Técnicas Reunidas
VENDOR DRAWING AND DATA REQUIREMENTS
FOR: COMBINED SAFETYSHOWER/EYEWASH STATION
VDDR Nº DPT SIGNED FOR REV
: : : :
10510-091-HS-037-00 091 - HSE MARIA ANTELO LOPEZ 0
DATE :
07/05/2025
Code
Document
Notes
With the BID
Critical
For Info(I) / For Review (R)
2,5
2,5
2
2,4
CAT-0001
CER-0002
CER-0001
CER-0003
CER-0006
CER-0004
DIA-0002
DIA-0011
CATALOGUES WITH MAIN DIMENSIONS AND CHARACTERISTICS CERTIFICATES AND DECLARATIONS OF CONFORMITY ELECTRICAL PROTECTION CERTIFICATES TYPE AND SPECIAL TEST CERTIFICATES CALIBRATION CERTIFICATES FOR SUPPLIED INSTRUMENTS TEST AND CERTIFICATION OF MATERIALS AUXILIARY SYSTEMS PIPING AND INSTRUMENT DIAGRAMS TWO-LINE LOOP DIAGRAMS (ILD´S)
DOS-0002
FINAL QUALITY DOSSIER
DOS-0003
INDEX QUALITY DOSSIER
HDD-0001
HDD-0006
LIS-0001
LIS-0002
LIS-0003
LIS-0017
COMPLETED DATA SHEETS FOR MAIN MECHANICAL EQUIPMENT INSTRUMENTS DATA SHEETS VENDOR DRAWINGS AND DOCUMENTS LIST RECOMMENDED SPARE PARTS LISTS MATERIALS AND COMPONENTS LISTS WITH IDENTIFICATION SPARE PARTS LIST FOR 2 YEARS OF OPERATION
LIS-0019
SUB-SUPPLIERS LIST
LIS-0020
PACKING LIST & CRATE CONTENT LIST
LIS-0024
PRELIMINARY CARGO LIST
LIS-0022
CUSTOMS CLASSIFICATION
LIS-0006
INSTRUMENT LIST
LIS-0004
I/O LIST PER EACH CARD
MAN-0001
INSTALLATION, OPERATION AND MAINTENANCE MANUAL
2,3,5
PLD-0019
NAMEPLATE DRAWINGS
PLD-0028
PLG-0003
IDENTIFICATION PLAN FOR LOOSE ITEMS AND BOM GENERAL ARRANGEMENT WITH DIMENSIONS AND LOADING DATA
PLN-0001
QUALITY CONTROL PLAN
2
PRC-0001
TESTS PROCEDURES
PRC-0009
PRC-0012
PRESERVATION AND STORAGE INSTRUCTIONS PACKING & TRANSPORTATION PROCEDURE
X
X
X
X
X
X
X
X
X
R
I
R
R
R
R
R
R
R
R
R
R
R
R
R
R
R
R
R
R
R
R
R
R
R
R
R
R
R
R
Days
15 after PO
7 after final inspection
7 after final inspection
7 after final inspection
30 after PO
7 after final inspection
15 after PO
30 after PO
15 after final inspection
30 after PO
15 after PO
15 after PO
15 after PO
15 after PO
30 after PO
30 after PO
30 after PO
30 before delivery
30 before delivery
30 before delivery
60 after PO
60 after PO
30 after final inspection
45 after PO
40 after PO
30 after PO
0 after PO
30 before delivery
60 before delivery
60 before delivery
Support of the Documentation
With the Shipment
DWG
DWG
XLS
XLS
XLS
XLS
Técnicas Reunidas
VENDOR DRAWING AND DATA REQUIREMENTS
FOR: COMBINED SAFETYSHOWER/EYEWASH STATION
VDDR Nº DPT SIGNED FOR REV
: : : :
10510-091-HS-037-00 091 - HSE MARIA ANTELO LOPEZ 0
DATE :
07/05/2025
Code
Document
Notes
PRG-0001
PROGRESS REPORT
1
PRG-0003
SUB-0001
OVERALL MANUFACTURING PROGRAM COPIES OF UN-PRICED SUBORDERS
With the BID
X
Critical
For Info(I) / For Review (R)
I
R
R
Days
30 after PO
15 after PO
0 after PO
Support of the Documentation
With the Shipment
GENERAL NOTES
1
2
3
4
5
To be sent the first week of every month.
Document linked to payment.
After final inspection. Manuals shall include main equipment and auxilliary equipment.
List of drawings that Vendor anticipates supplying (title, dwg, No., rev.) should be kept updated.
Document linked to shipment.
PROJECT NOTES
Project: Q-32794 - Tecnicas - Stade LNG Folder: RFQ Files