Infinity

Not logged in
Home

❯

Reference Examples

❯

Q 32705 Saipem COMP3

❯

RFQ Files

❯

200 20 PE DEC 00004_A

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

COMPANY Contract No.: LTC/C/NFP/5129/20 CONTRACTOR Project No.: 033764

ASSET

: NFPS

Document Title

:

PROJECT BASIS OF DESIGN FOR COMP3 PROJECT

COMPANY Document No.

:

200-20-PE-DEC-00004

CONTRACTOR Document No.

:

033764-B-D-18-SPM-EM-S-00001

Discipline

:

ADMINISTRATIVE, ENGINEERING MANAGEMENT

Document Type

: DESIGN CRITERIA

Document Category/Class

:

1

Document Classification

:

Internal

A

04-FEB-2025

Issued for Review

Jobi George Anirudh Nadiger Reetesh Jha

Tech. Manager Tech. Manager Eng. Manager

REV.

DATE

DESCRIPTION OF REVISION

PREPARED BY

REVIEWED BY

APPROVED BY

Saipem S.p.A

www.saipem.com

THIS DOCUMENT IS PROPERTY OF QatarEnergy LNG. THIS DRAWING OR MATERIAL DESCRIBED THEREON MAY NOT BE COPIED OR DISCLOSED IN ANY FORM OR MEDIUM TO THIRD PARTIES, OR USED FOR OTHER THAN THE PURPOSE FOR WHICH IT HAS BEEN PROVIDED, IN WHOLE OR IN PART IN ANY MANNER EXCEPT AS EXPRESSLY PERMITTED BY QatarEnergy LNG.

200-20-PE-DEC-00004_A

1 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

REVISION HISTORY

Revision

Date

Revision Description

A1

A

01-NOV-2024

Issued for Inter Disciplinary Check

04-FEB-2025

Issued for Review

HOLDS LIST

Hold No

Hold Description

1

2

3

4

5

Deleted

Section 5.1: Platform coordinates to be confirmed

Section 5.3.2: Water depth of brownfield platforms to be confirmed

Section 8.14: Splash zone data of brownfield platforms to be confirmed

Section 8.16: Subsidence data of brownfield platforms to be confirmed

200-20-PE-DEC-00004_A

2 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

TABLE OF CONTENTS

INTRODUCTION … 4 1.1. PROJECT OBJECTIVE … 4 1.2. PROJECT SCOPE … 4 2. DEFINITIONS AND ABBREVIATIONS … 7 2.1. DEFINITIONS … 7 2.2. ABBREVIATIONS … 7 3. REFERENCE DOCUMENTS, RULES, CODES AND STANDARDS … 8 3.1. COMPANY REFERENCES … 8 3.2. PROJECT DOCUMENTS … 11 3.3. STANDARDS … 11 4. SCOPE AND PURPOSE … 12 5. FACILITIES DESCRIPTION AND BASIS … 12 5.1. PROJECT LOCATION AND ORIENTATION … 18 5.2. CO-ORDINATE SYSTEMS … 19 5.3. WATER DEPTHS … 19 5.3.1. Greenfield … 19 5.3.2. Brownfield … 20 5.4. DESIGN LIFE … 21 5.4.1. Equipment Design Life… 21 5.4.2. Structure Design Life – Jackets, Topsides and Piles … 21 5.5. RELY UPON DATA … 21 6. ORDER OF PRECEDENCE … 21 7. UNITS OF MEASUREMENT … 22 8. ENVIRONMENTAL DATA … 24 8.1. GENERAL … 24 8.2. AMBIENT TEMPERATURE AND PRESSURE … 24 8.3. SOLAR RADIATION … 24 8.4. RELATIVE HUMIDITY … 24 8.5. WIND SPEED… 25 8.6. RAINFALL INTENSITY… 25 8.7. SEAWATER PROPERTIES … 25 8.8. SEA CURRENT DATA … 26 8.9. TIDE DATA … 26 8.10. EXTREME SEAWATER LEVEL … 26 8.11. WAVE DATA … 27 8.12. FATIGUE WAVE DATA … 27 8.13. SEISMIC DATA - OFFSHORE … 27 8.14. SPLASH ZONE … 27 8.15. MARINE GROWTH … 29 8.16. SUBSIDENCE … 29 8.17. GEOTECHNICAL DATA … 29 9. DISCIPLINE DESIGN BASIS … 29

200-20-PE-DEC-00004_A

3 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

  1. INTRODUCTION

The North Field is the world’s largest natural gas field and accounts for nearly all the State of Qatar’s gas production. The principal objective of the NFPS projects is to sustain plateau from existing QatarEnergy LNG Operation – S1, S2, S3, N1 and N2, production areas by implementing an integrated and optimum investment program consisting of subsurface development, pressure drop reduction steps and compression.

NFPS projects comprise 3 main investment programs:

  1. Investment #1: Drilling and Associated Facilities [WHP12S/ WHP13S/ WHP14S/

WHP12N/ WHP13N]

  1. Investment #2: Trunk line Looping and Intra-field pipeline looping [32” PL1LN, 32”

PL1LS, 38”PL610LS]

  1. Investment #3: Compression Complexes and associated facilities [Phase 1 CP6S & CP7S; Phase 2: CP8S & CP4N; Phase 3: CP4S & CP6N Phase 4: CP1S & CP1N]

Drilling and Looping, Investments #1 and #2, projects are in execution phase and are being executed as I1P1, EPCOL Projects except for WHP13N, which will be part of NFPS Compression Projects execution which compromises total up to 9 COMPs.

1.1. Project Objective

The objective of this Project includes:

• Achieve standards of global excellence in Safety, Health, Environment, Security and

Quality performance.

• Sustain the Qatarenergy LNG North Field Production Plateau by installing new RPs and one WHPs to support new Compression Complex facilities CP6S & CP7S and pre-installed facilities for future Compression Complex facilities including but not limited to CP4N & CP8S tie-in with integration to the existing facilities under Investment #3 program.

• Facility development shall be safe, high quality, reliable, maintainable, accessible,

operable, and efficient throughout their required life.

1.2. Project Scope

The Project Scope includes detailed engineering, procurement, construction, brownfield modifications, transportation & installation, hook-up and commissioning, tie-in to EXISTING PROPERTY and provide support for start-up activities of the following facilities and provisions for future development. The WORK shall be following the specified regulations, codes, specifications and standards, achieves the specified performance, and is safe and fit purpose in all respects.

for

‐

‐

Facilities - 1A

• RP5S RP with 2 x 28” CRA clad pipelines to RP7S and 2 subsea composite Cables and

associated J tubes from RP7S to RP5S & from CP7S to WHP13S.

• New Fuel Gas 8” CRA Spur-lines and flanged risers from Subsea skid to RP7S

200-20-PE-DEC-00004_A

4 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

• Hook-up and brownfield modification at WHP5S/RP5S bridge connection & WHP13S/CP7S Composite cable tie-in and E&I integration including RGA Control modification

• Pipeline decommissioning of 28” CS PL5 including associated demolition work at

WHP5S

Facilities - 2A

• RP6N RP with 1x28” CRA clad pipeline to WHP13N, 2 Subsea composite cables and

associated J tubes from WHP12N to RP4N and RP6N to WHP13N. • New fuel gas spur-line and flanged riser from subsea skid to RP6N • WHP13N Topside • Hook-up and brownfield modification at WHP6N/RP6N, RP4N- HPU-Umbilical and tie- in, WHP12N-new J tube installation, E&I migration, WHP6N/RP4N/WHP4N-E&I migration (Pre-CP4N), WHP13N and RP6N interconnection to NFB.

