Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

COMPANY Contract No.: LTC/C/NFP/5129/20 CONTRACTOR Project No.: 033764

ASSET

: NFPS

Document Title

: SPARE PARTS MANAGEMENT PLAN

COMPANY Document No.

: COMP3-SPM-PE-PLN-00002

CONTRACTOR Document No.

:

033764-B-D00-18-SPM-EM-P-10002

Discipline

:

ADMINISTRATIVE, ENGINEERING MANAGEMENT

Document Type

: PLAN

Document Category/Class

:

1

Document Classification

:

Internal

B

22-APR-2025

Issued for Approval

Armande B. Dala Maintenance Engineer

Mansoor Ahmed Lead Maintenance Engineer

Reetesh Jha Technical Manager

A

09-DEC-2024

Issued for Review Armande B. Dala Mansoor Ahmed Reetesh Jha

REV.

DATE

DESCRIPTION OF REVISION

PREPARED BY

REVIEWED BY

APPROVED BY

Saipem S.p.A

www.saipem.com

THIS DOCUMENT IS PROPERTY OF QatarEnergy LNG. THIS DRAWING OR MATERIAL DESCRIBED THEREON MAY NOT BE COPIED OR DISCLOSED IN ANY FORM OR MEDIUM TO THIRD PARTIES, OR USED FOR OTHER THAN THE PURPOSE FOR WHICH IT HAS BEEN PROVIDED, IN WHOLE OR IN PART IN ANY MANNER EXCEPT AS EXPRESSLY PERMITTED BY QatarEnergy LNG.

COMP3-SPM-PE-PLN-00002_B

Page 1 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

REVISION HISTORY

Revision

Date of Revisio

n

Revision Description

A1

A

B

20-NOV-2024

Issued for Inter-Discipline Check

09-DEC-2024

22-APR-2025

Issued for Review

Issued for Approval

HOLDS LIST

Hold No

Hold Description

1

Section 3.2: Project document number to be confirmed

COMP3-SPM-PE-PLN-00002_B

Page 2 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

TABLE OF CONTENTS

1

2

3

4

5

6

7

8

9

INTRODUCTION …4 1.1 PROJECT OBJECTIVE …4 1.2 PROJECT SCOPE …4 DEFINITIONS AND ABBREVIATIONS …7 2.1 DEFINITIONS …7 2.2 ABBREVIATIONS …7 REFERENCE, CODES AND STANDARDS …9 3.1 COMPANY REFERENCES …9 3.2 PROJECT DOCUMENTS …9 SCOPE AND PURPOSE OF DOCUMENT …9 4.1 SCOPE OF DOCUMENT …9 4.2 PURPOSE OF DOCUMENT …10 DESCRIPTION …10 5.1 RECOMMENDED SPARE PARTS LIST (RSPL) …10 5.2 1-MONTH START-UP SPARES AND SUPPLIES …10 5.3 2-YEAR OPERATING SPARES…11 5.4 OPERATING SUPPLIES…11 5.5 LIFE CYCLE SPARES …11 5.6 CAPITAL SPARES …11 5.7 CONSTRUCTION/PRE-COMMISSIONING SPARE PARTS …11 5.8 COMMISSIONING SPARES …11 5.9 INITIAL FILLS …12 5.10 SPECIAL TOOLS …12 RESPONSIBILITIES …12 6.1 CONTRACTOR RESPONSIBILITIES …12 6.2 FIELD MATERIAL MANAGEMENT …14 6.3 HAZARDOUS MATERIAL …14 6.4 SURPLUS MATERIAL …14 6.5 SUPPLIER RESPONSIBILITIES …15 SPARE PARTS DOSIER WORKFLOW …15 7.1 REPORTS …17 PROCUREMENT PROCESS…17 8.1 CARE, CUSTODY, AND CONTROL …18 APPENDICES …19 RECOMMENDED SPARE PARTS LIST (RSPL) TEMPLATE …19 LUBE TEMPLATE AND LUBE SAMPLE SHEET …25 CHEMICAL TEMPLATE AND CHEMICAL SAMPLE SHEET …26 SPECIAL TOOLS TEMPLATE AND SPECIAL TOOLS SAMPLE SHEET …27 BLINDS & SPACERS TEMPLATE AND SAMPLE SHEET …28 PIPING GASKET TEMPLATE AND PIPING GASKET SAMPLE SHEET …29

APPENDIX 1 APPENDIX 2 APPENDIX 3 APPENDIX 4 APPENDIX 5 APPENDIX 6

COMP3-SPM-PE-PLN-00002_B

Page 3 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

1

INTRODUCTION

The North Field is the world’s largest natural gas field and accounts for nearly all the State of Qatar’s gas production. The principal objective of the NFPS projects is to sustain plateau from existing Qatar Energy LNG Operation – S1, S2, S3, N1 and N2, production areas by implementing an integrated and optimum investment program consisting of subsurface development, pressure drop reduction steps and compression.

