Infinity

Not logged in
Home

❯

Reference Examples

❯

Q 32705 Saipem COMP3

❯

RFQ Files

❯

COMP3 SPM PO PRC 00005_B

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

COMPANY Contract No.: LTC/C/NFP/5129/20 CONTRACTOR Project No.: 033764

ASSET

: NFPS

Document Title

:

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

COMPANY Document No.

: COMP3-SPM-PO-PRC-00005

CONTRACTOR Document No.

:

033764-Z-Z-00-SPM-CH-P-10006

Discipline

: PROCUREMENT

Document Type

: PROCEDURE

Document Category/Class

Document Classification

:

:

1

Internal

B 17-Jan-2025

Issued for Approval

A 03-NOV-2024

Issued for Review

REV

DATE

DESCRIPTION OF REVISION

Caleffi Giacomo 20-Jan-2025 Caleffi Giacomo MATERIAL MANAGER Caleffi Giacomo

Landoni Giovanni 20-Jan-2025 Landoni Giovanni SUPPLY CHAIN MANAGER Landoni Giovanni

ETERNO Francesco PROJECT DIRECTOR ETERNO Francesco

PREPARED BY REVIEWED BY

APPROVED BY

Saipem S.p.A

www.saipem.com

THIS DOCUMENT IS PROPERTY OF QatarEnergy LNG. THIS DRAWING OR MATERIAL DESCRIBED THEREON MAY NOT BE COPIED OR DISCLOSED IN ANY FORM OR MEDIUM TO THIRD PARTIES, OR USED FOR OTHER THAN THE PURPOSE FOR HICH IT HAS BEEN PROVIDED, IN WHOLE OR IN PART IN ANY MANNER EXCEPT AS EXPRESSLY PERMITTED BY QatarEnergy LNG.

COMP3-SPM-PO-PRC-00005_A

Page 1 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

REVISION HISTORY

Revision Date

Revision Description

A1

01-OCT-2024

Issued for IDC

A

B

03-NOV-2024

Issued for Review

17 –Jan -2025

Issued for Approval

HOLDS LIST

Hold No

Hold Description

nil

COMP3-SPM-PO-PRC-00005_B

Page 2 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Table of Contents

1

INTRODUCTION … 6

1.1

1.2

Project Objective … 6

Project Scope … 6

2

DEFINITIONS AND ABBREVIATIONS … 9

2.1

2.2

Definitions … 9

Abbreviations … 11

3

REGULATIONS, CODES AND STANDARDS … 12

3.1

3.2

3.3

Company References … 12

Project Documents … 12

Standards … 12

4

5

6

SCOPE AND PURPOSES … 13

PACKING, MARKING AND SHIPPING DOCUMENTS … 14

PACKING GENERAL REQUIREMENTS … 15

6.1

6.2

6.3

6.4

package related to goods classified dual use … 15

General Notes For Packing … 15

Packing Sizes and Type Notes … 16

Preparation of the goods for packing … 17 Partial Dismantling … 18 Padding Of Fragile Parts … 18 Securing Movable Parts … 19 Cleaning … 19 Primary Preservation … 19 Protection of Openings … 19 Flexible Connection and Small Loose Parts … 20 Rust Prevention … 20 Spare Parts … 21 Other Instructions … 21

6.4.1 6.4.2 6.4.3 6.4.4 6.4.5 6.4.6 6.4.7 6.4.8 6.4.9 6.4.10

7

INTERNAL PACKAGING … 22

7.5

7.6

7.7

Aluminum Foil And Desiccants … 23

Protective Coatings … 23

VCI Method (Volatile Corrosion Inhibitor) … 24

8

EXTERNAL PACKAGE … 24

8.1

8.2

Inland packing (Domestic) … 24

Seaworthy packing … 24

8.3

Packing Construction Materials … 25 8.3.1 Wood … 25

COMP3-SPM-PO-PRC-00005_B

Page 3 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

8.3.3 8.3.4

Plywood … 26 Cardboard (flexible box) … 27

8.4

8.4.1 8.4.2 8.4.3 8.4.4

Instrumentation And Supporting Technology … 27 Humidity indicator … 27 Tilt & Shock and vibration indicator … 27 Shock Recorder System … 27 Thermal Recorder and Chillers … 27

9

PACKING STYLES AND CONSTRUCTION FEATURES … 28

9.1

9.2

9.2.1 9.2.2 9.2.3 9.2.4 9.2.5 9.2.6

Stackability … 28

TYPES OF PACKING … 28 Boxes / Cases … 29 Crates … 30 Bundles … 30 Saddles… 31 Unpacked Material … 32 Lifting Devices … 33

9.3

Dynamic loads … 33

10

PACKING OF GOODS BY CATEGORY … 35

10.1

Columns, Heat Exchangers, Pressure Vessels and Tubular Equipment … 35

10.2

Complete Plant Packages and Modules … 36

10.3

Plates … 37

10.4

Air Coolers … 38 Loose parts … 38 Assembled … 39

10.4.1 10.4.2

10.5

Transformers … 39

10.6 Machinery … 40

10.7

Electricals … 41 Panels … 41 Cables … 42 Cables Trays … 43

10.7.1 10.7.2 10.7.3

10.8

Piping … 43 Carbon steel, alloy steel, galvanized pipes and EXTERNALLY COATED piping … 43 Stainless steel, clad, cast iron, aluminum and plastic pipes … 44 Flanges, Fitting, Valves … 44 Bolts, Nuts and Washers … 45 Prefabricated Piping … 46

10.8.1 10.8.2 10.8.3 10.8.4 10.8.5

10.9

Steel Structures … 46

10.10

10.11

10.12

10.13

Vehicles … 47

Welding Electrodes … 47

Refractory Bricks and Element … 47

Mineral Wool / Foam Glass … 48

COMP3-SPM-PO-PRC-00005_B

Page 4 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

10.14

10.14.1

Hazardous GOODS, Chemical Products Y-Catalysts … 48 Lubricants … 48

10.15

10.16

10.17

Radioactive Materials … 48

PPE (personal protective equipment) … 48

BOP (blow out preventer) … 49

11

SHIPPING DOCUMENTATION … 49

11.1

Packing Lists … 49

11.2

Transport Drawings … 49

12

PACKING INSPECTION … 50

12.1 General … 50

12.2

Reporting … 50

13

14

15

MARKING INSTRUCTIONS … 51

STORAGE RECOMMENDATIONS … 52

ATTACHMENTS … 53

15.1

Attachment A - Standard tag for project cargo … 54

15.2

Attachment B – ISPM 15 Marking … 55

15.3

Attachment C - Marking Symbols … 57

COMP3-SPM-PO-PRC-00005_B

Page 5 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

1

INTRODUCTION

The North Field is the world’s largest natural gas field and accounts for nearly all the State of Qatar’s gas production. The principal objective of the NFPS projects is to sustain plateau from existing QatarEnergy LNG Operation – S1, S2, S3, N1 and N2 , production areas by implementing an integrated and optimum investment program consisting of subsurface development, pressure drop reduction steps and compression.

NFPS projects comprise 3 main investment programs:

  1. Investment #1: Drilling and Associated Facilities [WHP12S/ WHP13S/ WHP14S/

WHP12N/ WHP13N]

  1. Investment #2: Trunk line Looping and Intra-field pipeline looping [32” PL1LN, 32”

PL1LS, 38”PL610LS]

  1. Investment #3: Compression Complexes and associated facilities [Phase 1 CP6S & CP7S; Phase 2: CP8S & CP4N; Phase 3: CP4S & CP6N Phase 4: CP1S & CP1N]

Drilling and Looping, Investments #1 and #2, projects are in execution phase and are being executed as I1P1, EPCOL Projects except for WHP13N, which will be part of NFPS Compression Projects execution which compromises total up to 9 COMPs.

1.1 Project Objective

The objective of this Project includes:

• Achieve standards of global excellence in Safety, Health, Environment, Security and

Quality performance.

• Sustain the Qatarenergy LNG North Field Production Plateau by installing new RPs and one WHPs to support new Compression Complex facilities CP6S & CP7S and pre-installed facilities for future Compression Complex facilities including but not limited to CP4N & CP8S tie-in with integration to the existing facilities under Investment #3 program.

• Facility development shall be safe, high quality, reliable, maintainable, accessible,

operable, and efficient throughout their required life.

1.2 Project Scope

The Project Scope includes detailed engineering, procurement, construction, brownfield modifications, transportation & installation, hook-up and commissioning, tie-in to EXISTING PROPERTY and provide support for start-up activities of the following facilities and provisions for future development. The WORK shall be following the specified regulations, codes, specifications and standards, achieves the specified performance, and is safe and fit‐for‐ purpose in all respects.

Facilities - 1A

• RP5S RP with 2 x 28” CRA clad pipelines to RP7S and 2 subsea composite Cables

and associated J tubes from RP7S to RP5S & from CP7S to WHP13S.

• New Fuel Gas 8” CRA Spur-lines and flanged risers from Subsea skid to RP7S

COMP3-SPM-PO-PRC-00005_B

Page 6 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

• Hook-up and brownfield modification at WHP5S/RP5S bridge connection & WHP13S/CP7S Composite cable tie-in and E&I integration including RGA Control modification

• Pipeline decommissioning of 28” CS PL5S including associated demolition work at

WHP5S

Facilities - 2A

• RP6N RP with 1x28” CRA clad pipeline to WHP13N, 2 Subsea composite cables and

associated J tubes from WHP12N to RP4N and RP6N to WHP13N. • New fuel gas spur-line and flanged riser from subsea skid to RP6N • WHP13N Topside • Hook-up and brownfield modification at WHP6N/RP6N, RP4N- HPU-Umbilical and tie- in, WHP12N-new J tube installation, E&I migration, WHP6N/RP4N/WHP4N-E&I migration (Pre-CP4N), WHP13N and RP6N interconnection to NFB.

Facilities - 3A

• RP9S RP with 1x28” CRA clad pipeline to RP4S, • Hook-up and brownfield modification at RP4S/WHP9S, Modifications to integrate

RP9S to the RGA control network.

• Pipeline decommissioning of 28” CS PL9 to WYE on existing 38” trunkline PL48

including associated demolition work at WHP9S.

Facilities - 1B

• New fuel gas spur-line and flanged riser from subsea skid to RP4N • Fiber Optic Cable from RP6N to onshore LFP East, RP6N to RP4N and RP6N to LQ6S. • Hook-up and brownfield modification at RP6N Composite and FO Tie-ins NFB-PU (East)- FO Tie-in

(East)/BVS

Power & Control modifications, LQ6S/LFP Controls/Telecoms Integration

Facilities - 2B

• RP5N RP with 2 x 28” CRA clad pipelines to RP4N, 1 x 28” CRA clad pipeline to RP6N and 2 subsea composite Cables and associated J tubes from WHP12N to RP5N & from RP6N to RP5N.

• Hook-up and brownfield modification at WHP5N- RP5N Bridge connection, WHP12N Composite cable tie-in, RP4N Intrafield pipeline Hook up PL54 N/LN and E&I integration including NFB-PU Power & Control modifications

• Pipeline decommissioning of 2 x 16” PL56/PL54 Subsea Spur line from WHP5N to

reducing barred tee in subsea tie-in skid on PL6 / PL4.

Facilities - 3B

• 2 subsea composite Cables from RP4S to RP9S & from RP4S to WHP12S (with J-

tube)

• New Fuel Gas 8” CRA Spur-lines and flanged risers from Subsea skid to RP4S • Hook-up and brownfield modification at WHP12S/ RP9S/ RP4S Composite cable tie-

in, Spurline riser installation at RP4S RGA Power & Control modifications.

Facilities - 4B

• 2 subsea composite Cables from CP8S to RP11S & from RP8S to RP11S (with J-

tube), FO Cable from RT2 to Barzan WHP1.

COMP3-SPM-PO-PRC-00005_B

Page 7 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

• New Fuel Gas 8” CRA Spur-lines and flanged risers from Subsea skid to RT2. • Hook-up and brownfield modification at WHP8S/ WHP11S for Test separator Internal Upgrade and MEG system modification, Spur lines, Power & Control Tie-ins on RP8S, RP11S/WHP11S-Tie-in (Power and Control), RGA Power & Control modifications.

Facilities - 5B

• 2 subsea composite Cables from RT2 to WHP3S & from RT2 to WHP2S (with J-tube) • New Fuel Gas 8” CRA Spur-lines and flanged risers from Subsea skid to RP8S • Hook-up and brownfield modification at BRZ-WHP1 – FO cable tie-in, WHP2S/ WHP3S/ RT&RT2 Composite cable tie-in and associated modification, RGA Power & Control modifications.