Facilities - 3A

• RP9S RP with 1x28” CRA clad pipeline to RP4S, • Hook-up and brownfield modification at RP4S/WHP9S, Modifications to integrate RP9S

to the RGA control network.

• Pipeline decommissioning of 28” PL9 to WYE on existing 38” trunkline PL49including

associated demolition work at WHP9S.

Facilities - 1B

• New fuel gas spur-line and flanged riser from subsea skid to RP4N • Fiber Optic Cable from RP6N to onshore LFP East, RP6N to RP4N and RP6N to LQ6S. • Hook-up and brownfield modification at RP6N Composite and FO Tie-ins NFB-PU (East)- FO Tie-in

(East)/BVS

Power & Control modifications, LQ6S/LFP Controls/Telecoms Integration

Facilities - 2B

• RP5N RP with 2 x 28” CRA clad pipelines to RP4N, 1 x 28” CRA clad pipeline to RP6N and 2 subsea composite Cables and associated J tubes from WHP12N to RP5N & from RP6N to RP5N.

• Hook-up and brownfield modification at WHP5N- RP5N Bridge connection, WHP12N Composite cable tie-in, RP4N Intrafield pipeline Hook up PL54 N/LN and E&I integration including NFB-PU Power & Control modifications

• Pipeline decommissioning of 2 x 16” PL56/PL54 Subsea Spur line from WHP5N to

reducing barred tee in subsea tie-in skid on PL6 / PL4.

Facilities - 3B

• 2 subsea composite Cables from RP4S to RP9S & from RP4S to WHP12S (with J-tube) • New Fuel Gas 8” CRA Spur-lines and flanged risers from Subsea skid to RP4S • Hook-up and brownfield modification at WHP12S/ RP9S/ RP4S Composite cable tie-in,

Spurline riser installation at RP4S RGA Power & Control modifications.

Facilities - 4B

• 1 subsea composite Cable from CP8S to RP11S (or from RP8S to RP11S as Option). • New Fuel Gas 8” CRA Spur-line and flanged riser from Subsea skid to RP8S.

200-20-PE-DEC-00004_A

5 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

• Hook-up and brownfield modification at WHP8S/ WHP11S for Test separator Internal Upgrade and MEG system modification, Spur lines, Power & Control Tie-ins on RP8S, RP11S/WHP11S-Tie-in (Power and Control), RGA Power & Control modifications.

Facilities - 5B

• 2 subsea composite Cables from RT2 to WHP3S & from RT2 to WHP2S (with J-tube)

and FO Cable from RT2 to Barzan WHP1.

• New Fuel Gas 8” CRA Spur-line and flanged riser from Subsea skid to RT2 • Hook-up and brownfield modification at BRZ-WHP1 - FO cable tie-in, WHP2S/ WHP3S/ RT&RT2 Composite cable tie-in and associated modification, RGA Power & Control modifications.

Facilities - 6B

• RP3S RP with 1x24” CRA clad pipeline to RT2 with Stalk on risers, • Hook-up and brownfield modification at RT2

Intrafield pipeline and Composite/FO cable Hook-up, WHP3S for Production diversion and Utilities, Power and ICSS Hook-up, WHP2S for Composite Cable Tie-ins and Power & Control Integration RGA Power & Control modifications.

for 24”

• Decommissioning at

In-situ abandonment of existing Topside/subsea Composite Cables RT-WHP2S, RT-WHP3S, Topside/Subsea FO cable RT-BRXWHP1.

topside existing and

Figure 1.2.1: NFPS Compression Project COMP3 Scope

200-20-PE-DEC-00004_A

6 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

  1. DEFINITIONS AND ABBREVIATIONS

2.1. Definitions

Definition

Description

COMPANY

QatarEnergy LNG.

CONTRACTOR

Saipem S.p.A.

DELIVERABLES

FACILITIES

MILESTONE

PROJECT

SITE

SUBCONTRACT

SUBCONTRACTOR

All products (drawings, equipment, services) which must be submitted by CONTRACTOR to COMPANY at times specified in the contract. All machinery, apparatus, materials, articles, components, systems and items of all kinds to be designed, engineered, procured, manufactured, constructed, supplied, fabricated, tested and permanently installed by CONTRACTOR at SITE in connection with the NFPS Project as further described in Exhibit 6. A reference event splitting a PROJECT activity for progress measurement purpose. COMP3 - NFPS Offshore Riser/Wellhead Platform & Intrafield Pipelines Project (i) any area where Engineering, Procurement, Fabrication of the FACILITIES are being carried out and (ii) the area offshore required for installation of the FACILITIES in the State of Qatar Contract signed by SUBCONTRACTOR and CONTRACTOR for the performance of a certain portion of the WORK within the Project. Any organization selected and awarded by CONTRACTOR to supply a certain Project materials or equipment or whom a part of the WORK has been Subcontracted.

WORK

Refer to article 2 of CONTRACT AGREEMENT.

WORK PACKAGE

The lowest manageable and convenient level in each WBS subdivision.

2.2. Abbreviations

Code

PMT DCS DLE ESD HAT LAT SLE

Definition

Project Management Team Distributed Control System Ductility Level Earthquake Emergency Shutdown System Highest Astronomical Tide Lowest Astronomical Tide Strength Level Earthquake

200-20-PE-DEC-00004_A

7 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

  1. REFERENCE DOCUMENTS, RULES, CODES AND STANDARDS

3.1. COMPANY References

S. No Document Number

Title

LTC/C/NFP/5129/20

Contract Agreement

Exhibit 6A & 6B

Scope of Work

OMQ011 (181571_2_Part 2)

158164_REP02_FME_PSHA_ QATAR_GAZ_2020

413040-00200-EIA-001

Updated Metocean Criteria Offshore Qatar, Rev 3, 19 February 2019 Seismic Hazard Assessment for the North Field Production Sustainability (NFPS) Project (Qatar), Rev 04, 7 October 2020 NFPS Compression Project - Environmental Impact Assessment Report, Rev 3, 30 May 2022 Ras Laffan Environmental Data Summary, Rev. 5, Jan 2000

Geotechnical and Geophysical Survey Reports – Platforms

MRQ025-V02c-SR-RT5 (Rev.1)

MRQ025-V02d-SR-RT9

MRQ025-V02i-SR-RPQD6 (Rev.2)

GIQ345/218

GIQ345/213

GIQ345/214

GIQ403/145

GIQ403/142

GIQ403/242

GIQ403/243

Geophysical Survey Report Proposed Platform Location - RT5 (RGWHP5) 6 and 7 October 2018_ Issued as Final Geophysical Survey Report - Proposed Platform Location

  • RT9 (RGWHP9), Rev 1, 10 October 2018 Geophysical Survey Report Proposed Platform Location - RPQD6 (WHPQ6) OLD & RPQD6_REV1_ 2 October 2018_ Issued as Final Final Engineering Report - Provision of Underwater Inspection & Geotechnical / Geophysical Survey Services
  • RT9, Rev 1, 18 February 2019 Final Engineering Report - Provision of Underwater Inspection & Geotechnical / Geophysical Survey Services
  • RT5, Rev 1, 17 February 2019 Final Engineering Report - Provision 0f Underwater Inspection & Geotechnical/Geophysical Survey Services - RT5-BS, Rev 1, 17 February 2019 Geotechnical Field Report - Geotechnical Survey - Offshore Platform Structures (Compression Phase 2) - WHP13N Wellhead Platform, Rev 1, 20 September 2020 Geotechnical Field Report - Geotechnical Survey - Offshore Platform Structures (Compression Phase 2) - QG2 CP6N (RP6N) Riser Platform, Rev 1, 10 August 2020 Final Engineering Report - Geotechnical Survey - Offshore Platform Structures (Compression Phase 2) - QG2 CP6N (RP6N) Riser Platform, Rev 1, 26 September 2020 Final Engineering Report - Geotechnical Survey - Offshore Platform Structures (Compression Phase 2) - RP5N Riser Platform, Rev 1, 23 October 2020