NFPS projects comprise 3 main investment programs:

  1. Investment #1: Drilling and Associated Facilities [WHP12S/ WHP13S/ WHP14S/

WHP12N/ WHP13N]

  1. Investment #2: Trunk line Looping and Intra-field pipeline looping [32” PL1LN, 32”

PL1LS, 38”PL610LS]

  1. Investment #3: Compression Complexes and associated facilities [Phase 1 CP6S & CP7S; Phase 2: CP8S & CP4N; Phase 3: CP4S & CP6N Phase 4: CP1S & CP1N]

Drilling and Looping, Investments #1 and #2, projects are in execution phase and are being executed as I1P1, EPCOL Projects except for WHP13N, which will be part of NFPS Compression Projects execution which compromises total up to 9 COMPs.

1.1 Project Objective

The objective of this Project includes:

 Achieve standards of global excellence in Safety, Health, Environment, Security and

Quality performance.

 Sustain the Qatar Energy LNG North Field Production Plateau by installing new RPs and one WHPs to support new Compression Complex facilities CP6S & CP7S and pre- installed facilities for future Compression Complex facilities including but not limited to CP4N & CP8S tie-in with integration to the existing facilities under Investment #3 program.

 Facility development shall be safe, high quality, reliable, maintainable, accessible,

operable, and efficient throughout their required life.

1.2 Project Scope

The Project Scope includes detailed engineering, procurement, construction, brownfield modifications, transportation & installation, hook-up and commissioning, tie-in to EXISTING PROPERTY and provide support for start-up activities of the following facilities and provisions for future development. The WORK shall be following the specified regulations, codes, specifications and standards, achieves the specified performance, and is safe and fit-for- purpose in all respects.

Facilities - 1A

 RP5S RP with 2 x 28” CRA clad pipelines to RP7S and 2 subsea composite Cables and

associated J tubes from RP7S to RP5S & from CP7S to WHP13S.

 New Fuel Gas 8” CRA Spur-lines and flanged risers from Subsea skid to RP7S

COMP3-SPM-PE-PLN-00002_B

Page 4 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

 Hook-up and brownfield modification at WHP5S/RP5S bridge connection & WHP13S/CP7S Composite cable tie-in and E&I integration including RGA Control modification

 Pipeline decommissioning of 28” CS PL5 including associated demolition work at

WHP5S

Facilities - 2A

 RP6N RP with 1x28” CRA clad pipeline to WHP13N, 2 Subsea composite cables and

associated J tubes from WHP12N to RP4N and RP6N to WHP13N.  New fuel gas spur-line and flanged riser from subsea skid to RP6N  WHP13N Topside  Hook-up and brownfield modification at WHP6N/RP6N, RP4N- HPU-Umbilical and tie- in, WHP12N-new J tube installation, E&I migration, WHP6N/RP4N/WHP4N-E&I migration (Pre-CP4N), WHP13N and RP6N interconnection to NFB.

Facilities - 3A

 RP9S RP with 1x28” CRA clad pipeline to RP4S,  Hook-up and brownfield modification at RP4S/WHP9S, Modifications to integrate RP9S

to the RGA control network.

 Pipeline decommissioning of 28” PL9 to WYE on existing 38” trunkline PL49including

associated demolition work at WHP9S.

Facilities - 1B

 New fuel gas spur-line and flanged riser from subsea skid to RP4N  Fiber Optic Cable from RP6N to onshore LFP East, RP6N to RP4N and RP6N to LQ6S.  Hook-up and brownfield modification at RP6N Composite and FO Tie-ins NFB-PU (East)- FO Tie-in

(East)/BVS

Power & Control modifications, LQ6S/LFP Controls/Telecoms Integration

Facilities - 2B

 RP5N RP with 2 x 28” CRA clad pipelines to RP4N, 1 x 28” CRA clad pipeline to RP6N and 2 subsea composite Cables and associated J tubes from WHP12N to RP5N & from RP6N to RP5N.

