ABU DHABI NATIONAL OIL COMPANY (ADNOC) GHASHA CONCESSION PROJECTS

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

COMPANY DOC NO: 1-CF0000-59-PRO-0002-00

Rev. 03

ABU DHABI NATIONAL OIL COMPANY (ADNOC) GHASHA CONCESSION PROJECTS

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

Contractor Document Number: CF0000-1009002

03

02

Rev

11/12/2023

30/09/2023

IFU

IFU

Issued for Use

A. Parlato S. Feliziani P. Santoni

C. Copelli

Issued for Use

L. Ceoloni S. Feliziani P. Santoni

P. Santoni

Date (DD/MM/YYYY)

Status

Status Description

PREPARED

CHECKED

APPROVED 1

APPROVED 2

This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.

DOCUMENT CLASS - 1

Page 1 of 20

Uncontrolled When Printed

ABU DHABI NATIONAL OIL COMPANY (ADNOC) GHASHA CONCESSION PROJECTS

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

COMPANY DOC NO: 1-CF0000-59-PRO-0002-00

Rev. 03

This document is rolled over from PCSA document no. 1-CF0000-59-PRO-0002-00 Rev. 01

Rev

01

00

B1

A1

Date

(DD/MM/YYYY)

24/04/2023

28/03/2023

17/02/2023

25/01/2023

SUMMARY OF DOCUMENT REVISIONS

Status

Status Description

IFU

IFU

IFA

IFR

Issued for Use

Issued for Use

Issued for COMPANY approval

Issued for Review

DOCUMENT CLASS - 1

Page 2 of 20

Uncontrolled When Printed

ABU DHABI NATIONAL OIL COMPANY (ADNOC) GHASHA CONCESSION PROJECTS

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

COMPANY DOC NO: 1-CF0000-59-PRO-0002-00

Rev. 03

HOLD

Section

Description

HOLD LIST

DOCUMENT CLASS - 1

Page 3 of 20

Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0002-00

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

Rev

03

TABLE OF CONTENTS

PROJECT OVERVIEW … 5

1.1

EPC for HAIL & GHASHA Development Project … 5

PURPOSE … 6

DEFINITIONS AND ABBREVIATIONS … 6

3.1

3.2

Definitions … 6

Abbreviations … 6

REFERENCE DOCUMENTS … 7

DOCUMENT AND DRAWING NUMBERING – COMPANY NUMBERING SYSTEM . 8

5.1

5.2

5.3

5.4

5.5

5.6

Field Code (BB)… 9

Area Code (CC) … 9

Unit Code (DD) … 10

Discipline code (EE) … 12

Document Type (FFF) … 13

Serial Number (NNNN) … 14

VENDOR DOCUMENTS AND DRAWINGS NUMBERING – COMPANY NUMBERING SYSTEM … 15

SUBCONTRACTOR DOCUMENTS AND DRAWINGS NUMBERING – COMPANY NUMBERING SYSTEM … 15

REVISION NUMBER … 16

DOCUMENT FILE NAMING … 16

9.1

9.2

Isometric Drawings Coding system … 17

Isometric Electronic file naming … 17

DOCUMENT NUMBERING SYSTEM – CONTRACTOR NUMBERING SYSTEM … 17

10.1 Document Creator Code (PP) … 18

10.2 Document sequential number (QQ) … 18

ATTACHMENTS … 20

11.1 Attachment 1 – Supplier Documents Requirements Listing (SDRL) … 20

DOCUMENT CLASS 1

Page 4 of 20

Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0002-00

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

Rev

03

PROJECT OVERVIEW

1.1

EPC for HAIL & GHASHA Development Project

The Hail & Ghasha Development (HGD) Project is of strategic importance to the Emirate of Abu Dhabi. The Project will develop the untapped oil and gas reserves from the highly sour Hail and Ghasha fields. Production is targeted to start by Q4 2027 with sustainable production of 1 BSCFD of Raw Gas, and max production of 82.5 MSBPD of Oil, 76.3 MSBPD of Condensate, 9000 TPD of Sulphur and 5030 TPD of NGL. In addition, Project will capture 1.52 million tonnes of CO2 per year taking ADNOC’s committed investment for carbon capture capacity. The Hail and Ghasha fields are situated offshore ABU DHABI about 140 km away from ABU DHABI mainland in water depths varying from 0 to 15 meters.

The HGD Project comprises the following:

• Artificial Islands Construction;

• Offshore package – EPC 01: Offshore Drilling Centers (DCs), Subsea Pipelines, Umbilicals, Power Cable Connections, Seawater Intake Structure, Bridges, Risers, Flare Structure, facilities at Ghasha Offshore Processing Plant (“GOP”);

• Onshore package – EPC 02: Manayif Onshore Processing Plant (“OPP”), Manayif

Utilities, Offsite Pipelines & Tie-ins, Main Control and Other Buildings.

