Infinity

Not logged in
Home

❯

Reference Examples

❯

Q 32705 Saipem COMP3

❯

RFQ Files

❯

200 20 PI SPC 00050_B

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

COMPANY Contract No.: LTC/C/NFP/5129/20 CONTRACTOR Project No.: 033764

ASSET

: NFPS

Document Title

:

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

COMPANY Document No.

:

200-20-PI-SPC-00050

CONTRACTOR Document No.

:

033764-E-D-18-SPM-TB-S-00013

Discipline

: PIPING

Document Type

: SPECIFICATION

Document Category/Class

:

1

Document Classification

:

Internal

B

05-FEB-2025

Issued for Approval

Pranav Pandurkar Piping Material Engineer

A

05-NOV-2024

Issued for Review

Vikas Kumar

10-FEB-2025

10-FEB-2025

Suresh Gopalakrishnan Lead Piping Material Engineer Suresh Gopalakrishnan

Ravin George

Piping Lead

Ravin George

REV.

DATE

DESCRIPTION OF REVISION

PREPARED BY

REVIEWED BY

APPROVED BY

Saipem S.p.A

www.saipem.com

THIS DOCUMENT IS PROPERTY OF QatarEnergy LNG. THIS DRAWING OR MATERIAL DESCRIBED THEREON MAY NOT BE COPIED OR DISCLOSED IN ANY FORM OR MEDIUM TO THIRD PARTIES, OR USED FOR OTHER THAN THE PURPOSE FOR WHICH IT HAS BEEN PROVIDED, IN WHOLE OR IN PART IN ANY MANNER EXCEPT AS EXPRESSLY PERMITTED BY QatarEnergy LNG.

200-20-PI-SPC-00050_B

Page 1 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

REVISION HISTORY

Revision

Date

Revision Description

A1

A

18-OCT-2024

Issued for Inter-Discipline Check

05-NOV-2024

Issued for Review

B

04-FEB-2025

Issued for Approval Clauses Revised as below – Clause 3.3 – Page 11 & 12 Clause 3.4 – Page 12 Clause 5.1.17, 5.1.18 & 5.1.21 – Page 16 Clause 6.5.1, 6.5.5 & 6.5.6 – Page 19 Clause 8.3.3 – Page 20 Clause 8.3.4 & 8.5.2 – Page 21 Clause 8.9.1 – Page 22 Clause 9.1.16 – Page 23 Clause 10.1.2 & 11.1.2 – Page 24 Clause 13.1.9 – Page 26 Clause 14.1.3 – Page 27

HOLDS LIST

Hold No

Hold Description

200-20-PI-SPC-00050_B

Page 2 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

TABLE OF CONTENTS

1

1.1

1.2

2

2.1

2.2

3

3.1

3.2

3.3

3.4

3.5

4

INTRODUCTION … 5

Project Objective … 5

Project Scope … 5

DEFINITIONS AND ABBREVIATIONS … 8

Definitions … 8

Abbreviations … 9

REGULATIONS, CODES AND STANDARDS … 11

Order of Precedence … 11

Company References … 11

Project Documents … 11

Company Inspection requirement … 12

APPLICABLE CODES & STANDARDS … 12

PURPOSE OF DOCUMENT … 15

4.1

General … 15

5

5.1

5.2

6

GENERAL REQUIREMENTS … 15

GENERAL … 15

FABRICATION OF PIPES … 16

MATERIAL REQUIREMENTS … 17

6.1 METHOD OF MANUFACTURE … 17

6.2

6.3

6.4

6.5

7

8

8.1

8.2

8.3

8.4

8.5

CHEMICAL COMPOSITION … 18

HEAT TREATMENT … 18

SURFACE FINISH … 19

SOUR SERVICE SPECIFIC REQUIREMENTS … 19

WELDING … 20

TESTING AND INSPECTION … 20

GENERAL … 20

HYDROSTATIC TESTING … 20

CORROSION TESTING… 20

TENSILE TESTING … 21

HARDNESS TESTING … 21

200-20-PI-SPC-00050_B

Page 3 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

8.6

IMPACT TESTING … 21

8.7 METALLOGRAPHIC EXAMINATION FOR LTCS … 22

FERRITE CHECK AND METALLOGRAPHIC EXAMINATION FOR STAINLESS STEEL

8.8 MATERIAL … 22

8.9

HYDROGEN-INDUCED CRACKING (HIC) TESTING … 22

8.10 OTHER TESTS FOR CUNI … 22

8.11

INSPECTION … 22

9

9.1

9.2

NON-DESTRUCTIVE EXAMINATION (NDE) … 22

GENERAL … 22

VISUAL EXAMINATION … 23

9.3 MAGNETIC PARTICLE EXAMINATION … 23

9.4

9.5

9.6

10

11

12

13

14

15

LIQUID PENETRANT EXAMINATION … 23

ULTRASONIC EXAMINATION… 23

RADIOGRAPHY EXAMINATION … 24

POSITIVE MATERIAL IDENTIFICATION … 24

MARKING AND TRACEABILITY … 24

CERTIFICATION … 24

HANDLING, PACKING, PRESERVATION AND STORAGE … 26

DOCUMENTATION … 27

NON-COMPLIANCE / DEVIATION:… 27

200-20-PI-SPC-00050_B

Page 4 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

1

INTRODUCTION

The North Field is the world’s largest natural gas field and accounts for nearly all the State of Qatar’s gas production. The principal objective of the NFPS projects is to sustain plateau from existing QatarEnergy LNG Operation – S1, S2, S3, N1 and N2, production areas by implementing an integrated and optimum investment program consisting of subsurface development, pressure drop reduction steps and compression.

NFPS projects comprise 3 main investment programs:

  1. Investment #1: Drilling and Associated Facilities [WHP12S/ WHP13S/ WHP14S/

WHP12N/ WHP13N]

  1. Investment #2: Trunk line Looping and Intra-field pipeline looping [32” PL1LN, 32”

PL1LS, 38”PL610LS]

  1. Investment #3: Compression Complexes and associated facilities [Phase 1 CP6S & CP7S; Phase 2: CP8S & CP4N; Phase 3: CP4S & CP6N Phase 4: CP1S & CP1N]

Drilling and Looping, Investments #1 and #2, projects are in execution phase and are being executed as I1P1, EPCOL Projects except for WHP13N, which will be part of NFPS Compression Projects execution which compromises total up to 9 COMPs.

1.1 Project Objective

The objective of this Project includes:

• Achieve standards of global excellence in Safety, Health, Environment, Security and

Quality performance.

• Sustain the Qatarenergy LNG North Field Production Plateau by installing new RPs and one WHPs to support new Compression Complex facilities CP6S & CP7S and pre-installed facilities for future Compression Complex facilities including but not limited to CP4N & CP8S tie-in with integration to the existing facilities under Investment #3 program.

