compacted as required in Project documents.

• Sub-base of granular material, thickness and compaction as required in Project

documents.

• Road base course of crushed stone or quarry scalping, thickness and grain size

as required in Project documents.

• Cationic bitumen emulsion for priming and tack coats prior to star of bituminous

coating.

• Binder course of bituminous concrete hot mixed and laid. Composition, thickness

and tests as per Project documents.

• Wearing course of fine bituminous concrete hot mixed and laid. Composition,

thickness and tests as per Project documents.

• The California Bearing Ratio (CBR) shall be according to Project documents.

A strict topographic control shall be considered, and reports shall be provided including

horizontal alignment, surface level and slopes.

Surface regularity of pavement courses shall be properly finished.

Demolitions, Rehabilitations or Reinforcement of existing Civil works

The demolition or removal of existing foundations or structures shall be in accordance with

developed drawings. SUBCONTRACTOR shall submit to CONTRACTOR the proper

approval for any demolition of existent part. All demolitions shall be controlled, and

demolished material removed by SUBCONTRACTOR from work area.

The execution works need to be controlled and only can be done with CONTRACTOR

acceptance

HVAC Activities:

Products and Material Certificates SUBCONTRACTOR shall submit all the data sheet and

operational manuals of all the equipment for the HVAC installation system for CONTRACTOR

approval. SUBCONTRACTOR shall ensure that all material certificates are in compliance

with relevant Standards applicable to the project, material certificates shall be submitted to

CONTRACTOR approval before initiation of any work.

A topographic survey report regarding the placement and position of the main equipment will

be provided to CONTRACTOR.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 82 OF 162

10651-00-QAC-PD-0003

REV.: 01

A Work Method of Statement describing all

the activities will be submitted by

SUBCONTRACTOR before starting the activities, including a leak test methodology for the

refrigerant pipes (if apply). The approved SATIP or ITP will be followed. Fabricant Acceptance

Test (FAT) for the electrical power panel (if apply) will be requested to SUBCONTRACTOR.

STEEL STRUCTURE FABRICATION MINIMUM REQUIREMENTS

This is the minimum quality requirement, in compliance with the Design Codes and

International Standards, but not limited to, which SUBCONTRACTOR shall implement and

follow during the execution of the work under this Subcontract either at Fabrication Shop or

at Construction Site.

Materials Certificates

• All materials shall meet the requirements of the appropriate Project and applicable

Specifications.

• All materials shall be received at the workshop with their quality certificates. If materials

arrive at the workshop without quality certificates, they must be immediately identified

with this status. Materials can’t be used until quality certificates are regularized by the

supplier and approved by Quality Department.

• All materials shall be segregated and stored in adequate locations depending on their

material properties.

• SUBCONTRACTOR shall implement a material certificates control system, allowing

the correct traceability during fabrication process. Those certificates shall be available

for CONTRACTOR`s assurance at all stages of manufacture process.

Steel Structure Fabrication

• The minimum requirements of welding, heat treatment, Non-destructive Testing (NDT),

impact and hardness testing for shop fabrication, repair, or modification of steel

structure are defined at the applicable International Codes and Standards

• At all stages of manufacturing each piece or package of similar pieces of steel

components shall be identifiable by a suitable system approved by CONTRACTOR.

• Identification may be achieved as appropriate by batching or by the shape and the size

of the component or by the use of durable and distinguishing marks applied in a way

not producing damage. Chiselled notches are not permitted.

• Cutting shall be carried out in such a way that the requirements for geometrical

tolerances, maximum hardness and smoothness of free edges as specified in the

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 83 OF 162

10651-00-QAC-PD-0003

REV.: 01

International Standards are met. The SUBCONTRACTOR must define the cutting

methods to use at the workshop, specifying the material thickness range allowable for

each of the cutting methods. Hand thermal cutting should be used only if it is not

practical to use machine thermal cutting.

• All tolerances and dimensions shall be controlled by SUBCONTRACTOR during

fabrication process according Project Specifications and international standards.

• Holes for fasteners or pins may be formed by any process (e.g. drilling, punching, laser,

plasma or other thermal cutting), since complying with Project Specifications and

Standards.

• Any miss

located holes shall be plugged by welding and

repaired by

SUBCONTRACTOR hole plugging weld procedure.

• Joint Preparation shall be as per project applicable international Standard.

• Contact surfaces from slip resistant connections must be identified and the surface

treatment from those contact areas must be applied to provide a specific slip factor

according Project Specifications and International Standards. SUBCONTRATOR shall

submit evidence of accomplishment for the slip factor defined bay CONTRACTOR.

• The location of CJP (Complete Joint Penetration) welds used as splices to

accommodate available lengths of constituent products shall be approved by

CONTRACTOR Engineer.

Welding Consumables

• Electrodes, filler wires, and fluxes shall conform AWS A5.01 (or European/Japanese

equivalent) Other consumables may be used only with the approval of CONTRACTOR.

• Chemical Analysis shall be presented for individual batch/lot purchased and prior to

use at site/job

• Storage, Handling and Issuing of Consumables shall be as per the applicable

Standards and manufacturer’s recommendations.

• All consumables shall be stored and dried in accordance with the requirements of

International Codes and Project Specifications.

• All electrodes having low hydrogen coverings conforming shall be in hermetically

sealed containers or shall be baked by the user prior to use. After opening the

hermetically sealed container, electrodes not immediately issued for use shall be stored

in ovens held at temperature at least 120 ºC. Electrodes shall be rebaked no more than

once. Electrodes that have been wet shall not be used.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 84 OF 162

10651-00-QAC-PD-0003

REV.: 01

Welder Qualification

• All welders, welding operators, brazers, and brazing operators shall be qualified in

accordance with International Codes, like AWS or EN ISO.

• The test records of all welders and welding operators shall be available at all times at

the job location for review by CONTRACTOR Inspection.

• Welder or Welding Operator shall be qualified in all positions required to perform the

work.

• Welders shall be qualified whenever there is a change in Essential Variables.

• Possible causes of failure or rejection of weld joints shall be explained to the welders

in a Toolbox to control the repair rate and welder performance.

• Welders and Welding operators qualifications shall be considered as remaining in effect

indefinitely unless the welder is not engaged in a given process of welding for which

the welder or welder operating is qualified for a period exceeding s6 months or there is

some specific reason to question a welder’s or welding operator’s ability.

• Welders and Welders operators must be identified with an ID card that. The ID card

must be carried by the welder all time at job site.

• Current production repair rates of each welder shall be made available to

CONTRACTOR Inspection upon request. The repair rates shall be calculated on a

linear basis.

Welding Procedures

• Except for prequalified WPS’s conforming to the requirements of applicable Codes, a

WPS to use in production welding, shall be qualified and shall be properly documented.

• All welding procedures to be used shall be submitted as a complete package to

CONTRACTOR for the technical approval prior to the start of work. The welding

procedure shall include the Welding Procedure Specifications (WPS), Qualification

Test Records (PQR), qualification test results and Weld Maps/Tables

• WPS and PQR submitted for approval shall be in accordance with the requirements

stated in Project Specifications and International Codes.

• A copy of respective WPS & PQR for a particular welding job shall be available in an

area of welding activities being executed

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 85 OF 162

10651-00-QAC-PD-0003

REV.: 01

Welding Operations

• SUBCONTRACTOR shall track welding activities on a daily basis and submit to

CONTRACTOR each week a weld tracking and welder performance report for that

week work. Cut-off date for submitting weekly performance report shall be agreed by

CONTRACTOR.

• Inspector who represents the SUBCONTRACTOR and performs the Welding joint

Inspection shall be well qualified and certified as per the International Codes and

Standards or Project Specifications.

• Welding shall not be started until and unless the WPS & PQR have been approved by

the CONTRACTOR and Company.

• SUBCONTRACTOR Inspector shall ensure the Joint Fit-up to verify the joint integrity

and must perform 100% Weld Visual Inspection prior to request an RFI.

• Oil, moisture, rust, scale, sand, paint, metallic coatings (e.g., zinc), or other foreign

matter shall be removed from the weld surface and at least 25 mm (1 in) of adjacent

base metal prior to welding, including any such coatings on temporary attachments or

supports.

• Tack welds that are to be incorporated into the final weld shall be thoroughly cleaned,

prepared at each end, and inspected for cracks. Any cracked tacks shall be removed

before welding the joint.

• All tacks or temporary welds shall be performed with the same care, materials,

electrodes, minimum preheat, and procedures that are used for permanent welds.

• Welding area shall be covered completely whenever there is adverse effect from

environment such as rain, dust, wind, etc.

• Welding shall not be done when surfaces are wet or damp or exposed to rain or snow

or when the welders are exposed to inclement conditions.

• Contamination from the environment, such as wind-blown sand, shall be prevented by

the use of adequate shielding.

• Pre-heat treatment shall be in accordance with International Codes and Project

Specifications. For materials not covered by the Code the pre-heat treatment shall be

as specified in the approved welding procedure.

• As minimum Temperature indicating crayons/pencils shall be available with the welders

and used to measure preheat and interpass temperature, when required.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 86 OF 162

10651-00-QAC-PD-0003

REV.: 01

Post Weld Heat Treatment

• Post weld heat treatments (PWHT) shall be in accordance with International Codes. A

written procedure describing the general PWHT requirements shall be submitted for

review and approval of the CONTRACTOR. The PWHT procedure shall include

descriptions of the equipment, method of heating, location and type of heating

elements, temperature measurement, and thermocouple locations. The review and

approval process shall be the same as described for welding procedures.

• Prior to the start of work the SUBCONTRACTOR shall prepare a table listing each joint

or component requiring heat treatment, which shall be submitted to CONTRACTOR

Inspection for review. The table shall include the following information for each joint or

component: location, drawing number, diameter, wall thickness, material, heating rate

and cooling rate, soak temperature, and soak time.

• Joints that have been PWHTed and needs any welding or heating requires new PWHT.

Post weld heat treatment shall follow all welding and repairs.

Inspection Access

• CONTRACTOR shall have free access to the work at all times.

• CONTRACTOR shall have the right to inspect the fabrication at any state or stage and

to reject material or workmanship which does not conform to the specified

requirements.

• CONTRACTOR reserves the right to inspect, photograph, and/or videotape all material,

fabrication, coating, and workmanship and any materials, equipment, or tools used or

to be used for any part of the work to be performed. CONTRACTOR may reject the use

of any materials, equipment, or tools that do not conform to the specification

requirements, jeopardize safety of personnel, or impose hazard of damage to property.

• The SUBCONTRACTOR shall provide the authorized CONTRACTOR inspector all

reasonable facilities to satisfy him that the work is being performed as specified.

• The SUBCONTRACTOR shall furnish, install, and maintain in a safe operating

condition all necessary shoring, scaffolding, ladders, walkways, and lighting for a safe

and thorough inspection which is satisfactory to CONTRACTOR Inspection.

Non-Destructive Testing

• SUBCONTRACTOR

shall

contract direct NDT Service Provider

(sub-

CONTRACTOR(s)) to perform all NDT’s and prepare all NDT reports with sufficient

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 87 OF 162

10651-00-QAC-PD-0003

REV.: 01

number of direct duplicate copies (e.g. NCR Paper) to provide for “Control Copies”.

Control Copies of all NDT reports issued to the SUBCONTRACTOR must

simultaneously be submitted to the CONTRACTOR on-site Inspection Department

representative and the NDT Service Provider’s nearest area office.

•

i. All NDT reports shall clearly indicate by printed name, signature, and where

applicable identification reference of personnel conducting the NDT and

interpreting results.

•

ii. Witness, review, and approval by SUBCONTRACTOR shall be indicated by

printed name, signature, and applicable identification on the original NDT report.

Control Copies held by SUBCONTRACTOR’s NDT Service Provider (sub-

CONTRACTOR) and those issued to CONTRACTOR as noted above shall be

retained throughout the duration of the project.

• Non-destructive Examination (NDT) inspection procedures shall be established in

accordance with Project Standards, Procedures and Specifications. A written

procedure for each inspection method and technique, including acceptance

criteria, to be used shall be submitted to CONTRACTOR for approval. NDT

performed without approved procedures shall be considered unacceptable.

• All appropriate safety precautions shall be taken for each inspection method.

Particular care shall be taken when performing the RT at site to avoid the

Exposure of the source during site work operations.

• SUBCONTRACTOR shall establish a system of serialized log for all NDT uniquely

identifying the individual welds to be tested and method applied. This log is to be

an ongoing log of NDT requests and completions as the Project progresses. The

log reference (serial number) for each weld or welds examined shall be included

in NDT reports. NDT of any repair shall be sequentially identified in the log and

include the log reference of the initial NDT that determined need for the repair.

• Additional inspection of any weld joint at any stage of the fabrication may be

requested by CONTRACTOR Inspection, including re-inspection of previously

inspected joints. CONTRACTOR Inspection also has the right to request or

conduct independent NDT of any joint. If such testing should disclose gross non-

conformance to the Code requirements, all repair and NDT costs shall be done at

the CONTRACTOR’s SUBCONTRACTOR’s expense.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 88 OF 162

10651-00-QAC-PD-0003

REV.: 01

• All NDT personnel shall be qualified in accordance with International Codes and

Standards.

• 100% Visual Inspection is required by the SUBCONTRACTOR Inspector for

completed welds prior to request of RFI. Inspector must sign adjacent to the weld

joint as (V I Accepted.)

•

If the joint is required to be radiographed and radiography is not feasible, then UT

and MT may be used in lieu of RT. This requires the approval of CONTRACTOR

Inspection. This does not apply if radiography is required by International Codes.

• SUBCONTRACTOR Shall comply with the following NDT Frequency Inspection

on each type of welding connection if no other criteria has been approved by

CONTRACTOR:

UT/RT* METHOD

*RT when UT cannot be performed due to geometric restrictions

CJP of BEAMS and COLUMNS SPLICES

(for transport accommodation)

BEAMS

Moment Connection (CJP)

BASE COLUMNS

• 20% of all splices

• 40% of weld extension

• 20 % of beams

• 25% of weld extension

Connection between base plate and

• 30 % of columns

column;

• 50% of weld extension

Connection between base plate and shear

key.

SUPERIOR COLUMNS

Moment Connections (CJP)

MP/PT METHOD

Fillet Joints

• 20% of columns

• 25% of weld extension

• 2 elements per day or

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 89 OF 162

10651-00-QAC-PD-0003

REV.: 01

10 elements per week

• 10% of weld extension

• SUBCONTRACTOR shall submit at the end of each fabrication week demonstration

of NDT frequency inspection accomplishment.

NOTE - SUBCONTRACTOR shall submit all NDT and PWHT Reports to CONTRACTOR on

daily basis, according to the specific requirements applicable for the Project.

Repairs

• SUBCONTRACTOR has the option of either repairing an unacceptable weld or

removing and replacing the entire weld.

• The repaired or replaced weld shall be retested by the method originally used and

the same technique and quality acceptance criteria shall be applied.

•

In-process repairs (i.e., repairs performed prior to completion of the joint using the

same welding procedure as for the original fabrication) during production do not

require a separate repair procedure except for cracks.

• The repair procedure may use a welding procedure previously approved by

CONTRACTOR in conjunction with a separate method statement or it may be a

separate detailed welding procedure.

Steel Structure Storage

• Structural Steel components shall be packed, handled and transported in a safe

manner so that permanent deformation does not occur, and surface damage is

minimized. Handling and storage preventive measures shall be applied as

appropriate.

• Stacking of manufactured components stored before transportation or erection

shall be clear of the ground to be kept clean and avoid contamination.

•

If necessary, additional supports must be installed during storage to avoid

permanent deformations.

• Contact surfaces from slip resistant connections must be protected against

corrosion.

• Steel Structure must be storage in a way to avoid accumulation of water.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 90 OF 162

10651-00-QAC-PD-0003

REV.: 01

Calibration

• Stationary Station shall be calibrated every 6 months in duration.

• Welding Machines shall be calibrated for every 6 months.

• Torque Wrench used for Bolt Torqueing shall be calibrated every 3 months unless

specified in written.

• Tension Calibrator used in the installation of pretension joints and slip critical joints

must be calibrated every 3 months.

Structural Bolts

Bolts and Nuts sets shall have independent laboratory verification by SUBCONTRACTOR.

Samples to perform Tensile Test and Hardness test shall be selected as follows:

• A minimum of (1) sample for each mill heat number and each manufacturing lot for

each supplier;

Bolts and nuts not conforming to the applicable specification shall be rejected and

replaced by the SUBCONTRACTOR.

• Bolts stored shall be kept in dry conditions, protected from dirt and moisture in

closed containers prior to use, and shall be suitably packed and identifiable, per

lot number, heat number, dimensions and class.

• Bolts components that accumulate rust or dirt shall not be incorporated into the

work unless they are requalified.

Reception at Site

Steel structure reception at site shall be done and confirmed by SUBCONTRACTOR, delivery

notes shall be confirmed and approved by CONTRACTOR. The arrived parts, as per

SUBCONTRACTOR site erection drawings need to be checked and major damages shall be

recorded and put in quarantine to be repaired before installation.

Steel Structure Erection

Erection of structural steel cannot start before foundations release and approval by

CONTRACTOR. Topographical inspection reports shall be performed to the new and existing

parts before works erection at site and attached to the foundations release report. No

structure can be erected without survey reports performed to the existent or new foundations,

anchor bolts and/or steel structure. Erection plan shall be submitted by SUBCONTRACTOR

and approved by CONTRACTOR for steel structure erection be performed in the foundations

or existent structure. Preliminary tightening of anchor bolts shall be completed before

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 91 OF 162

10651-00-QAC-PD-0003

REV.: 01

grouting; after grouting works have been completed, the grouted elements shall be released

by CONTRACTOR for final tightening of anchor bolts. Any welding on site shall be approved

by CONTRACTOR. Approved WPS/PQR and qualified welders shall be submitted before any

welding activity starts.