200-20-PE-DEC-00004_A

8 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

S. No Document Number

Title Final Engineering Report - Provision of Underwater Inspection & Geotechnical/Geophysical Survey Services – RT-51, Rev 1, 18 February 2019 Geotechnical and Geophysical Survey Reports – Pipelines and Cables

GIQ345/219

MRQ025-V03a-SR-28 RT11 to RT8-OPT1

MRQ025-V03b-SR-28 RT11 to RT8-OPT2

MRQ025-V05b-SR-28in

RGWHP13 to RT7

MRQ025-V05e-SR-28in

RGWHP14 to RT6

MRQ025-V05f-SR-28in WHPQ12 to RPQD4

MRQ025-V05g-SR-28″ WHPQ13 to RPQD6

MRQ025-V05h-SR-24in RT-

51 to RT-52

MRQ025-V05i-SR-28in RT5

to RT7

MRQ025-V05j-SR-28in RT5

to RT7

MRQ025-V05k-SR-28in RT9

to RT4

MRQ025-V05l-SR-28in RT9

to RT4

MRQ029/101

MRQ029/202

MRQ046/101

Geophysical Survey Report 2 x 28″ CRA Clad Intrafield Pipelines from RT-11 to RT-8 (Option 1), Rev 1, 1 October 2019 Geophysical Survey Report 2 x 28″ CRA Clad Intrafield Pipeline from RT-11 to RT-8 (Option 2), Rev 1, 1 October 2019 Geophysical Survey Report Proposed 28″ CRA Clad Intrafield Pipeline from RGWHP13 to RT7 at RGWHP7 (Base Case), Rev 1, 3 March 2019 Geophysical Survey Report Proposed 28 inch CRA Clad Intrafield Pipeline from RGWHP14 to RT6 at RGWHP6, Rev 1, 3 March 2019 Geophysical Survey Report Proposed 28″ CRA Clad Intrafield Pipeline from WHPQ12 to RPQD4 at WHPQ4, Rev 1, 3 March 2019 Geophysical Survey Report - Proposed 28″ CRA Clad Intrafield Pipeline from WHPQ13 to RPQD6 at WHPQ6, Rev 1, 3 March 2019 Geophysical Survey Report Proposed 24″ CRA Clad Intrafield Pipeline from RT-51 at RGWHP3 to RT-52 at RGA, Rev 1, 3 March 2019 Geophysical Survey Report Proposed 28″ CRA Clad Intrafield Pipeline from RT5 at RGWHP5 to RT7 at RGWHP7 (Pipeline-1), Rev. 1, 3 March 2019 Geophysical Survey Report Proposed 28″ CRA Clad Intrafield Pipeline from RT5 at RGWHP5 to RT7 at RGWHP7 (Pipeline-2), Rev. 1 , 3 March 2019 Geophysical Survey Report Proposed 28″ CRA Clad Intrafield Pipeline-1 from RT9 at RGWHP9 to RT4 at RGWHP4, Rev 1, 3 March 2019 Geophysical Survey Report Proposed 28″ CRA Clad Intrafield Pipeline-2 from RT9 at RGWHP9 to RT4 at RGWHP4, Rev. 1, 3 March 2019 Geotechnical Factual Report - Pipeline Geotechnical Survey North Field Sustainability Project, Rev 2, 5 May 2019 Consultancy Report - North Field Production Sustainability Project: Pipeline-Seabed Interaction Assessment, Rev 1, 24 April 2019 Geotechnical Factual Report - Geophysical and Geotechnical Offshore Surveys for Pipeline/Cable Routes (Compression Phase), Rev 2, 14 October 2020

200-20-PE-DEC-00004_A

9 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

S. No Document Number

MRQ046-V01-SR-TO

MRQ046-V02a-SR-32in FG PL-LFP (EC) to RP6S MRQ046-V02b-SR-32in FG PL-LFP (WC) to RP6S MRQ046-V03b-SR-28in PL- RP5N to RP4N MRQ046-V03c-SR-28in PL- RP5N to RP6N MRQ046-V04b-SR-Cable CP1S to WHP2S MRQ046-V04c-SR-Cable CP4S to WHP12S MRQ046-V04d-SR-Cable WHP12N to RP5N MRQ046-V04e-SR-Cable BRZ WHP-1 to RT2 MRQ046-V04f-SR-Cable RP6N to LQ6S MRQ046-V05a-SR-8in FG Spurline to RT2 (CS1) MRQ046-V05b-SR-8in FG Spurline to RP4S (CS4) MRQ046-V05c-SR-8″ FG Spurline to RP7S (CS7) MRQ046-V05d-SR-8in FG Spurline to RP8S (CS8) MRQ046-V05f-SR-8in FG Spurline to RP4N (CS4N) MRQ046-V05g-SR-8″ FG Spurline to RP6N (CS6N)

Title Technical and Operations Report - Geophysical and Geotechnical Offshore Survey for Pipelines/Cables (Compression Phase) – North Field Production Sustainability, Rev 1, 20 October 2020 Geophysical Survey Report - 32″ Fuel Gas Pipeline from LFP (East Corridor) to RP6S, Rev. 1 , 20 October 2020 Geophysical Survey Report - 32″ Fuel Gas Pipeline from LFP (West Corridor) to RP6S, Rev. 1, 20 October 2020 Geophysical Survey Report - 28″ Intrafield Pipeline RP5N to RP4N, Rev. 1 , 20 October 2020 Geophysical Survey Report - 28″ Intrafield Pipeline RP5N to RP6N (Base Case), Rev. 1 , 20 October 2020 Geophysical Survey Report - Composite Cable CP1S to WHP2S, Rev. 1 , 20 October 2020 Geophysical Survey Report - Composite Cable CP4S to WHP12S, Rev. 1 , 20 October 2020 Geophysical Survey Report - Composite Cable WHP12N to RP5N, Rev. 1 , 20 October 2020 Geophysical Survey Report - Fibre Optic Cable BRZ WHP-1 to RT2, Rev. 1 , 20 October 2020 Geophysical Survey Report - Fibre Optic Cable RP6N to LQ6S, Rev. 1 , 20 October 2020 Geophysical Survey Report - 8” Fuel Gas Spurline to RT2 (CS1), Rev. 1 , 20 October 2020 Geophysical Survey Report - 8” Fuel Gas Spurline to RP4S (CS4), Rev. 1, 20 October 2020 Geophysical Survey Report - 8″ Fuel Gas Spurline to RP7S (CS7), Rev 1, 20 October 2020 Geophysical Survey Report - 8″ Fuel Gas Spurline to RP8S (CS8), Rev. 1, 20 October 2020 Geophysical Survey Report - 8″ Fuel Gas Spurline to RP4N (CS4N), Rev. 1, 20 October 2020 Geophysical Survey Report - 8″ Fuel Gas Spurline to RP6N (CS6N), Rev 1, 20 October 2020