 Hook-up and brownfield modification at WHP5N- RP5N Bridge connection, WHP12N Composite cable tie-in, RP4N Intrafield pipeline Hook up PL54 N/LN and E&I integration including NFB-PU Power & Control modifications

 Pipeline decommissioning of 2 x 16” PL56/PL54 Subsea Spur line from WHP5N to

reducing barred tee in subsea tie-in skid on PL6 / PL4.

Facilities - 3B

 2 subsea composite Cables from RP4S to RP9S & from RP4S to WHP12S (with J-tube)  New Fuel Gas 8” CRA Spur-lines and flanged risers from Subsea skid to RP4S  Hook-up and brownfield modification at WHP12S/ RP9S/ RP4S Composite cable tie-in,

Spurline riser installation at RP4S RGA Power & Control modifications.

Facilities - 4B

 1 subsea composite Cable from CP8S to RP11S (or from RP8S to RP11S as Option).  New Fuel Gas 8” CRA Spur-line and flanged riser from Subsea skid to RP8S.

COMP3-SPM-PE-PLN-00002_B

Page 5 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

 Hook-up and brownfield modification at WHP8S/ WHP11S for Test separator Internal Upgrade and MEG system modification, Spur lines, Power & Control Tie-ins on RP8S, RP11S/WHP11S-Tie-in (Power and Control), RGA Power & Control modifications.

Facilities - 5B

 2 subsea composite Cables from RT2 to WHP3S & from RT2 to WHP2S (with J-tube)

and FO Cable from RT2 to Barzan WHP1.

 New Fuel Gas 8” CRA Spur-line and flanged riser from Subsea skid to RT2  Hook-up and brownfield modification at BRZ-WHP1 - FO cable tie-in, WHP2S/ WHP3S/ RT&RT2 Composite cable tie-in and associated modification, RGA Power & Control modifications.

Facilities - 6B

 RP3S RP with 1x24” CRA clad pipeline to RT2 with Stalk on risers,  Hook-up and brownfield modification at RT2 for 24” Intrafield pipeline and Composite/FO cable Hook-up, WHP3S for Production diversion and Utilities, Power and ICSS Hook- up, WHP2S for Composite Cable Tie-ins and Power & Control Integration RGA Power & Control modifications.

 Decommissioning at

In-situ abandonment of existing Topside/subsea Composite Cables RT-WHP2S, RT-WHP3S, Topside/Subsea FO cable RT-BRXWHP1.

topside existing and

Figure 1.2.1: NFPS Compression Project COMP3 Scope

COMP3-SPM-PE-PLN-00002_B

Page 6 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

2 DEFINITIONS AND ABBREVIATIONS

2.1 Definitions

Definition

Description

COMPANY

Qatar Energy LNG.

CONTRACTOR

Saipem S.p.A.

DELIVERABLES

FACILITIES

MILESTONE

PROJECT

SITE

SUBCONTRACT

SUBCONTRACTOR

fabricated,

All products (drawings, equipment, services) which must be submitted by CONTRACTOR to COMPANY at times specified in the contract. All machinery, apparatus, materials, articles, components, systems and items of all kinds to be designed, engineered, procured, manufactured, constructed, supplied, tested and permanently installed by CONTRACTOR at SITE in connection with the NFPS Project as further described in Exhibit 6. A reference event splitting a PROJECT activity for progress measurement purpose. COMP3 - NFPS Offshore Riser/Wellhead Platform & Intrafield Pipelines Project (i) any area where Engineering, Procurement, Fabrication of the FACILITIES are being carried out and (ii) the area offshore required for installation of the FACILITIES in the State of Qatar Contract signed by SUBCONTRACTOR and CONTRACTOR for the performance of a certain portion of the WORK within the Project. Any organization selected and awarded by CONTRACTOR to supply a certain Project materials or equipment or whom a part of the WORK has been Subcontracted.

WORK

Refer to article 2 of CONTRACT AGREEMENT.

WORK PACKAGE

The lowest manageable and convenient level in each WBS subdivision.