Field Corrections

The adjustments made at site shall be performed according the applicable codes, columns

base plates corrections and adjustments need to be as per tolerances and codes applicable.

Minor corrections shall be executed at site, such as minor welding’s or drillings with approved

procedures for the work execution.

Site Inspection and Testing

All inspection and testing during site erection shall be done as per approved SATIP or ITP

for steel structure erection. The SUBCONTRACTOR shall employ an independent entity and

submit to CONTRACTOR for approval of testing agency to perform field and fabrication NDT,

such as VT, MPI, PT, UT or RT, tests depending of welding joints. All testing shall be in

accordance with applicable international codes and project specifications. Additional tests

could be applicable if requested. Site topographical reports shall be performed, and

tolerances shall be in accordance with applicable international codes and project standards.

Any discrepancy shall be solved in order to avoid future interferences with another activities.

Joints shall be specified in the erection drawings, all site corrections, adjustments or

modifications need to be included by SUBCONTRACTOR in the erection drawings. Tie-in of

any existent structures shall include the proper documentation as per applicable codes and

project specifications. Control of Steel structure erection including leveling and plumbness

check and tightness check of bolted connections shall be performed as per approved SATIP

or ITP and applicable standards. Bolt control and visual inspection records of welded parts

shall be applied as per specifications were SUBCONTRACTOR Quality department shall

perform

the proper

inspection before submitting

to

inspection and approval of

CONTRACTOR. SUBCONTARCTOR will be responsible for any touch-up of painted areas

necessary in areas which have been damaged during erection; inspection and test of repaired

areas shall be reported as per approved ITP for painting. After steel structure erection has

been completed and all required inspection and test records are available and accepted by

CONTRACTOR, a final inspection will be performed by SUBCONTRACTOR with

participation of CONTRACTOR (and COMPANY when required) and the structures released

for next activities.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 92 OF 162

10651-00-QAC-PD-0003

REV.: 01

ON SITE PIPING FABRICATION & WELDING MINIMUM REQUIREMENTS

These are the minimum quality requirements, in addition to the ones in the Design Codes

and International Standards but not limited to, which SUBCONTRACTOR shall implement

and follow during the execution of the work under this Subcontract, either at Fabrication Shop

(included fabrication yard work site) or at the Construction Site.

Piping Material

The minimum requirements for piping material are defined in the corresponding Piping

Material and in the SAES-L-105 COMPANY Specifications.

All materials shall be segregated and stored in separate locations depending on their material

properties.

Materials shall be marked or color coded in accordance with the project specification and

referenced Codes and Standards.

All exposed flange faces shall be protected against corrosion and damage by applying

suitable grease, and by bolting on wood or steel covers with at least four bolts. Plastic snap-

in end covers are acceptable.

All threaded connections shall be protected by thread protectors.

All bevelled ends shall be protected by snug fitting protectors.

Small branches and small header attachments shall be adequately braced or otherwise

protected to prevent damage during handling, shipping and storage.

Socket Weld ends shall be closed and protected by solid plastic plugs.

While piping materials and spools are in storage, open ends are to be capped to eliminate

debris and dirt accumulation. Where practical, this practice is to be used while work is in

progress.

SUBCONTRACTOR will prepare a log with all the certificates materials including heat

number and it will be share with CONTRACTOR.

SUBCONTRACTOR shall ensure a system to control the traceability of the material

certificates, from the reception to the final delivery of the spools.

SUBCONTRACTOR shall control each lot of material thorough an Excel file, with all the

information including (but not limited) heat number, certificates, commodity codes…

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 93 OF 162

10651-00-QAC-PD-0003

REV.: 01

In the release of the spools fabricated, SUBCONTRACTOR shall submit as minimum (but

not limited) the following documentation: welding map of the welds marked in isometrics,

welding summary of the spools (including number of welds, WPS, heat numbers materials,

NDTs associate…) and NDT reports.

SUBCONTRACTOR shall report following the requirements of 10651-000-PRC-PD-0012

“Welding maps and Piping Production Reporting Procedure” and 10651-000-PRC-PD-0018

“UG Welding maps and Piping Production Reporting Procedure”.

Piping fabrication

The minimum requirements for fabrication and installation of metallic plant piping systems

including those on offshore structures are defined in SAES-L-350. This standard supplements

ASME B31 Codes.

Fiberglass-Reinforced Thermoset Resin (RTR) piping installers shall be trained and qualified

in accordance with RTR manufacturer requirements under SAEP-407.

The minimum requirements of welding, heat treatment, Non-destructive Testing (NDT), and

hardness testing requirements for shop and field fabrication and installation, repair, or

modification of piping are defined in ASME B31.3 and SAES-W-011 COMPANY

Specification.

The minimum requirements governing the fabrication of carbon steel pipe spools, including

welding, heat treatment, cold bending, and threading of pipes, are defined in the applicable

code and in the 01-SAMSS-010 COMPANY Specification.

The quantity or extent of a designated LOT/BATCH shall be defined and agreed with

CONTRACTOR before the start of work.

The types of branch connections indicated for each Piping Material Class in the General

Piping Material Specification are the minimum requirements for strength on the basis of

pressure, temperature, and allowable stress and shall be in accordance with SAES-L-110.

The reinforcement pad shall be in accordance with SAES-L-110 specification. A 3-6 mm

weep hole shall be provided for each reinforcing. The weep hole shall not be mechanically

plugged, nor seal welded but can be plugged with grease.

Steel plate used for reinforcing pads, sleeves, saddles and other structural attachments shall

conform to a code listed plate material with specified minimum yield strength of 241.3 MPa

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 94 OF 162

10651-00-QAC-PD-0003

REV.: 01

(35,000 psi) or greater. All reinforcing and attachment welds shall be continuous. Skip or

stitch welding is not permitted.

All required examinations and repairs shall be completed and approved before reinforcing

pads are welded onto the pipe.

Each pad, or separately welded portion of pad, shall have a 6 mm (1/4 inch) diameter

threaded vent hole drilled prior to installation of the pad.

Vent hole plug of reinforcing pad shall be done prior to start of welding to facilitate the release

of gases during welding and Pad shall be air tested after welding. For nozzles with reinforcing

pads, the nozzle attachment weld shall be completed and inspected prior to installing the

reinforcing pad.

The minimum distance between parallel butt welds shall be 20 mm or three times the wall

thickness of the joint, whichever is greater. This distance shall be measured between the

edges of the adjacent cap passes.

Pressure containing welds (e.g., nozzles and other attachments) shall be separated from

other pressure containing welds by no less than 20 mm or three times the joint thickness,

whichever is greater.

Internal misalignment of butt joints shall not exceed 1.5 mm. Internal tapering in accordance

with ASME B31.3 by machining, back welding, or a combination may be used to correct the

misalignment the following methods are recommended in descending order of preference to

minimize misalignment:

• Use of spreaders or line-up clamps to correct out-of-round conditions

• Tapering or counter boring with taper to align butt weld ends. Slopes, angles and

minimum remaining thickness shall be per ASME B16.25.

Coated and clad or overlaid surfaces shall be protected from the welding arc, associated weld

spatter, and damage from ground clamps or other associated equipment.

Butt weld end valves that have PTFE or other heat-sensitive parts shall be protected from

the heat of welding, or Post Weld Heat Treatment (PWHT), in accordance with

manufacturer’s instructions.

Suitable means of tools shall be used when start of Stainless Steels and Alloy steels and

make sure these tools have not been used on CS.

For socket-welded connections, the axial gap between male and female component, as

shown in Figure 328.5.2C of ASME B31.3 code, shall be maximum of 3 mm and minimum of

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 95 OF 162

10651-00-QAC-PD-0003

REV.: 01

1.5 mm. All socket welds shall be at least two pass welds. If SMAW welding is being utilized

the largest size of electrode that is permitted is 3.2 mm diameter

For proper piping alignment at pumps, SUBCONTRACTOR shall place a field weld at the first

weld from the pump nozzle. Consider placing a field weld in piping near equipment nozzles

to facilitate alignment where pipe configuration is inflexible.

Pipe insertion into a socket weld fitting shall be at least 6 mm (1/4 inch) or the pipe nominal

wall thickness, whichever is greater. The more stringent criteria shall be applied if this subject

it is forecasted in any other applicable international standard or project specification.

The minimum gap between the end of the pipe and the bottom of the socket shall be 1.5 mm

(1/16 inch) before welding.

Tool Box meeting documented ( attendance signature form, main topic to comment during

the toolbox , welding defect analysis, lesson learns…etc) shall be arranged on a weekly basis

prior to start of job for 15 min among SUBCONTRACTOR Fabricator, welders and operators

to discuss about the on-going issues related to piping and welding activities.

NOTE: SUBCONTRACTOR must provide Two Weeks look ahead to CONTRACTOR on

Weekly basis planned fabrication activity of each Material i.e. CS, SS, AS, Duplex, etc. ,

before to start the works CONTRACTOR will inspect the workshop in order to ensure the

precautions taken by the SUBCONTRACTOR in the areas are suitable to avoid

contamination between different materials for instance CS and SS.

SUBCONTRACTOR shall implement all the extra precautions measures imposed by

CONTRACTOR after the inspection in order to reduce/avoid the contamination between

different materials.

Welding Consumables

Electrodes, filler wires, and fluxes shall conform to ASME SEC IIC, SAES-W-010 “Welding

requirements for pressure vessels”, SAES-W-011 “Welding requirements for on-plot piping”

or SAES-W-012 “Welding requirements for pipelines”. Other consumables may be used only

with the approval of CONTRACTOR and, depending upon the process and application

proposed, may require testing in addition to that specified by ASME SEC IX. Approval to use

other (unlisted in ASME SEC IIC) consumables shall be obtained through the welding

procedure review process.

All consumables shall be tested in accordance with AWS A5.01 (or European/Japanese

equivalent) and the following table for Lot Classification and Level of Testing. Additional

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 96 OF 162

10651-00-QAC-PD-0003

REV.: 01

testing requirements may be included in the purchase order. Certifications shall accompany

all materials shipped.

Material tests certificates for materials as minimum shall comply with ISO 10474 Type

3.1(Mechanical properties & Chemical analysis) or EN 10204 Type 3.1, (Mechanical

properties & Chemical analysis) and any additional applicable CONTRACTOR/Project

specifications.

SUBCONTRACTOR shall maintain a log book having all the welding consumable particulars

including supplier, manufacturer, brand name, batch number, quantity received and received

date, RFI and report of reception. Drying and elevated temperature storage (holding) shall be

performed in thermostatically controlled ovens only when they are required for use. Fully

detailed log book shall be maintained for each oven.

Electrodes that are with unlisted designation as per ASME Sec II C, shall not be used.

At the arrival of Duplex and Stainless Steel filler metals (electrodes and GTAW rods), before

beginning of welding activities, each batch should be tested on yard/site verifying Ferrite

content and Positive Material Identification.

Storage, Colour Coding, Handling and Issuing of Consumables shall be as per the Standards.

Must have Baking, Holding or Potable Ovens with a required or specified temperature range.

All consumables shall be stored and dried in accordance with the requirements of ASME

codes and SAES-W specifications.

Calibration of Ovens to be performed every Six months in duration.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 97 OF 162

10651-00-QAC-PD-0003

REV.: 01

Toolbox meeting shall be arranged on a weekly basis prior to start of job for 15 min among

SUBCONTRACTOR Fabricator, welders and operators to discuss about the ongoing issues

related to piping and welding activities.

Duplex and Stainless Steel welding consumables (electrodes) shall be basic covered

electrodes. Rutile covered electrodes are strictly forbidden.

At the arrival of Duplex and Stainless Steel filler metals (electrodes and GTAW rods), before

beginning of welding activities, each batch should must be tested on yard/site verifying Ferrite

content and Positive Material Identification.

For Low Alloy Steels filler metal PMI shall be applied. SUBCONTRACTOR will prepare one

mock-up welded for each different batch number, CONTRACTOR will confirm after analyse

ferrite and the PMI result if the batch is approved for use in the project or no.

Welder Qualification

All welders, welding operators, brazers, and brazing operators shall be qualified in

accordance with the ASME SEC IX and SAEP-1150, SAEP-321, SAEP-322, SAEP-323, and

SAEP-324, as applicable, for all welding, including tack, temporary, and repair welds.

All welders and welding operators for weld overlays shall be qualified in accordance with

ASME SEC IX.

The test records of all welders and welding operators shall be available at all times at the

work location for review by CONTRACTOR/COMPANY Inspection.

Performance qualification

tests shall not be performed on production

joints on

CONTRACTOR work.

Current production repair rates of each welder shall be made available to CONTRACTOR/

COMPANY Inspection upon request. The repair rates shall be calculated on a linear basis.

Unless specified in Project Standards or Specifications, Welding rejection Rate for the Project

shall not be more than 5% on joint basis and 0.2% on linear basis.

The maximum weekly repair rate for each welder should not exceed 2%, or as determined

by CONTRACTOR:

where

% RR = (LT / LW) X 100

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 98 OF 162

10651-00-QAC-PD-0003

REV.: 01

% RR = percent repair rate.

LT= welder’s total length of repairs in one week, mm.

LW = welder’s total length of weld radiographed in one week, mm.

SUBCONTRACTOR welders that are properly certified and pass a welder’s performance

qualification test conducted by the Welder Testing Centre (WTC) shall be registered and

issued a Job Clearance Card

(Form SA 4758-ENG) by

the

responsible

CONTRACTOR/COMPANY Unit prior to the start of work.

Welder must carry a Welder ID Card all time at job site, which shall be issued by

SUBCONTRACTOR and validated and signed it by the CONTRACTOR.

Renewal of Welders and Welders ID card shall be every 6 months.

If there is a specific reason to question a contract welder’s ability to make sound welds the

inspector may require the contract welder to perform an Ability Test as described in SAEP-

  1. Contract welders that fail the Ability Test shall be terminated. A written request to

terminate that welder from Welder Tracking System shall be addressed to the (WTS)

Administrator.

Possible causes of failure or rejection of weld joints shall be explained to the welders in a

Toolbox to control the repair rate and welder performance.

Welders shall be qualified whenever there is a change in Essential Variables

Separate Qualification is required when job demands butt joint size of 1/2” and below (4 test

Coupons at least).

Possible causes of failure or rejection of weld joints shall be explained to the welders in a

Toolbox to control the repair rate and welder performance.

Current production repair rates of each welder shall be made available to CONTRACTOR

Inspection upon request. The repair rates shall be calculated on a linear basis and joint basis.

A cumulative rejection rate on joint basis of 5% shall never be exceeded per welder and

overall in the project. Welders even with cumulative rejection less than 5% on joint basis shall

be judge/enquired/retrained if they have a weekly rejection rates above 5% (joint basis)

repeatedly (if other applicable project specification specifies a more stringent criteria this last

shall be followed).

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 99 OF 162

10651-00-QAC-PD-0003

REV.: 01

Welder shall be stopped by the SUBCONTRACTOR or even for the CONTRACTOR from

welding if the welder is above the % Rejection Rate established in the project until he proofs

his ability to weld after certain duration of training (the duration of the training needs to be

agreed with CONTRACTOR).

Welding Procedures

All Welding Procedure qualification tests shall be subject to witness and approval by

CONTRACTOR. SUBCONTRACTOR shall also appoint THIRD PARTY Inspector to witness

the same (if required) (refer to SAEP-352 for details).

The welding procedure shall include the Welding Procedure Request Form (refer to SAES-

W-011-Attachment A), Welding Procedure Specifications (WPS), Qualification Test Records

(PQR), material certificates, and Weld Maps/Tables (refer to SAES-W-011-Attachment B).

WPS and PQR submitted for approval shall be in accordance with the requirements stated in

SAES-W specifications and International Codes

When a welding procedure need to be qualifed at site or workshop, the qualification shall be

done according to all requirements from ASME IX paragraph QG-106.4. The pWPS shall be

done in agreement with CONTRACTOR.

CONTRACTOR will assigned personnel to supervised and wittness the procedure

qualification together with SUBCONTRACTOR and THIRD PARTY.

The THIRD PARTY hired by SUBCONTRACTOR shall issue at least two PQR and duplicate

all required documentation (laboratory

test), One with CONTRACTOR name as

MANUFACTURER and another with SUBCONTRACTOR name as MANUFACTURER.

In the PQR issue by Third party shall be include that qualification was conducted under

provisions of ASME IX QG-106.4

All Welding Procedures property of SUBCONTRACTORS, that were qualified previously to

the commencing of this project, can also be proposed for approval, if they fully comply with

all the requirements of the Project.

SUBCONTRACTOR shall submit Preliminary Welding Procedure Specifications (PWPS) and

valid Welding Procedure Qualification Records (PQR) for CONTRACTOR and OWNER

review and approval.

An IWE shall be within the personnel of the SUBCONTRACTOR available in workshop & Site

to guarantee the welding process. For especially critical welds, this IWE must be the

interlocutor with the CONTRACTOR, all welding procedures to be used shall be develop by

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 100 OF 162

10651-00-QAC-PD-0003

REV.: 01

IWE and submitted as a complete package to CONTRACTOR for the technical approval prior

to the start of work.