• Facility development shall be safe, high quality, reliable, maintainable, accessible,

operable, and efficient throughout their required life.

1.2 Project Scope

The Project Scope includes detailed engineering, procurement, construction, brownfield modifications, transportation & installation, hook-up and commissioning, tie-in to EXISTING PROPERTY and provide support for start-up activities of the following facilities and provisions for future development. The WORK shall be following the specified regulations, codes, specifications and standards, achieves the specified performance, and is safe and fit‐for‐ purpose in all respects.

Facilities - 1A

• RP5S RP with 2 x 28” CRA clad pipelines to RP7S and 2 subsea composite Cables

and associated J tubes from RP7S to RP5S & from CP7S to WHP13S.

• New Fuel Gas 8” CRA Spur-lines and flanged risers from Subsea skid to RP7S

200-20-PI-SPC-00050_B

Page 5 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

• Hook-up and brownfield modification at WHP5S/RP5S bridge connection & WHP13S/CP7S Composite cable tie-in and E&I integration including RGA Control modification

• Pipeline decommissioning of 28” CS PL5 including associated demolition work at

WHP5S

Facilities - 2A

• RP6N RP with 1x28” CRA clad pipeline to WHP13N, 2 Subsea composite cables and

associated J tubes from WHP12N to RP4N and RP6N to WHP13N. • New fuel gas spur-line and flanged riser from subsea skid to RP6N • WHP13N Topside • Hook-up and brownfield modification at WHP6N/RP6N, RP4N- HPU-Umbilical and tie- in, WHP12N-new J tube installation, E&I migration, WHP6N/RP4N/WHP4N-E&I migration (Pre-CP4N), WHP13N and RP6N interconnection to NFB.

Facilities - 3A

• RP9S RP with 1x28” CRA clad pipeline to RP4S, • Hook-up and brownfield modification at RP4S/WHP9S, Modifications to integrate

RP9S to the RGA control network.

• Pipeline decommissioning of 28” PL9 to WYE on existing 38” trunkline PL49including

associated demolition work at WHP9S.

Facilities - 1B

• New fuel gas spur-line and flanged riser from subsea skid to RP4N • Fiber Optic Cable from RP6N to onshore LFP East, RP6N to RP4N and RP6N to LQ6S. • Hook-up and brownfield modification at RP6N Composite and FO Tie-ins NFB-PU (East)- FO Tie-in

(East)/BVS

Power & Control modifications, LQ6S/LFP Controls/Telecoms Integration

Facilities - 2B

• RP5N RP with 2 x 28” CRA clad pipelines to RP4N, 1 x 28” CRA clad pipeline to RP6N and 2 subsea composite Cables and associated J tubes from WHP12N to RP5N & from RP6N to RP5N.

• Hook-up and brownfield modification at WHP5N- RP5N Bridge connection, WHP12N Composite cable tie-in, RP4N Intrafield pipeline Hook up PL54 N/LN and E&I integration including NFB-PU Power & Control modifications

• Pipeline decommissioning of 2 x 16” PL56/PL54 Subsea Spur line from WHP5N to

reducing barred tee in subsea tie-in skid on PL6 / PL4.

Facilities - 3B

• 2 subsea composite Cables from RP4S to RP9S & from RP4S to WHP12S (with J-

tube)

• New Fuel Gas 8” CRA Spur-lines and flanged risers from Subsea skid to RP4S • Hook-up and brownfield modification at WHP12S/ RP9S/ RP4S Composite cable tie-

in, Spurline riser installation at RP4S RGA Power & Control modifications.

Facilities - 4B

• 1 subsea composite Cable from CP8S to RP11S (or from RP8S to RP11S as Option). • New Fuel Gas 8” CRA Spur-line and flanged riser from Subsea skid to RP8S.

200-20-PI-SPC-00050_B

Page 6 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

• Hook-up and brownfield modification at WHP8S/ WHP11S for Test separator Internal Upgrade and MEG system modification, Spur lines, Power & Control Tie-ins on RP8S, RP11S/WHP11S-Tie-in (Power and Control), RGA Power & Control modifications.

Facilities - 5B

• 2 subsea composite Cables from RT2 to WHP3S & from RT2 to WHP2S (with J-tube)

and FO Cable from RT2 to Barzan WHP1.

• New Fuel Gas 8” CRA Spur-line and flanged riser from Subsea skid to RT2 • Hook-up and brownfield modification at BRZ-WHP1 - FO cable tie-in, WHP2S/ WHP3S/ RT&RT2 Composite cable tie-in and associated modification, RGA Power & Control modifications.

Facilities - 6B

• RP3S RP with 1x24” CRA clad pipeline to RT2 with Stalk on risers, • Hook-up and brownfield modification at RT2 for 24” Intrafield pipeline and Composite/FO cable Hook-up, WHP3S for Production diversion and Utilities, Power and ICSS Hook-up, WHP2S for Composite Cable Tie-ins and Power & Control Integration RGA Power & Control modifications. topside existing and

In-situ abandonment of existing Topside/subsea Composite Cables RT-WHP2S, RT-WHP3S, Topside/Subsea FO cable RT-BRXWHP1.

• Decommissioning at

Figure 1.2.1: NFPS Compression Project COMP3 Scope

200-20-PI-SPC-00050_B

Page 7 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

2

DEFINITIONS AND ABBREVIATIONS

2.1

Definitions

Definition

Description

COMPANY

QatarEnergy LNG.

CONTRACTOR

Saipem S.p.A.

DELIVERABLES

FACILITIES

MILESTONE

PROJECT

SITE

All products (drawings, equipment, services) which must be submitted by CONTRACTOR to COMPANY at times specified in the contract. All machinery, apparatus, materials, articles, components, systems and items of all kinds to be designed, engineered, procured, manufactured, constructed, supplied, tested and permanently installed by CONTRACTOR at SITE in connection with the NFPS Project as further described in Exhibit 6.

fabricated,

A reference event splitting a PROJECT activity for progress measurement purpose.

COMP3 - NFPS Offshore Riser/Wellhead Platform & Intrafield Pipelines Project

(i) any area where Engineering, Procurement, Fabrication of the FACILITIES are being carried out and (ii) the area offshore required for installation of the FACILITIES in the State of Qatar

SUBCONTRACT

Contract signed by SUBCONTRACTOR and CONTRACTOR for the performance of a certain portion of the WORK within the Project.

SUBCONTRACTOR

Any organization selected and awarded by CONTRACTOR to supply a certain Project materials or equipment or whom a part of the WORK has been Subcontracted.

WORK

Refer to article 2 of CONTRACT AGREEMENT.

WORK PACKAGE

The lowest manageable and convenient level in each WBS subdivision.