Facilities - 6B

• RP3S RP with 1x24” CRA clad pipeline to RT2 with Stalk on risers, • Hook-up and brownfield modification at RT2 for 24” Intrafield pipeline and Composite/FO cable Hook-up, WHP3S for Production diversion and Utilities, Power and ICSS Hook-up, WHP2S for Composite Cable Tie-ins and Power & Control Integration RGA Power & Control modifications. topside existing and

In-situ abandonment of existing Topside/subsea Composite Cables RT-WHP2S, RT-WHP3S, Topside/Subsea FO cable RT-BRXWHP1.

• Decommissioning at

Figure 1.2.1: NFPS Compression Project COMP3 Scope

COMP3-SPM-PO-PRC-00005_B

Page 8 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

2 DEFINITIONS AND ABBREVIATIONS

2.1 Definitions

Definition

Description

COMPANY

QatarEnergy LNG.

CONTRACTOR

Saipem S.p.A.

DELIVERABLES

FACILITIES

MILESTONE

PROJECT

SITE

All products (drawings, equipment, services) which must be submitted by CONTRACTOR to COMPANY at times specified in the contract. All machinery, apparatus, materials, articles, components, systems and items of all kinds to be designed, engineered, procured, manufactured, constructed, supplied, tested and permanently installed by CONTRACTOR at SITE in connection with the NFPS Project as further described in Exhibit 6.

fabricated,

A reference event splitting a PROJECT activity for progress measurement purpose.

COMP3 - NFPS Offshore Riser/Wellhead Platform & Intrafield Pipelines Project

(i) any area where Engineering, Procurement, Fabrication of the FACILITIES and (ii) the area offshore required for installation of the FACILITIES in the State of Qatar

SUBCONTRACT

Contract signed by SUBCONTRACTOR and CONTRACTOR for the performance of a certain portion of the WORK within the Project.

SUBCONTRACTOR

Any organization selected and awarded by CONTRACTOR to supply a certain Project materials or equipment or whom a part of the WORK has been Subcontracted.

WORK

Refer to article 2 of CONTRACT AGREEMENT.

WORK PACKAGE

The lowest manageable and convenient level in each WBS subdivision.

DELIVERY TERMS

FREIGHT FORWARDER

International standard delivery terms (INCOTERMS 2010) that define the transfer of title of GOODS and the responsibilities of each party in the agreement. The PURCHASE ORDER details the Delivery Terms under which the SUPPLIER is obligated to deliver the GOODS. A person or persons, firm or company (International Transportation Company or Third-Party Logistics Service Company) that has undertaken to perform the transport services from SUPPLIER’s contractual delivery point to the SITE.

COMP3-SPM-PO-PRC-00005_B

Page 9 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

GOODS

PACKAGE (or Packing Unit)

Packaging

or

PACKING

PACKING LIST

PROJECT

PURCHASE ORDER

PURCHASE ORDER DOCUMENTS

in

listed

All equipment, materials, articles or any other property or parts to be provided to the PURCHASER by the SUPPLIER under the PURCHASER ORDER DOCUMENTS and in addition includes the the PURCHASER ORDER relevant documentation DOCUMENTS. Any outside container such as a box, crate, barrel, drum, bundle or other such facility used to enclose or protect the items in transit and/or storage. All the activities related to the preparation, preservation and protection of the GOODS purchased, in order to prevent loss or damage along the transport chain (by road, rail, air or ocean) and storage for a minimum of 12 months after date of packing. Prospect bearing the package identification data (number, marking, weight size and characteristic) together with ones about the items it contains.

The project in which GOODS are to be used by PURCHASER and/or by PURCHASER’s client.

The written agreement between PURCHASER and SUPPLIER for the performance of the SUPPLY including any written amendment thereof. All the documents related to PURCHASE ORDER including the itself, this Specification and any other PURCHASE ORDER document referred to in the PURCHASE ORDER.

PURCHASER

The person so named in the PURCHASE ORDER.

SUPPLIER

SERVICES

The person appointed by PURCHASER to perform the SUPPLY and so named in the PURCHASE ORDER.

Technical assistance services and any all services including design, inspection, testing, training, expediting, quality assurance and control, painting, packing, delivery, and installation or fixing, in connection to the GOODS, a specified or required under the PURCHASE ORDER DOCUMENTS.

SITE

All the locations or areas where the PROJECT is performed.

SUPPLY

The delivery of the GOODS and the performance of the SERVICES specified in the PURCHASE ORDER, to be carried out by the SUPPLIER in accordance with Terms and Conditions of the PURCHASE ORDER DOCUMENTS.

COMP3-SPM-PO-PRC-00005_B

Page 10 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

2.2 Abbreviations

Code

ADR

Definition

European Agreement Concerning the International Carriage

BS 1133-8

British Standard Institution – Boxes, Cases and crates

BS 3482-6

British Standard Institution – Method of test for desiccants

DIN 55473

Weight of desiccant bags

DIN 55474

Determine the number of units desiccants bags required

HPE

IATA

IMO

German Federal Association for Wooden Packaging, Pallets and Export Packaging International Air Transport Association – Dangerous GOODS regulations

International Maritime Dangerous GOODS code

INCOTERMS 2010

Any mode of transport including multimodal

ISPM15 FAO

International Standards for Phytosanitary Measures

MIL C 104 C

USA – Military specification, Crate’s wood, Lumber and Plywood Sheathed Nailed and Bolted

MIL D 3464 D

Desiccants activated Bagged packaging Unit

MIL P 116 E

Determine the number of units of bagged desiccant

MIL – PRF – 131K CLASSE 1 NEF – ES – 001 – 09 FAPROMA

RID

SEI

Moisture barrier Bag, Flexible Barrier Material

Spanish packing Standards

(Rules for international transport of dangerous materials by Rail)

Cahier des charges (Syndicat de L’emballage Industriel – France)

UNI 10858 – 1

Terms, definitions and requirements

UNI 10858 – 2

UNI 10858 – 3

Special wood packages for bulk capacity between 300 kg and 10.000 Kg with and maximum size of (600x250x250 cm) Special wood packages for bulk capacity less than 300 kg and maximum size of (200x100x100 cm)

UNI 10858 – 4

Supporting operative packages for transport

UNI 9151 – 1

Terms and definitions

COMP3-SPM-PO-PRC-00005_B

Page 11 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

UNI 9151 – 2

Analysis of requirements

UNI 9151 – 3

Design and manufacturing

UNI EN ISO 780

Packaging – Pictorial marking for handling of GOODS

3 REGULATIONS, CODES AND STANDARDS

3.1 Company References

S. No Document Number

Title

LTC/C/NFP/5129/20

Contract Agreement

EXHIBIT 5

Project Instructions

PRJ-PJL-PRC-004

PRJ-PJL-PRC-005

Facilities Engineering and Vendor Document Numbering Procedure Facilities, System and Unit Number Codes and Descriptions Procedure

PRJ-PJL-PRC-006

Project Information Handover Procedure

PRJ-PJL-PRC-048

PRJ-PJL-PRC-049

Facilities Documentation Metadata Requirements Procedure Project Information Handover, Verification and Acceptance Procedure

3.2 Project Documents

S. No Document Number

COMP3-SPM-PO-PRC-10003 Expediting Procedure

COMP3-SPM-PO-PRC-00004 Transport & Customs Procedure

TBC

Specification for Preservation

3.3 Standards

S. No Document Number

Title

ISO 9001:2015

Quality Management System Requirements

COMP3-SPM-PO-PRC-00005_B

Page 12 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

4 SCOPE AND PURPOSES

This Specification covers a set of standards relating to the handling, storage, packing, preservation, marking and shipping documentation of GOODS provided by SUPPLIERs from its premises up to the final destination. These standards are the minimum requirements to be complied by the SUPPLIER for the packing, protection, marking and shipping documents of GOODS. This instruction has been prepared to assure the packing quality and to confirm the minimum requirements of Code & Standards. The present Specification SHALL be applied to the GOODS procured by the PURCHASER. The following guidelines and instructions, showed in the present Specification, SHALL be considered as an integral part of:

• RFQ (Requests for quotation). • PO issued by the PURCHASER to the SUPPLIERs.

The guidelines stated in the present Specification, SHALL be considered as the minimum requirements. If the instructions stated in the present Specification would be considered incomplete, the SUPPLIER SHALL take1 any additional measures2 MAY BE required to ensure that SUPPLIER’S obligations and responsibilities are fulfilled. The PURCHASER SHALL reserve the right to instruct SUPPLIER on additional packing features, if necessary.

Any additional activities may incur due to SUPPLIER non-compliance with present Specification instructions, SHALL be at SUPPLIER costs and care, including any necessary recovery action to ensure prompt (on schedule) shipment and the issuance of clean on-board transportation documents (bill of lading, etc.).

The SUPPLIER SHALL be accountable for all damages due to improper packing. Before proceeding with the packing of the GOODS, SUPPLIER shall immediately communicate3 to PURCHASER any identified conflicts between the requirements stated in the present Specification and any other PO related documents.

1 The best packing practice SHALL be proposed by SUPPLIER to CONTRACTOR in order to ensure that all the GOODS SHALL be delivered at the destination with no damages. 2 On the basis of its experience and lessons learned. 3 For clarification.

COMP3-SPM-PO-PRC-00005_B

Page 13 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

5 PACKING, MARKING AND SHIPPING DOCUMENTS

Packing is mainly requested to protect/preserve the GOODS from damage during transportation, including multiple-handling and storage. All the GOODS SHALL be shipped in suitable PACKING UNITS for preservation of them from weather and marine environment (corrosion, rain, moisture, etc.)4 conditions. Hereinafter some general features for the packing:

• Packing construction SHALL be carried out in accordance with the most up-to-date methods, standards and rules. As a minimum requirement, applicable rules shall be referred to departure and destination countries as well as at the transit countries.

• The packing SHALL be suitable to withstand loading, transit, unloading and handlings as per

environmental conditions from the point of departure to the final delivery point.

• The GOODS SHALL be properly fastened inside the package to prevent displacements, rotations, or vibrations during transport. Heavy GOODS5 SHALL be fastened to the package by proper bolting.

• The SUPPLIER SHALL attaches, to the final package, three (3) copies of special instructions covering in detail: proper care, maintenance, and on-site storage procedures for the GOODS. Moreover, these instructions SHALL be duly submitted to the PURCHASER prior to shipment.

• The SUPPLIER is solely accountable for proper packing, marking and preservation of the GOODS with regards to handling, transport, transhipment and storage at the final destination. The SUPPLIER SHALL be fully liable for the provision of: o o o o SUPPLIER shall be considered accountable of inadequate or insufficient packing or

Sufficient and adequate packing and protection of contents for an open yard storage6. Completeness of contents. Correct preparation of the packing list and other related shipping documents.

shipping documentation, being charged of any related extra-cost may incur.

• The application of suitable packing methods, (including relative materials and manpower) SHALL be at the sole SUPPLIER responsibility. In case of damages or loss due to inappropriate packing, noticed at delivery point (and/or at transit points), the GOODS SHALL be replaced or repaired at SUPPLIER’s expense.

4 In consideration of the climate zones crossed during the transit. 5 Such as motors and generators. 6 For at least twelve (12) months after the date of packing, as general rule.

COMP3-SPM-PO-PRC-00005_B

Page 14 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

6 PACKING GENERAL REQUIREMENTS

6.1 package related to goods classified dual use

Some commodities are classified as Dual Use GOODS, meaning they may be used for civilian or commercial activities as well as for Military Applications. The Dual Use classification derives from the technical specification of the product contained within the Regulations relating to dual use in force in the countries where the export takes place and within the Customs Nomenclature.

The Dual Use commodities could be subject to additional inspection by Customs Authorities therefore, in order to minimize any possible delays, they SHALL be packed separately and segregated, whenever possible, from all other non-dual use items.

The SUPPLIER is accountable for notifying to CONTRACTOR the presence of dual use items, submitting the relevant technical documents and information, such as the Dual Use codes/references, necessary to ask for and obtain the export licenses from the competent Governmental Authorities.