Note: Platform Nomenclature used in Survey Reports:

COMP3 Facilities Designation WHP13N RP3S RP5S BSP5S-1 RP9S RP5N RP6N

Platform Name in Geotechnical and Geophysical Reports WHP13N, WHPQ13 RT-51 RT5 RT5-BS RT9 RP5N RP6N, RPQD6

200-20-PE-DEC-00004_A

10 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

3.2. Project Documents

S. No Document Number

Title

200-20-PR-DEC-00051

RGE Process Design Basis for COMP3 Project

200-20-PR-DEC-00052

QG2 Process Design Basis for COMP3 Project

200-20-PR-DEC-00053

RGA Process Design Basis for COMP3 Project

200-20-SH-DEC-00013

Technical Safety Basis of Design for COMP3 Project

200-20-SH-DEC-00014

Environmental Basis of Design for COMP3 Project

200-91-EL-DEC-00008

Electrical Design Basis for COMP3 Project

200-20-ME-DEC-00009

Mechanical Design Basis for COMP3 Project

200-42-HV-DEC-00004

200-51-IN-DEC-00011

200-52-TC-DEC-00005

HVAC Design Basis - Offshore for COMP3 Project Instrument and Control Systems Design Basis for COMP3 Project Telecommunication Design Basis for COMP3 Project

200-20-PI-DEC-00009

Basis of Design for Piping for COMP3 Project

200-20-PI-DEC-00010

Piping and Layout Design Basis for COMP3 Project

200-20-PI-DEC-00011

200-22-ST-DEC-00004

200-21-ST-DEC-00003

200-20-ST-DEC-00007

200-20-PL-DEC-00005

Piping Stress Analysis Design Basis for COMP3 Project Topsides Structural Design Basis (Greenfield) for COMP3 Project Substructure Design Basis (Greenfield) for COMP3 Project Brownfield Structural Design Basis Offshore for COMP3 Project Metocean Basis of Design for COMP3 Project

200-25-PL-DEC-00007

Pipeline and Riser Basis of Design for COMP3 Project

200-20-PL-DEC-00007

200-25-PL-DEC-00008

702-25-PL-DEC-00003

200-20-PL-DEC-00006

Cable and Umbilical Basis of Design for COMP3 Project Flow Assurance Basis of Design for Intrafield Lines and Trunklines for COMP3 Project Flow Assurance Basis of Design for Spurlines for COMP3 Project Offshore Geophysical and Geotechnical Basis of Design for COMP3 Project

COMP3-SPM-PE-PRC-00003 Document Numbering Procedure COMP3-SPM-IM-PRC-00001 Document Control Procedure COMP3-SPM-PL-TQY-00006 Technical Query for Metocean Data For Pipeline Design

3.3. Standards

S. No Document Number

Title

N/A

200-20-PE-DEC-00004_A

11 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

  1. SCOPE AND PURPOSE

Purpose of this document is to define the overall design basis of the facilities under COMP3 Project

  1. FACILITIES DESCRIPTION AND BASIS

Compression 3 comprises of 3A and 3B scopes as described in Table 5.1 and 5.2 below:

Table 5.1: Summary of FACILITIES Scope for COMP 3A

Item

FACILITIES-1A

COMP3A Offshore Facility Description RP5S Riser Platform, Intra field pipelines / Subsea Cables (Linkage with RP7S) and Brownfield Modifications: Spur Line:

• 8” CRA Clad FG Spur line from Subsea Skid to RP7S topsides.

(Approx. 0.5 km)

Intra field Pipelines:

• 28” CRA Clad Intra-field Pipelines PL5S, from RP5S to RP7S

(Approx. 9.2 km) + Stalk on risers at RP5S and RP7S respectively

• 28” CRA Clad Intra-field Pipelines, PL5LS, from RP5S to RP7S

(Approx. 8.9 km) + Stalk on risers at RP5S and RP7S respectively

Riser Platform RP5S:

• Topsides, Jacket and Bridges (BR5S-1, BR5S-2) • Bridge Support Platform BSP5S-1 between WHP5S and RP 5S

Hook up and Brownfield Modifications:

• WHP5S - RP5S Bridge connection/hook up/protection structure. • RP7S Spur line tie-in • WHP13S Composite Cable tie-in and E&I Integration

Brownfield RGA Controls

• RGA to RP5S through WHP5S (Pre-CP7S Installation)

Pipeline Decommissioning:

• Decommission 28” CS pipeline PL5 from WHP5 to WYE on existing

38” trunkline PL75.

• Decommission and demolition of WHP5S topside pig launcher and

associated systems post pipeline PL5 decommissioning.

Composite Cables and J-Tubes:

• Composite Cable from RP7S to RP5S (Approx. 9.2 km) • Composite Cable from CP7S to WHP13S (Approx. 11.0 km) • One (1) post installed J-Tube on WHP13S

200-20-PE-DEC-00004_A

12 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

Item

COMP3A Offshore Facility Description WHP13N Wellhead Platform and RP6N Riser Platform with bridge link to WHP6N, Intra Filed Pipelines, Subsea Cables and Brownfield Works: Subsea Skid Umbilical:

• RP6N to Fuel Gas Subsea Skid (Approx. 0.5 km)

Intra field Pipelines:

• 28” CRA Clad Intra-field Pipelines PL13N, from WHP13N to RP6N

(Approx. 7.0 km) + Stalk on risers at WHP13N and RP6N respectively

Riser Platform RP6N:

• Topsides, Jacket and Bridges (BR6N-1)

Well Head Platform WHP13N: • WHP13N Topside

Spur Line:

FACILITIES-2A

Composite Cables and J-Tubes:

• 8” CRA Clad Flanged Riser for FG Spur line

• Composite Cable from WHP12N to RP4N (Approx. 12.3 km) • Composite Cable from RP6N to WHP13N (Approx. 7 km) • One (1) post installed J-Tube on WHP12N

Hook up and Brownfield Modifications:

• WHP6N- RP6N Bridge connection/hook up/protection structure and

helideck decommissioning.

• RP4N - HPU-Umbilical and tie-ins (Power & Control) • WHP12N - New J-tube installation, Composite Cable installation &

tie-in, E & I migrations

• WHP6N/ RP4N/WHP4N-E & I Migrations (Pre-CP4N)

Brownfield NFB Controls:

• WHP13N and RP6N Interconnection to NFB. • WHP4N controls from NFB through NFB-WHP12N connectivity

RP9S Riser Platform with bridge link to WHP9S Intra Filed Pipelines, Subsea Cables and Brownfield Works: Riser platform RP9S:

• Topside, Jackets and Bridge BR9S-1

Intra field Pipelines:

• 1X28” CRA Clad Intra-field Pipeline and stalk on risers, PL9S, from

RP9S to RP4S (Approx. 9.9 km)

Brownfield Modifications: RP4S Brownfield Modifications

• Hook up of the intra-field pipelines at RP4S. • Structural modifications WHP9S Brownfield Modifications

FACILITIES-3A

200-20-PE-DEC-00004_A

13 of 29

Classification: Internal

Item

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

COMP3A Offshore Facility Description • Topsides and Jacket Modification • Hook-up between WHP 9S and RP 9S • Production diversion from wellhead to RP9S • Supply of utilities including MEG from WHP9S to RP9S. • Topsides, Pig-launcher and associated piping

decommissioning/demolition.

RGA Brownfield

•

Modifications to integrate RP9S to the RGA control network.