SUPPLIER

Vendor / Subcontractor to Contractor

2.2 Abbreviations

Code

Definition

Project Specialist Leader

Preparation / Verification / Approval Workflow In EDMS

Record of Conversation

Technical Manager

Recommended Spare Parts List

PSL

PVA

ROC

TM

RSPL

COMP3-SPM-PE-PLN-00002_B

Page 7 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

Code

Definition

OSL

PO

OEM

OPM

PMT

RFSU

UOM

SPOC

Operating Supplies List

Purchase Order

Original Equipment Manufacturer

Original Part (Component) Manufacturer

Project Management Team

Ready for Startup

Unit of Measure

Single Point of Contact

COMP3-SPM-PE-PLN-00002_B

Page 8 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

3 REFERENCE, CODES AND STANDARDS

3.1 Company References

S. No

Document Number

Title

LTC/C/NFP/5129/20

Contract Agreement

EXHIBIT 5

EXHIBIT 6

Project Instructions

Scope of Work

ONS-OES-MNT-003

Spare Parts and Material Identification, Procurement, Delivery, Receipt, and Payment - OES-OED Supported Projects

OGO-OES-OVR-002

Projects System Completion and Handover

PRJ-PJL-PRC-004

PRJ-PJL-PRC-005

Facilities Engineering and Vendor Document Numbering Procedure

Facilities, System and Unit Number Codes and Descriptions Procedure

PRJ-PJL-PRC-006

Project Information Handover Procedure

PRJ-PJL-PRC-048

PRJ-PJL-PRC-049

Facilities Documentation Metadata Requirements Procedure Project Acceptance Procedure

Information Handover, Verification and

3.2 Project Documents

S. No

Document Number

Title

COMP3-SPM-PO-PLN-00001

Project Procurement Plan

COMP3-SPM-PO-PRC-00003

COMP3-SPM-PO-PRC-00002

COMP3-SPM-QM-PLN-00001 COMP3-SPM-SH-PLN-00001

COMP3-SPM-PO-PRC-00005

Expediting Procedure Project Vendors and Subcontractors Qualification Procedure Project Quality Plan Project HSE Plan HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

4 SCOPE AND PURPOSE OF DOCUMENT

4.1 Scope of Document

This document covers the CONTRACTOR’S Management of the Spare Parts Dossier up to the approval of COMPANY in connection with the execution of NFPS Offshore Riser/Wellhead Platform & Intrafield Pipelines Project. The main scope of this plan includes the following:

COMP3-SPM-PE-PLN-00002_B

Page 9 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN



Instruction for submission of Spare Parts List Dossiers

 Contractor and Supplier/Vendor Responsibilities

 Spare Parts Dossier workflows

This plan includes spare parts processes beginning with creation of the Spare Parts Lists by the Vendor; review and submission of the Contractor to Company.

4.2 Purpose of Document

The purpose of this Spare Parts Management Plan is to outline the responsibilities of all organizations involved on identifying materials and spare parts, including data and documentation requirements, for the development of Spare Parts Lists for all maintainable equipment; also, to provide instructions to ensure that complete and acceptable Recommended Spare Parts List (RSPL) and Spare Parts Dossier are submitted to COMPANY in accordance with a stipulated submittal schedule so that all Spare parts and Operating materials are available for each of the respective facilities listed under section 1.2..

5 DESCRIPTION

5.1 Recommended Spare Parts List (RSPL)

The Recommended Spare Parts List (RSPL) is developed by Supplier and maintained by CONTRACTOR and is a complete listing of all spare parts (1-Month Start-up, Life Cycle, and 2-Year Operating Spares and Capital Spares), Special Tools, recommended spares required for construction/pre-commissioning and commissioning.

The RSPL shall be developed based on Vendor recommendations for all installed maintainable equipment. Fully compliant Vendor RSPLs shall be provided by Vendor, reviewed by CONTRACTOR, and issued to COMPANY for review as per Exhibit 5 4.3.10.3 within eight (8) weeks of CONTRACTOR’s initial placement of the associated Purchase Order. If based on the PO complexity the issuance timing will require more than 8 weeks, Contractor will duly inform Company.

Prior to transmittal to COMPANY:

 CONTRACTOR shall confirm completeness of data (all required information is provided, e.g. tag references, part number, unit price, material, etc., and in the correct fields) as per the templates in the procedure; and

 CONTRACTOR shall review Vendor’s recommended quantities for Construction/Pre- Commissioning and Commissioning Spares and shall update as required to ensure delivery of the FACILITIES as per the requirements set for in the AGREEMENT.

Additionally, each RSPL shall include supporting documents/drawings of all spare parts included in the RSPL and interchangeability lists for parts that are common to multiple equipment that may be furnished by the same manufacturer. RSPL and OSL shall be developed as per the requirements set forth in ONS-OES-MNT-003– Spare Parts and Material Identification Procedure.

5.2 1-Month Start-up Spares and Supplies

COMP3-SPM-PE-PLN-00002_B

Page 10 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

1-Month Start-up Spares and Supplies (Reimbursable) are spares and supplies necessary for start- up and to maintain normal operations of the FACILITIES from RFSU, typically one (1) month or until OAC.