6.2 General Notes For Packing

In general, packing SHALL be suitable for shipping GOODS by any means of transport such as sea7 freight, airfreight, road or railway. The following table indicate the acceleration forces depending on the mode of transport. In particular, Rail shipment shall be in accordance with API RP 5L1, truck shipment shall be in accordance with API RP 5LT, and water shipment shall be in accordance with API RP 5LW.

of

Backwards/forwar Means ds acceleration transport 1,0 g Road transport Railway transport 4,0 g Maritime transport 0,4 g 1,5 g Air freight

Lateral acceleration 0,5 g 0,5 g 0,8 g

Vertical acceleration 0,5 g 0,3 g 1,0 g 3,0 g

Table 1: Accelerations during transport by different means

Packing of the GOODS SHALL be provided taking in consideration of the following key factors:

• Protection requirements. • Hygroscopic properties. • Means of transport to be used for shipping. • Transport route and duration8. • Anti-corrosion precautionary requirements. • Climatic conditions at final destination. • Centre of gravity and weight issues. •

free iron protection to avoid direct steel contact especially with CRA materials

7 Conventional or container. 8 Including climate zones crossed, storage/stop-over points and transshipments.

COMP3-SPM-PO-PRC-00005_B

Page 15 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Loading, stuffing and lashing the GOODS into containers SHALL be included in SUPPLIER scope. In general, all equipment and relative materials should be packed in closed wooden frame box.

Packaging shall be suitable to preserve the GOODS, for at least 12 months, after date of packing as general rule. SUPPLIER SHALL be accountable to provide PURCHASER all the necessary instructions for storage and preservation. SUPPLIER SHALL be accountable of any damages due to wrong or missing instructions and documentation.

6.3 Packing Sizes and Type Notes

The SUPPLIER SHALL be accountable for the packing and handling of the GOODS (to the PO delivery point), as per contractual delivery terms. GOODS to be divided in two below main groups on the basis of below dimensions and weight:

Dimensions [m]: Gross weight [tons]: 22,0.

11,8 x 2,3 x 2,1 (length x width x height).

GOODS SHALL be represented by items called:

IG (In Gauge cargo)

• GOODS to be transported represented by items9 having the usual road size (all the dimensions and weight within defined above).

• OOG (Out Of Gauge cargo) Each item exceeding even only one of the dimensions and weight defined above.

• Notes On Containerized Cargo (ISO Containers)

ISO Containers are NOT considered as packing but are classified as mean of transport (as a mode of dispatching the GOODS). As a consequence, the usage of ISO containers does not relieve SUPPLIER from its responsibility to provide suitable packing as specified in the present Specification.

In addition, the following requirements have to be considered when GOODS are stowed into ISO- Containers at the SUPPLIER premises:

  • The containers must be in good and sound general condition10. Shipper Owned Container (S.O.C.) or Carrier Owned Containers (C.O.C.) SHALL be used with written approval by PURCHASER.

  • Shipper Owned Containers (S.O.C.) SHALL have a valid C.S.C. homologation (as per IMO’s CSC Standard), for a minimum of 12 (twelve) months, after date of packing, certified by

9 Except for dangerous or hazardous items, each individual items SHOULD be packed into packages not less than 200 kg or not less than 0,5 cubic meters in volume in order to avoid theft and loss during transportation. Every package SHALL not exceed the dimensions as specified in the Material Requisition (where applicable) or in the standards in force in the countries involved during the transportation. 10 Wind and water tight, clean and free of smell or any other type of residues, all sealing and fittings in good order, easy opening doors, maximum 10 years of age.

COMP3-SPM-PO-PRC-00005_B

Page 16 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Lloyd or any other applicable authorized body. SUPPLIER SHOULD provide the C.S.C. homologation number/certificate to PURCHASER.

  • Stowing, lashing and securing of the GOODS inside containers must be executed by

SUPPLIER as per IMO’s CTU Standard.

If cargo of various sizes and weights is stowed together, overall PACKING UNITS stability shall be properly provided/improved. If cases or crates are stacked in several layers, the layer below must be able to withstand the total weight of the items stacked above.

If the cargo is loaded in open top containers or flat racks, the packaging must protect the GOODS from climate, weather conditions, handling and transhipments, during the main transport.

With regard to container loading, the following principles should be observed:

i. ii.

Total11 cargo weight SHALL not exceed the container allowable pay load. Volume optimization: SUPPLIER SHALL use best efforts to optimize the volume of each container, in accordance with applicable standards and regulation. Stowage into the container should be compact (as shown in pictures below).

iii. iv. Cargo securing must be provided in order to mitigate the effects of ship movements, such as rolling, pitching and yawing. The best way of securing cargo is to distribute it without any gaps over the entire floor. If gaps cannot be avoided, the space between the packaging and container walls must be filled using air bags, dunnage or other suitable stowage material. Individual cargo parts that do not fill up the floor must be secured by chocking and lashing. Lashing eyes are provided on the longitudinal beams on the floor, roof and corner posts. In case of pre-carriage by rail, special stuffing and lashing requirements of the rail operator(s) needed to be adopted (if any).

vi.

v.

Figure 1: Proper stowage of GOODS inside containers

6.4 Preparation of the goods for packing

11For each container.

COMP3-SPM-PO-PRC-00005_B

Page 17 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

The GOODS SHALL be prepared for packing purpose, in order to avoid any possible stresses during transportation. According to the selected type of means of transport, storage conditions and type of GOODS, this section shows the main guidelines to be followed by SUPPLIER before packing.

In general, all the surfaces of the GOODS to be packed SHALL be dry, clean and free from defects or production residues prior to packing. All threaded areas, except the CRA areas, SHALL be adequately greased and shielded from mechanical damages. Coating of CRA materials with rust protection (i.e. of the machined surfaces) is not allowed, as not suitable for use on CRA. Other type of machined surfaces SHALL instead be coated with an industry standard rust protection product, suitable for the requested application. All internals that are made of CRA are not to have lubricants as they will pit the CRA. Other internals parts of different type of machinery SHALL instead be treated with lubricants (rust preventatives) and oxidation inhibitors to protect the equipment from possible damages. Such protective materials SHALL be compatible with those that will be subsequently used in service.

Gasket contact surfaces for CRA materials are not to use rust protection. Any part that may be damaged by lifting, fastening, transportation and installation SHALL be removed and packaged in accordance with present Specification. All temporary supports and/or bracings and/or devices required for transporting or lifting SHALL be painted with a special colour for immediate identification.

In the next articles are listed the main activities that SHALL be provided (if applicable) concerning the preparations of the GOODS for packing.

Each supplier (or sub-supplier) SHALL submit packing details, including the Recommend requirements for packing and transportation.

6.4.1 Partial Dismantling

Dismantling of the GOODS may be necessary in order to: • Allow or simplify the handling of the GOODS. • Minimize the volume to be packaged, as well as shipped12. • Protect fragile components. • Avoid damage to the packaging.

GOODS may only be dismantled by SUPPLIER. Dismantling SHALL always subject to PURCHASER approval, in this case packing list shall be provided in both alternatives (dismantled and mounted).

6.4.2 Padding Of Fragile Parts

12 Optimizing transportation cost.

COMP3-SPM-PO-PRC-00005_B

Page 18 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Some types of GOODS MAY be subject to high mechanical stresses during transport. These types13 of GOODS SHALL be protected by damages through impacts, jolts or vibrations by the use of suitable padding.

6.4.3 Securing Movable Parts

Free14 parts must be secured by lashing down or using wedges and pads. These must be fixed to the main item before packaging. In case disassembled parts are not packed separately, they must be padded and firmly fixed to the main item or inside the packing.

6.4.4 Cleaning

The GOODS to be packed SHALL be free of manufacturing aids, production scrap metal and any possible corrosive material. Any holding liquids system (or equipment) must be purged before packing. Containers and piping systems SHALL be dried and hermetically closed. The SUPPLIER SHALL inform PURCHASER of the presence of such remaining liquids and their quantity. If SUPPLIER provided any anti-corrosion measures for the transport, PURCHASER SHALL be informed accordingly regarding the brand and type of used protection.

6.4.5 Primary Preservation

The GOODS SHALL be protected by corrosion during the transit. All equipment and materials and/or relative parts subject to corrosion, including machined parts, SHALL be coated with a proper rust preventative. All internal parts of machinery SHALL be treated with lubricant containing rust oxidation inhibitors to protect equipment from damages. Such lubricants SHALL be compatible with those that will subsequently be used in service and SHALL be identified by appropriate tagging. A “list of all lubricant and rust preventative” and “datasheet for anti-corrosion inhibitors” SHALL be provided with the packing list prior to shipment. Very fragile parts will be treated in their surface with suitable protective material, which cannot be washed off or crystallized by temperature changes, such as Tectyl, Rust-ban type or similar. The same protection may apply in case of sea shipment of stainless-steel equipment (that are not painted).

6.4.6 Protection of Openings

• Flanged openings for pressure vessels, reactors, heat exchangers, etc. SHALL be protected with bolted-on outside plywood (minimum 12 mm thick 4 bolts) with rubber gaskets between the flange and the plate. All flanged openings SHALL be wrapped with plastic waterproof tape.

• Butt weld connections SHALL be sealed with metal or heavy plastic cap, fully encompassing the end and over the body for some distance. It is forbidden the use of shrink-wrapping on open ends as they are not adequate for water protection.

13 Giving an Examples are electronic products, switching modules and micro mechanical products. Padding can also be used to guard protective films against perforation and friction damage caused by sharp corners of the packaged GOODS or other protruding elements. 14 Allowing displacements or rotations.

COMP3-SPM-PO-PRC-00005_B

Page 19 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

• All valve ends SHALL be protected with plastic caps; especially considering that the diameter for

most of the valves exceeds 24’’, marine plywood SHALL be used instead of plastic.

• Porous bags filled with desiccants SHALL be hung inside of the wooden or metal covers on all

major connections and openings.

• Unconnected pipe threads, to be used in normal operation, SHALL be closed with threaded metal

plugs or caps.

6.4.7 Flexible Connection and Small Loose Parts

• All flexible connections that could be subject to possible damage during shipment SHALL be disconnected and either tied to the main body or packed in separate boxes within the main package.

• Shaft Coupling:

o Flexible couplings SHALL be taken off and adequately supported and protected to prevent

damage.

o Rigid coupling SHALL be in accordance with the SUPPLIER’s recommendation to provide full

protection and safety in transit and storage.

• The SUPPLIER SHALL fix to the external of the package, on metal label, a list of the specific rust preventatives employed. The list SHALL include internal as well as external used rust preventatives with: name of the manufacturer, type number, and the locations where each product has been applied.

• The SUPPLIER SHALL also include in the package any special instructions deemed necessary for the removal or replacement of any rust preventatives, together with any special precautions to be taken to protect the equipment during storage period.

• Small or sophisticated parts of instruments and electric equipment SHALL be packed in waterproof wooden boxes and attention SHALL be made to prevent damage from moisture as well vibration during the transportation.

• If packages/ GOODS contains, vapour phase inhibiting oil, vapour phase inhibiting powder or silica gel, used to protect all internal metallic surfaces of equipment that are subject to corrosion. The type and quantity of them SHALL be clearly stated outside the equipment.

6.4.8 Rust Prevention

• Unless otherwise specified on the project requisition:

o unpainted machined metal surfaces. o gaskets contact surfaces of equipment flanges. o other surfaces which are normally not painted, both external and internal.

SHALL be cleaned, dried and coated with acceptable rust preventatives which will maintain a protective coating, for a minimum of 12 months, after date of packing.

• Regarding bulk materials (e.g., pipes, tube, flange, fitting, valve and etc.), the SUPPLIER SHALL propose the rust preventative which will maintain a protective coating for minimum twelve (12) months after date of packing.

• The SUPPLIER SHALL be fully liable to guarantee proper, sufficient and adequate rust

preventative.

• All cost whatever resulting from inadequate or insufficient rust prevention SHALL be fully charged

to SUPPLIER.

• The use of lubricants such as engine machine oils is strictly prohibited.

COMP3-SPM-PO-PRC-00005_B

Page 20 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

6.4.9 Spare Parts

Commissioning and erection spares SHALL be individually tagged and marked as “Commissioning Spare Parts” or “Erection Spare Parts” and SHALL be packed separated from the prime item(s) into separate inner boxes.

Spare Parts for TWO years operation SHALL be marked and tagged individually, covered with a suitable corrosion preservative, wrapped with greased paper and packed into separate inner boxes separately from the prime item(s)

• The boxes shall report the markings as specified and in addition with the words- “SPARE PARTS FOR TWO YEARS OPERATION”. The tag number of the spare part(s) SHALL be described in the packing list as an identification number to be recognized at the SITE.