200-20-PI-SPC-00050_B

Page 8 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

2.2

Abbreviations

Code

API

ASME

ASTM

BS

CE

CLR

COC

CRA

CS

CTR

Cu-Ni

DPI

EFW

ERW

FCAW

GMAW

GTAW

HIC

HRC

HV

IDC

ISO

ITP

Definition

American Petroleum Institute

American Society of Mechanical Engineers

American Society for Testing Materials

British Standards

Carbon Equivalent

Crack Length Ratio

Certificate of Compliance

Corrosion-Resistant Alloy

Carbon Steel

Crack Thickness Ratio

Copper nickel alloy

Dye Penetrant Inspection

Electric Fusion Welding

Electric Resistance Welding

Flux-Cored Arc Welding

Gas Metal Arc Welding

Gas Tungsten Arc Welding

Hydrogen Induced Cracking

Hardness Rockwell C

Hardness Vickers

Inter-Discipline Check

International Organization for Standardization

Inspection and Test Plan

200-20-PI-SPC-00050_B

Page 9 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

Code

LTCS

MPI

MTR

NACE

NDE

NFPA

NFPS

NPS

PAW

PMI

ppm

PQR

PSL

PWHT

QELNG

RGE

SAW

WPS

Definition

Low-Temperature Carbon Steel

Magnetic Particle Inspection

Material Test Report

National Association of Corrosion Engineering

Non-destructive Examination

National Fire Protection Association

North Field Production Sustainability

Nominal Pipe Size

Plasma Arc Welding

Positive Material Identification

Parts per million

Procedure Qualification Records

Product Specification Level

Post Weld Heat treatment

QatarEnergy LNG

RasGas Wet Gas Asset

Submerged Arc Welding

Welding Procedure Specifications

200-20-PI-SPC-00050_B

Page 10 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

3

REGULATIONS, CODES AND STANDARDS

3.1

Order of Precedence

In general, the order of precedence shall be as follows:

a) Qatari Governmental and Regulatory Requirements b) COMPANY Policies and Procedures c) Project Specifications d) Industry Codes and Standards e) COMPANY and CONTRACTOR’S lessons learned

If CONTRACTOR / VENDOR deems any deviations from the specifications will result in significant project cost and schedule saving, proposal to such deviations shall be submitted to COMPANY for review and approval. CONTRACTOR / VENDOR shall not proceed with any deviation to the Specifications without prior COMPANY APPROVAL.

3.2

Company References

S. No

Document Number

Title

LTC/C/NFP/5129/20

Contract Agreement

EXHIBIT 5

Project Instructions

PRJ-PJL-PRC-004

PRJ-PJL-PRC-005

Facilities Engineering and Vendor Document Numbering Procedure

Facilities, System and Unit Number Codes and Descriptions Procedure

PRJ-PJL-PRC-006

Project Information Handover Procedure

PRJ-PJL-PRC-048

Facilities Documentation Metadata Requirements Procedure

PRJ-PJL-PRC-049

Project Information Handover, Verification and Acceptance Procedure

3.3

Project Documents

S. No

Document Number

Title

COMP3-SPM-PE-PRC-00003

Document Numbering Procedure

200-20-CE-SPC-00031

200-20-CE-SPC-00034

COMP3-SPM-CC-PRC-00002

Specification for Piping General Welding Requirement & Inspection for COMP3 Project

Specification For Positive Material Identification (PMI) for COMP3 Project

Material Management and Traceability Control Procedure

COMP3-SPM-QM-PRC-00002

Source Inspection Procedure

200-20-PI-SPC-00050_B

Page 11 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

S. No

Document Number

Title

200-20-CE-SPC-00025

COMP3-SPM-PO-PRC-00005

200-20-CE-SPC-00033

COMP3-SPM-PO-PRC-00005

200-20-PI-SPC-00044

Specification for Topsides Material & Corrosion Requirements for Sour Service for COMP3 Project

Handling, Storage, Packing & Preservation Procedure

Specification for Weld Overlay for Piping Materials for COMP3 Project

Handling, Storage, Packing & Preservation Procedure

Piping Material Specification for COMP3 Project

3.4

Company Inspection requirement

S. No

Document Number

Title

COMP3-SPM-QM-PRC-00003 Project Quality Requirements for Suppliers

COMP3-SPM-QM-PLN-00001 Project Quality Plan

3.5

APPLICABLE CODES & STANDARDS

This section identifies the applicable international codes & standards to be used for the piping design of this project but not limited to those listed below. latest edition shall be followed for all international codes and standards as on the effective date of CONTRACT award.

3.5.1 API–AMERICAN PETROLEUM INSTITUTE

API SPEC 5L

2018

Specification for Line Pipe

200-20-PI-SPC-00050_B

Page 12 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

3.5.2 ASME–AMERICAN SOCIETY OF MECHANICAL ENGINEERS

ASME B1.20.1

ASME B36.10M

ASME B36.19M

ASME B16.25

ASME B31.3

ASME B31.8

ASME SEC V

2013

2018

2018

2022

2022

2022

2023

ASME SEC VIII Div 1 2023

ASME/BPVC SEC IX

2023

Pipe Threads, General Purpose (Inch)

Welded and Seamless Wrought Steel Pipe

Stainless Steel Pipe

Butt welding Ends

Process Piping

Gas Transmission and Distribution Piping Systems

Non Destructive Examinations

BPVC Section VIII - Rules for Construction of Pressure Vessels - Division 1

BPVC Section IX - Welding, Brazing and Fusing Qualifications

3.5.3 ASTM-American Society for Testing and Material

ASTM A20/A20M

Nov 2020

ASTM A106/A106M

Nov 2019

ASTM A153/A153M

May 2023

ASTM A262

Sep 2021

ASTM A312/A312M

May 2024

ASTM A333/A333M

Apr 2024

ASTM A358/A358M

Apr 2024

ASTM A370

Apr 2024

ASTM A516/A516M

Nov 2017

ASTM A671/A671M

Mar 2020

ASTM A672/A672M

Nov 2019

ASTM A700

Nov 2019

ASTM A790

Mar 2024

Standard Specification for General Requirements for Steel Plates for Pressure Vessels Standard specification for Seamless Carbon Steel Pipe for High Temperature Services Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware Standard Practices for Detecting Susceptibility to Intergranular Attack in Austenitic Stainless Steels Standard Specification for Seamless and Welded Austenitic Stainless-Steel Pipe Standard Specification for Seamless and Welded Steel Pipe for Low Temperature Service Standard Specification for Electric-Fusion-Welded Austenitic Chromium- Nickel Alloy Steel Pipe for High-Temperature Service Standard Specification for Standard test methods and definitions for mechanical testing of steel Products. Standard Specification for Carbon Steel Plate for Moderate and Lower, Temperature Service Standard Specification for Electric Fusion Welded Steel Pipe for Atmospheric and Low Temperatures. Standard Specification for Electric-Fusion-Welded Steel Pipe for High-Pressure Service at Moderate Temperatures Standard Guide for Packaging, Marking, and Loading Methods for Steel Products for Shipment Standard Specification for Seamless and Welded Ferritic/Austenitic Stainless Steel Pipe