5.3 2-Year Operating Spares

2-Year Operating Spares (Reimbursable) are parts required to maintain equipment in satisfactory working order after start-up and during the first two years of operation.

5.4 Operating Supplies

Operating Supplies (Reimbursable) are consumables (such as chemicals, catalysts, lube oil, etc.) required for equipment during the first two years and normal operation. The initial fill (Lump Sum Price) and consumption (Reimbursable) is a project scope until the Operational Acceptance Certificate (OAC) is granted which typically 1 month for Offshore and 2 months for Onshore.

5.5 Life Cycle Spares

Life Cycle Spares are spares required for covering one full maintenance cycle (one complete overhaul of the equipment). These Spares are ordered and purchased by Qatar Energy LNG OPCO through Qatar Energy LNG Supply after facility handover to the Operating Asset. Life Cycle Spares shall be arranged for all Equipment covered in Project Scope in RSPL.

5.6 Capital Spares

Capital Spares (part of LUMP SUM PRICE) are considered high value (>$250k USD) and/or long lead time (> 1 year) spares. These parts normally have a long-life span with minimal chance of failure, but if such a failure occurred, it has the potential to shut down the equipment for an extensive period.

Details of Capital Spares can be found in CONTRACT Exhibit 6. Additional Capital Spares identified by CONTRACTOR and APPROVED or identified by COMPANY during execution of the WORK, if any, shall be procured by CONTRACTOR on behalf of COMPANY on a reimbursable basis pursuant to Article 7.3. of the Articles of Agreement. CONTRACTOR shall deliver Capital Spares to the designated COMPANY location (e.g. Qatargas Warehouse) located in Ras Laffan Industrial City (RLIC), Qatar, prior to READY FOR STARTUP.

5.7 Construction/Pre-Commissioning Spare Parts

Construction/Pre-Commissioning Spare Parts (part of LUMP SUM PRICE) are consumable spare parts required during construction and installation.

5.8 Commissioning Spares

Commissioning Spares (part of LUMP SUM PRICE) are spare parts required for commissioning the FACILITIES up to RFSU. These are spares that may be consumed, broken, worn out, plugged up, or otherwise fail as systems are being commissioned.

COMP3-SPM-PE-PLN-00002_B

Page 11 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

5.9

Initial Fills

Initial Fills (part of LUMP SUM PRICE) are fills at maximum level necessary to begin normal operation of the FACILITIES, including all chemicals, lubricants, coolants, hydraulic fluids, etc., in accordance with Exhibit 6.

5.10 Special Tools

Special Tools (part of LUMP SUM PRICE) are designed and fabricated by Vendors to be used for installation, on site repair, or disassembly/maintenance/reassembly purposes. Special tools may be used by CONTRACTOR during performance of the WORK; however, Special Tools shall be handed- over to COMPANY in like-new condition.

6 RESPONSIBILITIES

6.1 Contractor Responsibilities

 Contractor shall include instructions for completing and submitting Spare Parts List, OSLs and Special tools within the “Call for Tender”, and then within the relevant purchase orders and sub vendor’s scope.

 Contractor shall furnish the instructions to Vendors outlining the responsibilities of the Supplier/Vendor for providing a detailed Spare Parts List dossier covering all types of Spares and Materials in the Company format. Company format and templates shall be in line with ONS-OES-MNT-003, and provided below:













RSPL Template

Lube Template

Chemical Template

Special Tools Template

Blinds & Spacers Template

Piping Gasket Template

For details, refer to Appendices.

 Ensuring that Vendor/Supplier submits a fully compliant Spare Parts List, OSL, Capital Spares,

and Special Tools.

 Contractor shall ensure a forecast plan is provided for the Spare Parts Dossier.

 Each PO Spare Parts Dossiers are to be reviewed by the Contractor for completeness, including all relevant supporting documents (i.e., all required information is provided, such as Scope of Supply covered, Tag references are shown in P&IDs and the Equipment Database, relevant Drawings/document numbers for all Equipment and Parts). Vendor-recommended

COMP3-SPM-PE-PLN-00002_B

Page 12 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

quantities for Commissioning and Operating Spares are to be reviewed by the Contractor, with recommendations updated as appropriate.

 Check that interchangeability lists for parts that are listed in Spare Parts List, OSLs and Special

Tools List are furnished.