• The purpose of tagging is to identify each equipment, materials, parts, tools, etc. shipped as cargo with the packing list and/or drawings. After filling necessary descriptions required in the format, the tag SHALL be attached to all individual equipment, material parts, tool, etc. (see attachment 14.8).

• The SUPPLIER’s own tag form is acceptable subject to the PURCHASER’s prior approval with regard to identification. Tags SHALL be filled out with ball-point pen in black with minimum information: o shipping tag number o PO number o project number.

An adequate quantity of moisture absorbent SHALL be added to protect the contents from corrosion for 12 months after the date of packing.

• For Packages/ Instrumented Skids:

o All loose parts shipped along with the main equipment, and its related auxiliary equipment (e.g., mechanical seals, level transmitters, flow meters, anti-surge system, etc.), must be packed separately by each discipline (mechanical, piping, electrical, instrument and etc.). Accordingly, the relevant discipline for each loose part SHALL be mentioned for easy identification and material control in the packing list for the effective execution of installation. o If small in quantity, all loose part may be packaged by separate rigid box or partition in the

box.

o When the same materials will be used for several units, they must be packed separately by

the unit for the effective material control on SITE.

6.4.10 Other Instructions

• All the parts subject to corrosion and other fragile parts must be wrapped into suitable foil with

added drying agent and packed into wooden boxes.

• The GOODS in boxes must be supported and secured against shifting and sliding which might result from sharp buffeting load and similar. Heavy parts such as motors and generators SHALL be securely fastened to the load-bearing member of bottom of the package by bolts. Anchorage of the GOODS to the PACKAGE SHALL be provided in order to prevent “slipping” and “tipping”. • The steel plates have to be lined with suitable cushion material to avoid scrubbing of the paint or

prime coating.

COMP3-SPM-PO-PRC-00005_B

Page 21 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

• Sensitive pipes due to material, wall thickness, surface treatment, etc., must be bundled and

packed in wooden boxes.

• All material SHALL be dry, clean and free from all defects, prior to packing protection against environmental corrosion/erosion caused by humidity, condensation, rain, dust, sand, salted air, and sea spray.

• All threaded areas SHALL be adequately greased and covered with adequate protective shield

to protect mechanical damage.

• Where twisting, bending or braking MAY happens due to mechanical transport loads, the GOODS must be supported or braced to make them suitable for a safety transport and/or disassembled by the SUPPLIER.

7

INTERNAL PACKAGING

Internal packaging purpose is to protect GOODS and/or equipment from shocks, weathering and environmental agents, preventing any damage of its contents or loss during transport. In addition, the packing must withstand the various handling operations from collection up to the delivery point, considering the inland transport conditions from the entry ports to the final destination. A proper communication between the SUPPLIER and PURCHASER is required in order to pack the GOODS using the most suitable packaging. In particular, SUPPLIER shall inform PURCHASER about the following means of protection:

•

If desiccant is being used, then indicator cards shall be used (or the desiccant itself is indicating)

• Protection of CRA materials from direct contact of the desiccant has to be implemented, as

wet desiccant tends to corrode CRA (crevice corrosion).

• The types of bags used must be affixed in such a manner that they do not come off and be

of such a material that they do not tear or break, even when wetted.

The following information will be required in order to define the most suitable packaging for each type of GOODS:

• GOODS features: type, size, number of units, mobile at loose parts.

• Packaging features: dimensions, type of base, type of jacking, type of latch.

• Features of the material to be used, physical/chemical and mechanical protection etc.

• Means of transport.

• Detail of the transport routing.

• Details of warehousing.

• Marking instructions.

• Other data or attached documents.

During transport (especially during overseas shipping), handling and storage of the GOODS may be exposed to intensive stresses such as rain, sea water, high air humidity and salt content, extreme temperatures, temperature fluctuation, chemical and biological agents, etc. The type and intensity of these stresses will depend on the transport routing, transit duration, interim storage and the properties of the packaged GOODS. Additional anti-corrosion measures will be required to protect the GOODS by all of these external environmental factors.

COMP3-SPM-PO-PRC-00005_B

Page 22 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

The SUPPLIER must inform the PURCHASER about the GOODS inclination to corrosion and which measures are required in order to preserve the GOODS properties. The packaging provider must also be advised if preliminary protection has already been applied and if so, whether this will have to be removed prior to packing. The SUPPLIER SHALL guarantee that the preliminary protections measures do not have any impact on the GOODS to be transported. The selected preservation method has to consider the features of GOODS to be transported. Three methods may be applied for preservation of GOODS to be packed:

• Use aluminium foil and desiccants.

• Use of protective PE foil films.

• Volatile Corrosion Inhibitor (VCI) method.

7.5

Aluminum Foil And Desiccants

According to MIL PRF-131 K and MIL D3464, flexible barrier material enclosure (with desiccants), are used to protect the packaged GOODS against air humidity during transport and stowage in order to prevent corrosion by mould and similar. The use of the flexible barrier material enclosure (waterproof packing) may consist of an operation aimed to create technical “vacuum” protecting sensitive GOODS against oxidation. The GOODS SHALL be anchored to the packing; spring lock and washers should be applied at the anchoring points at the holes made for passage of the bolts. Sheets of rubber foam material alternatively may be used. Out of gauge parts and sharp edges SHALL be properly padded to prevent wearing through or piercing of the enclosure. The air inside the barrier enclosure shall be exhausted, by extracting the air supply of moisture is decreased. Once the air is expelled, the barrier enclosure is welded. The drying of the remaining air inside the flexible barrier enclosure, is achieved by desiccants or moisture absorbers according to DIN 55473 or MIL D 3464 D. The required desiccants quantity shall be calculated in accordance with DIN 55474, or MIL P 116 E, for a maximum permissible ultimate humidity of 40%. The desiccants bags shall be placed in the upper section of the barrier enclosure and properly secured against falling. Direct contact between desiccant and packed goods is not allowed. The required amount of desiccants must be calculated in accordance with DIN 55474 or MIL P 116 E. The sealed film enclosure consists of vapour barrier material. Single sheets SHALL be heat-sealed together for Oversize/Overweight cargo. Desiccants must be placed or hung inside the package in such a manner, that contact to surface of the material to be packed is avoided at all times.

7.6

Protective Coatings

Protective coating SHALL be applied after cleaning and drying surfaces of the GOODS to be packaged. A suitable coating product has to be applied on the surfaces subject to corrosion. These products SHALL be applied by immersion, brushing or spraying. The solvent components will evaporate leaving a solid coating layer. This layer protects against corrosion, such as water and oxygen reaching the metal surface. According to specifications of the product to be applied, it MAY

COMP3-SPM-PO-PRC-00005_B

Page 23 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

remain active for a few days (in case of pre-or interim preservation) or for several years (final preservation). The removal of protective coatings from the packaged GOODS will be necessary at the end of transport and storage period.

7.7

VCI Method (Volatile Corrosion Inhibitor)

The VCI method functions through a vapour phase keeping product in a protective atmosphere inside the sealed protective enclosure. VCI molecules evaporate from the carrier material such as paper, film, foams or powered and saturate the surrounding air.

The molecules create a protective film on the layer of oxides that is present on all metal surfaces and inhibit the corrosion processes. A wide range of different VCI film types are existing as they differ in their protection effect on iron and non-iron metals as well as their alloys. Each single active agent is generally suited for only one type of metal or alloy. Therefore, the different agents are usually combined to offer a wider protection range. VCI carriers cannot be in direct contact with the CRA. Prior to packing, consultation with the VCI supplier may be required to exclude a potential reaction with the material of the GOODS. Removal of VCI after unpacking is not required.

8 EXTERNAL PACKAGE

8.1 Inland packing (Domestic)

The SUPPLIER must take caution for the packaging of materials, to be sent without intermediate handling and/or transshipment on the same country and/or neighbors. In these cases packaging MAY BE limited to protection of fragile parts. Anyway such kind of packing shall ensure the protection of the GOODS up to the arrival at SITE.

8.2

Seaworthy packing

The SUPPLIER SHALL provide all the packages to be compact and durable as much as possible. The minimum requested storage time is 12 months after date of packing. All PACKAGES SHALL be suitable to undertake all the external agents along the transportation chain up to (and including) storage at SITE. The PACKAGE design and construction SHALL in particular consider the following factors:

• Handling during loading at the production workshop, unloading at loading at ports, and at SITE

for, at least, 6 times.

• Outdoor storage after shipment to SITE. • Significant variation in ambient temperature/humidity during ocean shipment and storage. • Provisions for supporting and stacking of GOODS (packages) SHALL be included in the basis of

package design and construction.

• Packing style and gross weight of over 50 kg. SHALL have minimum 100 mm “under-beams” for

forklift clearance.

• Waterproof barrier material SHALL be inserted between upper and lower sheathing of the top

panel.

• “Under-beams” SHALL be provided at the bottom of skid, at height SHALL be minimum 100 mm.

Base skid SHALL be connected with header using bolt.

COMP3-SPM-PO-PRC-00005_B

Page 24 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

• Equipment/packages exceeding 5,0 tons gross weight SHALL be furnished with a shell plate of adequate thickness on areas where sling ropes and metal surfaces may come into contact with the package, as shown in below picture.

• SUPPLIER’s own experience and practice SHALL define any improvements to ensure GOODS safety. Observance of these minimum requirements does not constitute a limitation to SUPPLIER’s full responsibility for the packaging itself.

• Each type of GOODS SHALL be packed taking into consideration the following factors:

the GOODS’ hygroscopic properties.

o protection requirements of the GOODS to be packed. o o means of transport to be used. o o o o

transport routing and duration, storage/stop-over points and transhipment. required anti-corrosion measures. climatic conditions. centre of gravity and weight issues.

8.3

Packing Construction Materials

In general GOODS SHALL be packed using wood and/or wood-based products. Other packaging material may be used after prior agreement with the PURCHASER only. Cardboard is accepted only for airfreight shipments. To be remarked that the use of containers does not exclude seaworthy packing requirements.

8.3.1 Wood

The wooden parts must comply with the relevant standards on dimensions and quality:

• Softwood: Pine, in any of its various species and spruce.

• Hardwood: poplar and eucalyptus are the most frequently used although plane, elm, ash, oak,

birch, and basswood can also be used.

The wood to be used for the construction of the above mentioned structures must be solid and integral, featuring a humidity rate that must not exceed the limit of 20% and an absence of faults that may affect its resistance. The wood/timber to be used must be new, sound and well-seasoned, free from loose knots and decay.

COMP3-SPM-PO-PRC-00005_B

Page 25 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

The minimum required thickness for PACKAGES15 floor, side and top sheeting is 40 mm.

8.3.2

International Export Packing Requirements (ISPM 15)

ISPM15 which stands for International Standard for Phytosanitary Measures for Wood Packaging Material in International Trade. The International Standards for Phytosanitary Measures16, describes the processes of treatment of wood packing materials against pests and enters into force via binding national implementations. The IPPC (International Plant Protection Convention), a sister organization of FAO (Food and Agricultural Organization of the UN) has agreed a common standard for wood packaging in order to protect native forest from packaging-borne pests and harmonize the import regulations. Any expenses resulting from SUPPLIER’s failure to comply with this standard, when applicable, will be back charged to SUPPLIER. This standard SHALL be applied to solid timber (soft and hard woods) thicker than 6 mm when used as packaging material or for bracing. It is not applicable to timber-based manufactured materials. In case of ISPM15 applicability, involved PACKAGEs have to be marked as shown in the relative attachment to the present Specification at Article n. 16.3. It’s SUPPLIER’s responsibility to assess the applicability of ISPM15 standard in the country involved in the transportation (origin, transit, destination).

8.3.3 Plywood

Plywood is a composite material made of several layers with no more than 3 mm thickness bonded together by means of resins or adhesives applied by roller, spray or roll coverers; they are assembled so that the grain on each ply is at right angles to the adjacent sheet to afford maximum strength in all direction. Plywood used for packaging made of softwoods, eucalypts, pine and spruce.

Sheathing thickness will be determined by type of load, weight of contents, mode of transport, and estimated worst condition to which material will be subjected. The minimum required thickness for side and top sheeting is 8,5 mm.