Each CONTRACTOR / manufacturer / SUBCONTRACTOR / vendor or other who will perform

welding work (on equipment subject to regulations) has the obligation to use its own welding

procedures (WPS) in accordance with the relevant design code which apply according to

project requirements. In addition, and for those new welding procedures to be used in the

project, it should be CONTRACTOR decision if such procedures are qualified by

CONTRACTOR or by the SUBCONTRACTOR. In both cases SUBCONTRACTOR will

provide the necessary personnel and technical means free of charge (i.e. welders,

consumables, devices for inspection and test, QC personnel, transportation, laboratory for

test, etc.), being that provision of personal and technical means within the scope of the

SUBCONTRACT.

Once the PQR/WPS are approved by CONTRACTOR, SUBCONTRACTOR shall grant

permission officially to CONTRACTOR for using SUBCONTRACTOR’S WPS and supporting

PQRs for the extent of the Project. This permission shall be stated in writing.

A copy of respective WPS & PQR for a particular welding job shall be available in an area of

welding activities being executed

Welding Operations

SUBCONTRACTOR shall track welding activities on a daily basis and submit to

CONTRACTOR each week a weld tracking and welder performance report for that week

work. Cut-off date for submitting weekly performance report shall be agreed by

CONTRACTOR.

SUBCONTRACTOR shall not be started with welding works unless the WPS & PQR have

been approved by CONTRACTOR & COMPANY.

A copy of respective WPS for a particular welding job shall be available in an area of welding

activities being executed.

The first three (3) production pressure retaining butt welds welded by each new contract

welder shall be 100% radiographed. Radiographic acceptance shall be as specified by the

applicable design code governing the work.

Permanent backing rings or strips shall not be used.

Oil, moisture, rust, scale, sand, paint (except weldable primers for approved applications -

refer to SAES-W-011 for restrictions), metallic coatings (e.g., zinc), or other foreign matter

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 101 OF 162

10651-00-QAC-PD-0003

REV.: 01

shall be removed from the weld surface and at least 25 mm (1 in) of adjacent base metal

prior to welding, including any such coatings on temporary attachments or supports.

Thermally cut or gouged surfaces for all materials, including carbon steels, shall be power

brushed or ground prior to welding.

Tack welds that are to be incorporated into the final weld shall be thoroughly cleaned,

prepared at each end, and inspected for cracks. Any cracked tacks shall be removed before

welding the joint.

All tacks or temporary welds shall be performed with the same care, materials, electrodes,

minimum preheat, and procedures that are used for permanent welds.

Coated and clad or overlaid surfaces shall be protected from the welding arc, associated weld

spatter, and damage from ground clamps or other associated equipment.

For single-sided groove welds without backing, the process and electrode type used for the

root pass shall be considered an essential variable. The PQR shall be performed as a single-

sided groove weld without backing.

Procedures using any consumable with a “G” designation (ASME SEC IIC) shall be restricted

to the brand and type of electrode used for the PQR. The nominal chemistry of the specific

brand and type of electrode shall be identified on the WPS.

An inert backing gas shall be used for GTAW or GMAW root passes on single-sided groove

welds for materials of ASME P-No. 5 and higher.

For P-No. 5 and higher materials, any back purging shall be maintained until at least 10 mm

of the weld deposit thickness has been completed.

All pressure-containing welds shall be made with multiple passes. All socket welds shall be

at least two pass welds.

Weld overlays and welding of integral cladding shall conform to SAES-W-014 COMPANY

specification.

Welding of special corrosion-resistant piping materials shall conform to SAES-W-016

COMPANY specification.

It shall be a general practice of SUBCONTRACTOR to use Clamps or other suitable means

during Fit-up to avoid Tack Welds near or inside the groove.

Oxy fuel cutting shall not be done on Stainless Steel Material.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 102 OF 162

10651-00-QAC-PD-0003

REV.: 01

The use of nitrogen as a backing gas for Austenitic stainless steels is prohibited.

Maximum weld bead for SMAW & GTAW shall be 16mm & 13 mm respectively or three times

the Electrode dia whichever is greater.

Any oxide formation during welding SS & Alloys root pass shall be checked and cleared prior

to closing of Root in order to avoid failure of RT.

If found the corrosive surface during storage / fabrication / welding either inside or outside

surface of the Spool, shall be removed by Pickling or passivation.

Purging gas shall be maintained while welding Stainless steel & alloy materials throughout

the welding completion of root and hot passes of

the weld (at

least 10mm).

SUBCONTRACTOR must ensure the welders check before welding, the proper purge

composition using Pipe weld purge Oxygen Monitors.

Welding area shall be covered completely whenever there is an adverse effect from

environment such as rain, dust, wind (if exceeds 8 km/hr), etc.

Welding shall not be done when surfaces are wet or damp or exposed to rain or snow or

when the welders are exposed to inclement conditions.

Contamination from the environment, such as wind-blown sand, shall be prevented by the

use of adequate shielding.

Longitudinal seam joint for a big bore pipe shall be apart 45 to 180 degrees opposite to each

other and shall not be on the bottom position.

Welds shall not be resting on the beam/support surfaces.

Reinforcement Pad shall not overlap the pipe seam and in case can’t be avoided seam shall

be ground flush and RT for the covered part of the joint prior to pad welding.

When required Branch or Stub Inn joint, shall perform PT prior to start of placing the

Reinforcing Pad.

SUBCONTRACTOR Inspector shall ensure the Joint Fit-up to verify the joint integrity and

must perform 100% Weld Visual Inspection prior to raising an RFI. Fit-up shall be witnessed

and signed by SUBCONTRACTOR Inspector in order to verify the joint design, root gap,

bevel angle, cleanliness, high low, etc.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 103 OF 162

10651-00-QAC-PD-0003

REV.: 01

Prior to any repair for a rejected weld joint, shall perform PT for refit up and

SUBCONTRACTOR shall submit a repair procedure, get approved by CONTRACTOR

before starting of the job.

Low hydrogen electrodes shall be used.

Filler metal content Ni+Mn shall be limited to <1.2%.

Weld Identification

All weld joints shall be marked for identification by a weld number and a welder symbol. These

identifications shall be made with a suitable weather-proof marking material. The markings

shall be placed in a location such that they will be easily observed and remain visible for a

time suitable to the authorized COMPANY inspector.

The SUBCONTRACTOR shall establish and submit for approval an identification system that

shall uniquely identify each member and weld joint. The identification system shall be used

to identify all examinations, surveys, inspections, etc.

Welding Environment

Wind shields or tents shall be required when the wind is strong enough to affect arc stability

or shielding gas coverage or when deemed necessary by COMPANY inspection. GTAW,

GMAW, and gas shielded FCAW shall not be used for field or yard fabrication unless

adequate windshields are used. The wind velocity in the weld area for GTAW, GMAW, or gas

shielded FCAW shall not exceed 8 kph (2.2 m/s).

Welding shall not be done when surfaces are wet or damp or exposed to rain or snow or

when the welders are exposed to inclement conditions.

Contamination from the environment, such as wind-blown sand, shall be prevented by the

use of adequate shielding.

Pre-heat

Pre-heat treatment shall be in accordance with the ASME B31.3 and SAES-W COMPANY

specifications. For materials not covered by the Code or SAES-W COMPANY specifications,

the pre-heat treatment shall be as specified in the approved welding procedure.

If a weld joint is wet or has surface moisture or condensation, it shall be dried by heating for

a distance of 100 mm from the weld joint and shall be warm to the hand before welding unless

a greater pre-heat temperature is required.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 104 OF 162

10651-00-QAC-PD-0003

REV.: 01

The preheat temperature shall be established over a minimum distance of 75 mm Inch of

each side of the weld. If the wall thickness exceeds 25 mm and preheating is to be done from

the same side as the welding, then the heat source shall be removed for 1 minute to allow

for temperature equalization prior to measuring the temperature.

Interpass temperature shall be maintained effectively when job demands. Unless specified

otherwise, the maximum interpass temperature shall be 177° C for P-No. 8, P-No. 3X and P-

No. 4X materials and 315 deg. C for P-No. 1, P3 & P4 and P5 steels.

Temperature-indicating crayons, thermocouples, or calibrated contact pyrometers shall be

used to measure preheat and interpass temperatures. Temperature-indicating crayons shall

not be used for any weld joint that is to be coated or that will have a heat-shrink sleeve

installed on it.

Pre-heat

treatment shall be

in accordance with

International Codes and Project

specifications. For materials not covered by the Code the pre-heat treatment shall be as

specified in the approved welding procedure.

Preheating shall be done at least 3 Inch at adjacent sides of the joint. If the wall thickness

exceeds 25 mm and preheating is to be done from the same side as the welding, then the

heat source shall be removed for 1 minute to allow for temperature equalization prior to

measuring the temperature shall take care of preheating of joint when required. As a

minimum required 10ºC for CS and 10ºC for SS or as per the applicable Code interpass

temperature shall be maintained effectively when job demands. Unless specified otherwise,

the maximum interpass temperature shall be 150 deg. C for P-No. 8, P-No. 3X and P-No. 4X

materials and 315 deg. C for P-No. 1, P3 & P4 and P5 steels

If a weld joint is wet or has surface moisture or condensation, it shall be dried by heating for

a distance of 100 mm from the weld joint and shall be warm to the hand before welding unless

a greater pre-heat temperature is required.

Additional requirements for welding P-91 grade material (included dissimilar joints between

alloys steel (such as P91-P22)):

Recorded preheating shall be performed in all welds

Electrical resistances shall be used for preheating (torch shall not be applied)

Preheating shall be maintained through all the welding process. Preheat and interpass

temperatures shall be monitored and checked by thermocouples, in case it is not possible

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 105 OF 162

10651-00-QAC-PD-0003

REV.: 01

place thermocouples, temperature indicting crayons, surface contact pyrometers, or other

suitable methods shall be used.

For components made of groups P-15E, or dissimilar joints where P-15E material are

involved, (for example between alloys steel (P91-P22)). Interruptions in welding shall be

avoided. The welds shall be maintained at 250ºC-300ºC (400°F - 572°F) for two hours after

welding before cooling under insulation to 90ºC (200°F) or below prior to receiving PWHT.

The delay after cooling up to execution of PWHT shall be minimized and the welds shall be

protected against the exposure to moisture to avoid possible SCC in this period.

Minimum distance to be kept between joints:

Longitudinal Weld- Longitudinal Weld: Longitudinal welds in adjoining components shall be

staggered by twice the nominal wall thickness, with a minimum distance of 20 mm.

Buttweld-Buttweld: minimum distance from weld toe to weld toe should be 50mm or three

times the base metal thickness, whichever is larger.

Buttweld- fillet weld: from the weld toe to weld toe of joints: 50mm or three times the base

metal thickness, whichever is larger.

Branch connection-buttweld: from the weld toe to weld toe of joints: 50mm or three times the

base metal thickness, whichever is larger.

Branch connection- fillet weld: from the weld toe to weld toe of joints: 50mm or three times

the base metal thickness, whichever is larger.

In the case that the mentioned distances cannot be respected due to construction

necessities. Query shall be risen to avoid this requirement and mitigation measures shall be

taken into account. Additional PWHT and/or Non-Destructive Test will be performed to both

weld joints in order to ensure the soundness of construction in both joints.

Post Weld Heat Treatment

Post weld heat treatments (PWHT) shall be in accordance with ASME B31.3, and applicable

International Codes and project specifications (SAES-W specifications). A written procedure

describing the general PWHT requirements shall be submitted for review and approval of the

CONTRACTOR. The PWHT procedure shall include descriptions of the equipment, method

of heating, location and type of heating elements, temperature measurement, and

thermocouple locations. The review and approval process shall be the same as described for

welding procedures.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 106 OF 162

10651-00-QAC-PD-0003

REV.: 01

Prior to the start of work the SUBCONTRACTOR shall prepare a table listing each joint or

component requiring heat treatment, which shall be submitted to CONTRACTOR Inspection

for review. The table shall include the following information for each joint or component:

location, drawing number, diameter, wall thickness, material, heating rate, and cooling rate,

soak temperature, and soak time.

Joints that have been PWHTed and needs any welding or heating requires new PWHT. Post

weld heat treatment shall follow all welding and repairs but shall be performed prior to any

hydrotest.

Code exemptions for post weld heat treatment of P-No. 4 and P-No. 5 materials are not

permitted for applications involving either sour service or materials exceeding 1.5% nominal

chromium content and require CONTRACTOR previous approval.

Additional requirements for welding P-91 material (including dissimilar joints where P-91 is

involved):

All P-15E base material welded to group P-5, P-4, P-3 base material and welds between

group P-15E shall be given a PWHT with a minimum soak time of 2 hours. This requirement

shall apply on any part completely or partially fabricated by SUBCONTRACTOR.

Soaking time temperature shall be between 730-770 ºC

When components have both group P-15E to P-15E welds and group P-15E to group P5, P-

4 or P-3 welds;

• make all group P-15E to group P-15E welds first and perform PWHT.

• Then make any group P-15E to group P-5, P-4 or P-3 welds and PWHT.

At least two thermocouples shall be required to record preheating and PWHT and will vary

depending on the diameter of the pipe to be PWHT.

The delay after cooling up to execution of PWHT shall be minimized and the welds shall be

protected against the exposure to moisture to avoid possible SCC in this period.

PRODUCTION WELD HARDNESS TESTING

Testing shall be in accordance with NACE RP0472 and the requirements listed in SAES-W

COMPANY specification. Exemptions with respect to welding process and consumables are

not allowed. The testing guidelines in Appendix A of NACE RP0472 shall be mandatory.

Readings in the heat-affected zone shall be conducted if specified by the applicable Code or

Standard.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 107 OF 162

10651-00-QAC-PD-0003

REV.: 01

Production hardness testing of welds shall be performed as required by ASME B31.3 and

SAES-W COMPANY specifications.

Inspection Access

CONTRACTOR shall have free access to the work at all times.

CONTRACTOR shall have the right to inspect the fabrication at any state or stage and to

reject material or workmanship which does not conform to the specified requirements.

CONTRACTOR reserves the right to inspect, photograph, and/or videotape all material,

fabrication, coating, and workmanship and any materials, equipment, or tools used or to be

used for any part of the work to be performed. CONTRACTOR may reject the use of any

materials, equipment, or tools that do not conform to the specification requirements,

jeopardize safety of personnel, or impose hazard of damage to property.

The SUBCONTRACTOR shall provide the authorized CONTRACTOR inspector all

reasonable facilities to satisfy him that the work is being performed as specified.

The SUBCONTRACTOR shall furnish, install, and maintain in a safe operating condition all

necessary shoring, scaffolding, ladders, walkways, and lighting for a safe and thorough

inspection which is satisfactory to CONTRACTOR Inspection.

NOTE. - SUBCONTRACTOR shall submit all Welding Reports to CONTRACTOR on daily

basis, according to the specific requirements applicable for the Project. The daily report shall

be submitted in paper (originals) and also the Loaders given by CONTRACTOR to

SUBCONTRACTOR for that purpose.

Non-Destructive Testing

SUBCONTRACTOR shall comply entirely with “NDT & PWHT REQUIREMENTS STUDY”,

this study covers the Non Destructive Examinations (NDE) and Post Weld Heat Treatment

(PWHT) for the different piping classes to be executed during assembly, designed as per

ASME Code B31.3 (if any other project specification or applicable international code

forecast the performance of additional NDTs the most restrictive document shall be

applied).

Non-destructive Examination (NDT)

inspection procedures shall be established

in

accordance with ASME SEC V and Project Standards, Procedures and Specifications. A

written procedure for each inspection method and technique, including acceptance criteria,

to be used shall be submitted to CONTRACTOR for approval. Inspection procedures in

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 108 OF 162

10651-00-QAC-PD-0003

REV.: 01

conformance with other standards are acceptable only with the approval of Inspection

Department. NDT performed without approved procedures shall be considered

unacceptable.

All appropriate safety precautions shall be taken for each inspection method. Particular care

shall be taken when performing the RT at site to avoid the Exposure of the source during site

work operations.

Inspection at mill, shop, or fabrication yard shall not relieve the SUBCONTRACTOR

(manufacturer or fabricator) from his responsibility for repairing or replacing any defective

material or workmanship that may be subsequently discovered in the field.

SUBCONTRACTOR may, upon approval of the CONTRACTOR, delegate establishment and

continuation of the NDT Log to sub-CONTRACTOR directly responsible to provide

construction activities on the Project. Wherein such approved delegation has occurred,

SUBCONTRACTOR shall be responsible for the assurance of upkeep and accuracy of the

NDT Log.

Regarding welding activities, SUBCONTRACTOR shall ensure that NDT companies

proposed by SUBCONTRACTOR on site and/or in prefabrication shop must have enough

capacity to cover the daily necessities of the Production. The NDE companies on site or in

prefabrication shop must have enough capacity to cover the necessities properly and on time.

Action Plans/Corrective Actions shall be taken by SUBCONTRACTOR to mitigate whatever

backlog, and other delays in providing documentation, inspections, other process, etc.

The SUBCONTRACTOR will supply to the CONTRACTOR enough, competent and qualified

personnel to work under CONTRACTOR supervision supporting the NDT office activities

related to the NDT- PCA application for instance PCA NDT loaders, store the PWHT reports,

RT reports, PMI reports …etc. Approval requirement before mobilization and demobilization

is mandatory, If the performance is not the expected one, CONTRACTOR will keep the right

to revoke the previous acceptance

SUBCONTRACTOR shall maintain all necessary resources (e.g. computer, software, etc) for

NDT review analysis of NDT Service Provider´s NDT Report Data for AUT application such

as ToFD (Time of Flight Diffraction) and PAUT (Phased Array UT) and to assure that

SUBCONTRACTOR’s Level II Inspectors/Technicians and/or NDT Level III have been

trained by the Manufacturer or authorized Manufacturer representative.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 109 OF 162

10651-00-QAC-PD-0003

REV.: 01

Written reports and evaluations of all inspections performed by vendors, CONTRACTORs,

and fabricators shall be made and submitted to CONTRACTOR, at a frequency to be

determined by CONTRACTOR.