Pipeline Decommissioning:

• Decommission 28” CS pipeline PL9 from WHP9S to WYE on existing 38” trunkline PL49, including launcher and receiver on WHP9S.

Table 5.2: Summary of FACILITIES Scope for COMP 3B

Item

FACILITIES-1B

COMP3B Offshore Facility Description Pipeline / Subsea cables and Brownfield works support for CP6N & CP4N Complex: Spur line:

• 1 new 8” Fuel Gas Spur line installed, fully tested andpreserved from Subsea skid (Approx. 0.5 km) to Platform RP4N topsides, including the associated brownfield and hook up work.

Fiber Optic (FO) Cable:

• RP6N to onshore LFP East including Onshore LFP East to Fiber

Interface Box (FIB) at BVS East (Approx. Length 91.5 km)

• RP6N to RP4N (Approx. Length 20.6 km) • RP6N to LQ6S (Approx. Length 15.4 km)

Brownfield Modifications:

• Riser Platform (RP) RP6N - Composite and FO Tie-ins. • NFB-PU Power & Control modifications

Brownfield Works at LFP (BVS East)

• LQ6S/LFP (East)/BVS (East)- FO Tie-in Controls/Telecoms

Integration

RP5N FACILITIES Riser Platform with bridge link to WHP5N, Intra field Pipelines/Subsea cables and Brownfield Work: New Riser Platform RP 5N:

FACILITIES-2B

Hook up and Integration:

• ➢ Top side, Jacket and Bridge

• ➢ WHP5N- RP5N Bridge connection/hook up/protection structure and

tie-ins (Flow Diversion to RP5N, Power & Control)

Intra field Pipelines:

• PL56N, from RP5N to RP6N (Approx. 11.1 km)

200-20-PE-DEC-00004_A

14 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

Item

COMP3B Offshore Facility Description

• PL54N from RP5N to RP4N (Approx. 19.1 km) • PL54LN from RP5N to RP4N (Approx. 19.1 km) • Associated tie-ins to RP4N and RP6N topside.

Composite Cables:

• New composite cable WHP12N to RP5N (Approx. Length 9.1 km) • New Composite Cables RP6N to RP5N (Approx. Length 10.1 km)

Post Installed J-Tube:

• One (1) on WHP12N Brownfield Modifications:

• WHP’s

o WHP4N - HIPPS Decommission, Thermowell Upgrade, Flow Diversion between WHP and RP, Power and Control Tie-in, Piping Installation (including RP4N-WHP4N Bridge)

o WHP5N – Production Header Tie-in’s (Isolation with smart plug) and Flow diversion (x2), HIPPS decommissioning (x2), Test Separator Internals Upgrade. MEG system mods

to RP5N

o WHP12N - Power and Control Tie-in

• RP’s

o RP4N - Reconfigure existing HIPPS and install new HIPPS, Intra field, Pipeline PL54 N/LN, Power and Control Tie-ins, Dropped Object Protection Structure, BDV Platform and Piperack.

o RP6N – Hook-up of Intra-field Pipeline PL56N

• NFB-PU Power & Control modifications (Connection of Controls

related to RP5N to NFB through WHP5N)

Pipeline Decommissioning:

• 16” PL56 Subsea Spur line from WHP5N to reducing barred tee in

subsea tie-in skid on PL6

• 16” PL54 Subsea Spur line from WHP5N to reducing barred tee in

subsea tie-in skid on PL4

• Decommissioning of topside instrumentation and ICSS controls

associated with spur-line decommissioning in the platform WHP5N and associated logic modifications as applicable.

Pipeline / Subsea cables and Brownfield works support for CP4S Complex Composite Cables:

• New composite cable between RP4S – RP9S. (Approximate length

10km)

• New composite cable between RP4S – WHP12S. (Approximate

Length 6 km)

Post Installed J-Tube:

• One (1) on WHP12S

FACILITIES-3B

200-20-PE-DEC-00004_A

15 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

Item

COMP3B Offshore Facility Description Spur Line:

• 1 new 8” Fuel Gas Spur line installed, fully tested and preserved from Subsea skid. 0.9 Kms approximately to Platform RP4S topsides from Subsea Skid Brown Field Works:

• WHP12S - Composite cable pull-in and tie-in • RP9S - Composite cable pull-in and tie-in RP4S - Spurline riser

installation and tie-in Composite Cable pull-in and tie-in.

• RGA Power & Control modifications

Pipeline / Subsea cables and Brownfield works support for CP8S Complex: Composite Cables and J-Tubes:

• CP8S to RP11S (Approx. Length 6.8 km) / RP8S to RP11S as an

Option

Spur Line:

• 1 new 8” Fuel Gas Spur line installed fully tested and preserved from Subsea skid (Approx. 0.4 km) to Platform RP8S topsides, including the associated brownfield and hook up work.

FACILITIES-4B

• WHP’s

Brownfield Modifications:

o Test Separator Internal Upgrade and Associated Works-

WHP8S, WHP11S.

o MEG System modifications-WHP8S o MEG System modifications& Parallel header - WHP11S

• RP’s

o Spur lines, Power & Control Tie-ins on RP8S o RP11S/WHP11S-Tie-in (Power and Control) and Parallel

Piping Header

• RGA Power & Control modifications

Pipeline / Subsea cables and Brownfield works support for CP1S Complex Composite Cables:

• Subsea Composite Cable from RT2 to WHP3S (Approx. 7.1 km) • Subsea Composite Cable from RT2 to WHP2S (Approx. 7.6 km)

Fiber Optic cable:

• RT2 to Barzan WHP1 (Approx. 14.3 km)

FACILITIES-5B

Spur Line:

• 1 new 8” Fuel Gas Spur line installed, fully tested and preserved from Subsea skid (0.5 Km Approximately) to Platform RT2 topsides, including the associated brownfield and hook up work.

Brownfield Works: • WHP’s

o BRZ-WHP1 – FO Cable tie-in & Communication Tests

200-20-PE-DEC-00004_A

16 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

Item

COMP3B Offshore Facility Description

o WHP2S – Composite cable pull-in and tie-in o WHP3S – Composite cable pull-in and tie-in

• RGA Power & Control modifications • RT&RT2 – Composite Cable and associated modifications

RP3S Riser Platform with bridge link to WHP3S, Intra field Pipelines and associated Brownfield Work: New Riser Platform RP3S:

• Top side, Jacket, Bridge BR3S between RP3S and BSP3S and Bridge

support platform BSP3S

Intra field Pipelines:

• 1 x 24” CRA Clad Intra field Pipeline (PL3LS) and stalk on risers from

RP3S to RT2 (Approx. 6.8 km)

Brownfield Modifications: RT2 Brownfield Modifications:

• 24” intra-field pipeline and Composite/FO Cable Hook-up at RT2. • 2 x 12” New Post-Installed J-tubes • Structural modifications WHP3S Brownfield Modifications:

• Bridge connection, Utilities, Power and ICSS Hook-up to RP3S • Production diversion from wellhead WHP3S to RP3S • Receive Closed Drain/Vent from RP3S • Helideck removal • Decommission existing -RT-WHP3S Composite Cable at Topside

WHP2S Brownfield Modifications:

• Composite Cable Hookup and Power & Control Integration • Post Installed J-tube and structural Modifications. • Decommission existing WHP2S-RT Composite Cable at Topside

RGA Brownfield:

• Modifications to integrate WHP3S, WHP2S and RP3S ICSS Network

at RGA control room.