The HGD Project will be executed in a single phase approach. It will start production from three Drilling Centres (Reeah, Jzool & Seebah) in Ghasha Field to GOP and from Gaff Island in Hail Field to OPP. Remaining Drilling Centres, gas injection, and other associated facilities will be developed in ‘future’ to sustain production from Hail & Ghasha fields.

Figure 1 - Hail & Ghasha Fields

DOCUMENT CLASS 1

Page 5 of 20

Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0002-00

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

Rev

03

PURPOSE

The purpose of this document is to describe the numbering system to be used to number documents and drawings of the Project.

DEFINITIONS AND ABBREVIATIONS

3.1

Definitions

COMPANY

Abu Dhabi National Oil Company (ADNOC)

CONTRACTOR

Unincorporated JV NPCC -SAIPEM

PROJECT

SUBCONTRACTOR

Hail and Ghasha Development Project – Package 1: Offshore Facilities

An entity that has been awarded by CONTRACTOR the performance of part of the work or services of the PROJECT.

VENDOR/SUPPLIER

Any and all vendors of materials and equipment in connection with the PROJECT

3.2

Abbreviations

ADNOC

AGES

AGRU

BEDD

BPD

BSCFD

BWPD

CCP

DC

EPC

GOP

H&MB

HGD

HIPPS

HP

HPU

Abu Dhabi National Oil Company

ADNOC Group Engineering Standards and Specifications

Acid Gas Removal Unit

Basic Engineering Design Data

Barrel per Day

Billion Standard Cubic Feet per Day

Barrels of Water Per Day

Compression Centre Platform

Drilling Centre

Engineering, Procurement and Construction

Ghasha Offshore Processing

Heat & Material Balance

Hail & Ghasha Development

High Integrity Pressure Protection System

High Pressure

Hydrogen Production Unit

DOCUMENT CLASS 1

Page 6 of 20

Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0002-00

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

Rev

03

LP

MSBPD

MMSCFD

Low Pressure

Thousand Standard Barrels per Day

Million Standard Cubic Feet per Day

NGL

OPP

PWT

SOW

SRU

TDS

TGTU

TPD

TSS

UAE

VRU

Natural Gas Liquids

Onshore Processing Plant

Produced Water Treatment

Scope of Work

Sulphur Recovery Unit

Total Dissolved Solids

Tail Gas Treatment Unit

Tonn per Day

Total Suspended Solids

United Arab Emirates

Vapour Recovery Unit

REFERENCE DOCUMENTS

Sl. No.

Document No.

Document Title

1

2

3

4

5

6

1-CF0000-59-PRO-0006-00

1-CF0000-46-PRO-0225-00

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS S3D IMPLEMENTATION PROCEDURE

1-CF0000-28-KEY-2450-00 WBS AREA & UNIT PLOT PLAN KEY PLAN

1-CF0000-50-PRO-9819-00 DOCUMENT

MANAGEMENT

AND

CONTROL PROCEDURE

1-CF0000-59-PRO-0003-00 PROJECT PROCEDURE FOR TAG NUMBERING PROJECT INSTRUMENT NUMBERING RULES

1-CF0000-16-PRO-0198-00

SPECIFICATION

DOCUMENT CLASS 1

Page 7 of 20

Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0002-00

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

Rev

03

DOCUMENT AND DRAWING NUMBERING – COMPANY NUMBERING SYSTEM

CONTRACTOR shall code its drawings, specifications, data sheets, plans, procedures and other documents as per the following:

A

  • BBCCDD

EE

  • FFF

NNNN

MM

Where:

A is a prefix and shall be 1 to indicate Package 1.

BB is the Field Code as per par. 5.1 CC is the Area Code as per par. 5.2 DD is the Unit Code as per par. 5.3

EE is the Discipline Code as per par. 5.4

FFF is the Document Type as per par. 5.5

NNNN is the Serial Document Number as per par 5.6

MM is the Sheet Number. Sheet Number shall be a 2-digit numeric string – 00, 01, 02, 03, etc. The number of sheets applied to the documents and drawings. For documents and drawings where there are no sheet numbers, the sheet numeric string shall be 00.

Example: 1-CF5100-28-LST-9001-00

Drawings

Multi sheet drawings may be combined in one document to be identified and numbered as follows:

• The multi-sheet drawings’ COMPANY number identification, will keep 00 as MM (e.g. A-BBCCDD-EE-FFF-NNNN-00); this number will be used as document identification in Aconex/Page;

• The COMPANY drawing number in the title block will indicate the progressive sheet

number with -01 (for the first sheet), -02 (for the second sheet) and so on.

• The sheet number and the total number of sheets (e.g Sh 1 of 2) may be indicated

in the title block (e.g. in the drawing title field).