 Resolving any queries or deficiencies in the document as identified by the COMPANY at the

earliest (Vendor follow ups for Comments with concurrence of Engineering)

 The Contractor shall schedule/manage issuance of Spare Parts List POs based on lead-time sequence and issue to the Company for review and approval within 8 weeks after issuance of the equipment purchase order, or at a given date specified in the PO or in the Vendor document list. An any case, spare parts list will be issued only after complete finalization of design of the corresponding material

 The Contractor shall prepare and submit a Spare Parts Dossier Status Report to the Company

(PO-wise).

 The CONTRACTOR shall instruct the vendor to tag or label all the spare parts with the corresponding SAP code that COMPANY will provide upon approval of the vendor RSPL. In any case that tag or label (SAP code) are not available on the spare parts upon receipt at Contractor warehouse / spare parts staging area, then Contractor shall tag or label the spare parts prior to the delivery to COMPANY warehouse.

 The CONTRACTOR shall be responsible in the receiving, inspection, storage (based on the manufacturer storage procedure, if not available, follow project procedure) and control of all spare parts received at Contractor designated warehouse / or spare parts staging area.

 CONTRACTOR shall be responsible for preservation of all spares whilst they remain in CONTRACTOR’s due care and custody, in accordance with Supplier recommended preservation procedure or CONTRACTOR’s preservation procedure whichever is the more stringent.



In order for transfer of spares from the Contractor’s premises to the Qatar Energy LNG Warehouse to take place, a Historical Purchase Order (HPO is required to allow the Qatar Energy LNG Warehouse to receive the spares.

 The CONTRACTOR shall inform the COMPANY PMT (Single Point of Contact - SPOC) if any RSPL spare parts are ready for delivery then COMPANY PMT (SPOC) shall coordinate with COMPANY Warehouse Material Control Section for HPO Creation. PMT SPOC shall provide the following for the creation of the HPO:







Vendor’s Name (EPC Contractor): complete name, address and vendor reference number

Spare Parts List Template: in Excel format, with the approved quantities, SAP codes, and Unit price and currency in USD

The following additional activities shall be arranged during HPO creation with Header condition (ZMSC):

a) Transportation, warranty, and documentation charges

b) b) Customs duties, legalization, and clearance charges

c) 5% Contractor handling fees

d) Reference: Spare Parts List, PO number

COMP3-SPM-PE-PLN-00002_B

Page 13 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

 The Contractor shall inform the COMPANY PMT (SPOC) if any HPO spare parts ready for delivery then COMPANY PMT (SPOC) shall coordinate the schedule of delivery to COMPANY warehouse HPO Wise and inform Contractor accordingly.

 Contractor shall deliver spares to Qatar Energy LNG Warehouse HPO wise.

 Spare parts hand over slip (PO wise) and delivery notes shall be prepared by the Contractor

prior to delivery of spare parts to COMPANY warehouse.

 Prior to the delivery of spare parts to COMPANY warehouse, Contractor shall check and verify the Quality documentations / or test certificates (if required) are available along with the spare parts.

 The CONTRACTOR shall be available during the delivery and inspection of the spare parts at COMPANY warehouse, to clarify, verify and to response to query by COMPANY warehouse with regards to deficiency / non-conform / damage / shortage / overage of the spare parts being delivered, if any.

 The CONTRACTOR shall be responsible in closing in a timely manner any material deviation

report (MDR) raised against the spare parts delivered at COMPANY warehouse.

 The Contractor shall be responsible in the filing / safekeeping (PO wise) of all signed spare parts hand over slip documents and delivery notes (either hard or soft copy or both) and shall be available upon COMPANY’s request.

 Note: This is exclusively for Capital Spares, the CONTRACTOR prior to delivery to COMPANY warehouse, will call for a joint pre-release inspection between CONTRACTOR, Qatar Energy LNG warehouse and OES

6.2 Field Material Management

For Field material management Contractor will follow the requirement set by Exhibit 5 4.3.11. reference shall be made to project document “COMP3-SPM-QM-PLN-00001”- PROJECT QUALITY PLAN. and PROJECT EXECUTION PLAN “

Receiving material requirements will follow Exhibit 5 4.3.11.1, reference shall be made to project document COMP3-SPM-QM-PLN-00001”- PROJECT QUALITY PLAN, Para 9.10.

Warehousing requirements will follow Exhibit 5 4.3.11.2, reference shall be made to project document “COMP3-SPM-QM-PLN-00001”- PROJECT QUALITY PLAN, Para 9.10.

Issuing Material will follow Exhibit 5 4.3.11.3, reference shall be made to project document “COMP3- SPM-QM-PLN-00001”- PROJECT QUALITY PLAN, Para 9.10.