• Connectivity of the new FOC from BRZ-WHP1 - Restoring the ICSS and telecom connectivity at RGA post BRZ-WHP1 to Riser Tower (RT) Fiber Optic (FO) cable replacement.

•

Install workstation consoles.

Riser Tower (RT) Brownfield: Decommissioning of Cables:

• Decommission existing RT-WHP2S Composite Cable at Topside • Decommission existing RT-WHP3S Composite Cable at Topside • Decommission existing RT-BRZWHP1 Fiber Optic Cable at Topside

FACILITIES-6B

200-20-PE-DEC-00004_A

17 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

Item

COMP3B Offshore Facility Description Subsea Cables: In-situ abandonment of existing 2 Composite and 1 FO Cable from RGA Complex:

• Subsea composite cable from RT to WHP2S • Subsea composite cable from RT to WHP3S • FO Cable from RT to BRZWHP1

5.1. Project Location and Orientation

The locations of the new platforms are reported in table below (Hold 2).

Table 5.1.1: New Platform Coordinates and Orientations

Platform

RP3S BSP3S-1 RP5S BSP5S-1 RP9S WHP13N (3) RP5N RP6N

Platform Coordinates (2)

Easting [m]

Northing [m]

Platform Heading w.r.t. North (1) [deg]

603877.330 603860.780 610642.563 610629.200 595390.600 606259.100 611711.719 611641.905

2943928.570 2943995.880 2941441.871 2941372.900 2952965.000 2917549.500 2911988.959 2920882.974

23 23 45 0 45 30 30 90

Notes: (1) Orientations are measured anti-clockwise from True North to Platform North. (2) The coordinates refer to platform centerline. (3) As-built coordinates and orientation are specified for WHP13N Jacket installed by others.

The locations of existing platforms are reported in table below (Hold 2).

Table 5.1.2: Existing Platform Coordinates

Platform

WHP2S WHP3S WHP5S WHP8S WHP9S

WHP11S WHP12S WHP13S RP4S RP7S RP8S

Platform Coordinates

Easting [m] 601916.670 603887.520 610619.630 625078.000 595460.995

620559.705 599342.070 603863.130 602295.600 610787.900 625088.730

Northing [m] 2949676.350 2944006.940 2941300.840 2927021.000 2952915.333

2922307.593 2942867.140 2937100.860 2946945.650 2933941.120 2926941.360

200-20-PE-DEC-00004_A

18 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

Platform Coordinates

Easting [m] 620613.392 597981.130

597992.670 597930.620 585941.959 628488.832 611690.447 611544.620

617202.460 628478.120 602272.119

Northing [m] 2922194.710 2945311.080

2945192.140 2945104.840 2940361.913 2919326.115 2912046.680 2920957.711

2918483.020 2919268.710 2928938.363

Platform

RP11S PU (south) RT (south) RT-2 BRZ-WHP1 WHP4N WHP5N WHP6N

WHP12N RP4N PU (North)

5.2. Co-ordinate Systems

The co-ordinate system for all final geophysical coordinates shall be in Nahrwan Qatar datum using the UTM Zone 39 projection for grid coordinates. The following geodetic parameters describe the Nahrwan Qatar (Offshore) reference system.

Local Datum (Offshore) Datum Ellipsoid Semi major axis Reciprocal of flattening Projection Type Central Meridian Latitude Origin Central scale False Easting False Northing

: : : : : : : : : : :

Nahrwan 1967 Clarke 1880 (modified) 6378249.148m 293.465 UTM Zone 39N Transverse Mercator E 51 degrees N 0 degrees 0.9996 500,000.0m 0.0m

5.3. Water Depths

5.3.1. Greenfield

The water depths at the proposed locations are indicated below according to geophysical and geotechnical reports (refer Section 3.2).

Table 5.3.1.1: Greenfield platform water depths

Platform

RP3S BSP3S-1 (Note 1)

Geophysical ref. LAT

Max. W.D. [m] 63.4 63.4

W.D. tolerance [m] 0.634 0.634

200-20-PE-DEC-00004_A

19 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

Platform

RP5S BSP5S-1

RP9S RP5N RP6N

Geophysical ref. LAT

Max. W.D. [m] 65.7 65.4

W.D. tolerance [m] 0.657 0.654

67.6 46.2 56.2

0.676 0.462 0.562

Note-1: Water Depth of BSP3S-1 assumed same as RP3S

5.3.2. Brownfield

The water depth (Hold 3) considered for the existing platforms are indicated as follows:

Table 5.3.2.1: Brownfield platform water depths

Platform

WHP2S WHP3S WHP5S WHP8S

WHP9S WHP11S WHP12S WHP13S RP4S RP7S

RP8S RP11S PU (south) RT (south) RT-2 BRZ-WHP1 WHP4N WHP5N WHP6N WHP12N WHP13N (Note 1) RP4N

PU (North)

Min. W.D. [m]

65.700 63.764 45.522 63.900

67.600 62.500 60.600 61.600 64.300 62.700

63.800 62.200

60.800 60.253 61.000 TBC

63.400 TBC

56.100 50.300 TBC

62.300

TBC

Geophysical ref. LAT

Max. W.D. [m] 1-year 67.900 66.294 48.052 67.530

Max. W.D. [m] 10-years 68.000 66.364 48.122 67.600

Max. W.D. [m] 100-years 68.000 66.424 48.182 67.660

71.230 66.130 64.100 65.100 69.600 67.600

69.100 67.500

63.330 62.783 65.600 TBC

66.530 TBC

59.230 55.600 TBC 67.600

TBC

71.300 66.200 64.200 65.200 69.700 67.700

69.200 67.600

63.400 62.853 65.700 TBC

66.600 TBC

59.300 55.700 TBC 67.700

TBC

71.360 66.260 64.300 65.300 69.800 67.800

69.300 67.700

63.460 62.913 65.800 TBC

66.660 TBC

59.360 55.800 TBC 67.800

TBC

Note-1: WHP13N Jacket already installed by Others

200-20-PE-DEC-00004_A

20 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

5.4. Design Life

5.4.1. Equipment Design Life

The design life shall be a minimum of 30 years for all new and upgraded Facilities associated with the Services.

5.4.2. Structure Design Life – Jackets, Topsides and Piles

• The design life shall be minimum 30 years for all new structures.

5.5. Rely Upon Data

Following COMPANY-provided data shall be considered Rely Upon for the project:

• Production profiles:

o RGE: March 2020 Production Profile o QG2: May 2022 Production Profiles o RGA: July 2023 Production Profile

Note – For more details on the production profiles, refer to the corresponding Process Design Basis documents (Section 3.2, Ref. [48] to [50]).

• Environmental data as per Metocean Criteria Offshore Qatar (Ref. [3]) and Ref [6] • Environmental Impact Assessment (EIA) data as per NFPS Environmental Impact

Assessment (EIA) Report (Ref. [5])

• Geotechnical and Geophysical Survey Data as per survey reports in Section 3.2 (Ref. [7] to

[47])

  1. ORDER OF PRECEDENCE

Codes and standards to be applied shall follow the order of precedence listed below:

  1. Qatari Governmental and Regulatory Regulations

a. Qatar Supreme Council for the Environment and Natural Reserves (SCE), “Final SCE

Standards”, 9 June 2003.

b. Environmental Regulations for Ras Laffan Industrial City, Revision 1, 2005. c. Environmental Protection Law No. 30 of 2002. d. Executive By-Law No.4 of 2005

  1. COMPANY Procedures, Policies and Standards (Exhibit 5 Appendix I)
  2. Project Specifications
  3. Industry Codes and Standards
  4. COMPANY and CONTRACTOR’s Lesson Learned

For all Greenfield & Brownfield facilities applicable Codes and Standards including Addenda shall be the latest revisions by CONTRACT EFFECTIVE DATE. For any applicable codes and standards that will derive from Laws and/or International/Regional Conventions (for e.g. environmental), the latest revisions shall be in force.