Single sheet Drawings

For identification purpose in case any single-sheet drawing would require additional sheets during its lifetime, document identification and numbering can be as follows:

DOCUMENT CLASS 1

Page 8 of 20

Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0002-00

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

Rev

03

• The single sheet drawings’ COMPANY number identification, will keep 00 as MM (e.g. A-BBCCDD-EE-FFF-NNNN-00); this number will be used as document identification in Aconex/Page;

• The COMPANY drawing number in the title block will indicate -01 (for the first and

only one sheet).

5.1

Field Code (BB)

The following Field Code Shall be used in the Document Number

Code CF GH HL MM RW SB

Field Name Common (Offshore) Ghasha Hail Manayif Ruwais Subsea

5.2

Area Code (CC)

The following Area Code Shall be used in the Document Number

Code 00 01 01 02 02 03 03 04 05 06 07 30 49 51 51 60

Area Name Common Reeah (Drill Centre 01) Shalhah (Hail South) Duroob (Drill Centre 02) Mudaifena (Hail South East) Ghaff (Hail 3) HLE Seemeh (Drill Centre 03) Jzool (Drill Centre 04) Ghanem (Drill Centre 05) Seebah (Drill Centre 06) Injection Platform Well Head Tower Compression Centre Platform Chananiz (GOP) Manayif (OPP) Swalem (CLQ)

DOCUMENT CLASS 1

Page 9 of 20

Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0002-00

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

Rev

03

5.3

Unit Code (DD)

The following Unit Code Shall be used in the Document Number:

Code 00 01 12 14 15 20 21 22 25 26 28 31 32 33 34 35 36 37 38 39 40 41

42

43 44 45 47 48 49 51 52 53 55 56 57 58 59 60 61 62 63 64 65

Unit Name Common / General Wellheads / Manifolds Booster & Export Compression LP Flash Gas Compression Train 1 LP Flash Gas Compression Train 2 Inlet Facilities and Separation Oil Stabilization Train Condensate Stabilization Train Condensate Hydrotreater Oil & Condensate Export and Product Storage Cooling Medium System Acid Gas Removal - Train 1 Acid Gas Removal - Train 2 Injection Platform Jacket Injection Platform Topside Solvent Storage & Transfer Bridge Injection Jacket Gas Compression Injection Topside CO2 export pipeline Sour Gas Dehydration Gas Dehydration & Mercury and Mercaptan Removal - Train 1 Gas Dehydration & Mercury and Mercaptan Removal - Train 2 Sweet Gas Booster Compression Train 1 Sweet Gas Booster Compression Train 2 NGL Storage & Shipping NGL Recovery Units - Train 1 NGL Recovery Units - Train 2 Sales Gas Compression Export Sulphur Recovery - Train 1 Sulphur Recovery - Train 2 Sulphur Recovery - Train 3 Sulfur Storage & Shipping Tail Gas Treatment - Train 1 Tail Gas Treatment - Train 2 Tail Gas Treatment - Train 3 CO2 Recovery & Hydrogen Capture Future Nitrogen Rejection Potable & Utility Water Steam System & Demineralised Water System Air Separation unit Chemical Injection System Fuel Gas System

DOCUMENT CLASS 1

Page 10 of 20

Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0002-00

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

Rev

03

Code 66 67 68 69 70 71 72

73 74

75 76 77 78 79 80 81 82 84 85 87

89 90

91 92

93 94

95 96 97

98

99

Unit Name Chilled Water System & Propane Refrigeration System Instrument & Service Air System Nitrogen System Diesel System Seawater System Flare System & Vapour Recovery System Produced Water Treatment System & Sour Water Treatment Fire Protection System (Fire Fighting) Drain System, Oily water, Storm Water & Evaporation Pond Oil Free Low TDS Wastewater Treatment System Sewage Treatment Plant Piperacks (Interconnecting Unit) Hot Oil System Non Process Buildings Main Power Distribution & Emergency Power Telecom System Hydrogen Production Unit (HPU) Roads & Fences Harbour & Jetty Facilities Process Buildings (Substation, IES, Operator shelter, etc.) ICSS (MAC) A/G Risers and Shore Approaches Pipelines and Cables (Onshore Section) Subsea Pipeline Gathering Network (DCs Intrafield) Onshore Export Pipelines and Cables (excl. sulphur line) Onshore Sulphur Lines and Cables Export Subsea Umbilicals and Cables Network (DCs Intrafield) Gas Lift Gas Injection A/G Risers and Shore Approaches Pipelines and Cables (DCs Intrafield) Subsea Pipeline Gathering Network (Offshore export to Onshore) Subsea Umbilicals and Cables Network (Offshore export to Onshore)

DOCUMENT CLASS 1

Page 11 of 20

Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0002-00

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

Rev

03

5.4

Discipline code (EE)

The following Discipline Code shall be used in the Document Number:

Code 01 04 07 10 13 15

16 19 22 23 24 25 26 28 31 32 34 37 40 46 47 50 51 52 53 54 55 57 58 59 70 71 72

Discipline Name

Architectural Process Engineering Civil & Structural Electrical Environmental Control System & Automation includes DCS/ESD/F&G Instrumentation and Analyzers Geotech & Hydraulic Engineering Services (G&HES) Mechanical Engineering-STATIC Mechanical Engineering-ROTATING Mechanical Engineering-PACKAGES Materials Engineering Technology (MET) HVAC Plant Design & Piping (PD&P) Offshore Structures Marine Engineering Pipeline Project Engineering Process Safety Engineering Engineering Management Telecom Project Control / Planning Construction Health Safety and Environment IT QAQC Acceptance and Handover Contracts Procurement Project Mgt / Quality Mgt / Admin Social and HSE Initiatives Start-up / Commissioning Operations Readiness

DOCUMENT CLASS 1

Page 12 of 20

Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0002-00

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

Rev

03

5.5

Document Type (FFF)

The following Document Type shall be used in the Document Number:

Code

ADD BLD BOD BOM CAL CEC CNN CRT DFD DID DPT DSP DSS DWG FLD FRM GAA GAS GDD GDW HMB HUP IAP ICD INR ISO ITP KEY LAY LOD LOG LOP LST MAN MAR MEL MES MOR MPO MRL MSD MTO PAR

Drawing / Document Type Addendum Block Diagram Basis of Design Bill of Material Calculation Cause and Effect Diagram/Charts Calculation Note Criticality Rating Ducting Flow Diagram Ducting & Instrumentation Diagram Design Pressure – Design Temperature Diagram Decision Support Package Data Sheet Drawing Foundation Loading Diagram Form/Template Glossary of Abbreviations General Arrangements/Elevation General Document Gas Gathering Route Map Heat and Material Balance Hookup Diagram Inspection Assignment Package / PIM Package Inter Connecting Diagram Inspection report (General) Isometric Diagrams Inspection Test Plan Key Plan Layout Drawing Load Summary Logic Diagram Loop Diagram List Manual Material acceptance report/ Material approval request Master Equipment List Method Statement Material Requisition Material Purchase Order Material Lists Material Selection Diagram Material Take Off Purchase Order Recommendation

DOCUMENT CLASS 1

Page 13 of 20

Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0002-00

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

Rev

03

Code

PAS PFD PHL PID PLN POL PPL PRO PRQ PSD PSF PSL PVL QCP REG REP REQ SAT SCH SCM SKE SLD SOR SOW SPE SRP STD STU SVR TBD TBE TCN TIE TOR TRA TRP UFD VDR VNM WID WIN

Drawing / Document Type Pipeline Alignment Sheet Process Flow Diagram Philosophy Piping & Instrumentation Diagram Plan Policy / Procedure / Process Plot Plan Procedure Pre-qualification Pipe Support Detail Process Safeguarding Diagram Pipe Support Location Plan Project Vendor List Quality Control Procedure Register Report Requisitions Safety Analysis Table Schedule Schematic Diagram Sketch Single Line Diagrams Statement of Requirements Scope of Works Specification Simulation Standard Drawing Studies Site Visit Report Termination Block Diagram Technical Bid Evaluation Technical Note TIE-IN Schedule Term of Reference Task Risk Assessment Technical Report Utility Flow Diagram Vendor Document Register Vendor Manual Wiring Diagram Work Instruction

5.6

Serial Number (NNNN)

The serial number shall be 4-digit sequence number.

DOCUMENT CLASS 1

Page 14 of 20

Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0002-00

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

Rev

03

VENDOR DOCUMENTS AND DRAWINGS NUMBERING – COMPANY NUMBERING SYSTEM

VENDORS shall code their drawings, specifications, data sheets, plans, procedures and other documents as per the following:

A

  • PEEKKKKKKK

BBCCDD

  • GGG

NNNN

MM

Where:

A is a prefix and shall be 1 to indicate Package 1.

P is a letter and shall be P to indicate Purchase Order. EE is the Discipline Code as per par. 5.4 (Discipline Code is the main discipline driving the PO and is fixed for the respective full PO) KKKKKKK is the Purchase Order Number

BB is the Field Code as per par. 5.1 CC is the Area Code as per par. 5.2 DD is the Unit Code as per par. 5.3

GGG is the SDRL (Supplier Documents Requirements Listing) as per Attachment 1

NNNN is the Serial Document Number as per par 5.6

MM is the Sheet Number. Sheet Number shall be a 2-digit numeric string. The number of sheets applied to the VENDOR documents and drawings shall be 00.

Example: 1-P281235573-CF5100-D99-0005-00

Drawings

For Multi sheet drawings and single sheet drawings numbering kindly refer to section 5 for further explanation.