200-20-PI-SPC-00050_B

Page 13 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

ASTM B6

Apr 2023

ASTM B444

Jul 2023

ASTM B466/B466M

Apr 2018

ASTM B705

Apr 2024

ASTM E18

May 2024

ASTM E23

May 2024

ASTM E112

Jun 2024

ASTM E562

Aug 2020

ASTM G28

Jan 2023

ASTM G48

Dec 2020

Standard Specification for Zinc Standard Specification for Nickel-Chromium- Molybdenum-Columbium Alloys (UNS N06625 and UNS N06852) and Nickel-Chromium- Molybdenum- Silicon Alloy (UNS N06219) Pipe and Tube Standard Specification for Seamless Copper-Nickel Pipe and Tube Standard Specification for Nickel-Alloy (UNS N06625, N06219 and N08825) Welded Pipe Standard Test Methods for Rockwell Hardness of Metallic Materials Standard Test Methods for Notched Bar Impact Testing of Metallic Materials Standard Test Methods for Determining Average Grain Size Standard Test Method for Determining Volume Fraction by Systematic Manual Point Count Standard Test Methods for Detecting Susceptibility to Intergranular Corrosion in Wrought, Nickel-Rich, Chromium-Bearing Alloys Standard Test Methods for Pitting and Crevice Corrosion Resistance of Stainless Steels and Related Alloys by Use of Ferric Chloride Solution

3.5.4 BSI–BRITISH STANDARDS INSTITUTION

BSI BS EN 10204

2004

Metallic products. Types of inspection documents

BSI BS ISO 6892-2

2018

Metallic materials- Tensile testing- Part 2: Method of test at elevated temperature

3.5.5 EEMUA- Engineering Equipment and Materials Users Association

EEMUA Pub No. 234 Edition-1

2015

90/10 Copper nickel alloy piping for offshore applications Specification (Incorporating EEMUA 144,145 and 146)

3.5.6 NACE INTERNATIONAL

NACE MR0175/ISO 15156

4th Edition 2020

NACE TM0284

2016

Petroleum and Natural Gas Industries Materials for Use in H2S-Containing Environments in Oil and Gas Production

Evaluation of Pipeline and Pressure Vessel Steels for Resistance to Hydrogen-Induced Cracking

3.5.7

ISPM- International Standards for Phytosanitary Measures

ISPM 15

2009

International Standards for Phytosanitary Measures No. 15.

200-20-PI-SPC-00050_B

Page 14 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

4

PURPOSE OF DOCUMENT

4.1

General

This Specification covers the technical requirements of metallic pipes for topside piping as per ASME B31.3. The requirements stated in the specification are supplementary to the applicable reference international codes and standards for this project.

5

GENERAL REQUIREMENTS

5.1

GENERAL

5.1.1

In general, the requirements specified below shall be applicable, unless specified otherwise.

5.1.2 Materials shall be supplied in accordance with the purchase requisition. Substitutions shall not be made unless written approval from COMPANY. Such substitution shall meet the requirements of the latest standards and specifications referred in this specification.

5.1.3 All manufacturing and testing procedures, mill certificates, qualification and testing

certificates shall be submitted for COMPANY’s review and approval prior to start of work.

5.1.4 All items shall be supplied in accordance with the wall thickness or schedule as stated in

Purchase requisition.

5.1.5 Pipe material and grade together with NPS and schedule / wall thickness shall be as

specified in the description within the Material requisition Scope of Supply.

5.1.6 Dimensions of Carbon steel / Stainless steel / Alloy 625 steel pipe shall comply with ASME

B36.10M / API 5L or ASME B36.19M as applicable.

5.1.7 Manufacturing tolerance shall be within limit specified in respective ASTM / API specification.

5.1.8 Pipe ends shall be material description stated in purchase requisition.

5.1.9 Beveled end pipes shall be in accordance with ASME B16.25 Fig 2a/3a. Pipe threads shall

be in accordance with ASME B1.20.1.

5.1.10 Pipe lengths shall be as per the respective standards. If the standard does not define length,

Vendor shall refer to ASTM A106.

5.1.11 The permissible quantity variation for the straight pipes shall be -0% to +1% random length

over the total length to fulfil the requisitioned quantity.

5.1.12 Pipes shall preferably be supplied in double random length where possible. Single random lengths are also acceptable where double random lengths are unavailable or due to limitation in transportation. No intermediate circumferential welds.

5.1.13 Double seam welded pipes in lieu of single seam welded pipes are not acceptable.

5.1.14 Electric Resistance Welded (ERW) pipe, Furnace butt welded pipe and Spiral-welded pipe

shall not be used.

5.1.15 API 5L Grade pipes shall be PSL2 type as a minimum, PSL1 pipes are not acceptable.

200-20-PI-SPC-00050_B

Page 15 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

5.1.16 Galvanizing of pipes shall be in accordance with ASTM A 153 and the minimum galvanizing coverage (g/m²) shall be as per class B of ASTM A153. Threaded portion of pipes shall be free of galvanizing.

5.1.17 API 5L pipes for sour service conditions for offshore service shall meet the requirement of Annex H, J & K of API 5L. Materials for sour service shall be manufactured in accordance with and comply to Doc. No. 200-20-CE-SPC-00025 “Specification for Topsides Material & Corrosion Requirements for Sour Service for COMP3 Project” & NACE MR0175/ISO 15156. Non-sour service conditions for offshore service shall meet the requirement of Annex J & K of API 5L as applicable.

5.1.18 90/10 Cu-Ni Pipes shall be UNS C7060X material and dimension shall be in accordance with EEMUA 234. The max design pressure shall be as given in the corresponding piping classes in Piping Material Specification Doc No. 200-20-PI-SPC-00044.

5.1.19 CS/LTCS pipe materials shall be normalized or quenched and tempered.

5.1.20 Out-of-roundness and all the tolerances shall be in accordance with the applicable material

code/standard the pipe is manufactured.

5.1.21 Cladded Pipes shall be in compliance with Project specification Doc no: 200-20-CE-SPC-

00033 “Specification for Weld Overlay for Piping Materials for COMP3 Project”.

5.1.22 All Solid Inconel UNS N06625 material shall conform to the applicable ASTM Material Standard. Seamless pipe shall conform to the requirements of ASTM B444 UNS N06625.Welded pipe shall confirm to the requirements of ASTM B705 UNS N06625 Gr.1 CL.2.