Reports of Manual UT (MUT), Magnetic Particle Testing (MT) and Liquid Penetrant Testing

(PT) shall be prepared on-site at the time tests are conducted and prior to any repairs, if

required. If repairs deemed necessary are completed concurrent with ongoing MUT, MT,

and PT, reports will accurately reflect the initial rejection, and results of subsequent NDT

following repairs.

Additional inspection of any weld joint at any stage of the fabrication may be requested by

CONTRACTOR

Inspection,

including

re-inspection of previously

inspected

joints.

CONTRACTOR Inspection also has the right to request or conduct independent NDT of any

joint. If such testing should disclose gross non-conformance to the Code requirements, all

repair and NDT costs shall be done at the CONTRACTOR’s SUBCONTRACTOR’s expense.

All NDT personnel technicians, supervisor and helpers shall be qualified in accordance with

International Codes, SAEP-1140 or SAEP-1142 and Standards.

100% Visual Inspection is required by the SUBCONTRACTOR Inspector for completed welds

prior to issue of RFI. Inspector must sign adjacent to the weld joint as (VI Accepted.) Surface

irregularities, including weld reinforcement, inhibiting accurate interpretation of the specified

method of NDT shall be ground smooth.

Inspection of all welds shall include a band of base metal at least 25.4 mm wide on each side

of the weld.

Must make sure all NDT & PWHT activities have been completed and accepted prior to start

of Pressure Testing.

The joint must be cleaned and air blow inside prior to Radiography shot to avoid reshoot.

No more than two repairs are allowed for a particular joint which fails in NDT and shall be cut

and re-welded.

The joints which are radiographed shall be marked as ¨RT done¨ for easy identification of

Radiographed joint.

SUBCONTRACTOR shall establish a system of serialized log for all NDT uniquely identifying

the individual welds to be tested and method applied. This log is to be an ongoing log of NDT

requests and completions as the Project progresses. The log reference (serial number) for

each weld or welds examined shall be included in NDT reports. NDT of any repair shall be

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 110 OF 162

10651-00-QAC-PD-0003

REV.: 01

sequentially identified in the log and include the log reference of the initial NDT that

determined need for the repair.

SUBCONTRACTOR shall direct NDT Service Provider (sub-CONTRACTOR(s)) to prepare

all NDT reports with sufficient number of direct duplicate copies (e.g. NCR Paper) to provide

for “Control Copies”. Control Copies of all NDT reports issued to the SUBCONTRACTOR

must simultaneously be submitted to the CONTRACTOR on-site Inspection Department

representative and the NDT Service Provider’s nearest area office.

• All NDT reports shall clearly indicate by printed name, signature, and where applicable identification reference of personnel conducting the NDT and interpreting results.

• Witness, review, and approval by SUBCONTRACTOR shall be indicated by

printed name, signature, and applicable identification on the original NDT report.

Control Copies held by SUBCONTRACTOR’s NDT Service Provider (sub-

CONTRACTOR) and those issued to CONTRACTOR as noted above shall be

retained throughout the duration of the project.

• No specific action is involved required by SUBCONTRACTOR for control copies

of NDT reports unless deemed necessary by CONTRACTOR. Control copies of

NDT reports are for record purpose and if necessary, investigative review of the

SUBCONTRACTOR’s NDT performance

Radiography Reports shall include date, radiographer, weld identification, number of films,

radiation description (source, type, strength, size, exposure time, source distance), film

(brand, type, processing), and film reviewer. The minimum requirements for written

procedures that governing the radiographic examination of welds are defined on SAEP-1143

“Radiographic examination”.

SUBCONTRACTOR shall submit its test reports test reports to the CONTRACTOR

Representative as

specified by

the applicable COMPANY

standards. The

SUBCONTRACTOR shall review its test reports prior to submittal

For all other test reports/validation records whether performed by SUBCONTRACTOR Test

reports/validation records shall be maintained current and available at SUBCONTRACTOR

site office for CONTRACTOR review.

NDT Reporting

• Report shall comply with the minimum requirements from the applicable standard.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 111 OF 162

10651-00-QAC-PD-0003

REV.: 01

• One different report shall be issued per isometric/date the most restricted. If some

of two previous variables change, a new report shall be issue. Applicable for all

NDTs except Radiographic and Ultrasonic.

• One report per weld shall be issue when Radiography or Ultrasonic is used.

• The codifications of the reports will be as follow:

TT-SSS-III-NNNNN (“ “/B/BSR)

Where:

• TT: Type of NDT (RT, UT, PAUT, PT, MT, FE, PMI, VT, HT, TM)

o

o

o

o

o

o

o

o

o

o

RT: Radiographic Test

UT: Conventional Ultrasonic Test

PAUT: Phased Array Ultrasonic Test

TM: Ultrasonic thickness measurement Test

PT: Penetrant Test

MT: Magnetic Test

VT: Visual Test.

FE: Ferrite Test

PMI: Positive Material Test

HT: Hardness Test.

• SSS: Name of Mechanical SUBCONTRACTOR, identified by 3 unique letters for the

Project (Example SICMIC (SIC)).

•

III: Name of Inspection/NDT SUBCONTRACTOR, identified by 3 unique letters for the

Project (TPR for example).

• NNNNN: Sequential number starting from 00001.

• B/BSR:

1 FINAL DIGIT (B) - This digit will ONLY be used for those PT/MT reports

performed on the bevels (if required).

1 FINAL DIGIT (BSR) - This digit will ONLY be used for those RT/UT reports

performed before stress relief (PWHT) is done. (if used)

o

o

Example:

o

RT-SIC-TPR-00001 - First RT report, from SICMIC, by NDT Company named

TPR

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 112 OF 162

10651-00-QAC-PD-0003

REV.: 01

▪ RT-SIC-TPR-00040BSR - RT report number 40, by NDT Company

named TPR before PWHT is performed.

VISUAL EXAMINATION

All welds shall be visually examined. Visual examination shall be performed prior to another

NDT.

Where accessible, welds shall be visually examined from the root side to ensure that proper

penetration and fusion have been achieved.

RADIOGRAPHY

The minimum requirements for written procedures that governing the radiographic

examination of welds are defined on SAEP-1143 “Radiographic examination”. This procedure

applies to radiographic examinations of the welds made by the SUBCONTRACTOR.

ASME SEC V, Article 2 shall be used to determine the minimum number and required

locations of radiographs for circumferential joints.

Particular care shall be taken when performing the RT at site to avoid the Exposure of the

source during site work operations.

Fluorescent intensifying screens shall not be used. Fluor-metallic screens shall be approved

by CONTRACTOR prior to use.

Tungsten inclusions in Gas Tungsten Arc welds shall be evaluated as individual rounded

indications. Clustered or aligned tungsten inclusions shall be removed and repaired.

All field radiographic exposures (vendor, shop, and yard radiography are exempt) shall be

performed using at least two (2) people: a SAEP-1140 or SAEP-1142 qualified Level II

radiographer and an assistant who is qualified to operate all of the equipment.

If a pressure-containing weld will not be hydrotested, it shall be radiographed only after

approval of a waiver request. If the joint is required to be radiographed for other reasons (e.g.,

service conditions, design requirements) or if radiography is not technically practical, then

other NDT methods shall be specified.

If the joint is required to be radiographed and radiography is not feasible, then UT and MT

may be used in lieu of RT. This requires the approval of CONTRACTOR. This does not apply

if radiography is required by ASME B31.3.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 113 OF 162

10651-00-QAC-PD-0003

REV.: 01

100% Visual Inspection is required by the SUBCONTRACTOR Inspector for completed welds

prior to issue of RFI. Inspector must sign adjacent to the weld joint as VT ACPTD.

The joint must be cleaned and air blow inside prior to Radiography shot to avoid reshoot.

No more than two repairs are allowed for a particular joint which fails in RT and shall be cut

and re-welded.

The joints which are radiographed shall be marked as ¨RT done¨ for easy identification of

Radiographed joint.

Radiography Reports shall include date, radiographer, weld identification, number of films,

radiation description (source, type, strength, size, exposure time, source distance), film

(brand, type, processing), and film reviewer.

Dark room shall be facilitated with an illuminator of specified intensity for proper reviewing of

the RT films.

Radiography Tested films shall be stored at a required temperature in a separate Dark room

which can be utilized for reviewing of the Radiography tested films.

MAGNETIC PARTICLE

The minimum requirements for written procedures that governing the magnetic particle

examination of welds and components are defined on SAEP-1144 “Magnetic Particle

Examination”. This procedure applies to magnetic particle examinations of the welds made

by the SUBCONTRACTOR. The requirements for vendor magnetic particle examinations are

given in Project Standards and Specifications.

The acceptance criteria for magnetic particle examination shall be ASME SEC VIII, Appendix

The procedures governing magnetic particle examinations need to specify the steps to be

taken to prevent electrical faults, inhalation of harmful materials, skin irritation, and ignition of

flammable materials.

Permanent magnet yokes are not permitted.

Prods are not permitted for use on air hard enable materials or on materials with impact

testing requirements or on the fluid side surface of components in sour service.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 114 OF 162

10651-00-QAC-PD-0003

REV.: 01

MT Examination Reports shall include date, examiner, item examined, material thickness,

surface temperature, white light intensity, UV light intensity, contrast coating, particle

description, MT equipment used, and magnetic current.

LIQUID PENETRANT

The minimum requirements for written procedures that governing the liquid penetrant

examination of welds and components are defined on SAEP-1145 “Liquid Penetrant

Examination”. This procedure applies to liquid penetrant examinations of the welds made by

the SUBCONTRACTOR. The requirements for vendor liquid penetrant examinations are

given in Project Standards and Specifications.

The acceptance criteria for liquid penetrant examination shall be ASME SEC VIII, Appendix

The procedures governing liquid penetrant examinations need to specify the steps to be

taken to prevent inhalation of harmful materials, skin irritation, and ignition of flammable

materials.

ULTRASONIC

Ultrasonic testing may be substituted for radiography if approved by COMPANY inspection.

A computerized automatic ultrasonic system must be used for all welding performed with an

automatic/mechanized GMAW welding system operating in the short-circuiting mode. The

system must be approved by Inspection Department.

When a computerized automatic ultrasonic system is used, it shall be operated within the

equivalent of one hour’s production from joints currently being welded.

SUBCONTRACTOR shall provide UT digital file and viewer on weekly basis.

POSITIVE MATERIAL IDENTIFICATION

The minimum requirements for guidance for Plant Inspectors performing Positive Material

Identification (PMI) are defined in SAIP-07 “Positive material identification requirements”.

NDT COVERAGE

All welds will be inspected in accordance with CONTRACTOR NDT & PWHT Study, ASME

B31.3, Project Standards, Procedures and Specifications, Safety requirements based on the

fluid service categorization and piping material classification and the additions listed below.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 115 OF 162

10651-00-QAC-PD-0003

REV.: 01

All information provided from CONTRACTOR does not exempt SUBCONTRACTOR from

compliance with Project Specifications, Standards and applicable Codes, etc. No

requirement as per direct or indirect reference to Project Specifications, Standards,

applicable Design Code, etc. shall be waived unless approved by CONTRACTOR and/or

COMPANY.

The listed extent of NDT shall be applied using the following methods:

VISUAL EXAMINATION

All welds shall be visually examined. Visual examination shall be performed prior to another

NDT.

Where accessible, welds shall be visually examined from the root side to ensure that proper

penetration and fusion have been achieved.

RADIOGRAPHY

Welds in piping shall be inspected in accordance with ASME B31.3 and with the additions

stated in SAES-W-011 and SAES-W-012 and according Project Standards, Procedures and

Specifications, Safety requirements based on the fluid service categorization and piping

material classification.

MAGNETIC PARTICLE TESTING AND LIQUID PENETRANT TESTING

These Non-destructive tests shall be inspected in accordance with ASME B31.3 and with the

additions stated in SAES-W-011 and SAES-W-012 and according Project Standards,

Procedures and Specifications, Safety requirements based on the fluid service categorization

and piping material classification.

These tests must be performed as following:

• Magnetic particle testing (MT) for ferromagnetic materials.

• Liquid penetrant testing (PT) for non-ferromagnetic materials.

All pressure containing welds, other than butt welds, (including branch connections such as

weldolets, sockolets, and welding bosses) shall be 100% examined.

All attachment welds on pressurized components that are not hydrotested after making the

attachment weld shall be 100% examined.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 116 OF 162

10651-00-QAC-PD-0003

REV.: 01

ULTRASONIC TESTING

Welds shall be inspected in accordance with ASME B31.3 and with the additions stated in

SAES-W-011 and SAES-W-012 and according Project Standards, Procedures and

Specifications, Safety requirements based on the fluid service categorization and piping

material classification.

POSITIVE MATERIAL IDENTIFICATION (PMI)

PMI shall be conducted for the materials listed in Table 1 of SAES-A-206 COMPANY

specification.

REPAIRS

Welds may be repaired twice at any defect location. If a weld is still not acceptable after the

second repair, then CONTRACTOR has the sole authority for the decision to permit additional

repair attempts or to require that the entire weld be cut out. The limitation on the number of

repairs does not include adjacent sequential repairs where the length of the area to be

repaired is limited by structural strength or other considerations.

Repair of cracks that are fabrication related shall require the approval of CONTRACTOR &

COMPANY assigned inspector. The repair procedure including inspection, excavation

approved welding procedures shall be reviewed and approved by the inspector. Cracks that

are related to the base metal or welding consumable shall be evaluated by CONTRACTOR

before any repair attempts. Crater cracks do not require special repair and shall be ground

out only.

In-process repairs (i.e., repairs performed prior to completion of the joint using the same

welding procedure as for the original fabrication) during production do not require a separate

repair procedure except for cracks.

The repair procedure may utilize a welding procedure previously approved by

CONTRACTOR in conjunction with a separate method statement or it may be a separate

detailed welding procedure.

All repaired welds shall be inspected using the original testing method. Additional test

methods may also be required, if deemed necessary by the CONTRACTOR inspector.

Replacement weld (cut-out) shall be examined as a repair.

Damage or deformation to the base metal or welds, including dimensional changes, caused

by external forces (intentional or accidental) requires special repair and inspection

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 117 OF 162

10651-00-QAC-PD-0003

REV.: 01

procedures to be submitted to CONTRACTOR for review and approval prior to undertaking

the repairs.

Any weld not meeting the acceptance criteria of the applicable code or standard shall be cut

out or repaired. Other methods, such as sleeving, shall not be permitted.

Repairs to offshore or onshore pipeline shall be repair as SAES-W-012.

PIPING HANDLING, STORAGE AND ERECTION

All materials shall be handled with care during fabrication and installation to prevent damage.

Lined and coated pipes and fittings shall be lifted with wide fabric or rubber-covered slings

and padding shall be used to prevent damage to lining or coating in accordance with SAES-

H-200.

Spools shall be segregated in a separate location depending on their Material. Such as CS,

SS, AS, etc.

Proper care shall be taken while storage and handling of SS piping to avoid any

contamination.

Proper colour coding shall be maintained either as per code or project specifications to avoid

mishandling and utilization of material during fabrication.

Piping spools shall be laid on a wooden plank in order to avoid contamination with the ground

and it shall be covered with Pipe end caps or by suitable means to restrict the debris, dust or

other foreign particles entry.

When erection of pipe, shall be verified that no weld joint or seam is resting on Structural

beam on pip racks.

Piping spools shall be Air Blow prior to erection to remove if any debris or welding spatters

which will be accumulated during grinding and welding activities.

Piping spools end caps to be maintained before and after fabrication activities to avoid

accumulation of any debris, dust and other foreign materials.

Flange face shall be protected by covering it with Wooden or plastic material to avoid any

damage to Flange face serrations.

Gasket colour coding shall be marking directly in the workshop, by brush and/or spray

painting, in the either as per guide colour cod.ng Ral number materials. For small bore gasket

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 118 OF 162

10651-00-QAC-PD-0003

REV.: 01

(diameter ≤ 2”), the colour mark will be stripes all around the circumference and painted on

two sides. Marking applied for big bore gasket (diameter > 2”) the colour mark will be

providing all around the circumference and painted on four sides for proper colour gasket

identification during flange close erection.

The pickling & passivation apply to all welds on Stainless Steels & Alloys, shall be to make

daily part of welding activities. Of this mode, the pickling & passivation apply on welds after

finished avoiding that long periods of time do not pass without applicate the pickling &

passivation.

Additionally, when required Pickling or Passivation shall be done on Stainless Steels & Alloys

to remove any corrosion, discoloration or oxidation traces with a CONTRACTOR approved

material.

CALIBRATION

Baking, Holding Ovens and Quiver shall be calibrated every twelve (12) months in duration.

Welding Machines shall be calibrated for every twelve (12) months.

The calibration interval for Pressure Gauges which are to be used during Pressure Testing

shall not exceed one (1) month prior to test date.

Safety Relief Valve to be used during pressure test shall be calibrated within two (2) weeks

prior to the pressure test.

Manifolds which are to be used for Pressure Testing shall be designed as per applicable code

and approved by CONTRACTOR, then certify under pressure conditions by CONTRACTOR.

If mechanical integrity is questionable, CONTRACTOR has the right to call for re-test.

Torque Wrench used for Bolt Torqueing shall be calibrated every three (3) months unless

specified in written by the manufacturer.