SUBCONTRACTOR DOCUMENTS AND DRAWINGS NUMBERING – COMPANY NUMBERING SYSTEM

SUBCONTRACTORS shall code their drawings, specifications, data sheets, plans, procedures and other documents as per the following:

A

  • PEEKKKKKKK

BBCCDD

  • GGG

NNNN

MM

Where:

A is a prefix and shall be 1 to indicate Package 1.

DOCUMENT CLASS 1

Page 15 of 20

Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0002-00

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

Rev

03

P is a letter and shall be A to indicate Agreement. EE is the Discipline Code as per par. 5.4 (Discipline Code is the main discipline driving the PO and is fixed for the respective full PO) KKKKKKK is the Agreement Number

BB is the Field Code as per par. 5.1 CC is the Area Code as per par. 5.2 DD is the Unit Code as per par. 5.3

GGG is the SDRL (Supplier Documents Requirements Listing) as per Attachment 1

NNNN is the Serial Document Number as per par 5.6.

MM is the Sheet Number. Sheet Number shall be a 2-digit numeric string. The number of sheets applied to the SUBCONBTRACTOR documents and drawings shall be 00.

Example: 1-P281235573-CF5100-D99-0005-00 For multi sheet drawings and single sheet drawings numbering kindly refer to section 5 for further explanation.

REVISION NUMBER

Revision sequence shall be according to Reference Document [1].

DOCUMENT FILE NAMING

The name of the Project document files will be assigned, prior to their loading into CONTRACTOR and COMPANY Engineering Documents Management System, as described here below.

File name:

• A-BBCCDD-EE-FFF-NNNN-MM_YY.xxxx

(Ex.1-CF0101-04-DSS-9001-00_A1.docx)

where:

YY= Revision issued to COMPANY (eg. A1, B1, 01 etc.)

xxxx = Extension assigned by the application program indicating the format (e.g.

DOCX for Microsoft Word, DWG for Autocad, XLSX for Excel, etc).

The file name of attachments to Project documents shall be obtained by adding the

following suffix to the file name of the Project document:

•

_AttK (Ex. 1-CF0101-04-DSS-9001-00_A1_Att1.docx)

where:

• K = attachment number (e.g. 1, 2, 3 etc.)

DOCUMENT CLASS 1

Page 16 of 20

Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0002-00

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

Rev

03

9.1

Isometric Drawings Coding system

Isometric coding uses the piping line numbering and shall be as follows:

BBCCDD-SSS-LLL_WWWW

Where:

BB: Field Code as per par. 5.1

CC: Area Code as per par. 5.2

DD: Unit Code as per par. 5.3

SSS: Sequential Line Number (as per P&IDs)

LLL: Fluid Code (as per P&IDs)

WWWW: WBS Codes As per Reference Document [3]

Each isometric tag is unique in all plant.

Example for line: GH5120-002-HCX-36”-68013SL-H

Isometric number: GH5120-002-HCX_WWWW

Field/Area/ Unit Code (BBCCDD)

Sequential Line Number as per P&IDs (SSS)

Fluid Code as per P&IDs (LLL)

WBS

(WWWW)

GH5120

002

HCX

As per Reference Document [3]

9.2

Isometric Electronic file naming

The name of the CONTRACTOR isometric document will be assigned, prior to their loading into CONTRACTOR and COMPANY Engineering Documents Management System, as described here below:

BBCCDD-SSS-LLL_WWWW.zip

Where the file .zip will contain one PDF file and the native files (PCF or SHA).

DOCUMENT NUMBERING SYSTEM – CONTRACTOR NUMBERING SYSTEM

In addition to the numbering system described above, for the purposes of its internal document management, CONTRACTOR, SUBCONTRACTORS, Third Parties Services providers and VENDORS shall code their drawings, specifications, data sheets, plans, procedures and other documents as per the following:

DOCUMENT CLASS 1

Page 17 of 20

Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0002-00

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

Rev

03

BBCCDD

PPQQQQQ

Where:

BB is the Field Code as per par. 5.1 CC is the Area Code as per par. 5.2 DD is the Unit Code as per par. 5.3 PP is the Document Creator Code as per par 9.1 QQ is the Document sequential number as per par 9.2

10.1

Document Creator Code (PP)

The following Document creator code shall be used by each party who requires the creation of the document in the document management system.

Code 10 20 30 40 50

Document Creator Saipem Islands Saipem Subsea NPCC Islands NPCC Subsea Saipem Islands (Specific for Drilling Centers)

10.2

Document sequential number (QQ)

The sequential number shall be selected so as to provide a unique PPQQQQQ over the Project.