5.2

FABRICATION OF PIPES

5.2.1 Seamless pipes

a. Seamless pipe shall be made in a single section.

b. Material and product traceability is complete along the full manufacturing process starting

from the initial ingot.

c. The heat treatment sequence shall be as per applicable manufacturing procedure based on either ASTM / API. API Material for carbon steel with SMYS minimum 415 Mpa (60 ksi and over) and 448 Mpa (65 ksi and over) shall be delivered in quenched and tempered conditions. Stainless steel shall be in the solution annealed condition, for Inconel shall be in the annealed condition unless otherwise specified. Final heat treatment shall be performed simultaneously from inside and outside of the pipe.

d. Considering that such heavy wall pipes (> 31.75mm) are due for high duty service, the whole external and internal surfaces are machined as to eliminate all defects inherent to the process. Manual grinding is prohibited for that purpose.

e. External and internal surfaces are then fully inspected by DPI or MPI and are free from any

linear indication for all seamless pipes.

f. The inspection and test plan shall clearly identify the sequence of operations from receiving ingot. Each process production operation, heat treatment, surface preparation and non- destructive operation shall be individually and sequentially identified by that document.

g. Local weld repair on pipe is not allowed.

200-20-PI-SPC-00050_B

Page 16 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

h. Pilger mill process is acceptable for 300 series Stainless Steel pipes up to 2” in diameter subject to process qualification for each supply. ABS, DNV or other recognized certification scheme for the pilger mill process shall be provided.

i. Pilger mill process is not acceptable for other CRA materials.

5.2.2 Longitudinally welded pipes

a. For carbon steel, the Electric Fusion Welding (EFW) process shall be used exclusively and for API 5L X60/X65 grade Submerged Arc Welding (SAW) process shall be used exclusively.

b. For Stainless Steel, the Electric Fusion Welding (EFW) shall be used.

c. Subject to COMPANY approval, Plasma Arc Welding (PAW) and automatic Gas Tungsten Arc Welding (GTAW) are acceptable welding processes. Gas Metal Arc Welding (GMAW), Flux-Cored Arc Welding (FCAW), Shielded Metal Arc Welding (SMAW) and ERW are not acceptable.

d. The welds shall be made using an approved welding process. The weld seam shall also be welded on the inside if the welding process employed does not ensure full penetration, with the internal weld bead of uniform thickness, free of appreciable distortion.

e. The weld seams shall be subjected to full length (100%) radiographic inspection by X-ray

method onto radiographic films (Fluoroscopic inspection is not acceptable)

f. All EFW (A672 Gr. B60/C60 Cl.22, A671 Gr.CC60 Cl.22, B705 UNS N06625 Gr.1 CL.2, A358 TP 316/316L Cl.1) Pipes shall be subject to 100% radiography on seam weld. Radiography shall be conducted after heat treatment.

g. As per ASTM B705 Clause 6.1 welded pipes to be made by an automatic welding process with no addition of filler metal. If welding processes adopted is not feasible to carry out seam weld without the addition of filler metal, Manufacturer shall follow requirement of filler material in compliance with ASTM B775.

6

MATERIAL REQUIREMENTS

6.1 METHOD OF MANUFACTURE

6.1.1 All material used shall be new and not recycled.

6.1.2 Carbon Steel (CS) Seamless pipes shall be hot finished and normalized.

6.1.3 Plates used for welded pipes shall be normalized. Weld Joints on welded pipes shall be

double-welded, full-penetration welds.

6.1.4 CS & LTCS Pipes shall be fully killed, fine grained. The primary melting process being open- hearth, basic-oxygen, or electric-furnace, possibly combined with separate degassing or refining.

6.1.5 SS pipes shall be manufactured by electric arc or electric furnace, degassed and refined.

6.1.6 Nickel alloy materials (UNS N06625) shall be annealed materials only, with the chemical composition, mechanical properties, heat treating requirements, and grain size requirements complying with respective ASTM specifications.

200-20-PI-SPC-00050_B

Page 17 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

6.1.7 Copper alloy materials (UNS C7060X) shall be annealed materials only, with the chemical composition, mechanical properties, heat treating requirements, complying with respective ASTM specifications.

6.1.8 Welding / weld repairs (where approved by COMPANY) shall be carried out prior to heat

treatment. Weld repairs are not permitted on either the pipe or body.

6.1.9 Flame cut bevel ends are not permitted.

6.1.10 SS316 pipes shall be supplied as dual grade (i.e. 316/316L) and shall be marked accordingly. The material strength shall be as per 316SS and the Carbon content shall be as per 316L, therefore both strength and chemical composition shall be satisfied.

6.1.11 Austenitic stainless-steel pipes shall be supplied in the solution annealed condition and

Inconel pipes in the annealed condition in accordance with corresponding ASTM Specification.

6.1.12 All SS 316 and Inconel 625 shall be subjected to Pickling as per ASTM A380.

6.1.13 Carbon steel pipes shall be of seamless construction for pipe sizes up to and including NPS 16 and shall be of welded construction for pipe sizes 18” & above. Stainless steel up to and including NPS 6 shall be seamless. For Copper Nickel up to and including NPS 10 shall be seamless For Nickel alloy pipes, sizes up to NPS 6 seamless construction is considered.

6.1.14 The internal surface of the line pipe shall be made free from mill scale after quenching and

tempering.

6.2

CHEMICAL COMPOSITION

6.2.1 Chemical composition shall be as per the relevant ASTM/API Specification unless restricted

otherwise, through this specification or other applicable ASTM specification.

6.2.2 The carbon content shall be 0.23% maximum for Carbon steel / Low Temperature Carbon

steel and 0.03% maximum for Stainless steel.

6.2.3 Carbon equivalent (CE) as per equation below shall be 0.42 maximum for normalized or

quench and tempered CS /LTCS and low alloy steels.

CE = %C +

%Mn 6

%Cr + %Mo + %V 5

%Ni + %Cu 15

6.2.4 Where “NACE” is specified, the chemical composition shall meet the requirements of NACE

MR-01-75 / ISO 15156 Region 3.

6.2.5 Chemical composition of the Cu-Ni material shall be as per corresponding EEMUA

publication.

6.3

HEAT TREATMENT

6.3.1 Cold working, welding / weld repairs shall be carried out prior to final heat treatment for

CS/LTCS.

6.3.2 ASTM A671 welded pipes shall be stress relieved / normalized condition.

6.3.3 Alloy 625 materials shall be stabilized annealed.

200-20-PI-SPC-00050_B

Page 18 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

6.3.4 Cu-Ni material shall be annealed.

6.3.5 Stainless steel material shall be as per respective ASTM specification.

6.3.6 Seamless pipes, welded pipe shall be normalized or hot finished. Hot finishing is only

acceptable where the temperature is > 780°C < 945°C.