Calibration shall be performed at established periods as specified in the most stringent of

COMPANY standards, others applicable standards, or manufacturer recommendations, if no

standards apply, the calibration cycle shall not exceed twelve (12) months.

PRESSURE TESTING

SUBCONTRACTOR shall prepare a pressure test procedure and submit it to the

CONTRACTOR for review at least thirty (30) calendar days prior to the start of the Pressure

Testing tests.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 119 OF 162

10651-00-QAC-PD-0003

REV.: 01

The SAES-L-150 “Pressure testing of plant piping and pipelines”, SAES-A-004 “General

requirements for pressure testing” and SAEP-1160 Section 8 “Tracking and Reporting of

Welding NDT and Pressure Testing for Capital Projects – Section 8 Pressure Testing

Verification” are the minimum mandatory requirements governing pressure testing of new

and existing pipelines, plant piping and pressure containing process equipment (hereinafter

called equipment) which are designed and constructed in accordance with ASME B31.1,

ASME B31.3, ASME B31.4, or ASME B31.8 codes as applicable. This standard supplements

ASME B31 and other applicable codes.

The test Procedures shall be prepared and conducted in accordance with SAES-A-004,

“General Requirements for Pressure Testing”. CONTRACTOR shall submit hydro test

procedure documents for review and approval by COMPANY PMT. The documents shall

include detailed safety precautions and section by section cleaning, gauging, hydrostatic

testing, and drying plans taking full cognizance of the pipeline profile and installation

characteristics. It shall also include step-by-step procedures for hydro test isolation,

equipment setup, scraper operations, filling, pressurization, stabilization period, hydro test

hold period, valve operation, and data logging/recording. The procedure shall include details

of where and how the pressure test procedure shall include all required documentation

specified in GI-0002.102, paragraph 5.2.

The requirements regarding test water quality and lay-up condition shall be in accordance to

SAES-A-007, “Hydrostatic Testing Fluids and Lay-up Procedures”. Water used for Hydro Test

shall be laboratory tested to confirm as minimum PH Scale, chloride content, Sulphate

reducing bacteria (SBR) content, total suspended solids (TSS) content, dissolved Oxygen

and residual Oxygen scavenger contents of the water (limits shall accomplish project

requirements, or the ones specified by CONTRACTOR. If water supplied by Vendor, shall

acquire a Quality Certificate.

Specific Testing Requirement shall be consulted on SAES-A-004 “General requirements for

pressure testing” that specifies in detail which piping or equipment that shall be pressure

tested and provides the specific applicable standard. It also defines any specific exemptions”

Where pressure variations due to test water temperature changes occur, such as in cross-

country pipelines, thermocouples shall be installed to obtain accurate pipe metal temperature

measurements to determine the acceptance of the pressure test. COMPANY shall be

consulted for any deviations on the 24-hour pressure chart.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 120 OF 162

10651-00-QAC-PD-0003

REV.: 01

Safety permit for the pressure testing shall be acquired from the Safety Department and must

available during the pressure testing.

The effect of the static head of the testing liquid shall be considered when determining the

effective test pressure of any elements within a tested system.

Protection from Overpressure

All systems (piping and equipment) while being pressure tested shall be protected from being

overpressure by the following:

• Relief valve(s) of adequate capacity set to relieve at 5% above the test pressure shall be

installed unless the test pressure is less than 85% SMYS at which time it can be set at

10% above the test pressure. Sizing of these relief valves used for testing shall follow the

requirements of API RP 520, Part 1. The relief valve(s) shall be tested, dated, and tagged

within one week prior to the pressure test for new construction projects, and within one

month for maintenance operations.

•

In addition to the pressure relieving device, a bleed valve shall be provided to protect the

piping and equipment from overpressure. The bleed valve shall be readily accessible in

case immediate depressurization is required.

• An isolation valve shall be provided between the pressure testing manifold and the system

being tested. The isolation valve shall be rated for the manifold test pressure when in the

closed position.

Before employing the pressure testing manifold in the actual system pressure test, it shall be

separately pressure tested to at least 1.2 times the system test pressure but not less than

the discharge pressure of the pump used for the pressure testing. Test pressures and test

durations shall be based on the applicable standard SAES-L-150.

All joints including welded shall be left exposed for visual leak detection during the strength

test. All welded joints may be primed and painted prior to hydrostatic testing unless a sensitive

leak test is required as defined in ASME Section V, Article 10.

The minimum requirements for pressure test shall be in accordance with SAES-L-150, SAES-

A-004 and SAES-A-007 COMPANY specifications.

The test procedure shall be available on site at all times.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 121 OF 162

10651-00-QAC-PD-0003

REV.: 01

The pressure test procedure shall include all required documentation specified in GI-

0002.102, paragraph 5.1.2.

Filling and pressurizing shall be done on the upstream side of check valves in the system.

The test fluid shall be injected at the lowest point in the system to minimize entrapped air.

When filling at the lowest point is not practical, the Inspection Department/ Operations

Inspection Engineering Unit shall be consulted. All vents shall be open during filling.

After the test pressure is reached and before commencement of inspection of the system,

the isolation valve between the temporary test manifold/piping and the piping/equipment

under pressure test shall be closed and the test pump disconnected. The isolation valve

downstream of the manifold shall be opened after the pump is disconnected.

During the application of the test pressure, all in-line valves if not used as test isolation valves

shall be in an open position.

All piping and equipment shall comply with the lay-up procedures per SAES-A-007.

Test Records shall be recorded on Pressure Test Report Form 2642-ENG and the applicable

“Safety Instruction Sheet” per SAES-A-005.

Pneumatic testing is not permitted without written approval of the CONTRACTOR. Flare

lines 24-inch NPS and larger with a design pressure of 517 kPa (ga) (75 psig) or lower may

be pneumatically strength tested in accordance with paragraph 345.5 of ASME B31.3.

Water quality of intended hydrostatic test shall be determined according to SAES-A-007

specification.

Type 300-series stainless steels shall be tested only with water that has very low chloride

content in order to avoid pitting and stress corrosion cracking. The maximum allowable

chloride concentration is 50 ppm. Verify the quality of the water following the requirements of

SAES-A-007 specification.

Minimum of Two Pressure Gauges shall be used during Pressure Testing, one at the lowest

point and other at the highest point of the Test Limit.

No repair or modification shall be entertained after testing (Hydro/Pneumatic). If any, the

particular part or the whole shall be retested.

Joints shall be exposed and visible during testing to reveal any leakage.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 122 OF 162

10651-00-QAC-PD-0003

REV.: 01

SUBCONTRACTOR shall apply a clear identification method for gaskets that allows easy

verification after installation. The proposed method is subject for CONTRACTOR’s approval

prior to gaskets placement. Temporary gaskets used for pressure testing shall be replaced

after test.

If the drop in ambient temperature may cause the test medium to freeze during the test,

appropriate precautionary measures must be taken to protect the equipment or piping

systems.

Testing

Test preparation

An approved test procedure shall be available at the site prior to commencing any pressure

testing activities.

New piping systems shall be cleaned in accordance with SAES-L-350.

Soft seated valves and control valves shall not be installed until after the lines have been

thoroughly flushed.

Components in new piping systems which interfere with filling, venting, draining or flushing

shall not be installed until after line flushing and pressure testing are completed. These

include orifice plates, flow nozzles, sight glasses, venturies, positive displacement and

turbine meters and another in-line equipment.

Pressure gauges and pressure recorders shall be calibrated before the tests.

• The calibration interval shall not exceed one (1) month. Calibration certificates shall

be made available to Inspection personnel prior to commencement of the pressure

test. Stickers shall be applied indicating the latest calibration date.

• All gauges shall have a range such that the test pressure is within 30 to 80% of the

full range.

• A minimum of two pressure gauges are required for the test system. One pressure

gage shall be on the test manifold and the other(s) on the test system. Their accuracy

shall be within 5% of one another.

• When large systems are tested, Inspection personnel will determine the need for

additional gauges.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 123 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Recording gauges shall be used where it is necessary to keep a permanent record,

e.g., when the test duration exceeds four hours, or otherwise as required by this

standard.

• Expansion joints and spring hangers or spring supports shall be provided with

temporary restraints where needed to prevent excessive travel or deformation under

the test loads.

• Equipment Excluded from Pressure Test.

• The following list defines the equipment that shall be excluded from the in-situ

pressure testing of the tested system. Also, other unlisted sensitive equipment or as

designated by COMPANY Inspector can be added:

• Rotating machinery, such as pumps, turbines and compressors;

• Strainers and filter elements;

• Pressure relieving devices, such as rupture disks and pressure relief valves;

• Locally mounted indicating pressure gauges, where the test pressure will exceed their

scale range;

• Equipment that cannot be drained;

•

Instrument Devices.

For Isolation of Test Sections paddle blinds or spectacle blinds shall be used to isolate the

test sections. They shall be the same class rating of the system or may be fabricated based

on appropriate calculations. When this is not practical, closed block valves (gate, globe, plug

or ball) may be used to isolate equipment or piping sections (provided the valves are not

passing, otherwise the spectacle plate/blind shall be installed in the closed position). If closed

block valves are used in lieu of blinds, provisions shall be made to ensure no overpressure

can occur in the system that is not being tested, due to possible leak through the valves.

When a block valve is used for isolating test sections, the differential pressure across the

valve seat shall not exceed the seat test pressure during pressure testing and shall not

exceed the rated seat pressure during tightness test. Both sides of this valve shall be

protected by relief valves during the test.

Vents shall be provided at all high points in the tested system as needed.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 124 OF 162

10651-00-QAC-PD-0003

REV.: 01

Excluding scrapable, submarine and buried pipelines, drains shall be provided at all low

points in the system and immediately above check valves in vertical lines.

Unless the check valve has a by-pass valve, the disc of the check valve shall be removed,

and securely attached to the outside of the check valve prior to the pressure test.

Temporary connections shall be provided for de-pressurizing and draining of the system to

the sewer or disposal area.

Temporary supports shall be installed prior to hydrostatic testing, and flushing of the piping if

they were determined to be required per SAES-L-150. These supports shall not be removed

until after the system has been fully drained. The structural support system for stacked

equipment shall be verified for hydrostatic loads prior to testing.

After Completion of Pressure Test

After pressure testing has been successfully completed and approved by the Owner’s

Inspector, the following operations shall be made.

Release of pressure and draining shall be done on the downstream side of check valves. All

vents shall be opened before draining to facilitate drainage and to prevent formation of a

vacuum. No test fluid shall remain in low spots.

The test fluid shall be disposed in accordance with SAEP-327 or as directed by the Owner.

Vents and drains used only for the pressure test shall be plugged, seal welded and penetrant

tested.

All temporary items installed for testing purposes (e.g., manifolds, valves, blinds, spacers,

supports) shall be removed.

Items that were removed from testing shall be reinstalled.

Items, such as instrument air tubing, check valve discs which were disconnected before

testing shall be reconnected.

Isolation valves closed for the test purposes and that are required to be in the open position

for process reasons shall be opened. If the valve cavity has a drain, the cavity shall be

drained.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 125 OF 162

10651-00-QAC-PD-0003

REV.: 01

Tie-ins / Hot Taps

Inspection of in service lines

SUBCONTRACTOR is the responsible to develop, implement, execute and assess the piping

inspection system for tie-in locations. General ITPs shall be prepared by SUBCONTRACTOR

for CONTRACTOR review and approval. Specific inspection plans for each type of tie-in

location shall be prepared by SUBCONTRACTOR. Minimum requirements set by

CONTRACTOR are developed in document “Tie-Ins Quality Control Procedure”. Inspection

access also shall be followed by SUBCONTRACTOR as established in the item 4.9.9 of this

document for Tie in or/and Hot Tapping. SUBCONTRACTOR shall develop the inspection

procedure that shall contain the quality assurance inspection management system. The

SUBCONTRACTOR shall follow the inspection in service piping as per applicable API 570.

NDT and inspection reports shall be delivered to CONTRACTOR for review (and approval

when required). Final assessment reports of tie-in locations shall be officially submitted to

CONTRACTOR for review.

Piping Tie-ins

Tie-in spools prefabrication and erection works shall be performed as per “Tie-Ins Quality

Control Procedure” and approved ITPs “Tie-In Prefabrication” and “Tie-In Erection”.Tie-in

requires coordination with SUBCONTRACTOR CONTRACTOR and Employer, no works

shall be performed without CONTRACTOR approval and Employer request for work permits.

Materials

All materials (such as weldolets, split tee pipe diameters, valves) to be installed in the tie-in

shall be tested in accordance with standards and project specifications; if materials are

supplied by SUBCONTRACTOR, SUBCONTRACTOR shall deliver the material certificates

and submit for CONTRACTOR review before installation. The material to be installed by the

SUBCONTRACTOR, it shall consider the design and calculation code followed such as

ASME B31.3 or ASME B31.4 to confirm the proper diameter used in the reduction that shall

be applied according the piping diameter of service line.

Welding Considerations

Prior to start the cutting activities the piping wall thickness need to be measured if it is suitable

to perform the Tie–in or not, the information about deterioration of the minimum required

thickness shall be considered and evaluated by CON. NDTs shall be performed to the piping

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 126 OF 162

10651-00-QAC-PD-0003

REV.: 01

flange for butt-weld preparation is required, and the report needs to be submitted by the

Quality Department of SUBCONTRACTOR to CONTRACTOR, for evaluation and review as

per ASME V. Additional vents or drains shall be

included

in

the sketch by

SUBCONTRACTOR and confirmed by CONTRACTOR. This activity shall be reviewed Tie-

in plans and strategies with CONTRACTOR, SUBCONTRACTOR shall ensure the

quantitative and/or qualitative acceptance criteria for the prescribed activities that have been

accomplished satisfactorily according standards applied to the project. After completion Tie-

in shall be inspected previously by the SUBCONTRACTOR and after by sending an RFI, to

CONTRACTOR, as per section 4.5.2 of this document, the inspection shall ensure if the new

connection is installed according to design and if all documentation is according the project

and applicable specifications.

During Prefabrication stage Verification of material base certificates, filler material

certificates, welders qualifications and welding procedures, and all quality related documents

as per approved ITP for tie-in prefabrication. Compliance of PWHT results (when required)

with project specifications. NDT performance according to project specification. Final review

of applicable drawings (welding map, isometric), weld history inspection/NDT and PWHT,

HT, etc. clearance. Verification of leak test (In case it is possible to carry out leak test in shop

(flanged spool), as per engineering design, and approved test pack contents.

On Stream Inspection Study

The objective of an OSI Study is to increase the operational reliability of the stationary

equipment and pipeline used into the Project.

OSI Study is a plan systematic monitoring of piping, vessels and tanks for general loss ofwall

thickness and localized metal loss, but not limited to using non-destructive procedures (UT)

including Thickness Measurement Locations (TMLs), also includes Condition Monitoring

Locations (CMLs) i.e. CUI, Nipple survey, Dead Leg, etc. establishing the suitability of the

pressure boundary for continued operation.

This analysis is performed on P&IDs identifying with different colors and labels each

corrosion circuits to stablish the first step in the development of On Stream Inspection Study.

This is carried out as part of either an OSI and defines corrosion circuits within each system

based on materials of construction, operating conditions and active damage mechanisms.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 127 OF 162

10651-00-QAC-PD-0003

REV.: 01

Piping OSI isometric drawings are developed for each circuit to indicate CML, positions of

the TMLs and limits of the circuit.

SUBCONTRACTOR will follow ENGINEER instructions regarding OSI requirements,

SUBCONTRACTOR will perform the corresponding thickness measurement and specific

deliverables will be submitted by SUBCONTRACTOR.

FLANGE MANAGEMENT

This is the minimum quality requirement, in compliance with the Design Codes and

International Standards, but not limited to, which SUBCONTRACTOR shall implement a

Flange Management System during the execution of the work under this Subcontract.

The Main purpose is to define and set the principal requirements to achieve a good Flange

Management System with the least possible leaks during the Hydro test, pre-commissioning

or commissioning phase.

Flange Management System.

SUBCONTRACTOR shall to prepare and send to CONTRACTOR for approval the Flange

Management Plan with two different procedures, first “Bolt Torqueing procedure” & second

“Bolt Tensioning procedure”.

SUBCONTRACTOR shall develop the tightening torque calculation study according to

International Standards and Project Specification. SUBCONTRACTOR will calculate the

torque to apply for the different sizes, technic to apply, materials, etc.

• Torque Calculating; for this specific calculation, SUBCONTRACTOR shall consider

the mechanical resistance (friction) given by solid lubrication paste approved

previously by M.A.R. with the possible combinations between sizes, materials…etc.

• Tensioning Calculation; For this specific method , SUBCONTRACTOR / THIRD

PARTY shall study individually the force to set up in the tensioning machine in order

to get the value proposed according vendor instruction or Engineering drawing, the

bolt elongation calculation is mandatory for all the individual tensioning works, the

Torque summary Tables will send to CONTRACTOR for review and approval.

SUBCONTRACTOR shall communicate immediately and officially (Technical Query) to the

CONTRACTOR any discrepancy discovered between the elements included in a Flange

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 128 OF 162

10651-00-QAC-PD-0003

REV.: 01

Connection ,for instance, Isometric Drawing shows RF flange and the General Equipment

Drawing shows RTJ flange.

Every single Flange connection shall be

identified as accepted after

the

torqueing/Hydraulic/Tensioning using the combination label identification (properly filled) and

fixed with the metallic Ball Lock Cable.

Labelling/Tag only can be signed only by SUBCONTRACTOR QC INSPECTOR and operator

qualified and approved previously by CONTRACTOR.