OSB (Oriented Strand Board) is a panel of a wood-based product made from wood shavings bonded together with synthetic glue, pressed and subjected to specific pressures and temperatures. There are existing four types of OSB, depending on their mechanical strength and resistance in moist environments: • OSB/117: panel for general purpose and indoor use • OSB/23: panel for use in dry environments • OSB/3: structural panel for use in humid environment • OSB/4: high-performance structural panel for use in wet environments In general, the timber must be used minimizing connecting joints. Scrap is not permitted for the composition of commercially available wooden parts. The wooden parts, bigger than commercial

15 Crates/Boxes/Cases, all the wooden containers. 16 Publication No. 15 March 2002.

17 Not allowed for packing.

COMP3-SPM-PO-PRC-00005_B

Page 26 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

ones, can be built by connecting two or more commercial elements but the following instructions must be followed: • The connections to be minimized. • The connections must be located on load bearing units in order to assure the fixing of the same

support to the two external faces.

• The contact of points of connection must be continuous.

8.3.4 Cardboard (flexible box)

Cardboard is a structure made of a central nerve of corrugate paper strengthened on the outside by two layers of paper, glued with adhesive to the crests of the corrugate paper. Cardboard is accepted only for airfreight shipments.

8.4

Instrumentation And Supporting Technology

If specifically required by PURCHASER, SUPPLIER shall provide the following additional instruments.

8.4.1 Humidity indicator

Humidity indicators must be used if specifically required.

8.4.2 Tilt & Shock and vibration indicator

Tilt & Shock indicator must be used if specifically required.

8.4.3 Shock Recorder System

The System “Impact Recorder system” performs independent measurements with regards to the environmental conditions and shock data. Its measurements are registered on a hard memory; anyway could be sent in real time through GMS/GPRS connection.

8.4.4 Thermal Recorder and Chillers

Coating raw materials require chillers and thermal recorders recording the shipment, to ensure the material is still suitable for use.

COMP3-SPM-PO-PRC-00005_B

Page 27 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

9 PACKING STYLES AND CONSTRUCTION FEATURES

In order to properly design the packages, the type of load to which they MAY be subject to throughout all phases18 of use and which may also regard storage, handling and transport must be correctly assessed. The packing must be carried out in such a manner that the package absorbs or minimizes the impacts of any external mechanical stress may occur during handling, transportation and storage.

9.1 Stackability

Stackability19 is a key factor in the optimization of all the transportation processes and costs, as a consequence the packing unit must be marked indicating the minimum allowable stacking weight according to below types of loads.

For all the packing unit types (e.g., boxes, cases, crates, steel frames) up to 3,5 m height, the SUPPLIER SHALL provide packing of the GOODS in compliance with below stackability features:

• Distributed load

Load (pressure) which SHALL be supported by the overall top surface of the package. Overall top surface equal to: “Package length” x “Package width” from packing list.

Package

Transport

Case & crate Road – direct

railway –

Case Crate

container Sea Sea

Distributed Load (minimum) 0750 kg/sqm20

1250 kg/sqm3 1250 kg/sqm3

Table 2: Requested allowable loads for stackability

• Connections

For all the packing units21, SUPPLIER SHALL facilitate stackability and fastening by the installation of proper parts to connecting and/or holding packages to each other’s.

• Other features

In case GOODS shall be packed in steel frames, such packages SHALL BE designed in order to allow the stackability (i.e., by having the same shape). Anyway, SUPPLIER shall agree with PURCHASER the packing design philosophy and others main features.

9.2

TYPES OF PACKING

18 (From contractual delivery point to the final destination). 19 Packing unit’s ability to be stacked to each other’s during transport and storage. 20 Square meter, [m2]. 21 Within each shipping lot.

COMP3-SPM-PO-PRC-00005_B

Page 28 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Packing SHALL be in compliance with the following types: • Wooden boxes or boxes covered with plywood panels or OSB 3 (Oriented Strand Board). • Crates featuring non-continuous wooden board. • Bundle ties with wooden or iron clamps with threaded tie rods. • All packaging must be free of puncture hazards i.e., nails, staples etc. • GOODS that have not been packed.

In the next paragraph are detailed these main types of packing with regards to the features and construction.

9.2.1 Boxes / Cases

Figure 2: Wooden box

Figure 3: Box with plywood’s lining

Figure 4: Wooden box with diagonal battens

Boxes SHALL be used for any assembling, machinery or structural components or materials having fragile surfaces, which need mechanical and/or physical and/or-chemical protection. The level of protection to be applied has to be in accordance with the type of equipment.

Boxes/Cases Design Main Features: • Base frame longitudinal skid consisting of a load bearing floor of bottom boards, reinforced with

transversal and longitudinal runners and square end walls joists.

COMP3-SPM-PO-PRC-00005_B

Page 29 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

• Side and end walls must be supported to absorb the stacking loads acting on the roof, the

horizontal thrusts and its own weight in order to prevent the deformation of the box.

• Sheeting with solid wood boards always mounted vertical.

• Sheeting with multilayer panels or with wood-based panels.

• The lid has to be furnished with structural lid support of battens or joists to bear staking weights and absorb transversal stress during handling. The main function of the joist is to add stability at the points where ropes or chains are applied during lifting operations.

9.2.2 Crates

Figure 5: Wooden crate

Figure 6: Wooden crate with diagonal battens

Boxes/Cases Main Features: Crates are to be used for fabricated equipment for which the shape or fragility rules out of saddles or bundles. The construction of the base frame SHALL be as per above paragraph “boxes/cases”. Side and end walls and lid sheating shall be made up of non-continuous planking such as boards mounted vertically, with spacing between the boards, but not exceeding the board width.

9.2.3 Bundles

Bundles SHALL be used for GOODS not requiring packaging in a crate or box:

• Due to physical/mechanical features of the GOODS to packaged. • When its structure of the products allow grouping (put the single pieces together, in contact). Bundles shall be made using steel bands/strip and cushion (non-combustible material such as polypropylene). Cushion SHALL be placed between the steel band/strip and the material to avoid damage or rusting. The ends of the bundle requiring protection22, wooden bar SHALL be applied at the ends. The bundles SHALL be secured by threaded rods, nuts and lock-nuts or equivalent so that no parts can slip when the bundled is tilted.

22 Or when items are likely to be exposed to the risk of dropping out.

COMP3-SPM-PO-PRC-00005_B

Page 30 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Figure 7: Steel Bundle (e.g. for pipes).

Figure 8: Wooden bundle

9.2.4 Saddles

All vessels, tanks, and similar equipment/GOODS without suitable permanent saddles SHALL be supplied and fitted with fabricated shipping saddles (made up in wood or steel23) suitable for withstanding stresses during road, sea and rail transportation. Such kind of saddles SHALL be included in the SUPPLIER’s scope of supply. Consequently, the SUPPLIER SHALL advise any requirements for saddles, lifting beams or any other special lifting equipment as per to PURCHASER requirements. Special transport equipment (with particular regards to saddles) SHALL be included in the SUPPLIER’s scope, as per below main features:

i.

ii.

iii.

iv.

saddles and relative securing to the item representing GOODS should be designed to withstand dynamic transportation loads (due to accelerations). Proper saddles securing SHALL be provided able to prevent any horizontal, vertical or transverse displacement (and/or rotations) between the cargo and the saddles. saddles SHOULD be approximately symmetrical24 as per centre of gravity of the item. If necessary, to load the saddle by of trailers or other jacking equipment at the SUPPLIER’s works, any requirement to prepare the saddle for application of such equipment SHALL be removable (bolt on type). All equipment SHALL be capable of being lifted by overhead crane regardless of the method used to load. saddles SHALL be designed considering that the equipment could be stored during transport phases with the aid of supports/stools. As a consequence, the saddles SHALL be dimensioned in order to accommodate both the trailers and the support/tools and the ends SHALL sustain the weight of the equipment. saddle’s height should be minimized in order to reduce overturning momentums. However, must be provided sufficient clearance to downward pointing nozzles and man-ways plus projecting platforms, piping and ladders.

23 At Supplier convenience. 24 Along item/equipment longitudinal axis.

COMP3-SPM-PO-PRC-00005_B

Page 31 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

v.

vi.

vii.

viii.

saddle’s base must be suitable for securing and lashing onto the transporting vehicle either by bolting, clamping or welding. contact25 faces of each saddle must be accurately matched to the circumference of the equipment supported and protected interposing between each saddle and the equipment suitable soft material (i.e., neoprene layer), at the same time to prevent damage of painted surfaces or at spots susceptible for local stress and ensure friction between saddle and the equipment. saddles SHALL allow the fixing of the PACKAGE onto the transporting vehicle by application of anchoring points, such as lugs with holes. Turnbuckles SHALL be appropriately tensioned. saddle’s configuration (number, position, detailed dimensions DWG) and load per square metre SHALL be submitted to PURCHASER for approval prior to finalize the design. For any technical reason the PURCHASER reserves the right to change the saddle configuration for mean of transport26 compatibility purpose (e.g., Sea-Vessel, Barge, Rail Wagon, SPMT, etc.).

o As per general guidance, SUPPLIER SHALL consider below instructions:

▪ As minimum requirement, saddles SHALL be capable to spread on the

ground 25 MT per square meter.

▪ Saddles centre-to-centre distance27 SHALL be a multiple of 1600 mm or 2200 mm (to be finalized by PURCHASER); but not exceeding about 12,0 m. ▪ Saddle width (“B” as per below DWG) SHALL be not less than 1200 mm. ▪ Saddle length (“A” as per below DWG) SHALL not exceed the equipment

diameter.

Figure 9: Transport saddles typical pictures Additional Notes On Saddles The upper part of the ends must allow enough space to position the necessary anchoring elements. The wooden elements must be connected to ensure that the whole saddle is SHALL be compact. This can be done using passing eyebolts, with metal ribs or other systems suitable for the purpose. The use of wood-based panels to cover the saddles can be considered suitable for this purpose.

9.2.5 Unpacked Material

PACKAGE design must be agreed with PURCHASER before dispatch. Such kind of GOODS may allow shipment in unpacked condition (e.g., with no packing). These GOODS SHALL be adequately protected against possible damages by slings or wires. Each unpacked material SHALL be considered as individual package and SHALL be marked and

25 Saddle to equipment. 26 Defined to be used. 27 Along item/equipment longitudinal axis.

COMP3-SPM-PO-PRC-00005_B

Page 32 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

managed accordingly. Each PACKAGE SHALL be provided with a base frame (made up in wood or steel28) and anchors to make the fastening during transport.

9.2.6 Lifting Devices

Where specialised lifting devices, for example a lifting beam or spreader beam, SHALL be required, or is specified by the SUPPLIER, the SUPPLIER SHALL be accountable for supplying the lifting device complete with all required sets of accessories, such as slings, shackles, eyebolts, etc. necessary for the safe application of the device. Technical documents such as drawings, quality certification and TPI/manufacturers inspection certification SHALL be provided for each component of the lifting device.

Lifting device SHALL be designed if possible, for both applications, shipping and SITE erection, and it SHALL ensure that the lifting is carried out in manner that the PACKAGE remain horizontal.

Lifting device and all lifting points applied to the PACKAGE, for example trunnions, necessary for connecting the lifting device, they SHALL be painted with a special colour for immediate identification.

Unless otherwise agreed, the cost for the provision of the lifting device is included in the price of the PURCHASE ORDER.

9.3

Dynamic loads

PACKING, and contained GOODS, is subject Dynamic loads during handling and transport. The value of the dynamic load (Cd) acting on the packaging is the result by following formula:

Cd = P x a Where: P = Weight [kg] a = Acceleration [m x s^-2]

Here below the involved types of accelerations: • LONGITUDINAL (braking or acceleration of the means of transport) • TRANSVERSAL (acceleration by effect of curvilinear trajectory of the means of transport) • VERTICAL. Considering the features of the GOODS to be packaged and the order of magnitude of dynamic loads, the stability of the PACKING must be ensured by suitable reinforcement of PACKING structure, as hereinafter shown in detail (“Fastening elements” and “Supplementary lid structure”).

• Fastening elements

These PACKING structural elements are able to prevent longitudinal and transversal shifts tie- rods, bolts or struts, able to perform anchorage and prevent tipping:

28 At Supplier convenience.

COMP3-SPM-PO-PRC-00005_B

Page 33 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Vertical Load

Horizontal Load : No Bracing

Horizontal Load: Bracing With Diagonals

Horizontal Load: Bracing With Panels

Figure 10: Reinforcements

• Supplementary lid structure

o The lid supports may be placed as free-standing elements in order to.

o Withstand the upper loads on the lid and transporting it to the vertical.

o Withstand the external lateral loads on the package, particularly caused by action of ropes or chain on the upper lateral edges during hoisting operations (compression actions).

o Withstand a concentrated load on a portion of surface of (60x60 cm.) in the worst

position, to ensure the best safety for the operators.