6.3.7 Cold drawn pipes shall be normalized or stress relieved.

6.3.8 Heat treatment temperature, soak duration and cooling medium shall be stated on the material test certificate and be in accordance with the relevant ASTM Specification.

6.4

SURFACE FINISH

6.4.1 Surface finish of seamless pipes shall be as per corresponding ASTM and API Specification.

6.4.2 Welded pipes shall be free of injurious defects and shall have a workmanlike finish, same as the identical requirement that appears in Specification ASTM A20 with respect to steel plate surface finish.

6.5

SOUR SERVICE SPECIFIC REQUIREMENTS

6.5.1 Material, where specified for use in sour service including backing materials used for CRA clad items, shall meet the requirements of NACE MR-01-75 / ISO15156 Region 3 according with specification Doc. No. 200-20-CE-SPC-00025 “Specification for Topsides Material & Corrosion Requirements for Sour Service for COMP3 Project”.

6.5.2 Cold-worked austenitic stainless steels are not allowed in sour service.

6.5.3 The Sulphur and Phosphorus content of material for seamless pipes shall be not more than 0.010 wt. % and 0.015 wt. %, respectively. In addition, the material shall only be alloyed with vanadium and niobium, but not with vanadium only.

6.5.4 Materials shall be identified using one of the following methods where specified for sour

service use:

a. Low stress, interrupted dot stamps applied to external surfaces not exposed to the sour

environment

b. Die stamps applied at a temperature above 595 C (1100 F) or applied prior to final heat

treatment at a minimum temperature of 595 C (1100 F)

c. Indelible markers that are free of chlorides, sulphides, and heavy metals such as lead,

where stamping is not permitted or is impractical.

6.5.5 Additionally, for corrosion testing refer Material Requirement in Specification for Topsides Material & Corrosion Requirements for Sour Service for COMP3 Project Doc. No. 200-20- CE-SPC-00025.

6.5.6 Hardness values for sour service material shall be as per NACE 0175/ISO 151516 and Specification for Topsides Material & Corrosion Requirements for Sour Service for COMP3 Project Doc. No. 200-20-CE-SPC-00025.

200-20-PI-SPC-00050_B

Page 19 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

7 WELDING

7.1.1 Repair of weld (where approved by COMPANY) is permitted for weld portion only and shall

be carried out prior to heat treatment. Repair welding of parent material is not permitted.

7.1.2 The Welding procedure and welder’s qualification records shall be qualified in accordance with ASME IX and supplementary requirements. Welder qualification shall be carried out on same material grade as used in production. Any change of material or brand / make of welding consumables shall require requalification.

7.1.3 WPS / PQR shall include the same examinations as for the production testing.

8

TESTING AND INSPECTION

8.1

GENERAL

8.1.1 Testing and examinations shall be carried out after the final heat treatment.

8.1.2 End squareness shall be within 1.2 mm (0.047 in.) of true 90 degrees.

8.1.3 Test samples for production testing shall realistically represent the actual component and shall preferably be from specimen taken from heat treated or hot finished or quenched & tempered component to reflect the actual properties of component.

8.1.4 Tensile test, hardness tests shall be carried out for each heat (each Lot) and heat treatment load. The testing shall be carried out on the component with the heaviest wall thickness within the load.

8.2

HYDROSTATIC TESTING

8.2.1 All pipes shall be hydro tested. Eddy Current tested pipes in lieu of hydrotest are not acceptable. The test pressure shall be such that the hoop stress calculated based on the minimum allowable wall thickness and including stresses from end loading is at least 95% of the specified minimum proof strength at room temperature. Hydrostatic testing shall be carried out prior to non-destructive testing.

8.2.2 Where tests fail to meet the specified requirements, the sampled pipe shall be rejected. Two further pipes from the same lot shall then be tested. The results for both of these further tests shall be satisfactory without recourse to retesting. Any one of test if found unsatisfactory, then the lot of pipes shall be rejected.

8.2.3 The chloride content of test fluid for stainless and alloy steel shall not exceed 30 ppm.

8.3

CORROSION TESTING

8.3.1 Corrosion testing is not required for CS / LTCS / Cu-Ni pipes unless specified otherwise.

8.3.2 Manufacturer shall carry Intergranular corrosion test for stainless steel in accordance with

practices A262, Practice E.

8.3.3

Inter-granular corrosion test in accordance with ASTM G28 Method “A” shall be carried out for Alloy 625 pipes on each batch and heat of material. The acceptance criteria is 0.08 mm/ month (36 mpy) as maximum corrosion rate.

200-20-PI-SPC-00050_B

Page 20 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

8.3.4 For Nickel Alloy 625 pipes, pitting corrosion tests shall be performed in accordance with ASTM G48 Method A. The test shall be performed at a temperature of 50° C (122° F) for 72 hours. The acceptance criteria shall be corrosion rate < 4.0 g/m2/24h and no visual pitting at 20x magnification.

8.4

TENSILE TESTING

8.4.1 Tensile tests shall be performed in accordance with ASTM A370 and EEMUA Publication

234 for Cu Ni.

8.4.2 Specimens shall be taken from one pipe representing each lot. Room temperature testing shall be carried out in transverse direction on flattened plate type specimens and in longitudinal direction on plate type specimens without flattening.

8.4.3 Where material is used at temperature above 120 °C, the material shall undergo elevated temperature tensile tests according to ISO 6892-2 at design temperature, carried out in the transverse direction on flattened plate type specimens.

8.4.4 The acceptance criteria shall be according to corresponding ASTM Specification.

8.5

HARDNESS TESTING

8.5.1 Hardness tests shall be performed in accordance with ASTM E18 for CS/LTCS and EEMUA

publication 234 for Cu-Ni.

8.5.2 Maximum hardness of CS pipes shall be 22HRC. No part of the weld, HAZ or base metal

shall exceed 250 HV10.

8.5.3 Hardness measurements shall be carried out after final heat treatment.

8.5.4 Limitations on maximum hardness for components designated for use in NACE service maximum hardness limitations stated in NACE MR-01-75 / ISO 15156 shall apply.

8.6

IMPACT TESTING

8.6.1

Impact testing shall be carried out where specified in material description, purchase order or required as per ASME B31.3.

8.6.2 For LTCS Charpy impact testing shall be carried out as per ASTM E23 at – 46°C

8.6.3 The Minimum Impact Test value: Min. 24 J average for 3 specimens; Min. 19 J for individual specimen at -29°C (or -46°C for LTCS). Test shall be performed according with relevant ASTM standard requirements.

8.6.4 All carbon steel pipes above 12.7 mm thick in Non- Sour Service shall be Charpy Notch Toughness impact test Type-A (V-Notch), tested at minus (-) 29°C unless otherwise stated in purchase order.