To support the selection of the document sequential number the following numeric ranges should be used:

MANAGING DEPARTMENT

CONSTRUCTION / INSTALLATION

NUMERIC RANGE 02000-04999

PROCESS UTILITIES PROJECT MANAGEMENT, TECHNICAL MANAGEMENT

COMMISSIONING

QUALITY

PROCUREMENT

PROJECT CONTROL

CIVIL / STRUCTURAL

STATIC EQUIPMENT MACHINERY AND PACKAGES

08000-08999 86000-86999 09000-09499

09500-09599

09600-09699

09700-09799

09800-09999

10000-18999

20000-29999 30000-39899

DOCUMENT CLASS 1

Page 18 of 20

Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0002-00

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

Rev

03

MANAGING DEPARTMENT

ELECTRICAL CATHODIC PROTECTION INSTRUMENTATION AUTOMATION AND CONTROL TELECOMMUNICATION

PIPING ENGINEERING (Material specs) PIPING ENGINEERING (Stress specifications) PIPING ENGINEERING (Support Specifications) PIPING ENGINEERING (Layouts & MTO)

PIPING ENGINEERING (Coating, painting and insulation) PIPING ENGINEERING (Welding)

PIPELINE

LOSS PREVENTION AND ENVIRONMENT

HEALTH, SAFETY & ENVIRONMENT

POST ORDER

NUMERIC RANGE 40000-46999 47000-47999 50000-59999 48000-48999 49000-49999

60000-60699 61000-61099 61100-61499 62000-67999

60700-60799 60900-60999

80000-83999

85000-85799

85800-85999

73000-73899

DOCUMENT CLASS 1

Page 19 of 20

Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0002-00

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

Rev

03

ATTACHMENTS

11.1

Attachment 1 – Supplier Documents Requirements Listing (SDRL)

DOCUMENT CLASS 1

Page 20 of 20

Uncontrolled When Printed

GHASHA CONCESSION HAIL AND GHASHA DEVELOPMENT PROJECT

SUPPLIER DOCUMENTS REQUIREMENTS LISTING (SDRL)

Number of Hard Copies

Number of Hard Copies

Number of Hard Copies

I

D E R U Q E R T L U B S A

I

L = TEST & INSPECTION REPORTS

L01

L02

L03

L04

L05

L06

L07

L08

L09

L10

L11

L12

L13

L14

L15

L16

L17

L18

L19

MATERIAL TEST CERTIFICATE

WELDER PERFORMANCE QUALIFICATION CERTIFICATES

NDE OPERATOR QUALIFICATIONS

PRODUCTION TEST RESULTS (INCLUDING WELDING)

NDE RECORDS

HEAT TREATMENT RECORDS/STRESS RELIEF CHARTS

MATERIAL TRACEABILITY RECORDS

NAMEPLATE RUBBING/PHOTO’S

ELECTRICAL MACHINERY TYPE TESTS

ROUTINE TEST CERTIFICATE – ELECTRICAL MACHINERY

MEASUREMENT OF RESISTANCE

PAINTING / INSULATION INSPECTION REPORT

CERTIFICATE OF INSTALLATION OF VESSEL INTERNALS/LINING INCLUDING VIDEO DIGITAL PHOTOGRAPHS

EQUIPMENT PRESERVATION CERTIFICATE

CERTIFICATE OF EQUIPMENT CLEANLINESS

LEAKAGE TEST CERTIFICATE

HARDNESS TEST REPORT

PIPE RECONCILIATION

TPI Vendor Inspection Report/EPC FDR(EPC/TPI USE)

M = SHIPPING & PACKING DOCUMENTS

M01

M02

SHIPPING & PACKING DOCUMENTS

HAZARDOUS MATERIAL SHIPPING CERTIFICATES

N = RENEWABLE TEST AND CALIBRATION DATA

N01

N02

N03

N04

N05

N06

N07

N08

N09

N10

N11

N12

N13

N14

N15

N16

N17

PRESSURE TEST CERTIFICATES

INSTRUMENT TEST & CALIBRATION CERTIFICATE

LIFTING EQUIPMENT REGISTER & TEST CERTIFICATES

INSULATION RESISTANCE TEST PRESSURE VESSEL & EXCHANGER REGISTER & CODE DATA CERTIFICATES (IIA), AB25 MANUFACTURER DATA REPORT FOR PRESSURE VESSELS

CERTIFICATE OF COMPLIANCE

RELEASE NOTES

CERTIFYING AUTHORITY RELEASE NOTES

TECHNICAL DEVIATION REQUESTS

COSHH DATA SHEETS

CERTIFICATE OF CONFORMITY

PROGRAMABLE EQUIPMENT REGISTER AB96 GENERAL ENGINEERING REQUIRMENTS FOR DESIGN & CONSTRUCTION OF PRESSURE PIPING SYSTEMS

√

AB31 DESIGN REGISTRATION APPLICATION

AB83 CONSTRUCTION DATA REPORT FOR PIPING SYSTEMS AB83F CONSTRUCTION DATA REPORT FOR PIPING SYSTEMS MANUFACTURED OUTSIDE ALBERTA