COMP3-SPM-PO-PRC-00005_B

Page 34 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Figure 11: Weight distribution on the lid elements.

10 PACKING OF GOODS BY CATEGORY

The following requirements are the minimum requirements for suitable packing execution for transportation purpose. The compliance with these minimum requirements does not relieve SUPPLIER from its responsibility of the proper packaging execution. SUPPLIER based on its own experience and practice SHALL provide any improvements to ensure GOODS protection and preservation during transportation and storage.

10.1

Columns, Heat Exchangers, Pressure Vessels and Tubular Equipment29

Shop-assembled pressure vessels, tanks, heat exchanges including transfer lines for reforming furnaces for ammonia plant, should be skidded with wooden or steel saddles30, properly shaped and fastened to the piece by metal clamps in order to avoid possible sacks; fastening by wire ropes is forbidden, unless otherwise specified. Timber may be placed in the base of the steel saddles to increase friction between the packages and the ship’s deck.

Saddles SHALL be fastened to the piece in order to allow quick removal and reassembly of the saddle as well. Turnbuckles SHALL be properly tensioned considering possible tension relieving due to wood shrinkage.

29 Shop-assembled or prefabricated pressure vessels, columns, tanks, heat exchangers; 30 As per Article n. 9.2.4 of present Specification;

COMP3-SPM-PO-PRC-00005_B

Page 35 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Special ocean carriers/heavy lift vessels may require the quantity of saddles31, their dimensions and fastening system for the unit to consider the effect dynamic forces during navigation. In such a case, detailed drawings and calculations for saddles/fastening systems and the supporting arrangement SHALL be forwarded to PURCHASER for review.

The saddles height SHALL be the lowest possible one. Nozzles, manholes, etc., SHALL be sealed by compatible metal disks (5 mm32) or plywood disks (9 mm4) with gaskets (5 mm4), duly bolted; (fixing by wire or adhesive tape is strictly forbidden).

All parts subject to damage or scratches33 SHALL be properly protected or removed whenever possible.

Wooden boards SHALL be fixed by bolts and nuts. Nails are forbidden. The width of the wooden boards SHALL be of the same size of the base of the saddle.

Removable parts that may have an excessive volume MAY BE requested to be (whenever possible), dismantled and separately packed and prepared for assembly at the SITE.

Taking in consideration the centre of gravity location, lifting points SHALL be properly positioned in order to avoid any possible damage to the item (or parts of it) by lifting ropes, chains or any other lifting device.

The holes of the lifting points SHALL be properly sized (minimum 36 mm diameter) for connection of hooks/shackles for lifting and any other lashing device. Lifting lugs SHALL be properly sized to accommodate lifting ropes.

In case the GOODS SHALL be lifted from the shell, protections of rubber or wood SHALL be provided in correspondence of the lifting points.

In case handling with forklifts is prohibited, all skidded units SHALL be provided with lifting lugs to avoid scratches and damage to the equipment caused by the lifting ropes.

For heat exchangers fitted with expansion joints or bellows, a suspended protection SHALL be used. This protection SHALL be made up of wooded reinforcing, fastened by steel rods (or caged), preventing displacements in any direction.

10.2 Complete Plant Packages and Modules

This chapter includes for example, furnaces and boilers, generating sets, water treatment plant, desalination plant, etc.

Packing SHALL be a rigid structure container/skid as per land and sea transport main requirements34. Module SHALL be sealed with framed wooden side covered with plywood sheeting.

31 According to mechanical, dimensional, and interferences constraints. 32.Minimum thickness. 33 e.g. by lifting and/or handling ropes or other handling devices, including surfaces. 34 As per Article 6.1 of present document.

COMP3-SPM-PO-PRC-00005_B

Page 36 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

The position of the centre of gravity SHALL be defined by considering the internal distribution of the equipment and elements of which the module is made up of.

As a general rule, a slope of 8% SHALL be considered, as well as bumpy road conditions, uneven surfaces, gravelled roads. Due to these, strain and vibrations could be generated into the modules.

All parts and equipment inside a module SHALL be fixed and braced in order to minimize/absorb vibrations to or between them.

Instruments and electrical components (mounted inside modules) must be protected from damages as if they were standalone parts. Installation of them SHALL be properly executed for avoiding any displacements or rotations.

In case it is necessary to lift the PACKAGE with the aid of devices ensuring that the lifting takes place in a balances manner, the lifting device complete with all accessories (shackles, ropes/chain, eye bolts, etc.) must be provided by SUPPLIER with all necessary quality certifications. All llifting equipment SHALL be painted with a special colour for immediate identification. Unless otherwise agreed, the cost for the provision of the lifting device is included in the price of the PURCHASE ORDER.

Design of Modules and Packages SHALL be realized minimizing as much as possible shipping volume. Removable parts that may have an excessive volume MAY BE requested to be (whenever possible), dismantled and separately packed and prepared for assembly at the SITE. All parts subject to damage or scratches35 SHALL be properly protected or removed whenever possible.

The SUPPLIER must provide (at least two months prior to shipment), the transport drawings showing the centre of gravity, spreader beams and any other relevant handling information that FREIGHT FORWARDER, must be aware of this is in order to properly arrange all necessary for a successful and secure transportation of the module.

10.3 Plates

Plates are normally be sent to installation SITES without any form of surface treatment unless otherwise specified in the PURCHASE ORDER, in which case the type of treatment required will also be specified.

Plates SHALL be bundled and edge protect with heavy-duty cardboard, the net weight of each bundle SHALL not exceed 5 tons, as per below instructions:

• Bundles up to 2 tons total net weight SHALL be made by placing plates on wooden skids.

• Bundles up to 5 tons total net weight SHALL be made by U-iron skid structures, unless otherwise

agreed.

Plates treated with anti-rust, painted or cladded must be also covered with polyethylene film and handled with care, using hemp ropes, canvas slings or other suitable methods to prevent damage or wear to the coating. Any parts of hoisting machine which will be in contact with painted surfaces must be covered with a suitable material.

35 E.g. by lifting and/or handling ropes or other handling devices, including surfaces.

COMP3-SPM-PO-PRC-00005_B

Page 37 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Rolled steel plates36 SHALL be provided with suitable bracing to minimize any deformation/bending during transit. Spacers SHALL be provided between the rolled plates. Plates over two meters diameter SHALL be cut into two more sections in order to reduce their overall dimension and facilitate handling and transport.

Each plate and each structural component must be clearly marked with the specification number, the drawing number and the assembly code number

Figure 12: Plate bundles

10.4 Air Coolers

10.4.1 Loose parts

Air cooler should be packed in wooden crates enabling to stack identical sized crates in three (3) layers. Lifting and lashing points free for use must be clearly marked.

• Air cooler tube bundles SHALL be provided with lifting plates, with support beams bolted to the side walls, enabling to stack same size air coolers at least in three (3) layers. This arrangement SHALL allow the connection, by proper bolting, of more bundles (same width), making up a single packing unit.

• Finned surfaces SHALL be protected by plywood sheet (or equivalent) with the purpose to avoid fins damages. SUPPLIER SHALL ensure that finned tubes SHALL be properly separated from each other by application of spacers with the aim to protect the equipment from strains to bumps or bending moments from out-of-balance weight distribution during: transport, loading and unloading operations.

• Auxiliary materials and equipment for air coolers (e.g., fans, motors, steel structure/works, etc.) SHALL be packed in accordance with the present Specification, considering standard stackability requirements37.

36 Properly bundled or packed. 37 As per Article n. 9.1 of the present Specification.

COMP3-SPM-PO-PRC-00005_B

Page 38 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Figure 13: Air cooler rube bundles typical shipping arrangement.

10.4.2 Assembled

Assembled air coolers SHALL be packed with their own support steel structure38. The SUPPLIER SHALL protect the finned surfaces of the tube bundles as per above article. After laying plywood sheets on finned tubes surfaces, the SUPPLIER SHALL cover the entire tube bundle with tarpaulin to protect the equipment form seawater and rain. In Assembled case, support structures for assembled air cooler, shall be suitable for Sea, Land and Rail transportation.

10.5 Transformers

Transformers MV / LV power up to 3150 KVA (if represented by General Cargo items) SHALL be boxed and will be shipped complete and filled with oil, however, the instrumentation must be removed and packaged separately. The transformer base SHALL be bolted to the PACKAGE by suitable bolting arrangement on the suitable package/transformer load bearing element.

Transformers over 3150 KVA, must be packed as add-on packaging (e.g., non load bearing crates). Fragile parts/components39 have to be additionally protected. The crate has to be furnished with openings to access the lashing points on the transformer base frame. Self-supporting items must provide adequate clearance for handling.

Radiators and external isolators, if shipped disassembled from the rest of the equipment, have to be packaged in crates.

To be remarked that SUPPLIER has to submit drawings (for approval) including detailing packing, as per Article n. 12.2 of the present Specification.

38 The same for the installation at the SITE, anyway total height should be minimized by (shortening the legs, to be re-assembled at SITE). 39 Particularly subject to damage.

COMP3-SPM-PO-PRC-00005_B

Page 39 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Figure 14: Transformer on pallet

10.6 Machinery

Machinery category include Pumps, Compressors, Turbines and relative accessories. These GOODS categories SHALL be packed in wooden boxes. In addition, even if already detailed in above Articles of the present Specification, to be remarked that:

• Surface protection SHALL be as per Article n. 7 “Internal Packaging”. • Threaded connections SHALL be closed by well-greased threaded plugs. • All flanged connections SHALL be protected by bolted metal disks and rubber gaskets. • The base plate SHALL be bolted to the bottom of the case. • All disassembled parts SHALL be identified and packed separately, even if contained in the same

PACKAGE.

• Vapour barrier bags SHALL be heat sealed to avoid air filtration.

For machinery exceeding 30 machinery/compressors, protruding from the PACKAGE.

lifting

tons,

lugs should be provided

fixed

to

the

In case it is necessary to lift the PACKAGE with the aid of devices ensuring that the lifting takes place in a balances manner, the lifting device complete with all accessories (shackles, ropes/chain, eye bolts, etc.) must be provided by SUPPLIER with all necessary quality certifications. Unless otherwise agreed, the cost for the provision of the lifting device is included in the price of the PURCHASE ORDER. All lifting equipment SHALL be painted with a special colour for immediate identification.

All mechanical and rotating equipment SHALL be adequately packaged for shipment and prepared for extended unprotected storage at the SITE. Spare parts for these machines SHALL be packed and marked in accordance with applicable reference standard requirements.

COMP3-SPM-PO-PRC-00005_B

Page 40 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

To be remarked that SUPPLIER has to submit drawings (for approval) including detailing packing, as per Article n. 12.2 of the present Specification.

10.7 Electricals

This GOODS category includes (but is not limited to) panels, motors, generators, other electrical equipment, instrumentation and connections. Electricals SHALL be packed in wooden case and protected by a thermo-welded hermetic barrier.

10.7.1 Panels

Electrical panels are particularly susceptible to damage from strains, as a consequence extra preventative measures to protect the GOODS shall be adopted as follows.

a) Individual packing • Reinforce

the packing, so the assembled equipment can withstand vibration during

transportation.

• Protect the instrument’s connectors. • Fix wiring, piping, lamps, panels and switchboxes applying additional interior bracings. • Close openings of any piping. • Protect instruments, switches, displays etc. on the front panel.

b) Moisture proof interior packing • Wrap the entire panel with the moisture proof barrier material, remove the inside air and heat-

seal the pouch. Desiccating agents have to be applied in sufficient amount.

• if there are any protruding parts, same have to be wrapped with felt or other cushioning material.

These actions shall be provided in order to prevent damage to moisture barrier material.

c) Plug-in instrumentation installed on panels SHALL be properly fastened to the frame. Should such plug-in instrumentation be susceptible to damage during transportation or deterioration during the storage period, they must be removed and packed separately.

d) Instrumentation, MV and LV Bus Duct SHALL be packed with shock-absorbing material to

prevent damage.

e) For material and equipment particularly subject to deterioration due to vibration or shocks (i.e., telemetering and tele-control equipment), the boxes SHALL made up of double bottoms or double casing, supported by shock absorbing rubber or synthetic pads.