Labelling/Tag on flanges shall be install always after QC inspection, never before the

inspection. Install the label signed before the inspection will be consider minor offence but

three minor offences will be considered as a major offence and the responsible to sign the

label will be expelled from the project due serious misconduct.

The Work Procedures and the Reparation Work Procedures shall be officially issued by

SUBCONTRACTOR and they must be validated by CONTRACTOR Construction/Quality

department. The signed documents shall be recorded by CONTRACTOR Quality

Department.

SUBCONTRACTOR shall attend/ sort out, all the Site Observation received from

CONTRACTOR side related to the Flange Management System immediately after to receive

it.

Material Certificates

SUBCONTRACTOR shall submit to CONTRACTOR the corresponding Material Approval

Request (MAR) related as a minimum and not limited as per CONTRACTOR request:

• Solid lubrication paste (Example: Molyslip Copaslip or Molykote 1000).

• Rust Proof Compound (Example: Caltex/Chevron).

• Labels (flame retardant or fireproof).

• Markers (waterproof and approved for TAG/Labels)

• Metallic Ball Lock Cable Ties.

• Flange Insolation Galvanic kit.

CONTRACTOR shall revise all of it and shall approve or not according to Contract and

applicable Standards.

CONTRACTOR Quality Department shall record the signed originals.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 129 OF 162

10651-00-QAC-PD-0003

REV.: 01

Flange Management Team organization

SUBCONTRACTOR shall designate enough, competent and qualified personnel to

coordinate the Flange Management System related

to

the piping, Mechanical &

Instrumentation FIELD scope of work, SUBCONTRACTOR shall designate in their

organization one Flange Management Responsible and a proper number of technicians

proportional to the SUBCONTRACTOR scope of work. Their responsibility will be implement

the Flange Management System in the Field, checking: bolts (length and size), gaskets,

verifying proper valve installation checking the valve MESC ode against the iso), Valve

orientation, flange face without damages/defects, bolt lubrication, select the proper torque

and method to apply, install the label after inspection…etc

SUBCONTRACTOR RESPONSABILITIES

• SUBCONTRACTOR SITE MANAGER and SUBCONTRACTOR QA/QC Manager are

the responsible to implement properly the Flange Management System in their scope

of work.

• SUBCONTRACTOR Flange Management Inspectors are the responsible to verify the

qualified joint assemblers follow the tight process according the procedures.

• SUBCONTRACTOR HSE MANAGER is the responsible to ensure the proper work

conditions during the tight works and inspection activities.

SUBCONTRACTOR will provide training by certified specialist or third party (which is highly

recommended), for Bolt torqueing crews and QC inspectors, as minimum. The purpose of

this training is to develop skills, which in turn will enable them to recognize and comply with

safe systems of work, and to report and correct unsafe conditions and practices, among

others.

As a minimum, all the personnel (technicians, Joint Assemblers) involve in the Flange

Management System will have the specific training ASME PCC-1-2019” Guidelines for

Pressure Boundary Bolted Flange Joint Assembly”, (in a theorical and practical way) If the

personal proposed by SUBCONTRACTOR does NOT have the specific training course or if

the performance in the field is not the proper one, CONTRACTOR keeps the right to force to

the SUBCONTRACTOR to attend the specific Flange Management Induction imparted by

CONTRACTOR and SUBCONTRACTOR will assume totally the derived cost.

SUBCONTRACTOR shall prepare the Joint Assembler Card for the training assistants and

CONTRACTOR will verified and sign if proceed, this card will be mandatory to keep it

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 130 OF 162

10651-00-QAC-PD-0003

REV.: 01

during the field assembly works. Carry out Flange assemblies without the proper ASME

PCC-1-2019 training, at less of 6 month experience in Flange Management activities, and

mockup of two flange joints…according ASME PCC-1 2019 requirements minor

offences will be considered as a major offence and will be expelled from the project due

serious misconduct.

CONTRACTOR will keep the right to revoke without cost for CONTRACTOR any

SUBCONTRACTOR personnel

involve

in

the Flange Management System

If

the

performance in the field or in the office is not the expected one due lack of knowledge, or

responsibility

Flange Management Data Base

Unless another Software is specifically approved by CONTRACTOR for this scope P.C.A

.(Piping Control Application) Software will be the official tool to control the flange

management related to:

• Underground pipes

• Aboveground pipes

• Mechanical Equipment(including manholes closure scope)

•

Instruments installation

SUBCONTRACTOR shall supply as per CONTRACTOR requirement enough, competent

and qualified personnel to work under CONTRACTOR supervision supporting the Flange

Management office activities such: Prepare labels to install in the field, verified production

against the PCA data, prepare the daily production (PCA Loaders), study the pending scope

in subsystem basis, follow the STQs related to the Flange Management, study the Flange

Connection belonging to the equipment (Pipe connections, manholes…etc).

SUBCONTRACTOR

Inspectors shall report

in daily basis

the Permanent Flange

Management Production (assembly & disassembly) carried out in the workshop/field.

Tools and Machinery- Bolt Tightening.

SUBCONTRACTOR shall have available and calibrated for their scope, the proper tool and

machinery to carry out the different types of closures such

• Torque wrench (Covering the full range).

• Tensioners (including “Slim Line Tensioner” for tight with limited access).

• Spanners.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 131 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Torque Multiplier Wrench (Included Manual)

• Hydraulic bolt tensioning machine.

• Hydraulic nut

• Hydraulic flange spreader

• Hydraulic nut splitter tool.

• Flange alignment tool.

• Portable facing machines for flanges

• Solid lubricant paste (Copaslip,Molykote…)

• Anticorrosive Compund (Flange Preservation).

• Controlled Torque Impact Wrench

• Tommy bar tool

• Wire Brushes for Different Materials.

• Flange Insolation Galvanic kit.

• TAG/Labelling

• Marker (waterproof and approved for filled TAG/labelling)

• Temporay Gaskets

SUBCONTRACTOR shall keep a detail excel file with all the Flange Management tools

available in the project showing the tool calibration date, expired date, serial number, type,

comments…etc.

Torque Wrench used for Bolt Torqueing shall be calibrated every three (3) months unless

specified in written by the manufacturer. SUBCONTRACTOR will send to CONTRACTOR

the pdf calibration certificates for review and approval.

Validation & Identification: SUBCONTRACOTR shall mark the equipment / tools with a

label/sticker provide by the laboratory.

Preservation

SUBCONTRACTOR shall preserve all the material provide by CONTRACTOR during the

construction phase (Workshop/Site), SUBCONTRACTOR shall take all the precautions to

ensure the proper preservation specially in all the sealing elements/parts such bolts, nuts,

washers, flanges faces, .etc.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 132 OF 162

10651-00-QAC-PD-0003

REV.: 01

SUBCONTRACTOR shall use specific product like “Rust Proof Compound” (Caltex/Chevron)

for special seal parts such RTJ groove, grease or other products with COOPER are totally

forbidden.

Seat groove should preserved/protected with efficient and special product for metal

“Machined flanged openings shall be coated with a suitable anti-corrosion agent before

sealing. All flanged openings shall be sealed with bolted-on metal or marine grade plywood

of 6mm minimum thickness, using at least three (3) bolts (wiring is not acceptable) and

gaskets. The joint shall then be effectively sealed with waterproof tape (Denso tape or

equivalent). All openings shall be plugged / capped with Yellow end caps on all pieces of pipe

PAINTING/COATING MINIMUN REQUIREMENTS

This is the minimum quality requirement, in compliance with the Design Codes and

International Standards, but not limited to, which SUBCONTRACTOR shall implement and

follow during the execution of the work under this Subcontract.

Coating works shall be according to Project Requirements (such drawings, Specifications,

COMPANY specifications, Project Procedures, SATIPs (or approved ITPs if applicable), etc.)

SUBCONTRACTOR shall issue Coating Work Procedures, Method Statements and

Personnel Qualifications as per the corresponding scope for CONTRACTOR review and/or

approval.

Internal and external coating minimum requirements

Any fabricated parts at site shall be abrasive blasted and primed prior to installation.

All site welds shall be abrasive blast cleaned.

Welded joints may be primed and painted prior to hydrostatic testing unless a sensitive leak

test is required as defined in ASME Section V, Article 10

Abrasive materials

• Blasting abrasives shall be dry, clean and free from contaminants that will be

detrimental to the performance of the coating. Abrasives shall be selected that are

capable of producing the required profile and that have a minimal health impact.

Abrasive types shall be subject to CONTRACTOR approval. Non-metallic abrasives

shall meet the requirements of the appropriate part of EN ISO 11126-series. Test

methods shall be in accordance with the tests specified in EN 11127-series. Metallic

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 133 OF 162

10651-00-QAC-PD-0003

REV.: 01

type abrasives shall meet the requirements of the appropriate part of EN ISO 11124-

series. Grit type abrasive shall be used as blast medium. Shot and beads shall NOT

be used. Size of abrasive particles for blast cleaning shall be such that the prepared

surface profile height (anchor pattern profile) is in accordance with the requirements

for the applicable coating system. The surface profile shall be graded in accordance

with EN ISO 8503-2. to an approved ISO surface profile comparator Type G.

Alternatively, comparison may be made to equivalent segments as defined on the

Keane Tator Profile Comparator, subject to the CONTRACTOR’s acceptance.

• The surfaces shall be inspected and confirmed prior to blast cleaning free from any

foreign matter such as weld flux, residue, slivers, oil, grease, salt, etc. All steel shall

be tested for salt contamination after blasting. The maximum acceptable value for any

single measurement shall be 50mg/m2. Any steel exceeding the allowable water-

contaminant levels shall be water washed in combination with suitable detergent prior

to blasting. The frequency and nature of these checks shall be enough to maintain

the required standard of salt contamination

• The type of abrasive shall be approved by M.A.R. material that will achieve the

surface profile, cleanliness requirements and the type of abrasive blasting method i.e.

manual blasting and / or automated blasting and shall comply with ISO 8501-1.

• The use of reclaimed slag abrasives is prohibited. The use of reclaimed garnet is

permitted for pre-blasting work provided if it meets the requirements of previous point.

• The use of silica sand as abrasive material is prohibited in Saudi Aramco.

Requirements before abrasive blasting

• The substrate shall not contain oil, grease or lubricant.

• When required, solvent cleaning shall be carried out in accordance with SSPC-SP1.

Kerosene, diesel or other degreasers that leave an oily film shall not be used, unless

the surface is consequently cleaned with a non-greasy solvent or cleaner.

• All sharp edges, fillets, corners, countersunk and welds shall be rounded or smoothed

by grinding (min R > 2 mm) steel dressing will be in accordance with ISO 8501-3

grade P3 , with the exception of aspects 1.1, 1.2, 1.4, 3.1, 3.5, 3.6 which will be

according to P2. Steel dressing shall be such that proper surface wetting can be

achieved. Defects are as defined in ISO 10163-2 Class A subclass 1 for plates, and

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 134 OF 162

10651-00-QAC-PD-0003

REV.: 01

ISO 10163-3 class D subclass 1 for sections. Defect types 1.5 and 1.6 shall be

repaired with grinding unless agreed otherwise

• Equipment which could be damaged by blast, dust or particle matter shall be suitably

protected by masking, wrapping,

taping or shielding

to prevent damage.

SUBCONTRACTOR shall protect carefully the Valve stems; each valve stem shall be

wrapped with a cloth followed by a duct tape to protect stem damage from impact of

the abrasive blasting and avoid gum residue due to the hot exposure to the sun

• Abrasive blasting shall be carried out only when steel surface is at least 3ºC above

the Dew Point. shall be executed in closed, air-conditioned rooms with relative

humidity of ≤ 65% and a dewpoint distance of ≥ 5 ºC. The climatic conditions must be

maintained from start of blast work until application of the first coating film.

• Abrasion by hand or power tools shall be permitted only where the use of blast

cleaning equipment can be shown to have a detrimental effect on the adjacent

structure, materials or equipment and the procedures have been accepted by the

CONTRACTOR. In these instances, the surface shall be cleaned to a St 3 standard

in accordance with BS EN ISO 8501-1

• The cleanliness and roughness of the blast cleaned surface shall be specified for

each coating system. Where no requirements are specified, the standard shall be Sa

2½ in accordance with EN ISO 8501-1, the roughness shall be >50 microns EN ISO

8503-5 grade Medium G and dust rating 2 according to ISO 8502-3.

•

In addition to visual examination, and except where otherwise specified, random

measurements of blast profile shall be made at a minimum frequency of ten (10) per

shift per work area, or one per fifty (50) square metres if greater, using ‘Testex’ tape

or other approved method

Requirements after abrasive blasting

• Abrasive shall be removed from the cleaned surfaces by dry brushing or blowing down

with a clean, dry compressed air. Internal surfaces shall be dry brushed, and vacuum

cleaned . The surfaces must be thoroughly dust tested (pressure-sensitive tape

method). The particle quantity shall not exceed 2 and the particle size shall not exceed

class 3 for liquid coatings according to EN ISO 8502-3, Table 1.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 135 OF 162

10651-00-QAC-PD-0003

REV.: 01

• After blasting, check the substrate for the chloride content. Residual chloride shall not

exceed 40 mg/m2. Wash down the surface with sweet water to remove chloride

contamination. Lesser surface concentrations can be required by the coating system

supplier and in this case the proposed concentrations shall be obeyed.

• Abrasive blast cleaned surfaces shall be re-inspected prior to priming or coating if the

surfaces are held for more than 4 hours after blasting. Correction shall be done and

retested before coating application.

Coating application

• All buried onshore and plant carbon steel pipelines and piping and other above grade

carbon steel pipelines in industrial or marine exposure shall be externally coated (and

internally coated when required) complying with SAES-H-002 requirements.

• All blast cleaned or otherwise prepared surfaces, shall be visually inspected for

conformance to the specified standard of cleanliness and roughness immediately

prior to application of the first coat

• Completion of all work must be continuously supervised by the SUBCONTRACTOR

• Coating which have gelled shall not be used.

•

In case of multi-coat application, the primer, intermediate coat and topcoats shall be

of contrasting colors.

• The thickness of each coat shall be determined prior to the application of subsequent

coats complying with the required thickness specified in the applicable APCS.

• Prior to application, all coating shall be thoroughly mixed until it is homogeneous.

•

If a thinning is required, the thinner type and the quantity to be added shall be as given

in Saudi Aramco Data Sheet (see per SAES-H-101)

• All coating materials for each coating system shall be supplied by the same

Manufacturer (unless otherwise approved by CONTRACTOR and COMPANY), which

shall also either supply the thinner or approve the thinner being used with its products.

• Coatings shall be applied in a uniform manner to the specified film thickness without

runs, sags or other blemishes. The coating manufacturer’s recommended time

intervals between coats shall be followed.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 136 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Coating shall not be applied if one or more of the following conditions exist unless the

coating is specifically formulated for the averted condition:

➢ Surface temperature, humidity and dew point fall outside the recommended

limits from the coating manufacturer’s data sheet.

➢ The substrate temperature is less than 10°C; or less than 3°C above dew point.

➢ The substrate contains oil, grease, dirt, loose paint, loose rust, or other surface

contaminants.

➢ Adverse weather conditions exist such as, but not restricted to, the following:

o Wind is strong enough to blow sand, salt spray, or other foreign matter onto

the surface being coated.

o Wind is strong enough to cause dry spray or to otherwise seriously disturb the

spray pattern when application is by spray gun.

• All weld lines, edges, bolts, nuts and rivets shall be given a brush applied stripe coat

prior to all paint applications. Brush application (“stripe coating”) must to be done for

every layer coat to ensure adequate film thickness at difficult to coat areas, including

angles, corners, edges, bolts, nuts, rivets and interstices. Stripe coating shall be

applied in accordance with coating suppliers’ recommendations

• When using inorganic zinc primer, the SUBCONTRACTOR shall check for surface

zinc oxide formation immediately prior to applying an epoxy topcoat. Any oxide

formation shall be removed.

• Recoating intervals shall be as given in the Saudi Aramco Data Sheet. (according to SAES-H-101V). In stringent application conditions, the latest Materials Technical Data Sheet of the manufacturer shall be used as a supporting document. The coating supplier must specify the maximum and minimum application and curing temperature and other relevant limitations regarding application and curing conditions for each product in any coating system

• The finished coating film shall have the following characteristics:

  • The dry film thickness shall be within the minimum and maximum limits allowed in

the applicable APCS.

• Generally free of application related defects such as runs, sags, drips, dry spray or

foreign matter

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 137 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Uniform in appearance

• Adhesion strength of all coating systems shall not be less than that required in the

appropriate SAMSS for new product approval

• Areas with blisters, cracks, porous or below minimum dry film thickness shall be

repaired.

SUBCONTRACTOR shall ensure as a minimum the following coating inspections and tests

shall be applied:

• Surface Contamination: Tests indicating the extent of substrate contamination as a

result of iron, chlorides and dust are specified in ISO 8502-1, ISO 8502-2 and ISO

8502-3, respectively.

• Wet Film Thickness, WFT: Spot checks shall be carried out during the course of the

painting operation to ensure that film thickness is being maintained. These shall be

performed according to the procedure described in ISO 2808, Method No. 7B.

• Dry Film Thickness, DFT: ISO 2808, Method No.6, describes the test techniques

suitable for measurement of the dry film coating thickness.

• The DFT of each coat and of the final system shall be measured and recorded in

sufficient locations to ensure compliance with the specification at all points on the

component. A microprocessor-based electromagnetic/inductive DFT gauge capable

of storing multiple readings in batches shall be used. Gauges shall meet the

requirements of EN ISO 2808, shall be calibrated before use and the Employer shall

be provided with calibration records.