8.6.5 All API 5L Gr.X60/X65 pipes With UNS N06625 Weld Overlay shall be impact tested at -

46°C or -29°C in accordance with the Material Description.

8.6.6 All CS pipes for sour services shall be impact tested at -29°C regardless the thickness.

200-20-PI-SPC-00050_B

Page 21 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

8.7 METALLOGRAPHIC EXAMINATION FOR LTCS

8.7.1 Grain size evaluation in accordance with ASTM E112 shall be carried out at the same area as the location of specimens for mechanical testing. The area examined shall be a minimum of 10 x 10mm (or full section thickness for material thinner than 10mm). The microstructure on a suitably etched specimen shall exhibit a grain size of ASTM #8 or finer.

8.8

FERRITE CHECK AND METALLOGRAPHIC EXAMINATION FOR STAINLESS STEEL MATERIAL

8.8.1 Ferrite checks shall be made on the deposited weld metal in any length of welded pipe from

each heat.

8.8.2 The ferrite content shall be determined according to ASTM E562 and shall be within the

range 4% - 10%.

8.9

HYDROGEN-INDUCED CRACKING (HIC) TESTING

8.9.1 Flat–rolled carbon and low alloy steel material where specified for use in sour service shall be Hydrogen-Induced Cracking (HIC) resistant to meet the following acceptance criteria when tested in Solution A of NACE TM0284 for 96 hours:

a. Crack Length Ratio (CLR) ≤ 10.0%

b. Crack Thickness Ratio (CTR) ≤ 1.5%

c. Crack Sensitivity Ratio (CSR) ≤ 2%

8.10 OTHER TESTS FOR CUNI

8.10.1 Flattening, Double Bend, Drift tests shall be performed as per EEMUA publication 234 as

applicable.

8.11

INSPECTION

8.11.1 Inspection and witnessing during various stages of manufacture, testing and final inspection shall form a part of scope of purchase order. Supplier shall provide free access to supplier / sub-supplier facilities for COMPANY or COMPANY’s representative or third-party inspection agency to carry out inspections, test witnessing and final inspection as per agreed hold points of Inspection and Test Plan.

8.11.2 Where inspection and tests are required on randomly selected items, manufacturer shall make available a complete lot for purchaser or purchaser’s representative or third-party inspector to select randomly the items to conduct inspect or test as required by purchase order. Manufacturer’s pre-selected items from lot and presented for inspection or testing will not be accepted.

9

NON-DESTRUCTIVE EXAMINATION (NDE)

9.1

GENERAL

9.1.1

Inspection and NDE shall be in accordance with applicable codes (i.e. ASTM, API) and the extend of NDE inspection shall meet as per NDE table.

200-20-PI-SPC-00050_B

Page 22 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

9.1.2 VENDOR/SUB-SUPPLIER shall submit all NDE procedures to be used for manufacturing to EPC CONTRACTOR / COMPANY for review and approval. All NDE procedures shall be reviewed and endorsed by EPC CONTRACTOR.

9.1.3 All final NDE shall be performed after PWHT where applicable. That is, after performing all surface disturbance methods, for ex: grinding, machining, etc., in case of non PWHT.

9.1.4 Extent of NDT examination shall be as EPC CONTRACTOR / COMPANY specification,

approved ITP and NDE methods.

9.1.5 NDT Personnel performing inspection and interpretation of test results shall be certified to Level II by a Certification Body or Authorized Qualify Body in accordance with ISO 9712 or the ASNT Central Certification Program (ACCP). Personnel qualification to an employer- based qualification scheme as SNT-TC-1A may be accepted, but only with prior Purchaser approval and employer’s written practice is reviewed and found acceptable and the Level III is ASNT Level III or ACCP Professional Level III and certified in the applicable method. Purchaser appointed Level III or certifications are not acceptable.

9.1.6

In case internal weld overlay is applicable for any of the below mentioned items, the Vendor shall also comply with the requirements of Project specification Doc. No. 200-20-CE-SPC- 00033.

9.2

VISUAL EXAMINATION

9.2.1 Each item shall be 100% visually examined externally and wherever possible internally.

9.2.2 VENDOR shall submit the NDE procedure for COMPANY approval.

9.3 MAGNETIC PARTICLE EXAMINATION

9.3.1 10% of total supplied pipes shall be subject to 100% MT examination to bevel ends.

9.3.2 The acceptance criterion shall be in accordance with ASME Section VIII, Division 1 – Appendix 6. If discontinuities exceed limitations on any pipes examined during the initial 10% requirement, a further 10% shall be examined. If discontinuities are found during this period of testing, 100% of all pipes shall be examined.

9.3.3 NDT inspector qualification shall be minimum Level II, unless specified otherwise.

9.4

LIQUID PENETRANT EXAMINATION

9.4.1 Liquid penetrant examination shall be carried out where Magnetic particle test is not feasible.

Liquid penetrant testing shall be carried out after final machining.

9.4.2 LP testing shall be carried out according to ASME V Article 6. Acceptance criteria shall be

as per ASME VIII Div. 1 Appendix 8.

9.4.3 NDT inspector qualification shall be minimum Level II, unless specified otherwise.

9.5

ULTRASONIC EXAMINATION

9.5.1 Ultrasonic examination where specified in purchase order or project specification shall be

carried out as per project specifications and relevant ASTM, API specification.

9.5.2 Acceptance criteria shall be as per ASME VIII Div. 1 Appendix 12.

200-20-PI-SPC-00050_B

Page 23 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

9.6 RADIOGRAPHY EXAMINATION

9.6.1 Radiographic examination where specified in purchase order or project specification shall be

carried out as per project specifications and relevant ASTM specifications.

9.6.2 Acceptance criteria shall be as per ASME SEC VIII Div. 1 Appendix 4.

10 POSITIVE MATERIAL IDENTIFICATION

10.1.1 Positive material identification is not necessary for carbon steel, low temperature carbon

steel component.

10.1.2 Positive material identification shall be carried out for stainless steel, Cu-Ni alloy components as per Doc No. 200-20-CE-SPC-00034 “Specification for Positive Materials Identification (PMI) for COMP3 Project”. PMI Instrument used shall have latest calibration and shall be approved by COMPANY.

11 MARKING AND TRACEABILITY

11.1.1 All Components shall be marked to ensure full traceability to heat and heat treatment lot.

11.1.2 Components shall be marked as per the requirements of corresponding ASTM Refer to Material Management and Traceability Control Procedure requirements Doc. No: COMP3- SPM-CC-PRC-00002.

11.1.3 Marking shall include the size (NPS) pipe schedule number or nominal wall thickness in millimeters, rating, charge or heat number and the manufacturer’s unique symbol and material specification. In addition, Contractors “Mark code/Ident code” shall also to be included in the marking.

11.1.4 Material identification shall be applied by the manufacturer directly to the item, using low

stress stamps or paint stencils.