AB41 STATUTORY DECLARATION FORM FOR REGISTRATION OF FITTINGS

P = MATERIAL ENGINEERING DATA (SUPPLIER WELDED)

P01

P02

P03

P04

P05

P06

WELD PROCEDURE SPECIFICATIONS (WPS) & QUALIFICATIONS (WPQ) RECORDS

NON-DESTRUCTIVE EXAMINATION PROCEDURES (NDE)

MANUFACTURING PROCEDURES INCLUDING HEAT TREATMENT

SURFACE PREPARATION & PAINTING PROCEDURE

WELD PROCEDURE FOR CASTING REPAIR

POSITIVE MATERIAL IDENTIFICATION PROCEDURE

Q = MATERIAL CERTIFICATE (FABRICATION SITE WELDED)

Q01

Q02

R = Manuals

R01

R02

R03

R04

MATERIAL CERTIFICATES - BULK ITEMS

MATERIAL CERTIFICATE - PACKAGE WELDED INTERFACES

DESPATCH DOSSIER

OPERATING/MAINTENANCE MANUAL

MECHANICAL CATALOGUES

MANUFACTURING RECORD BOOK(MRB)

I

N O T A T N E M U C O D L A N F

I

I

H C T A P S D D E D U L C N

I

E B O T

I

R E S S O D

S K E E W + O P

L A U N A M M & O

B R M

e u g o a t a C

l

l

a c

i

n a h c e M

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

I

D B H T W

I

I

W E V E R R O F

I

D E R U Q E R T A M R O F

E

4

4

4

4

4

4

4

4

4

4

4

4

4

4

4

4

4

4

4

4

4

4

4

4

4

4

4

4

4

9

4

4

4

4

4

4

4

4

4

4

4

4

4

4

4

4

4

Rev

STATUS DESCRIPTION

DATE

Prep

Checked

Approved

SUPPLIER DATA REQUIREMENTS LIST (SDRL)

PO / ENQUIRY No. :

DESCRIPTION :-

DOC. No.: XXXX-XXXX-XX-REQ-XXXX

  SHEET 1 OF

1

I

D E R U Q E R T L U B S A

I

A = CONTROL DOCUMENTS

A01

A02

A03

A04

A05

A06

A07

A09

A10

A11

A12

A13

VENDOR DOCUMENT REGISTER

FABRICATION / PRODUCTION SCHEDULE

PROGRESS REPORTS

BOUGHT OUT ITEMS / SUB ORDER COPIES

TABLE OF CONTENTS

SUPPLIER/SUB-SUPPLIER CONTACT DIRECTORY

PURCHASING/SUB-CONTRACTS EXPORT COMPLIANCE CHECKLIST

LIST OF CONFORMANCE/EXCEPTIONS

SUB-CONTRACTOR WORK PROPOSAL

SAFETY POLICY & PERFORMANCE RECORDS

INSURANCE CONFIRMATION

VENDOR SUB-ORDERS

B = INTERFACE AND ARRANGEMENT DRAWINGS

B01

B02

B03

B04

GENERAL ARRANGEMENT DRAWINGS

ACCEPTABLE NOZZLE LOADS

INTERFACE AND CONNECTION SCHEDULE

FOUNDATION LOADING DIAG. & SUPPORT DETAILS

C = DESIGN AND OPERATIONAL DATA

C01

C02

C03

C04

C05

C06

C07

C08

C09

C10

C11

C12

C13

C14

C15

C16

C17

C18

C19

PIPING & INSTRUMENT DIAGRAMS (P&ID’S)