In the event that a coating system is found to have been applied with excessive

thickness it shall be brought to the CONTRACTOR’s attention. The CONTRACTOR

shall decide on the appropriate action to be taken. Acceptance of excessive thickness

by the CONTRACTOR should be considered only if the measured thicknesses are

confirmed by the coating manufacturer in writing as not being detrimental to the

satisfactory service life and performance of the coating system, and if testing

demonstrates that there is no loss in system adhesion or inter-coat adhesion.

• Adhesion: The adhesion of the primer to the steel substrate and the intercoat

adhesion of the subsequent coat(s) after curing shall be determined by the application

of either a cross-cut test in accordance with ISO 2409 or a pull-off test described in

ISO 4624 or ASTM D4541.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 138 OF 162

10651-00-QAC-PD-0003

REV.: 01

Coating adhesion tests shall be conducted on test panels (300x200x6mm) to be

blasted and painted at the same time as the structure/piping. The frequency should

be one test panel every 1.000 m2 (frequency may be modified as per projects

requirements). From the beginning to the end of the project. Test panels must be

prepared and coated under the same conditions of the element or structure.

The adhesion tests shall be performed using a pull-off method in accordance with ISO

  1. The coating around the periphery of pull-off dollies shall be trepanned down to

the substrate prior to conducting the pull-off test. The test procedure and number of

tests shall be detailed in the coating ITP which shall be subject to the Contrator´s

approval. Pull off tests shall be undertaken 14 and 28 days after coating on the test

pieces. Acceptance criteria shall be agreed between parts before doing the test (for

example results exceeding or equal to 5Mpa are acceptable).

• All coatings shall be tested for adequacy of cure. The test method and frequency shall

be submitted by the CONTRACTOR for the Employer’s approval and can involve

solvent wiping, pencil hardness testing or other chemical or mechanical methods.

Defect repair

• Cover all coated areas near to the defective area before commence repair or patching

up. Use heavy duty textile or fabric adhesive tape.

• SUBCONTRACTOR shall prepare and send for CONTRACTOR approval one Repair

procedure ,individually , for each painting system covering as a minimum and not

limited the next examples : all defective areas, coating film defects, coating damages,

Coating damage not exposing Substrate surface, Coating damage exposing

Substrate surface and defect fully cured epoxy …etc.

• All defects shall be repaired according to the touch up and repair procedures accepted

by CONTRACTOR and COMPANY

• The repair procedure must be aligning with the paint manufacturer recommendation

and project specifications.

• All coated surfaces shall be visually examined after application of each coat for

deleterious film defects e.g. blisters, pinholes, dry spray, runs, sagging, wrinkling, mud

cracking, delamination, loss of adhesion, embedded particles, overspray and other

contamination. Inspection shall be undertaken from a distance no greater than 3m

and no less than 0.5m. Defects detected during such inspection shall be repaired.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 139 OF 162

10651-00-QAC-PD-0003

REV.: 01

Where the defect is considered aesthetic and will not detrimentally affect the durability

of the coating the CONTRACTOR may request a relaxation to the repair requirement.

Any relaxation is subject to the Employer’s written approval and will be deemed to be

strictly without prejudice to the requirements and obligations set out in the Conditions

of Contract.

• Subject to CONTRACTOR (and COMPANY) approval and after determining the scale

and type of the defects, the following methods of repair shall be applied:

o For major defects (products, application and unsatisfactory inspection results),

paint shall be removed completely by abrasive blast-cleaning and the entire

painting system shall be re-applied.

o

-Minor defects (localized appearance, scratches, etc.) are subject to the

approval of the Manufacturer, CONTRACTOR and COMPANY, according to

the chosen system localized paint removal with total or partial elimination of

the system and re-painting.

o

-For thickness defects, a building-up of the insufficiently thick areas shall be

carried out, considering the re-coating

• All defects shall be corrected and all damage from inspections (i.e. adhesion testing,

wet film thickness tests etc.) shall be repaired.

Installation externally FBE, 3LPE and 3LPP coated line pipe and piping general requirements

• SAES-H-200 shall be followed.

• Ditch preparation shall be in accordance with SAES-L-350 and SAES-L-450.

• Coated pipeline shall be 100% inspected with a pulse-type DC holiday detector. Defective locations shall be clearly marked with a crayon immediately upon discovery

Coating equipment

Following inspection equipment that calibrated and certified shall be provided as minimum

but not be limited to with the SUBCONTRACTOR and Applicator:

• Dry Film Thickness gauge with calibration shim plates.

• Slig psychrometer.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 140 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Holiday detector.

• Surface temperature thermometer.

• Coating material thermometer.

• Wet film thickness gauge.

• Elcomenter adhesion tester (or equivalent).

Coating/Blasting personnel qualifications

SUBCONTRACTOR coating personnel shall be certified in accordance with SAEP 316.

All personnel employed in abrasive blast cleaning operations shall be suitably trained and

experienced and be capable of producing consistently the required surface profiles on

representative structural steel surfaces.

Operators shall be qualified in accordance with CONTRACTOR procedure accepted by

Employer. The personnel shall have relevant knowledge of health and safety hazard, use of

protection equipment, coating materials, mixing and thinning of coatings, coating pot-life,

surface requirements, etc.

Coating inspection shall be carried out by at least Level 2 Qualified Coating Inspectors

certified to National Association of Corrosion Engineers (NACE), BGAS Grade 1/2 or

FROSIO or equivalent qualification schemes. All shall be sent for CONTRACTOR approval.

SUBCONTRACTOR shall send for CONTRACTOR approval, enough, competent and

qualified Quality Personnel (Inspectors/supervisors NACE Level II or CSWIP / BGAS Grade

1/2, or another acceptable equivalent ) to follow and coordinate the painting activities.

Coating materials

SUBCONTRACTOR shall only use coating material that has been approved by COMPANY

as meeting the requirements for the APCS or SAMSS. If no applicable APCS or SAMSS

exists, the product must be certified in writing by COMPANY that it is suitable for the intended

service.

Coating materials mandatory technical properties and storage, mixing, and application

requirements shall be as given in COMPANY Data Sheets defined in SAES-H-002V and

SAES-H-101V.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 141 OF 162

10651-00-QAC-PD-0003

REV.: 01

Approved Protected Coating Systems

SUBCONTRACTOR shall follow the applicable APCSs described in SAES-H-001 and in

SAES-H-002, where type of coating, surface preparation and dry film thickness requirements

are defined.

Colours and Identification for Piping and Equipment

Applicable colour coding as per Coating Specification 10651-00-XXX-ES-XXXX.

INSULATION

Insulation works shall be according to Project Requirements (such drawings, Specifications,

CLIENT specifications , Project Procedures, SATIPs (or approved ITPs if applicable).

SUBCONTRACTOR shall officially issue Coating Method Statements, Work Procedures and

Personnel Qualifications for CONTRACTOR approval.

All data sheets of material that are not supplied by CONTRACTOR will be submitted to

CONTRACTOR for approval. A Work Method of Statement describing all the activities will be

submitted by SUBCONTRACTOR before starting the activities, including special process

methodology for expansion joints, instruments (if apply), including the length of the personal

protection. For Heat tracing installation, SUBCONTRACTOR will follow the applicable

drawings, and sharp edges will be avoiding in order to do not damage the cable. Heat tracing

cable will be covered with insulation. Coordination between different Parties shall exist in

order to do not cause delay

Minimum insulation requirements shall be as follows.

General requirements

• SAES-N-001 shall be followed.

• Fireproofing shall be in accordance with SAES-B-006 or SAES-B-009, as appropriate

•

Insulation shall not be installed in pumps, air-cooled equipment, compressors, steam

traps, nameplates, expansion joints, rotating joints and other applications where the

intended use would be compromised.

•

Insulation shall be installed following Manufacturer instructions.

• Unless otherwise specified, insulation shall not be applied until completion of the

following:

o Required hydrostatic and/or pneumatic pressure testing

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 142 OF 162

10651-00-QAC-PD-0003

REV.: 01

o Application of required substrate protective coating systems, including touch-up

of previously applied coatings

o

Installation and testing of required tracing systems

o Cleaning of surfaces that are to receive insulation

• Application of insulation may proceed before pressure testing is complete, provided

that all welds and flanged and threated connections are left exposed until pressure

testing is complete

• All insulation shall be smooth and free from cracks, voids and depressions greater

than 3 mm. All cracks, voids and depressions in the insulation greater than 3 mm shall

be refitted, not filled.

• Before the application of weatherproof jacketing all surfaces shall be sealed with a

vapor barrier mastic

• Membrane type vapor barrier mastic and reinforcing fabric shall be installed without

fish mouthing gaps or folds and shall have a minimum of 50 mm overlap at all joints

•

Installed insulation shall have the required permanent protection of temporary

protection applied if the insulation can be damaged by rain or other forms of

atmospheric moisture.

• When applying double or multi-layer insulation, each succeeding layer shall be

staggered to the longitudinal and circumferential joint of the layer beneath. All joints

of all layers shall be staggered.

Insulation materials

•

Insulation materials shall comply with SAES-N-001 requirements.

• Other materials received different than those specified in applicable Project

specifications shall have prior written approval from CLIENT/CONTRACTOR

•

Insulation and accessory materials shall meet Project Material Data Sheet Insulation

grades class or type as per Project specifications.

•

Insulation material shall be 100% asbestos free.

• Materials shall be used prior to the expiration date. Sealants, mastics and adhesives

shall be supplied in factory sealed containers.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 143 OF 162

10651-00-QAC-PD-0003

REV.: 01

• All material shall be qualified for use on austenitic stainless steel in accordance with

ASTM C795.

•

If requested by CONTRACTOR, Manufacturer test reports shall be furnished.

• Material manufacturer shall also furnish a chemical analysis in accordance

with ASTM C871 for materials. This chemical analysis shall not vary by

more

than 50%

from

the chemical analysis of

the production

lot

tested

under ASTM C692.

• Unless otherwise specified in the Purchase Order, certification of chemical

analysis

is not required

for each production

lot

from which material

is

furnished for this project, however the manufacturer shall state that it will

not vary by 50% from those done during the production lot tested under

ASTMC795 .

• Testing shall be conducted by a Laboratory accredited by

the National

Institute of Standards and Technology’s National Voluntary Laboratory

Accreditation Program (NVLAB).

• Hot insulation materials shall satisfy minimum requirements of quality standard in

accordance with ASTM C533 type I for calcium silicate

• Cold insulation material shall satisfy the minimum requirements of quality standard in

accordance with ASTM C591

Personnel protection insulation

Personnel protection insulation when required shall comply with SAES-B-053 requirements.

Insulation accessories

• Where metal jackets are not required, vapor barriers shall be capable of providing

weatherproof protection. A metal jacket does not qualify as a vapor barrier.

• Jackets for insulation systems that require fireproofing shall be stainless steel,

galvanized steel or aluminized steel.

• Elastomeric coatings shall be used for weatherproofing on plastic foam and cellular

glass when there is no requirement for metal jackets.

• Corrugated jacketing shall not be used to cover cold insulation.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 144 OF 162

10651-00-QAC-PD-0003

REV.: 01

Insulation installers qualification

• Cold Insulation Installers must have previous commercial experience and must supply

references to CONTRACTOR AND CLIENT prior to being granted authorization to

work.

• Cold Insulation Installer’s work history (with references) has been submitted to

CONTRACTOR AND CLIENT for review & SA authorization obtained to perform work.

ON SITE E&I MINIMUM REQUIREMENTS

These are the minimum quality requirements, in addition to the ones in the Design Codes

and International Standards but not limited to, which SUBCONTRACTOR shall implement

and follow during the execution of the work under this Subcontract, either at Fabrication Shop

(included fabrication yard work site) or at the Construction Site.

Instrumentation Requirements

• Reference instruments must not be used without their updated calibration certificate.

• Air used for pneumatic test must be clean, dry and free of oil.

• Transmitters, primary elements and valves must be check/calibrated before being

installed to ensure proper operation.

• Calibration verification will be performed at site before place the instrument in its final

position. A pneumatic test for hook up and tubing methodology will be submitted to

CONTRACTOR before starting the activities. - All data sheets of material that are not

supplied by CONTRATOR will be submitted to CONTRATOR for approval. - Direct

contact between different materials (as Stainless steel and Carbon Steel) will be

avoided by SUBCONTRACTOR using a material to avoid contamination/corrosion (as

Teflon).

Electrical Requirements

• Cable trays must be properly supported and when supports are welded to structure,

AWS D1.1 is fully applicable for all the welders and welding process, (welds must be

galvanic protected).

• Cable trench and trays must be clean before starting installation.

• Before cable laying works, an isolation and continuity test must be performed on cable

drums to ensure that no damaged cable are going to be installed.

•

Instruments/pipes/electrical equipment cannot be used to support cables. Cables

must have their own support and no damageable tension shall be given to connectors.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 145 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Minimum-bending radius of any cable shall be fulfilled.

• Cable ends must be protected from rainfall and water entries while they are not

connected yet.

• Cable must be kept away from hot spots and high temperature pipes. They shall be

protected from scratches and burns from other activities.

• For Heat tracing installation, SUBCONTRACTOR will follow the applicable drawings,

and sharp edges will be avoiding in order to do not damage the cable. Special care

shall be taken with the mineral cable (if apply). Coordination between different Parties

shall exist in order to do not cause delays. - All data sheets of material that are not

supplied by CONTRACTOR will be submitted to CONTRACTOR for approval. Direct

contact between different materials (as Stainless steel and Carbon Steel) will be

avoided by SUBCONTRACTOR using a material to avoid contamination/corrosion (as

Teflon).

TEST PACKAGE

CONTRACTOR will prepare the preliminary scope definition for each Test Package.

SUBCONTRACTOR shall review this scope definition and revert their comments to

CONTRACTOR, who will consider their implementation. Otherwise the preliminary scope

definition will be deemed as accepted by the SUBCONTRACTOR.

CONTRACTOR will submit to SUBCONTRACTOR the Test Package Table of contents

detailing all the Engineering documents and control forms that needs to be included in the

Test Package.

Based on the definition of Test Packages and Tables of Contents described above,

SUBCONTRACTOR shall prepare all the Test Packages.

The main Standard Test Packages to be done (but not limited to) are listed below:

• Piping

o Piping Test Package

o Pipeline Test Package

o Piping Tie-Ins Test Package

• Mechanical

o Static Equipment Box-Up / Final Inspection Package.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 146 OF 162

10651-00-QAC-PD-0003

REV.: 01

o Rotary Final Inspection Package.

o Skid / Miscellaneous Package.

o API / Field Tank Box-Up Package.

• Electrical

o Motor Test Package.

•

Instrumentation

o

Instrument Loop Test Package.

Piping Test Package

SUBCONTRACTOR shall submit Hydrostatic Test Packages prior to conducting hydrostatic

tests of piping, pipeline, and equipment for CONTRACTOR review and approval in

accordance with SAEP-1160, Section 8. The hydrostatic test shall comply with SAES-A-004,

SAES-L-150, and GI 0002.102.

Test package shall describe the limits of piping and equipment included in each pressure

test, the test conditions and all other necessary information to confirm the completion of the

work and to enable the pressure tests to commence.

The Piping Test Packages based on the subsystem Marked up p&ids developed by

pre/commissioning department, with all the documentation required, shall be submitted ,with

all the documentation required, for CONTRACTOR’s review and approval in accordance to

Project Specifications and Procedures, but in any case no later than thirty (30) days prior to

the start of the activity. Piping Test Packages will be kept in a common working room. At least

five (5) working days prior to the Piping Pressure Test date, all the previous activities must

be completed and signed in the Test Package.

Unless otherwise instructed by CONTRACTOR, SUBCONTRACTOR shall compile and

prepare the Piping Test Package with the following documents:

• Cover page showing the progressive Test Package No., location / unit, system /

subsystem and the Test conditions

• Table of contents:

• Release form for testing

• Marked up P&IDs

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 147 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Line list marked for Test Package

•

•

Isometric drawing list

Isometrics drawings (weld map) + detail drawing of special supports (if applicable)

• Welding map

• Pressure Test line check

• Tightness report for bolting (only for final screwed joints)

• Terminal Test points identification

• Water test analysis certificate (if applicable)

• Piping Pressure Test

• Flushing

• Reinstatement

• Punch list

The SUBCONTRACTOR will prepare and keep updated with the hydrotest progress one

“Marked up P&ID Master” with (as a minimum and no limited as per CONTRACTOR

requirement) all the test pack marked with the test pack number , revision , test limits

,pressure test, tested date ,The master shall be updated after each hydrotest and will be

updated during all the hydrotest face ,once the SUBCONTRACTOR finish the test in one

subsystem completely the SUBCONTRACTOR will send the copy to the CONTRACTOR for

comments and approval.

SUBCONTRACTOR shall not commence any pressure test activity before:

• CONTRACTOR review and approval for the respective pressure test package to

verify clearance of all pending items from pre-pressure test line punch listing.

• Document verification by CONTRACTOR safety officer for complete implementation

of safety measures as detailed in the project approved pressure testing procedure.

