Técnicas Reunidas

VENDOR DRAWING AND DATA REQUIREMENTS

FOR: COMBINED SAFETYSHOWER/EYEWASH STATION

VDDR Nº DPT SIGNED FOR REV

: : : :

10510-091-HS-037-00 091 - HSE MARIA ANTELO LOPEZ 0

DATE :

07/05/2025

Code

Document

Notes

With the BID

Critical

For Info(I) / For Review (R)

2,5

2,5

2

2,4

CAT-0001

CER-0002

CER-0001

CER-0003

CER-0006

CER-0004

DIA-0002

DIA-0011

CATALOGUES WITH MAIN DIMENSIONS AND CHARACTERISTICS CERTIFICATES AND DECLARATIONS OF CONFORMITY ELECTRICAL PROTECTION CERTIFICATES TYPE AND SPECIAL TEST CERTIFICATES CALIBRATION CERTIFICATES FOR SUPPLIED INSTRUMENTS TEST AND CERTIFICATION OF MATERIALS AUXILIARY SYSTEMS PIPING AND INSTRUMENT DIAGRAMS TWO-LINE LOOP DIAGRAMS (ILD´S)

DOS-0002

FINAL QUALITY DOSSIER

DOS-0003

INDEX QUALITY DOSSIER

HDD-0001

HDD-0006

LIS-0001

LIS-0002

LIS-0003

LIS-0017

COMPLETED DATA SHEETS FOR MAIN MECHANICAL EQUIPMENT INSTRUMENTS DATA SHEETS VENDOR DRAWINGS AND DOCUMENTS LIST RECOMMENDED SPARE PARTS LISTS MATERIALS AND COMPONENTS LISTS WITH IDENTIFICATION SPARE PARTS LIST FOR 2 YEARS OF OPERATION

LIS-0019

SUB-SUPPLIERS LIST

LIS-0020

PACKING LIST & CRATE CONTENT LIST

LIS-0024

PRELIMINARY CARGO LIST

LIS-0022

CUSTOMS CLASSIFICATION

LIS-0006

INSTRUMENT LIST

LIS-0004

I/O LIST PER EACH CARD

MAN-0001

INSTALLATION, OPERATION AND MAINTENANCE MANUAL

2,3,5

PLD-0019

NAMEPLATE DRAWINGS

PLD-0028

PLG-0003

IDENTIFICATION PLAN FOR LOOSE ITEMS AND BOM GENERAL ARRANGEMENT WITH DIMENSIONS AND LOADING DATA

PLN-0001

QUALITY CONTROL PLAN

2

PRC-0001

TESTS PROCEDURES

PRC-0009

PRC-0012

PRESERVATION AND STORAGE INSTRUCTIONS PACKING & TRANSPORTATION PROCEDURE

X

X

X

X

X

X

X

X

X

R

I

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

R

Days

15 after PO

7 after final inspection

7 after final inspection

7 after final inspection

30 after PO

7 after final inspection

15 after PO

30 after PO

15 after final inspection

30 after PO

15 after PO

15 after PO

15 after PO

15 after PO

30 after PO

30 after PO

30 after PO

30 before delivery

30 before delivery

30 before delivery

60 after PO

60 after PO

30 after final inspection

45 after PO

40 after PO

30 after PO

0 after PO

30 before delivery

60 before delivery

60 before delivery

Support of the Documentation

With the Shipment

PDF

PDF

PDF

PDF

PDF

PDF

DWG

DWG

PDF

PDF

PDF

PDF

PDF

PDF

PDF

PDF

PDF

PDF

PDF

XLS

XLS

XLS

PDF

PDF

XLS

PDF

PDF

PDF

PDF

PDF

Técnicas Reunidas

VENDOR DRAWING AND DATA REQUIREMENTS

FOR: COMBINED SAFETYSHOWER/EYEWASH STATION

VDDR Nº DPT SIGNED FOR REV

: : : :

10510-091-HS-037-00 091 - HSE MARIA ANTELO LOPEZ 0

DATE :

07/05/2025

Code

Document

Notes

PRG-0001

PROGRESS REPORT

1

PRG-0003

SUB-0001

OVERALL MANUFACTURING PROGRAM COPIES OF UN-PRICED SUBORDERS

With the BID

X

Critical

For Info(I) / For Review (R)

I

R

R

Days

30 after PO

15 after PO

0 after PO

Support of the Documentation

With the Shipment

PDF

PDF

PDF

GENERAL NOTES

1

2

3

4

5

To be sent the first week of every month.

Document linked to payment.

After final inspection. Manuals shall include main equipment and auxilliary equipment.

List of drawings that Vendor anticipates supplying (title, dwg, No., rev.) should be kept updated.

Document linked to shipment.

PROJECT NOTES

Project: Q-32794 - Tecnicas - Stade LNG Folder: RFQ Files


Loading authentication...