200-20-PE-DEC-00004_A

21 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

  1. UNITS OF MEASUREMENT

SI units shall be used for the Project.

Table 7.1: Units of Measurement

Parameters Area Cathodic current density

Concentrations

Coefficient of Transfer Conductivity Current Density Flowrate (mass-liquid & gases) Flowrate (molar)

Flowrate (volume-liquids)

Flowrate (volume-gases)

Force Frequency

Heat Flow

Heat Flux intensity (for flare radiation) Heat transfer coefficient

Linear Measure

Mass

Mass Enthalpy

Abbreviation m2 A/m2 % mol ppm(v) ppm(w) W/m2.K μS/cm A kg/m3 kg/h kg/s kgmol/h m3/h bbl /d lit/h Sm3/h (Note-1) Sm3/s (Note-1) MMSCFD (Note-1) SCFM (Note-1) Nm3/h (Note-1) kN Hz W kW MW W/m2 W/cm2

Units Square meter Amp per square meter percent mole parts per million (by volume) parts per million (by weight) watt per square meter kelvin Micro Siemens per centimeter Amp kilogram per cubic meter kilogram per hour kilogram per second kilogram-mole per hour cubic meter per hour barrels per day Liter per hour Standard cubic meter per hour Standard cubic meter per second Million Standard cubic feet per day Standard cubic feet per minute Normal cubic meter per hour Kilo Newton hertz Watt kilowatt megawatt watt per square meter watt per square centimeter watt per square meter per degree Celsius W/m2 °C millimeter micrometer (micron) meter kilometer kilogram ton, metric gram milligram kilojoule per kilogram

mm µm m km kg t g mg kJ/kg

200-20-PE-DEC-00004_A

22 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

Parameters Material hardness Molar Mass

Molar Volume

Momentum Pipe Diameter Potential

Power

Pressure

Pressure differential

Quantity of heat

Resistance Sound Power Level Sound Pressure Level Specific Volume Specific Heat Capacity

Specific Energy & Latent Heat

Stress

Temperature

Throughput

Thermal Conductivity

Time Velocity

Viscosity

Volume

Units Newton per millimeter square kilogram mole cubic centimeter per mole cubic meter per kilomole kilogram meter per second Inch Volt kilowatt megawatt millimeter of mercury millimeter of water bar absolute bar gauge Bar joule kilocalorie kilojoule Ohm decibel decibel cubic meter per kilogram kilojoule per kilogram kelvin kilojoule per kilogram Megajoule per kilogram Newton per square metre (Pascal) degree Celsius kelvin metric ton per annum kilogram per hour watt per meter kelvin watt per meter per degree Celsius Second / minute / hour / day meter per second centipoise pascal second centistoke millimeter square per second cubic meter cubic centimeter liter

Abbreviation N/mm2 kg.mol cm3/mol m3/kmol kg.m/s in V kW MW mmHg mmH2O bara barg bar J kcal kJ Ω dB dB m3/kg kJ/kg.K kJ/kg MJ/kg N/m2 °C K t/a kg/h W/m.K W/m °C s /min / h / d m/s cP Pa.s cSt mm2/s m3 cm3 L

Note-1: “Standard” conditions are defined at 15.6°C and 101.325 kPa (a). “Normal” conditions are at 0°C and 101.325 kPa (a).

200-20-PE-DEC-00004_A

23 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

  1. ENVIRONMENTAL DATA

The metocean conditions data presented in this section are as per Ref [3] and are directly applicable to Fixed Facilities design. For Pipeline and Cables design the data from Ref [3], integrated as per Ref [72] and are taken into consideration and further discussed in the dedicated design basis Ref [65] & [66].

8.1. General

Site Conditions: Salt laden atmosphere, offshore environment.

8.2. Ambient Temperature and Pressure

Table 8.2.1: Ambient Temperature for offshore environment (from Ref.[6], Table 6.2.1)

Description Expected maximum daily average temperature Expected maximum daily temperature Expected minimum daily temperature Expected yearly maximum temperature Expected yearly minimum temperature

Ambient Temperature (°C) 36 41.4 12.7 45.6 8.3

Design temperature for equipment operating at atmospheric conditions: 49 °C

For HVAC design ambient conditions, please refer to HVAC Design Basis - Offshore for COMP3 Project, Doc. No. 200-42-HV-DEC-00004.

Table 8.2.2: Atmospheric Pressure (from Ref.[6], Table 6.4.1)

Description Minimum barometric pressure Maximum barometric pressure

Atmospheric Pressure (mbar) 998 1020

8.3. Solar Radiation

The maximum solar radiation measured at Doha Airport is 969 W/m2 (310 Btu/h.ft2). The maximum temperature of surfaces exposed to solar radiation (black bulb thermometer) can reach 84 °C.

8.4. Relative Humidity

Table 8.4.1: Relative Humidity

Description Minimum Average Maximum

Relative Humidity (%) 37 71 100

200-20-PE-DEC-00004_A

24 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

8.5. Wind Speed

Table 8.5.1: Extreme All-Year Wind (from Ref.[3], Summary Table I).

Return Period

1-year 10-years 50-years 100-years

1-hr Mean Wind Speed at 10 m [m/s]

10-min Mean Wind Speed at 10 m [m/s]

1-min Mean Wind Speed at 10 m [m/s]

3-sec Gust Speed at 10 m [m/s]

13.8 16.3 18.0 18.7

14.8 17.5 19.4 20.2

16.0 19.1 21.2 22.1

17.6 21.1 23.6 24.6

Table 8.5.2: Wind Speed in Adverse Direction (for Flare Radiation & Dispersion calculations)

Description Maximum Minimum

Wind Speed (m/s) 8.9 0.5

8.6. Rainfall Intensity

Table 8.6.1: Estimated Rainfall Intensity (from Ref.[6], Table 6.6.1)

Description Once in 2 years Once in 10 years Once in 50 years

Estimated Rainfall Intensity (mm/h) 12 27 41

The maximum precipitation measured in 24h at Doha Airport is 80.1 mm.

8.7. Seawater Properties

Table 8.7.1: Seawater Properties All Year (from Ref [3], section 3.5, Table 3.5.1)

Depth Level Temperature (°C) Near-Surface Near-bed Salinity (PSU) Near-Surface Near-bed Density (kg/m3) Near-Surface Near-bed Resistivity (ohm m) Near-Surface Near-bed

Minimum

Mean

Maximum

18.1 16.0

36.9 39.0

27.2 24.1

39.5 40.4

35.0 32.5

40.7 42.0

1.02 x 103 1.03 x 103

1.03 x 103 1.03 x 103

1.03 x 103 1.03 x 103

0.17 0.17

0.18 0.18

0.20 0.20

200-20-PE-DEC-00004_A

25 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

Table 8.7.2: Seawater Properties, Winter (from Ref [3], section 3.5, Table 3.5.2)

Depth Level Temperature (°C) Near-Surface Near-bed Salinity (PSU) Near-Surface Near-bed Density (kg/m3) Near-Surface Near-bed Resistivity (ohm m) Near-Surface Near-bed

Minimum

Mean

Maximum

18.1 17.2

38.9 39.2

23.6 23.2

40.0 40.3

30.9 31.1

40.7 41.4

1.02 x 103 1.03 x 103

1.03 x 103 1.03 x 103

1.03 x 103 1.03 x 103

0.17 0.17

0.18 0.18

0.20 0.20

8.8. Sea Current Data

Table 8.8.1: Extreme All-Year Current (from Ref [3], Summary Table III).