6.3 Hazardous Material

For Hazardous Material Contractor will follow the requirement set by Exhibit 5 4.3.11.4. reference shall be made to project document “COMP3-SPM-SH-PLN-00001”- PROJECT HSE PLAN.

6.4 Surplus Material

For SURPLUS Material Contractor will follow the requirement set by Exhibit 5 4.3.11.5. reference shall be made to project document PROJECT EXECUTION PLAN.

COMP3-SPM-PE-PLN-00002_B

Page 14 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

6.5 Supplier Responsibilities

The main responsibility of Supplier and Sub-vendor is to the submission of Spare Parts List, Operating Supplies List, and Special Tool List.

The Supplier shall prepare a detailed Spare Parts List dossier (PO-wise) covering all types of Spares and Material in the Company format. The Spare Parts Dossier shall include Spare Part List (for Commissioning, Start-up, 2-year operation, and Life Cycle spares), Operating Supplies List, Special tools List and Capital Spares Lists.

The Supplier shall ensure that a Spare Parts List dossier is submitted as outlined below:

 The Spare Parts List shall be submitted in an electronic spreadsheet format.

 The language used shall be English.

 List all equipment (tagged/untagged) and its parts within their scope of supply, and this shall include all Priced Spare Parts, repairable and replaceable, whether recommended for stock or not.

 All relevant datasheets, drawings, catalogues, and manuals shall be provided against each PO Spare Parts dossier. Highlight or otherwise mark so that the parts on the Spare Parts List can be easily found in the documentation.

 Conduct a QA/QC check prior to submission to ensure all references datasheets, drawings,

catalogues, and/or manuals are available against each PO Spare Parts dossier.

 Ensure that all mandatory requirements are filled in the Spare Parts dossier, i.e., “Equipment Model Number”, “Part Description”, “Material Specification”, “EPC Contractor/Manufacturer Drawing Number”, “Part Quantity Per Equipment”, “OEM and OPM Part Number”, “OPM Name (i.e., real manufacturer name)” ” Unit of Measure (UOM)”, and “Unit Price”. These shall be indicated in the appropriate columns of the Spare Parts List dossier.

 For

the purchase of Bulk Piping Materials

(e.g., Manual Valves/Non-Return Valves/Strainers/Traps/etc.) for each PO release, a Spare Parts List dossier shall be issued utilizing the same part number across all PO releases for spare parts that are interchangeable. Supplier must also provide piping specifications and valve identification numbers assigned by the Company, total valve quantity, etc., as per Company template.

7 SPARE PARTS DOSIER WORKFLOW

 CONTRACTOR to finalize the list of PO items with COMPANY where the development of

Spare Parts Lists is applicable.

 The List of applicable PO Items required for the Spare Parts Lists will be provided to Contractor’s Engineering Disciplines and Procurement along with the Instructions to Suppliers/Vendors.

COMP3-SPM-PE-PLN-00002_B

Page 15 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

 CONTRACTOR’s Engineering Discipline and Procurement shall advise the VENDOR after PO award to inform the applicability of Spare Parts Lists and provide the Instructions outlining the responsibilities of the Supplier/Vendor for providing a detailed Spare Parts List dossier.

 Vendor shall prepare and submit the Spare Parts Dossier complete with information necessary

as per the instructions provided to them by CONTRACTOR.

 Upon receipt of Spare Parts Dossier, the CONTRACTOR shall review the dossier for

completeness.

 The CONTRACTOR shall send to the Supplier any comments if applicable and expedite

VENDORs to re-submit the dossier with corrections as per comments.

 Once the Spare Parts Dossier is deemed acceptable by CONTRACTOR, the Dossier will be issued to COMPANY for their review and approval. Upon all clarifications are resolved, COMPANY OES will recommend 2 year spares recommendation quantities in RSPL and submit final RSPL to COMPANY PMT for purchase.

COMP3-SPM-PE-PLN-00002_B

Page 16 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

Figure 7.1: Spare Parts Dossier, Receiving/Inspection Flowchart

7.1 Reports

The CONTRACTOR shall issue a Spare Parts Dossier Report to COMPANY (PO-wise). This Status Report shall be continuously updated and submitted to COMPANY as requested.

8 PROCUREMENT PROCESS

COMP3-SPM-PE-PLN-00002_B

Page 17 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

In order to ensure the proper Procurement Process for the spare parts delivery, CONTRACTOR will prepare and monitor its implementation of the related procurement plan and procedures.