12 CERTIFICATION

12.1.1 All material certifications shall be in accordance with the EN 10204 Type 3.1 in general and Type 3.2 for Sour services complying with NACE MR 0175/ISO 15156. Material Certificate shall show the chemical composition, mechanical test records, heat treatment records and any other records of supplementary tests specified in purchase order.

12.1.2 Material certificates in accordance with BS EN 10204 3.1 and 3.2 shall contain, as a

minimum, the following information as applicable:

a) Chemical analysis: All chemical elements for which a specification limit is set shall be reported. The carbon equivalent (CE) shall be calculated and included in the certification.

b) Mechanical properties, with results of the following mechanical tests where a specification

limit is set:

• Tensile tests (both ultimate and yield).

• Elongation Test.

200-20-PI-SPC-00050_B

Page 24 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

• Bend Test.

•

Impact Test.

• Hardness Tests.

c) For welded pipes, the following information shall also be included. Specimens for impact testing shall be taken from three places: heat affected zone, weld metal, and parent metal:

• A statement of the heat treatment applied. Where heat treatment invokes supplementary NDE or mechanical tests, these are mandatory and shall be included in certification.

• Non-destructive test results.

• Hydrostatic and/or pneumatic test results.

• HIC Test Results (for welded pipes in sour service).

• Corrosion testing (IGC/Pitting etc.)

12.1.3 TPA witnessing key tests during manufacturing shall be as per COMPANY approved

Inspection & Test Plan (ITP).

12.1.4 For items intended for sour service, the manufacturer shall provide a statement of compliance with NACE MR0175 / ISO15156 Specification for Sour Service in addition to the other material certificates required.

12.1.5 Certificates shall be referenced to the following:

a) Mill and/or manufacturer’s name and location.

b) The Purchase Requisition and Purchase Requisition Item tag numbers.

c) Heat number/ Heat treatment batch no. traceable to pipe marking.

d) Description of the pipes covered by the certificate, including the nominal pipe size,

schedule / thickness, etc.

e) Material type, specification, and grade (e.g. carbon steel ASTM A106 Gr. B).

f) Dimensional tolerances.

However, minimum content as specified on material standard shall also be included.

12.1.6 All CRA material shall be subjected to PMI.

12.1.7 Inter-granular corrosion (IGC) test in accordance with ASTM A262 Practice E shall be carried

out for Stainless Steel Pipes.

12.1.8 Inter-granular corrosion test in accordance with ASTM G28 shall be carried on UNS N06625.

12.1.9 All testing shall be done per heat/heat treatment batch in line with code requirement.

12.1.10 Test reports shall include heat treatment batch / lot number. The same shall be included

under Vendor document requirements.

200-20-PI-SPC-00050_B

Page 25 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

13 HANDLING, PACKING, PRESERVATION AND STORAGE

13.1.1 Material handling, packaging, preservation and storage shall be as per purchase order

requirements.

Identification and Marking Techniques

a) Marking shall be as per relevant Standards as mentioned on the purchase description.

b) Cold hard stamping is not permitted on C.S. material. Stamping, if required, shall be by

using low stress stamping or vibro etching only.

c) Stainless steel, nickel alloy components shall not be electro-etched prior to solution

annealing.

Identification and Marking Requirements

The following requirements supplement the marking and identification requirements of relevant reference codes, standards and material specification.

The following markings are required additionally:

a) Purchase Order Number

b) Material Designation

c) Size/Thickness

d) Heat or Melt Number/Heat Treatment Condition (if applicable)

e) Specification and grade of material

f) Batch number.

13.1.2 Material handling shall ensure to prevent or minimize the possibility of contamination.

13.1.3 Use of bare steel hooks, chains or lifting forks without the use of protective insulating material

is not permitted.

13.1.4 Stainless steel brushes designated exclusively for use on Stainless Steel may be used for

brushing or descaling Stainless steel products.

13.1.5 Preservation and protection of components shall be as per project specifications and

requirements of ASTM A700.

13.1.6 Beveled end pipes shall be supplied with ends protected to avoid transport damages. Pipes shall be shipped with end protectors to protect beveled ends. Pipe bevels shall be protected by metal / plastic caps.

Threaded pipes shall be wrapped and packed with an appropriate material and shall be protected with hard plastic plugs or caps.

13.1.7 Wooden boxes shall be fumigated and certified to requirements of ISPM 15.

13.1.8 Vendor shall provide the details of preparation and packing methods employed in his bid and

as well as along with the shipping documents.

200-20-PI-SPC-00050_B

Page 26 of 27

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPECIFICATION FOR PIPES FOR COMP3 PROJECT

13.1.9 Packing, protection, preservation, identification, marking, and storage of all items shall be in accordance with COMPANY Specification Doc No. COMP3-SPM-PO-PRC-00005 “Handling, Storage, Packing & Preservation Procedure” or with purchase order.

13.1.10 Stainless Steel shall be protected externally before transporting to site. The protection shall

be maintained during construction and operation at site.

13.1.11 The supplier shall provide adequate protective measures i.e. suitable reinforcements to

avoid buckling and ends ovalization for large bore pipes.

14 DOCUMENTATION

14.1.1 Vendor shall certify that all components are in compliance with the relevant ASTM specifications, codes and project specification referred here-in and enclosed with purchase order.

14.1.2 List below gives the minimum required supplier documents. However, supplier shall submit all the documents / reports as a part of supplier documentation as per purchase order and as required by Project documentation requirements. All documents / certificates shall be signed by responsible person of supplier.

a. Mill Certificate

b. Mechanical Test Records

c. Metallographic Test records

d. Impact Test Records

e. Heat Treatment Records

f. Hardness Test Records

g. Non-Destructive Test Records (MP / LP / Radiography / UT) as applicable

h. PMI test Records

i. Pickling and Passivation Records (as applicable)

j. Hydro-test Records (as applicable)

k. Other test reports for Cu-Ni (as applicable)

l.

Inter Granular Corrosion Report (as applicable)

14.1.3 For additional requirements refer to Specification for Material Management and Traceability

Control Procedure Requirements Doc. No: COMP3-SPM-CC-PRC-00002.

15 NON-COMPLIANCE / DEVIATION:

If any of the requirements of this Specification cannot be met, VENDOR/SUPPLIER must provide written notification of non-compliances in “Technical clarification form and Deviation form” as attached in the Material Requisition, with explanations, in accordance with project instructions. This notification will be evaluated and must have COMPANY approval before final acceptance.

200-20-PI-SPC-00050_B

Page 27 of 27

Project: Q-32705 - Saipem COMP3 Folder: RFQ Files


Loading authentication...

Graph View

Backlinks

  • 00 Index

Created with Infinity Constructor © 2025

  • Elynox | Go Further