Pipeline Test Package

Unless otherwise instructed by CONTRACTOR, SUBCONTRACTOR shall compile and

prepare the Pipeline Test Package with the following documents:

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 148 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Cover page showing the progressive Test Package No., location / unit, system /

subsystem and the Test conditions

• Table of contents:

• Release for Hydro Test

• Marked up P&IDs

•

•

Isometric Drawing List

Isometrics drawings (weld map)

• Welding map

• Approval of Test headers (or other test system)

• Water test analysis certificate (if applicable)

• Cleaning activities

• Gauging

• Review of Temperature gauges during thermal stabilization

• Hydro Test

• Depressurization and dewatering activities

• Reinstatement

• Drying activities

• Punch List

The SUBCONTRACTOR will prepare and keep updated with the hydrotest progress one

“Marked up P&ID Master” with (as a minimum and no limited as per CONTRACTOR

requirement) all the test pack marked with the test pack number , revision , test limits

,pressure test, tested date ,The master shall be updated after each hydrotest and will be

updated during all the hydrotest face ,once the SUBCONTRACTOR finish the test in one

subsystem completely the SUBCONTRACTOR will send the copy to the CONTRACTOR for

comments and approval.

SUBCONTRACTOR shall not commence any pressure test activity before:

• CONTRACTOR review and approval for the respective pressure test package to

verify clearance of all pending items from pre-pressure test line punch listing.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 149 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Document verification by CONTRACTOR safety officer for complete implementation

of safety measures as detailed in the project approved pressure testing procedure.

Piping Tie-Ins Test Package

Unless otherwise instructed by CONTRACTOR, SUBCONTRACTOR shall compile and

prepare the Piping Tie-Ins Test Package with the following documents:

• Cover page showing the progressive Test Package No., location / unit, system /

subsystem and the Test conditions.

• Table of contents

• Release form for testing.

• Marked up P&IDs.

• Line list marked for Test Package.

• Tie-In information.

•

Isometrics drawings (weld map) + detail drawing of special supports (if applicable).

• Welding map.

• Terminal Test points identification.

• Water test analysis certificate (if applicable).

• Piping Pressure Test.

• Flushing.

• Punch list.

The SUBCONTRACTOR will prepare and keep updated with the hydrotest progress one

“Marked up P&ID Master” with (as a minimum and no limited as per CONTRACTOR

requirement) all the test pack marked with the test pack number , revision , test limits

,pressure test, tested date ,The master shall be updated after each hydrotest and will be

updated during all the hydrotest face ,once the SUBCONTRACTOR finish the test in one

subsystem completely the SUBCONTRACTOR will send the copy to the CONTRACTOR for

comments and approval.

SUBCONTRACTOR shall not commence any pressure test activity before:

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 150 OF 162

10651-00-QAC-PD-0003

REV.: 01

• CONTRACTOR review and approval for the respective pressure test package to

verify clearance of all pending items from pre-pressure test line punch listing.

• Document verification by CONTRACTOR safety officer for complete implementation

of safety measures as detailed in the project approved pressure testing procedure.

Static Equipment Box-Up / Final Inspection Package

These Packages will contain the engineering documentation, tests and inspection records

necessary to release each Static Equipment Package for the Box-Up and/or Final Inspection

of each Static Equipment.

The Static Equipment Box Up/ Final Inspection Package, with all the documentation required,

shall be submitted for CONTRACTOR’s review and approval in accordance to Project

Specifications and Procedures, but in any case, no later than thirty (30) days prior to the start

of the activity. Static Equipment Box Up/ Final Inspection Packages will be kept in a common

working room. At least five (5) working days prior to the Box-Up/Final Inspection date, all the

previous activities must be completed and signed in the Test Package.

Unless otherwise instructed by CONTRACTOR, the Static Box Up / Final Inspection Package

shall be compiled with the following documents:

• Cover page showing the progressive Test Package No., revision, location / unit and

system / subsystem.

• Table of contents:

• Equipment general arrangement drawing

• Equipment data sheet

• P&ID

• Material receiving inspection report

• Acceptance of civil / steel structure work for mechanical assembly (including

topographic report of the foundation)

•

Installation report

• Screed Mortar / grout

• Anchor bolts tightening

• Tray level and dimensional check (If applicable)

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 151 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Tray Test (if applicable)

• Flange alignment and bolts tightening checked (multi Heat Exchangers connection,

nozzles, manholes, …)

• Static equipment final inspection / closure authorization

• Punch list.

Rotary Final Inspection Package

These Packages will contain the engineering documentation, tests and inspection records

necessary to release each Rotary Equipment Package for the Final Inspection of each Rotary

Equipment.

The Rotary Final Inspection Packages, with all the documentation required, shall be

submitted for CONTRACTOR’s review and approval in accordance to Project Specifications

and Procedures, but in any case, no later than thirty (30) days prior to the start of the activity.

Rotary Final Inspection Packages will be kept in a common working room. At least five (5)

working days prior to the Rotary Equipment Final Inspection date, all the previous activities

must be completed and signed in the Test Package.

Unless otherwise instructed by CONTRACTOR, the Rotary final inspection Test Package

shall be compiled with the following documents:

• Cover page showing the progressive Test Package No., revision, location / unit and

system / subsystem

• Table of contents:

• Equipment general arrangement drawing

• Equipment data sheet

• P&ID

• Material receiving inspection report

• Acceptance of civil / steel structure work for mechanical assembly (including

topographic report of the foundation)

• Elevation and levelling report

• Pre-alignment report

• Screed Mortar / grout

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 152 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Anchor bolts tightening

• Pipe flanges alignment and final alignment report

• Air cooler installation inspection

• Rotary equipment final inspection

• Punch list

Skid / Miscellaneous Final Inspection Package

These Packages will contain the engineering documentation, tests and inspection records

necessary to release each Skid and/or Miscellaneous Equipment Package for the Final

Inspection of each Skid/Miscellaneous Equipment.

The Skid / Miscellaneous Final Inspection Package, with all the documentation required, shall

be submitted for CONTRACTOR’s review and approval in accordance to Project

Specifications and Procedures, but in any case, no later than thirty (30) days prior to the start

of the activity. Skid / Miscellaneous Final Inspection Package will be kept in a common

working room. At least five (5) working days prior to the Skid / Miscellaneous Final Inspection

date, all the previous activities must be completed and signed in the Test Package.

Unless otherwise instructed by CONTRACTOR, the Skid / Miscellaneous Final Inspection

Package shall be compiled with the following documents:

• Cover page showing the progressive Test Package No., revision., location / Unit and

System/Subsystem

• Table of contents:

• Equipment general arrangement drawing

• Equipment data sheet

• P&ID

• Material receiving inspection report

• Acceptance of civil / steel structure work for mechanical assembly (including

topographic report of the foundation)

• Skid / Miscellaneous levelling

• Screed Mortar / grout

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 153 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Anchor bolts tightening

• Final coupling alignment (If applicable)

• Rotary equipment final inspection (if applicable)

• Final / Temporary closure Authorization (if applicable)

• Skid/Miscellaneous piping and Mechanical Package verification

• Electrical and Instrument Package verification

• Punch list

API / Field Tank Box-Up Package

These Packages will contain the engineering documentation, tests and inspection records

necessary to release each API / Field Tank Package for the Box-Up.

The API / Field Tank Box Up Package, with all the documentation required, shall be submitted

for CONTRACTOR’s review and approval in accordance to Project Specifications and

Procedures, but in any case, no later than thirty (30) days prior to the start of the activity. API

/ Field Tank Box Up Packages will be kept in a common working room. At least five (5)

working days prior to the Box-Up date, all the previous activities must be completed and

signed in the Test Package.

Unless otherwise instructed by CONTRACTOR, the API / Field Tank Box Up Package shall

be compiled with the following documents:

• Cover page showing the progressive Test Package No., revision, location / unit and

system / subsystem

• Table of contents:

• Equipment general arrangement drawing

• Equipment data sheet

• P&ID

• Acceptance of civil / steel structure work for mechanical assembly (including

topographic report of the foundation)

• Tank Drawings (weld map) and details Drawings

• Tank Welding Map (Tank joint summary report)

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 154 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Reinforcing pad pneumatic test

• Water test analysis certificate (is required)

• Hydrostatic test and settlement verification

•

Internal coating inspection (thickness / adhesion)

• Tank closure authorization

• Punch list.

Motor Test Package

These Packages will contain the engineering documentation, tests and inspection records

necessary to release each Motor Test Package for the Motor Test.

The Motor Test Package, with all the documentation required, shall be submitted for

CONTRACTOR’s review and approval in accordance to Project Specifications and

Procedures, but in any case, no later than thirty (30) days prior to the start of the activity.

Motor Test Package will be kept in a common working room. At least five (5) working days

prior to the Motor Test date, all the previous activities must be completed and signed in the

Test Package.

Unless otherwise instructed by CONTRACTOR, the Test Packages for Motor Test shall be

compiled with the following documents:

• Cover page showing the progressive Test Package No., revision, location / unit and

system / subsystem

• Table of contents:

• Motor data sheet

• One line diagrams

• Schematic diagrams

•

Interconnecting diagram / list

• Relay settings

• Cable test: continuity and insulation resistance (Control, Power Hi pot)

• Motor and control station installation

• Motor insulation resistance Test

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 155 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Release for Motor Test

• Motor Test

• Punch list.

Loop Test Package

These Packages will contain the engineering documentation, tests and inspection records

necessary to release each Loop Test Package for the Loop Test.

The Loop Test Package, with all the documentation required, shall be submitted for

CONTRACTOR’s review and approval in accordance to Project Specifications and

Procedures, but in any case, no later than thirty (30) days prior to the start of the activity.

Loop Test Package will be kept in a common working room. At least five (5) working days

prior to the Loop Test date, all the previous activities must be completed and signed in the

Test Package.

Unless otherwise instructed by CONTRACTOR, the Loop Test Packages shall be compiled

with the following documents:

• Cover page showing the progressive Test Package No., revision, location / unit and

system / subsystem

• Table of contents:

•

•

ILD (including alarm and trip setting)

Instrument data sheet

• P&IDs

•

Instrument layout

•

SIL Certificates

• Factory calibration or site verification

• Orifice plate site measurement verification

•

Instrument installation

• Cable Test record: continuity and insulation resistance (single cable)

•

Instrument connections Leak Test (pneumatic and process Hoop Up)

• Pre-Loop check (multicables and junction boxes)

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 156 OF 162

10651-00-QAC-PD-0003

REV.: 01

• Loop Test (General Loop / MCC Loop)

• Punch list.

Relief Valve Test Package

These Packages will contain the engineering documentation, tests and inspection records

necessary to release each Relief Valve Test Package for the Relief Valve verification of

calibration.

The Relief Valve Test Package, with all the documentation required, shall be submitted for

CONTRACTOR’s review and approval in accordance to Project Specifications and

Procedures, but in any case, no later than thirty (30) days prior to the start of the activity.

Relief Valve Test Package will be kept in a common working room. At least five (5) working

days prior to the Relief Valve Test date, all the previous activities must be completed and

signed in the Test Package.

Unless otherwise instructed by CONTRACTOR, the Relief Valve Test Packages shall be

compiled with the following documents:

• Cover page showing the progressive Test Package No., revision, location / unit and

system / subsystem

• Table of contents

•

Instrument specification sheet

• Safety instruction sheet

• P&ID

• Relief valve testing and calibration report

• Relief valve installation report

• Gasket verification and bolt torqueing

• Punch list

Test Package – Document Control

SUBCONTRACTOR is responsible of the execution of the different Tests and Inspections

defined in the different Test Packages. SUBCONTRACTOR shall be responsible to keep and

collect in folders all the documentation related and generated during the preparation and

implementations of each Test Package. These Test Package shall be updated in a daily basis

with the possible new versions and revisions of such documents. ORIGINAL REPORTS

SHALL BE UNDER CONTRACTOR CUSTODY.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 157 OF 162

10651-00-QAC-PD-0003

REV.: 01

The activities related to these Test Packages shall be controlled and managed in a dedicated

software. CONTRACTOR will indicate to SUBCONTRACTOR which software shall be used

or, if necessary, SUBCONTRACTOR will be required to provide a dedicated software (usually

SQMS) for CONTRACTOR’s review and approval.

After the selection of the dedicated software described above, and during the execution of

the works, a different dedicated software may be required by COMPANY or CONTRACTOR.

In this case, the dedicated software will be substituted, and the SUBCONTRACTOR shall

adopt it.

Test Package Control Software shall be used by SUBCONTRACTOR under the supervision

and guidance of CONTRACTOR (QA/QC Folder Coordinator).

A specific room shall be enabled by CONTRACTOR where SUBCONTRACTOR, under the

supervision and guidance of CONTRACTOR (QA/QC Folder Coordinator), shall prepare the

hard copy of the Test Packages. All Test Packages shall be kept inside this room all the time.

SUBCONTRACTOR is not authorized to move the Test Packages out of this room.

Soft copy of the Test Package shall be prepared at the same time that the hard copy.

On a daily basis SUBCONTRACTOR under supervision of CONTRACTOR (QA/QC Folder

Coordinator) shall:

• Print (QR Coded** and pre-filled information) and prepare using the software the

necessary documents as required for each Test Package.

** Replace the QR Code manually, replace the QR Code using Photoshop software

or similar software in any original QR Code form shall be considered as serious fault

by SUBCONTRACTOR side. This practice is totally forbidden.

• Keep updated the Test Packages and the dedicated software:

o Scan the Control Forms and upload these in the software (dully filled and

signed off)

o Archive the Control Forms inside each Test Package folder (hard copy) after

completion of the Tests and Inspections (dully filled and signed off)

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 158 OF 162

10651-00-QAC-PD-0003

REV.: 01

o After performing the Test, SUBCONTRACTOR, shall check the Engineering

and/or documents included in Test Packages, searching for the changes done

during the test execution (Red Marked). If Red Marked documents are found,

these documents shall be uploaded in the software in order to have the same

documents as inside the Test Packages.

o After performing the last test of each Test Package (considering the the Test

Package closed), SUBCONTRACTOR shall scan the whole Test Package

and it will be upload to Software (usually SQMS)

SUBCONTRACTOR shall provide at all-time adequate number of competent and qualified

personnel to prepare the Test Packages (hard copy and soft copy). These personnel will work

in the specific room enabled for this purpose and under the supervision and management of

CONTRACTOR (QA/QC Folder Coordinator).

All the material resources (printers, scanners, folders, paper, etc…) necessary to perform the

activities previously described in this section shall be provided by SUBCONTRACTOR and

located in the specific room enabled for the preparation of the Test Packages.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 159 OF 162

10651-00-QAC-PD-0003

REV.: 01

QUALITY PENALTIES

Quality issue

Acceptance criteria

Associated penalty

Resources/Key Personnel/ Number of Inspectors.

Quality SUBCONTRACTOR Personnel at Site/Workshop according to the ratios defined in the procedure “Quality Requirements for SUBCONTRACTORs”.

In those cases when SUBCONTRACTOR does not have the personnel required and defined by Contract, CONTRACTOR may arrange required resources for covering these positions and charge back the associated cost to SUBCONTRACTOR.

Approval of SUBCONTRACTOR´s Final Quality Dossiers.

SUBCONTRACTOR has obtained TR approval of SUBCONTRACTOR Final Quality Dossiers.

Archive and control of Original QC Forms.

The totality of the QC forms produced on Site/Workshop have been correctly stored and preserved in the store room provided for this purpose.

X-Ray Films Warehouse.

The totality of the X-Ray Films produced at Site/Workshop have been correctly stored and preserved in the store room provided for this purpose.

In case of non compliance of any of the Quality Issue acceptance criteria, the applicable certification shall be retained until the submittal of the quality documents or registers which assure the fulfilment of the requirement.

Closure of NCRs opened by TR to the SUBCONTRACTOR.

Zero open NCRs on construction activities related to the certification to be paid by TR.

WRR (Welding Rejection Rate): General WRR (Joint Basis)

WRR (Welding Rejection Rate):

<5% WRR Joint Basis

<5% WRR Joint Basis

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 160 OF 162

10651-00-QAC-PD-0003

REV.: 01

Individual WRR By Welder (Joint Basis)

NDT carried out &

RT and PWHT carried out.

Regarding the 100% of NDTs that shall be done according the monthly production, SUBCONTRACTOR shall not perform less than 90%. (EXPLANATORY NOTE – Pending tests will be assessed in a monthly basis in relation to production, and it will be checked that the Backlog is < 10%or less than Three Days of Production)

Regarding the 100% of RTs and PWHT that shall be done according the monthly production, SUBCONTRACTOR shall not perform less than 90%. (EXPLANATORY NOTE – Pending tests will be assessed in a monthly basis in relation to production, and it will be checked that the Backlog is < 10% or less than Three Days of Production)

ATTACHMENTS AND TEMPLATES

CONTRACTOR may carry out the NDTs . The associated cost to test may be charged back to SUBCONTRACTOR if it is required by CONTRACTOR.

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 161 OF 162

10651-00-QAC-PD-0003

REV.: 01

10651-00-QAC-PD-0003-TMP01- INSPECTION AND TEST PLAN FORM

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

RIYAS NGL FRACTIONATION FACILITIES PKG. 1 & PKG. 2

10651

QUALITY REQUIREMENTS FOR SUBCONTRACTORS

PAGE 162 OF 162

10651-00-QAC-PD-0003

REV.: 01

10651-00-QAC-PD-0003-TMP02- REQUEST FOR INSPECTION FORM

This document is property of UTE TR Jafurah and Consortium of Técnicas Reunidas Saudia for Services and Contracting Co Ltd. and SINOPEC Engineering (Group) Co., Ltd. Saudia. Its reproduction without previous permission in writing is strictly forbidden

DocuSign Envelope ID: 03FDD037-BB84-4A1E-8BC3-4D1D90E45F1F

Project: Q-31108 - Tecnicas - Riyas Folder: RFQ Files


Loading authentication...

Graph View

Backlinks

  • 00 Index

Created with Infinity Constructor © 2025

  • Elynox | Go Further