Return Period

1-year 10-years 50-years 100-years

Total Current Speed [m/s]

Near-surface 1.23 1.40 1.51 1.56

Near-bed 0.62 0.70 0.76 0.79

Residual Current Speed [m/s] Near-surface 0.48 0.65 0.76 0.81

Near-bed 0.24 0.33 0.38 0.41

8.9. Tide Data

Table 8.9.1: Tidal Heights (from Ref [3] Summary Table V)

Tidal Descriptor Highest Astronomical Tide Mean Higher High Water Mean Lower High Water Mean Sea Level Mean Higher Low Water Mean Lower Low Water Lowest Astronomical Tide

Relative to MSL (m) 0.64 0.44 0.29 0.00 -0.11 -0.54 -0.79

Relative to LAT (m) 1.43 1.23 1.08 0.79 0.68 0.25 0.00

8.10. Extreme Seawater Level

Table 8.10.1: Extreme All-Year Water Levels (from Ref [3], Summary Table IV).

Relative to MSL

Return Period

1-year

Extreme Water Level [m] 4.65

Positive Residual Level [m] 0.31

Negative Residual Level [m] -0.56

Relative to LAT Extreme Water Level [m] 5.44

200-20-PE-DEC-00004_A

26 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

Return Period

10-years 50-years 100-years

Relative to MSL

Extreme Water Level [m] 6.01 6.95 7.37

Positive Residual Level [m] 0.38 0.42 0.44

Negative Residual Level [m] -0.79 -0.95 -1.02

Relative to LAT Extreme Water Level [m] 6.80 7.74 8.16

8.11. Wave Data

Table 8.11.1: Extreme All-Year Wave (from Ref [3], Summary Table II).

Return Period

Significant Wave Height [m]

1-year 10-years 50-years 100-years 1000-years 2000-years 10000-years

3.6 4.6 5.4 5.7 6.7 7.0 7.7

Mean Zero- Crossing Period [s] 5.1 5.7 6.1 6.2 6.7 6.9 7.2

Peak Period [s]

8.4 9.2 9.8 10.0 10.7 10.9 11.3

Maximum Crest Height [m] 4.3 5.6 6.5 6.9 8.2 8.6 9.5

Maximum Wave Height [m]

7.0 9.0 10.5 11.1 13.1 13.8 15.2

8.12. Fatigue Wave Data

Refer Metocean Design Basis (Ref [64]).

8.13. Seismic Data - Offshore

Wave Period Associated with Maximum Wave Height [s] Lower Central Upper 8.4 9.3 9.9 10.1 10.7 11 11.4

9.2 10.1 10.7 11.0 11.7 11.9 12.4

7.4 8.2 8.7 8.9 9.5 9.7 10.0

A Probabilistic Seismic Hazard Assessment (PSHA) and a Site Response Analysis (SRA), has been performed in order to define the surface ground motion that will be considered for the seismic design purposes and structural verifications, taking into account the local soil conditions. The horizontal peak ground accelerations (PGA) and spectral accelerations for the sites are:

Table 8.13.1: Horizontal Peak Ground Accelerations and Spectral Accelerations

Description PGA T = 0.2 s T = 3.0 s

ELE (g) 0.092 0.23 0.028

ALE (g) 0.30 0.75 0.083

8.14. Splash Zone

For the Greenfield facilities, the splash zone is defined as that region between (-)2m with respect to Low Astronomical Tide (LAT) and (+)2m with respect to Highest Astronomical Tide (HAT). The details of Splash Zone calculation is reported below:

200-20-PE-DEC-00004_A

27 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

Table 8.14.1: Splash Zone Elevations for New Facilities

Elevation description Elevation relative to LAT HAT Subsidence Settlement Water Depth tolerance Calculated Splash Zone Upper Limit Splash Zone Upper Limit Elevation relative to LAT Water Depth tolerance Calculated Splash Zone Lower Limit Splash Zone Lower Limit

[m] +2.00 +1.43 +1.10 +0.30 +0.64 +5.47 +5.50 -2.00 -0.64 -2.64 -2.70

Accordingly, above table the splash zone is considered from -2.7m to +5.5m with respect to LAT.

For existing facilities, the following splash zone data (Hold 4) as per original design shall be considered:

Table 8.14.2: Splash Zone Elevations for Existing Facilities.

Platform Name

QGN WHP4N QGN WHP5N QGN WHP6N QGN WHP12N QGN WHP13N Jacket QGN RP4N QGN PU BRZ-WHP1 QGS RT QGS RT-2 QGS PU QGS WHP2S QGS WHP3S QGS WHP5S QGS WHP8S QGS WHP9S QGS WHP11S QGS WHP12S QGS WHP13S QGS RP4S

Existing Splash Zone Lower limit (LAT) -1.917m TBC -1.626m -2.700m TBC -2.700m -3.200m TBC -2.053m -2.700m -2.300m -2.300m -2.300m TBC -2.300m -2.630m -2.300m -2.200m -2.200m -2.700m

Existing Splash Zone Upper limit (LAT) +3.683m TBC +3.974m +5.600m TBC +5.600m +6.400m TBC +3.300m +5.600m +3.300m +3.300m +3.300m TBC +3.300m +2.970m +3.300m +5.100m +5.100m +5.600m

200-20-PE-DEC-00004_A

28 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

PROJECT BASIS OF DESIGN FOR COMP3

Platform Name

QGS RP7S QGS RP8S QGS RP11S

Existing Splash Zone Lower limit (LAT) -2.700m -2.700m -2.700m

Existing Splash Zone Upper limit (LAT) +5.600m +5.600m +5.600m

8.15. Marine Growth

Marine growth profile, relative to LAT, is as follows:

Table 8.15.1: Marine Growth Profile

Depth EL(+)2.49m to EL(-)6.0m EL(-)6.0m to EL(-)30.0m EL(-)30.0m to mudline

Thickness (mm) 100 50 25

Marine growth dry density is 1359 kg/m3

8.16. Subsidence

Subsidence allowance for Greenfield platform design shall be 1.1m.

For existing facilities, the following subsidence data (Hold 5) as per original design shall be considered:

• 1.1m for platforms WHP12N, WHP12S, WHP13S, WHP9S, RT-2 (South), RP7S, RP8S,

RP11S, RP4N and RP4S

• 0.6m for platforms WHP4N, WHP5N, WHP6N, WHP5S, BRZ-WHP1 • No subsidence considered for platforms RT (North & South), PU (North & South), WHP2S,

WHP3S

8.17. Geotechnical Data

Geotechnical data for greenfield and brownfield facilities are as per the survey reports listed in References Section 3.1.

  1. DISCIPLINE DESIGN BASIS

Refer Section 3.2 for the dedicated Design Basis of each discipline (Ref [48] to [69]) covering all the design data applicable to the project.

200-20-PE-DEC-00004_A

29 of 29

Project: Q-32705 - Saipem COMP3 Folder: RFQ Files


Loading authentication...

Graph View

Backlinks

  • 00 Index

Created with Infinity Constructor © 2025

  • Elynox | Go Further