COMP3-SPM-PO-PRC-00005_B

Page 41 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Figure 15: Packing for electrical panels

10.7.2 Cables

Cables40 SHALL be supplied on wooden reels. Reels SHALL be provided with thermo-retractable caps in order to avoid moisture penetration, especially for cables with mineral paper or hygroscopic insulation. In addition:

• Reels should be protected by wood lagging nailed to the out circumference of the reel with no gaps allowed between lagging. Steel bands SHALL be applied to the outer lagging with a stretching tool and secured with steel seals.

• Reels must allow handling by forklift therefore must be provided with a wooden frame on the

bottom.

• The minimum diameter of the reels SHALL be twice the minimum bending radius of the cable. • The ends of the cable SHALL be sheathed and inserted inside the drum. • Wooden reels SHALL be sound and protected by water-repellent paint. Marking SHALL be

executed on metal plates fixed on two sides.

• The external surfaces of cables SHALL be peripherally protected with tarred paper and/or

cellophane sheeting.

• The end of the cables must be sealed with special caps and SHALL be maintained closed until

it will be used at SITE.

• One metal tag stating PACKING LIST with a copy of the packing list inside will be fixed on each

reel.

Figure 16: Cable reels

40 Electrical and instrumentation.

COMP3-SPM-PO-PRC-00005_B

Page 42 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

10.7.3 Cables Trays

Cable trays SHALL be packed in cases or crates.

• These GOODS are generally shipped with the aid of ocean containers therefore the PACKAGE will be supplied with maximum length of 5.8 m. (for 20’ Dry Van containers) or 11.8 m. (for 40’ Dry Van).

• The use of containers doesn’t relieve SUPPLIER to provide seaworthy packing.

10.8 Piping

10.8.1 Carbon steel, alloy steel, galvanized pipes and EXTERNALLY COATED41 piping

“Carbon steel” and “stainless steel” pipes materials must always be packed separate from each other. In order to protect the bevelling, all the bevelled ends SHALL be covered with plastic caps42. “Not recessed” caps are not allowed.

• Pipes up to ½” diameter SHALL be packed in seaworthy crates with a maximum weight of 1,5

ton and a maximum length of 11,8 meters (allowing the use of 40’ Dry Van containers).

• Pipes from ½ “to 6” SHALL be packed in bundles with a maximum length of 11,8 meters, allowing the use of 40’ Dry Van containers. These weights of the bundles SHALL not exceeding 1,5 ton and pipes SHALL be of the same diameter and similar length. Bundles SHALL be equipped with a sufficient number of steel bands in order to make the PACKAGE, firm and stable.

• Pipes with a diameter over than 6” (included) SHALL be shipped loose, with a maximum length

of 11,8 meters, allowing the use of 40’ Dry Van containers.

Bevelled ends of pipes over 38 in. diameter SHALL be protected by Aluminium-Rings or wooden padding. Pipes supplied with double random length (DLR) will be of 11,8 m maximum. Pipes supplied with single random length (SRL) will be of 5,8 m maximum.

In case of bundled pipes, GOODS shall be loaded from the top into open top containers, the slings used for strapping during packing must not be removed after stuffing into containers and must remain inside to facilitate stripping operations at destination.

Pipes loaded in bundles SHALL be individually marked with at least the heat number, the number of the bundle and the number of the pipe, as referred in the Master Packing List for Bundles.

Nesting of tubes is not permitted.

41 Or bituminized. 42 Minimum depth of 80 mm in order to facilitate handling by using hooks.

COMP3-SPM-PO-PRC-00005_B

Page 43 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Figure 17: Pipes standard packing

Externally coated or bituminized pipes included in a bundle SHALL be protected by vegetable or synthetic fibre cord, in order to avoid direct contact between the metal strap or the fastening elements and the surface of the pipe. Fibre slings SHALL be used instead of wire ropes. If transported loose, pipes SHALL be provided with plastic or rubber rings, in order to avoid damage to the coating.

Figure 18: Coated pipe packing arrangement

10.8.2 Stainless steel, clad, cast iron, aluminum and plastic pipes

• Stainless steel pipes SHALL be crated or boxed and also be covered by polyethylene plastic to

protect material from rainwater or splashes.

• Cemented pipes SHALL be transported loose; they SHALL be handled with particular care (use of forklift is forbidden and fibre sling SHALL be used instead of wire ropes). The maximum distance between the supporting or lifting points SHALL be 1,8 meters to avoid bending. Each support SHALL be lined with rubber in order to absorb any shock during transport. Maximum stacking height SHALL be 1,2 metres.

• Each loose pipe SHALL be marked according to the marking instructions referred in these

guidelines.

• Cladded piping shall be shipped on wooden bundle/skid and SHALL be handled with particular

care.

10.8.3 Flanges, Fitting, Valves

Different nature of GOODS/types/sizes shall be packed separately to each other’s.

Up to DN 150, these GOODS SHALL be packed in seaworthy stackable cases.

Over DN 150, these MAY BE packed in crates. The use of pallets as PACKAGE (or wooden skid, as per below pictures) SHALL be agreed with PURCHASER.

COMP3-SPM-PO-PRC-00005_B

Page 44 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

In any case, stackability43 requirements SHALL be observed and be advised and detailed in the packing list.

Figure 19: Packing (on pallet/skid) for fittings over DN 150

Although the size of the cases must be adjusted to the GOODS packed inside, the following sizes SHALL be used as a general rule, in order to optimize ISO containers capacity. • Length 1200 mm x width 1000 mm. Overfilling of flanges, fitting, valves in boxes without proper fixing may compress and subsequently break the package walls. In order to prevent this, a maximum height of 0,8 m MAY BE considered as limit for packing units filling. Boxes construction SHALL allow the use of forklift. GOODS SHALL be corrosion protected by special heavy-duty grease. Contact surfaces of flanges and flanged fittings SHALL be duly protected to avoid mechanical damage.

Notes on Valves in order to avoid damages: • Valves shall be positioned inside the packing in vertical position. • Stainless and non-ferrous material valves shall be protected also with polyethylene sheets. • Banding straps, if being used, shall use a protective material in between the item and the strap

itself, to avoid scratching/marking/damage/contamination

Figure 20: Valves packing details

10.8.4 Bolts, Nuts and Washers

Bolts, nuts and washers, etc., suitably greased, will be sorted by type, placed in polypropylene raffia sacks and packed in cases.

43 As per Article n. 9.1 of the present Specification.

COMP3-SPM-PO-PRC-00005_B

Page 45 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

10.8.5 Prefabricated Piping

Prefabricated piping SHALL be packed in crates or, if agreed, in a S.O.C. (Shipper Owned Container) as per Article n. 6.2 of the present Specification. Each shipment SHALL include all prefabricated parts belonging to specific isometric drawing(s).

Figure 21: Packing of prefabricated piping

Piping spools with total net weight not exceeding 500 kg and suitable dimensions, SHALL shipped in Cases. Piping spools with the total net weight exceeding 500 kg, or dimensions larger than 1200 x 1000 mm SHALL be packed in crates. Piping spools MAY BE also packed onto individually designed pallets/wooden skids (i.e., shipping saddles) with a suitable capacity but SUPPLIER SHALL agree this packaging solution with PURCHASER.

10.9 Steel Structures

Steel structures include GOODS as, beams, ladders, handrails, any steelwork prefabricated items. These SHALL be packed to facilitate handling operations, and stackability44.

Depending on the method of transportation adopted, the packaging type SHALL be agreed with PURCHASER.

All items will have an inscription in indelible ink showing the reference numbers of the assembly drawings.

As general rules, the following guidelines are to be considered for PACKAGE execution:

Structural beams SHALL be positioned on skids (or pallets) for easy handling and in order to optimize the shipping volume. Transversal reinforcement elements have to be applied between the layers for strengthening the stack and protect the beams (including coating if any). PVC protectors SHALL be applied on the contact point and steel strap passages when fixing the stack. The overall bundle sizes SHALL allow the positioning of them into containers.

44 As per Article n. 9.1 of the present Specification.

COMP3-SPM-PO-PRC-00005_B

Page 46 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Figure 22: packing for steel structures.

The choice of the method of packing for Ladders and handrails depend on the shipping method agreed with PURCHASER. In case of container shipping, regardless of which are shipper owned (S.O.C.) or carrier owned container (C.O.C.)45, ladders and handrails SHALL be packed in standard pallets or individually designed wooden skid corresponding to the structure sizes, suitable for lifting with fork-lifts or by rope for loading into containers. Transversal reinforcement elements between the various pieces have to be applied for safeguarding the material and improving the package stability. Stairs with safeguard, lightweight and deformable items, have to be packed on individually designed skids/pallets to protect the material from deformation. The stack must be fixed with steel strapping. In case of conventional shipping, as break bulk, the aforesaid materials are to be packed in wooden crates.

10.10 Vehicles

The following protective measures SHALL be taken before packing of vehicles:

  • Minimize the liquids (fuel, cooling water and lubricating oil).
  • Disconnect the battery.
  • Remove all accessories and packing them separately.
  • Securely fasten accessories to the operator’s seat wherever possible.
  • Remove spare tyres.
  • Grease properly the axles.
  • Glass parts must be protected by plywood or other screening material in order to avoid handling

damages.

10.11 Welding Electrodes

Welding electrodes SHALL be contained in hermetically soldered metallic boxes. These boxes shall be absolutely water and moisture proof and packed in wooden cases.

10.12 Refractory Bricks and Element

45 As per Article n. 1.2 of the present Specification.

COMP3-SPM-PO-PRC-00005_B

Page 47 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Refractory bricks SHALL be packaged in three-layer paper bags wrapped in polyethylene bags and fastened tightly onto pallets.

10.13 Mineral Wool / Foam Glass

Unless otherwise agreed, mineral wool SHALL be packed in double polyethylene bags, fastened onto the pallets or packed in cases for long term preservation. Foam glass SHALL be packed in three-layer cardboard boxes lined with polyethylene wrapping and fastened onto pallets or packed in cases for long term conservation.

10.14 Hazardous GOODS, Chemical Products Y-Catalysts

Regardless of the hazardous nature, these materials may be packed in bags protected by polyethylene sheeting or in steel drums. These drums SHALL be:

  • Palletized to facilitate the handling.
  • Wrapped in heat shrinkable film.
  • Strapped with metal or plastic straps. Chemical products SHALL be packed according to their compatibility with other chemicals. It is recommended that hazardous materials SHALL be packed in small volumes to enable partial deliveries.

Local laws, international regulations such as IMDG, ADR, IATA, RID regulates the transportation of dangerous GOODS. Current regulations and ordinances enacted by the respective carriers governs the packing and transportation of dangerous GOODS. GOODS classified as hazardous material (e.g., paints, gas bottles, chemicals, or similar) must be packed, labelled and marked in accordance with IMO/ADR/IATA regulation. Hazardous GOODS or parts contained in any minimum supply must be packed separately in accordance with the above mentioned regulations. In addition SHALL be handled as a single shipment being identified on a separate packing list and MSDS46 to be supplied to PURCHASER.

10.14.1 Lubricants

Lubricants SHALL be shipped in 220 litres drums. Steel drums must be duly fastened onto pallets to facilitate the handling.

10.15 Radioactive Materials

Instruments, lighting-rods (etc.), containing a specific activity of more than 74 KBq (0,002 MCI/g) are classified as radioactive. Radioactive materials must be sealed in leaded safes and packed in wooden cases. Packing, labelling and marking SHALL be according to IATA/IMO/ADR regulation, depending on the method of transport.

10.16 PPE (personal protective equipment)

46 Material safety datasheet

COMP3-SPM-PO-PRC-00005_B

Page 48 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

This is extremely important as leaving PPE lying around increases the risk of parts deteriorating by exposure to dirt, oil, UV rays, sunlight etc. PPE must be stored according to the manufacturer’s instructions and packed in cases sealed with aluminium foil and desiccants.

10.17 BOP (blow out preventer)

Item in this category requires a special handling and long-term planning. Lifting and lashing points SHALL be provided to secure the load during handling and transport. These items may need special skids (tailor made) on the basis of weight distribution (maximum allowable load considered 20 tons/sqm).

11 SHIPPING DOCUMENTATION

Shipping documents (related to packing) SHALL show the transport descriptions of the GOODS such as shipping configuration of the items, technical description, number of items contained within any PACKAGE, dimensions and weights for each numbered package and any other specific requirement (i.e., P.O. line-item weight, etc.). If required stackability47 properties of the GOODS shall be clearly shown.