For further details, refer to below listed documents.

 Project Procurement Plan  Expediting Procedure  Project Vendors and Subcontractors Qualification Procedure  Project Quality Plan

8.1 Care, Custody, And Control

As per Exhibit 5, Section 4.3.10.2, CONTRACTOR will maintain care, custody, and control and shall be responsible for warehousing and preservation (as required) of all spares and operating supplies until delivery to COMPANY prior to READY FOR STARTUP for the associated Mechanical Acceptance Package (MAP) (or part thereof).

For the transfer of care, custody, and control from CONTRACTOR to COMPANY for remaining spares and supplies shall be at time of acceptance of the spares and supplies by COMPANY at designated location.

COMP3-SPM-PE-PLN-00002_B

Page 18 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

9 APPENDICES

Appendix 1 Recommended Spare Parts List (RSPL) Template

Cover Sheet Template

COMP3-SPM-PE-PLN-00002_B

Page 19 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

COMP3-SPM-PE-PLN-00002_B

Page 20 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

Cover Sheet Sample

COMP3-SPM-PE-PLN-00002_B

Page 21 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

Equipment Detail Sheet Template

Equipment Detail Sheet Sample

Equipment Details Sheet Sample – Exclusively for Manual Valves

COMP3-SPM-PE-PLN-00002_B

Page 22 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

Spare Parts Sheet Template

NOTE: The Spare Parts List shall be reviewed for Lifecycle spares, and purchase is only for 2-year Operating spares. The PMT will purchase the OES-approved 2-years Operating spares and hand over to the Qatar Energy LNG Warehouse.

Spare Parts Sheet Sample

COMP3-SPM-PE-PLN-00002_B

Page 23 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

QA/QC Requirements for Material Receiving Inspection

COMP3-SPM-PE-PLN-00002_B

Page 24 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

Appendix 2 Lube Template and Lube Sample Sheet

Lube Template

NOTE: The project shall arrange the Lubes list in this format, which includes Oil, Grease, Solvent, Solution, etc.

Initial fill and consumption is project scope, and it shall last until the Operational Acceptance

Certificate (OAC) is granted.

Lube Sample Sheet

COMP3-SPM-PE-PLN-00002_B

Page 25 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

Appendix 3 Chemical Template and Chemical Sample Sheet

Chemical Template

NOTE: The Project shall arrange the Chemicals/Catalyst list in this format. Initial fill and consumption is project scope, and it shall last until the Operational Acceptance Certificate (OAC) is granted.

Chemical Sample Sheet

COMP3-SPM-PE-PLN-00002_B

Page 26 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

Appendix 4 Special Tools Template and Special Tools Sample Sheet

Special Tools Template

NOTE: The Project shall arrange the Special tools list in this format.

PMT to follow:

  1. All lifting tools shall have parent equipment load test certificates

  2. Arrange supporting documents for all special tools

  3. The Project shall handover all Tools identified and purchased with main Equipment PO to

Qatar Energy LNG Warehouse for future maintenance

Special Tools Sample Sheet

COMP3-SPM-PE-PLN-00002_B

Page 27 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

Appendix 5 Blinds & Spacers Template and Sample Sheet

Blinds & Spacers Template

NOTE: The Project shall arrange the Blinds/Spacers list in this format.

PMT to follow:

  1. The Project shall ensure to manufacture all Blinds and Spacers in line with procedure TCH-AIG-

PRC-088 Lifting Lug Welding and Testing – for Spades, Spacers and Blind Flanges

  1. Blinds/spacers shall have lifting lugs and be load-tested as per procedure TCH-AIG-PRC-088 prior

to handover to the Qatar Energy LNG Warehouse for future maintenance

  1. All relevant Certificates shall be arranged during handover

Blinds & Spacers Sample Sheet

COMP3-SPM-PE-PLN-00002_B

Page 28 of 29

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

SPARE PARTS MANAGEMENT PLAN

Appendix 6 Piping Gasket Template and Piping Gasket Sample Sheet

Piping Gasket Template

NOTE: The Project shall arrange the Piping Gaskets list in this format.

PMT to follow:

  1. The PMT shall purchase new Piping and insulation gaskets identified by OES and hand over to

the Qatar Energy LNG Warehouse for future maintenance 2) All relevant Certificates shall be arranged during handover

Piping Gasket Sample Sheet

NOTE: Update installed quantity if item tag is not available.

NOTE: Insulation gasket kit shall be included in the Piping Gasket List.

COMP3-SPM-PE-PLN-00002_B

Page 29 of 29