11.1

Packing Lists

Packing list have to be placed in waterproof envelope and securely fixed to the external surface of each package protected by plastic or aluminium cover. This cover will be clearly marked “PACKING LIST”, with waterproof ink.

11.2 Transport Drawings

In case of Oversize/Overweight items, the SUPPLIER SHALL submit packing, transportation and lifting drawings, at least 12 weeks prior to shipment, showing (as minimum requirement): vii. viii.

PURCHASE ORDER/Tag number The general arrangement item and packing, with regards to:

o Weight and dimensions of each piece. o Centre of Gravity (CG) position and quote. o Position of lifting and lashing points. o Positions of supports/saddles etc.

ix.

Any detail of:

o Lifting lugs and/or sling detailed drawings (sizes etc.). o Saddle detailed drawings (sizes, weight, materials etc.). o Lifting point, chain/slings/ropes maximum allowable angle.

x. Cargo securing measures inside/on the packaging. xi. xii.

Size and type of spreader-bars, ropes and shackles SHALL be used. Any other specific transport requirements.

In addition, along with the final Packing List, the SUPPLIER SHALL submit:

47 Ability of the GOODS to be stacked.

COMP3-SPM-PO-PRC-00005_B

Page 49 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

xiii. Weight certificate with actual weights and dimensions. xiv.

Photos of the equipment.

The SUPPLIER/SUPPLIER will specify each piece with points designated for lifting and slinging/lashing, in order to distribute the load equally and keep the piece in stable and horizontal position during lifting operations as shown below:

Figure 23: Typical details for transport DWG.

12 PACKING INSPECTION

12.1

General

The instructions of packing inspection stated hereunder SHALL be applicable to the GOODS under the PURCHASE ORDER. Packing inspections SHALL be made by the PURCHASER’s appointed representative inspector. Inspection SHALL be extended to a visual, dimensional, quantity check of GOODS, etc. The SUPPLIER SHALL allow free access and support to personnel and required equipment to the PURCHASER’s inspector at all times. In case of an inspection, all GOODS and packages are to be placed accessible and consolidated for effective inspection.

12.2 Reporting

When the inspection is finished, the SUPPLIER SHALL immediately furnish a report with the following minimum requirements:

• The SUPPLIER SHALL take photographs, showing the main shipping mark, exterior and interior views of packages and how the equipment or machines are secured on the load bearing elements per each package.

• Photographs SHALL be submitted to the PURCHASER electronically by e-mail. • Modification of PACKAGE. If the PURCHASER or its appointed inspector identifies packing defects, the SUPPLIER SHALL immediately correct the defect(s) on his own responsibility and expenses and SHALL inform PURCHASER about the results of the corrective actions carried out. In case of any damage or expenses due to the delay of a shipment due to corrective actions, the SUPPLIER SHALL be accountable for the damages or expenses in full.

COMP3-SPM-PO-PRC-00005_B

Page 50 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

13 MARKING INSTRUCTIONS

The SUPPLIER is required to properly mark each package providing each package details in the “Final Packing List”.

Labels attached to the GOODS SHALL be in English language. If specifically requested in the PURCHASE ORDER, the writing may also be bilingual, another language besides English. All individual items, included in a single packing unit, SHALL be marked separately. The marking SHALL be stencilled on two sides (long sides), and one on the top end in clear text, anyway according to the box dimensions.

If the package does not have space enough to apply the shipping marks, metal labels with full shipping marks of suitable size, SHALL be fixed firmly to the package. The colour to be used SHALL contrast with the package surface. Black or white paint is recommended to be used as standard practice. The use of yellow or red paint is not allowed.

All items48, SHALL be supplied fully marked and tagged by the SUPPLIER with the PO number, item in accordance with project number, requirements/material specifications.

item code number and cast/heat numbering,

All the GOODS have to be clearly marked with handling marks, such as slinging points the centre of gravity (CG) on all sides, and any other applicable handling mark. Correct marking features are extremely important for Oversize/Overweight cargo, with particular regards to Pressure Vessel and Heat Exchangers. Marking symbols shall be used as per shown in the Attachment E at the present Specification.

SHIPPING MARKS

PO No. (If Applicable) MARKS: According to final Destination

PORT OF …………….. or ……………………………..AIRPORT (please check with nominated forwarding agent prior to marking)

48 including pipe and piping components, valves, flanges, fittings, “In line” instruments, “Off-line” instruments, special items, etc.

COMP3-SPM-PO-PRC-00005_B

Page 51 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Tag No (If Applicable) P.O Item Nos Gross weight (Kilos) Net weight (Kilos)

Length x width x height Total cube in (in Cube Meters) Package Stackable . NOT . YES (maximum kgs) The following International Symbols must be used.

  • All boxes and crates shall also be marked with appropriate international standard symbols for

handling.

Hazardous, dangerous or restricted material have to be marked according to the applicable international standard. Packages containing dangerous GOODS SHALL be marked on (at least) two sides with appropriate labels in conformity with IMDG/IATA regulations. All hazardous GOODS SHALL be identified by the appropriate hazardous class and technical (or proper) shipping name.

Spares parts must be clearly marked as spare parts and SHALL not be included with main equipment.

Bundles and loose items which are not suitable for application of shipping marks directly onto the bundles or pieces must be supplied with indestructible labels or boards bearing the shipping mark. Labels or boards are to be tied firmly to the package with stainless steel wire.

Metal or other weatherproof tags SHALL be clearly legible and must invariably be affixed to bundles and single units at both ends. Linen, paper or light cardboard tags are definitely not allowed.

Precautionary information such as handling marks must be stencilled on each package to indicate proper handling and storage practices.

14 STORAGE RECOMMENDATIONS

The SUPPLIER’s storage recommendations SHALL be marked on each package and indicated on the packing list.

The symbols for the type of storage are:

• X or “A”

: storage in heated/ventilated warehouse and with special precautions.

• XX or “B”

: storage in closed warehouse.

• XXX or “C”

: storage in open shed.

• XXXX or “D”

: storage in open air.

COMP3-SPM-PO-PRC-00005_B

Page 52 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

15 ATTACHMENTS

Attachment A - Standard tag for project cargo

Attachment B - ISPM 15 Marking

Attachment C - Marking Symbols

COMP3-SPM-PO-PRC-00005_B

Page 53 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

15.1 Attachment A - Standard tag for project cargo

EXAMPLE

…

TAG NO.:

CT NO.

PO NO.

REQ NO.

DWG. NO.

PART NO.

ITEM NO.

DESCRIPTION

SIZE

QUANTITY

SUPPLIER NAME

TOTAL

( )

COMP3-SPM-PO-PRC-00005_B

Page 54 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

15.2 Attachment B – ISPM 15 Marking

HT Standard marking

a

b

a) Country code b) Product manufacturer number c) Identifies the phytosanitary treatment

c

used

d) Phytosanitary tracing references e) Inspection agency logo

d

e

How to read the marking:

Inside the left box: IPPC/FAO logo internationally recognized symbol.

Inside the right box: IT-00-000: identification code of the company that performed the treatment or that produced the packaging with treated raw materials, which includes:

• IT: country where the treatment was performed or where the packaging was produced using pre-

treated raw materials (in this case, Italy).

• 00: region where the treatment was performed or where the packaging was produced using pre-

treated raw materials.

• 000: company that performed the treatment or that produced the packaging using pre-treated

raw materials.

Under the left box: 0000/00: Batch number for the tracking and tracing of the packaging, which includes:

• 0000: progressive code that identifies the number of treatment or the production with pre-treated

raw materials.

• 00: year of treatment or of production with pre-treated raw materials.

COMP3-SPM-PO-PRC-00005_B

Page 55 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Here below the states which have adopted the ISPM-15 of FAO

NORTH AMERICA United States, Canada, Mexico

LATIN AMERICA

EUROPE

AFRICA

ASIA PACIFIC

Argentina, Brasil, Bolivia, Chile, Colombia, Costa Rica, Cuba, Dominican Republic, Ecuador, Guatemala, Honduras, Nicaragua. Jamaica, Paraguay, Peru, Trinidad & Tobago, Venezuela

Bulgaria European Union Norway Switzerland Turkey Ukraine

Egypt Kenya Nigeria Senegal Seychelles South Africa Tanzania

Australia, China, India, Indonesia, Israel, Japan, Jordan, Lebanon, Malaysia New Zealand, Oman, South Philippines, Korea, Sri Lanka, Syria Taiwan, Thailand Vietnam

COMP3-SPM-PO-PRC-00005_B

Page 56 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

15.3 Attachment C - Marking Symbols

Shipping and Information Marks

  1. Identification mark
  2. Identification number

Package No. If necessary, also the total number of packages

  1. Destination
  2. Port of Destination
  3. Country of Origin
  4. Net Weight
  5. Gross Weight
  6. Dimensions Length x Width x Height

(Example) GDV ABC 123

5 / 25 PITTSBURGH VIA NEW-YORK MADE IN GERMANY 700,00 [kg] 800,00 [kg] 850,0 x 220,0 x 200 [cm]

Symbols (to be marked on Packing Units)

No. Symbol

Meaning Fragile

Purpose / Function The contents of the package are fragile and must therefore be handled with care.

Use no hooks No hooks may be used when handling

this package.

Top

Indicates the correct, upright position of the package.

Notes ISO 7000, No. 0621. Example of use:

ISO 7000, No. 0622

ISO 7000, No. 0623. Example of use:

Keep from heat

away

The package must be protected from heat.

ISO 7000, No. 0624

COMP3-SPM-PO-PRC-00005_B

Page 57 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Symbols (to be marked on Packing Units)

Meaning Protect radioactive sources

from

Purpose / Function The contents of the package can be degraded or rendered useless as a result of radioactivity.

Notes ISO 7000, No. 2401

Keep dry

The package must be kept in a dry environment.

ISO 7000, No. 0626

Center gravity

of

Indicates the center of gravity of a package that is to be handled as a single unit.

ISO 7000, No. 0627. Example use: of

Do not roll

The package must not be rolled.

ISO 7000, No. 2405

No hand truck here

Hand trucks must not be used on this side to handle the package.

ISO 7000, No. 0629

Do not use truck forklift here

Clamp here

Do not clamp here

Stacking weight limitation

The package must not be handled using forklift trucks.

ISO 7000, No. 2406

Clamps must be applied to the sides indicated to handle the package.

ISO 7000, No. 0631

No clamps may be applied to the the sides package.

to handle

indicated

ISO 7000, No. 2404

Indicates load for packages.

the maximum stacking

ISO 7000, No. 0630

No. Symbol

COMP3-SPM-PO-PRC-00005_B

Page 58 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Stacking limitation

identical Maximum number of packages that may be stacked, where n stands for the number of permitted packages.

ISO 7000, No. 2403

Do not stack

Stacking of the packages is not permitted and no loads should be placed on the package.

ISO 7000, No. 2402

Sling here

Slinging equipment must be applied as shown in order to lift the package.

ISO 7000, No. 0625. Example use: of

Permitted temperature range

the

Indicates temperature range within which the package must be stored and handled.

ISO 7000, No. 0632. Example use: of

Electrostatic sensitive device

Do not destroy barrier

Contact with packages bearing this symbol should be avoided at low levels of relative humidity, especially if insulating footwear is being worn or the ground/floor is nonconductive. Low levels of relative humidity must in particular be expected on hot, dry summer days and very cold winter days.

A barrier layer which is (virtually) impermeable to water vapor and contains desiccants for corrosion protection is located beneath the outer packaging. This protection will be ineffective if the barrier layer is damaged.

Since the symbol has not yet been approved by the ISO, puncturing of the outer shell must in particular be avoided for any packages bearing the words “Packed with desiccants”.

Tear here

open

This symbol is intended only for the recipient.

COMP3-SPM-PO-PRC-00005_B

Page 59 of 60

Classification: Internal

NORTH FIELD PRODUCTION SUSTAINABILITY (NFPS) PROJECT

COMP3 - NFPS OFFSHORE RISER/WELLHEAD PLATFORM & INTRAFIELD PIPELINES PROJECT

HANDLING, STORAGE, PACKING & PRESERVATION PROCEDURE

Do not expose to magnetic fields

Only transport upper on layer or: Top layer or: Do not stack

COMP3-SPM-PO-PRC-00005_B

Page 60 of 60

Project: Q-32705 - Saipem COMP3 Folder: RFQ Files


Loading authentication...

Graph View

Backlinks

  • 00 Index

Created with Infinity Constructor © 2025

  • Elynox | Go Further