ONE LINE ELECTRICAL DIAGRAMS

SCHEMATICS DIAGRAMS

UTILITIES SCHEDULE

WEIGHT DATA SHEETS

EQUIPMENT DATA SHEETS

NOISE LEVEL DATA SHEETS

SCHEDULE OF ELECTRICAL EQUIPMENT IN HAZARDOUS AREAS

DETAILS DESCRIPTION OF OPERATION

HVAC DUCTING & INSTRUMENT DIAGRAMS & FLOW DIAGRAMS

PROCESS FLOW DIAGRAMS, HEAT & MASS BALANCE

ELECTRICAL POWER SUPPLIES DATA SHEET

ENCLOSURE VENTILATION REQUIREMENTS

INSTRUMENT INDEX AND I/O SCHEDULE

INSTRUMENT DATA SHEET

CAUSE AND EFFECT CHARTS

INSTRUMENT / ELECTRICAL LOGIC DIAGRAM

VDU SCREEN DISPLAY GRAPHICS

BLOCK WIRING SCHEMATICS

C20

VALVE INDEX

C21

C22

C23

C24

C25

C26

VALVE DATA SHEETS

LINE (PIPING) LIST

SUPPLIER MASTER TAG LIST

DRUM LIST

LIST OF SPECIAL TOOLS

BILL OF MATERIAL

D = GENERAL DETAIL AND SUB-ASSEMBLY DRAWINGS

D01

D02

D03

D04

D05

D06

D07

D08

D99

CROSS SECT DWG / EXPLODED VIEW DIAGRAM

MECHANICAL SEAL DRAWINGS

SHAFT ALIGNMENT DRAWINGS

NAME PLATE FORMAT DRAWINGS

SUB ASSEMBLY DRAWINGS

DETAILED FABRICATION DRAWINGS

SHOP DETAILS

INSTALLATION DRAWINGS

MISCELLANEOUS DRAWINGS/DESCRIPTIVE LITERATURE

E = INSTRUMENT & ELECTRICAL DRAWINGS

E01

E02

E03

E04

E05

E06

E07

E08

E09

E10

E11

ELECTRICAL CONNECTION DIAGRAMS

INST / ELECT PANEL DETAIL DRAWING

TERMINATION DIAGRAMS

CABLE SCHEDULE

INSTRUMENT TERMINATION & HOOK UP DETAILS

LOOP DIAGRAMS

INSTRUMENT PLC DATA COMMUNICATION PROTOCOL

INSTRUMENT, F&G LOCATION PLANS

SHUTDOWN & CONTROL FUNCTION CHARTS

EARTHING ARRANGEMENTS

ELECTRICAL POWER REQUIREMENTS LIST

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

√

I

H C T A P S D D E D U L C N

I

I

R E S S O D

S K E E W + O P

L A U N A M M & O

B R M

E B O T

√

√

√

I

N O T A T N E M U C O D L A N F

I

I

D B H T W

I

I

W E V E R R O F

I

D E R U Q E R T A M R O F

E

1

1

1

1

1

5

1

1

1

1

1

1

2

4

3

3

2

2

2

4

4

3

3

3

3

2

2

3

3

3

3

3

3

1

3

3

3

3

3

3

10

1

1

3

3

3

3

1

1

1

1

3

2

3

3

3

3

1

3

3

3

3

PLEASE NOTE :-

( i ) A detailed description for each of the documents requested is given in the attached sheets. *

CONTRACTOR to refer to ANNEXURE 10G, Section 08 for the applicability of these documents and further requirements.

LEGEND :-

O - REVIEW BY ENGINEERING IN THE PROJECT OFFICE

R - REVIEW BY ENGINEERING AT THE SELLERS WORKS

S - REVIEW BY INSPECTOR AT THE SELLERS WORKS

A - REVIEW BY AUDIT AT THE SELLERS WORKS

F - CERTIFIED DOC. TO BE SENT TO

J -

INCORPORATE CERTIFIED ISSUE IN J01

SITE WITH MATERIALS

K -

INCORPORATE CERTIFIED ISSUE IN K01

H- DOC SHALL BE RETAINED IN

SAFE CUSTODY BY SELLER

E-FORMAT REQUIRED :-

1 - ANY

2 - Microstation

3 - NATIVE (WORD, EXCEL)

4 - PDF

e u g o a t a C

l

l

a c

i

n a h c e M

I

D E R U Q E R T L U B S A

I

F = CALCULATIONS & PERFORMANCE DATA

F01

F02

F03

F04

F05

F06

F07

F08

F09

F10

F11

F12

F13

F14

F15

F16

F17

F18

F19

F20

F21

F22

F23

F24

F25

F26

F27

F28

F29

F30

F31

F32

F33

F34

F35

F36

F37

F38

F39

F40

F41

F42

F43

F44

F46

F99

PRESSURE VESSEL/TANK MECH CALCS.

PROCESS/UTILITY CALCULATIONS

STRUCTURAL STEEL CALCULATIONS

FOUNDATION SUPPORT CALCULATIONS

SYSTEM HEAD LOSS CALCULATIONS

LATERAL CRITICAL SPEED CALCULATION

TORSIONAL CRITICAL SPEED CALCULATIONS

BEARING LIFE CALCULATIONS

THRUST BEARING SIZING CALCULATIONS

HEAT EMISSION CALCULATIONS

ACOUSTIC ANALYSIS FOR RECIPROCATING COMPRESSORS

HYDRAULIC CALCULATIONS

EXCHANGER THERMAL RATING CALCULATIONS

INSTRUMENT CALCULATION (ALSO REFER F25)

ENCLOSURE VENTILATION SYSTEM CALCULATIONS

EXHAUST DUCT CALCULATIONS

COUPLING SELECTION CALCULATIONS

LUBE & SEAL OIL SIZING CALCULATIONS

ANTI SURGE VALVE SIZING CALCULATIONS

PULSATION DAMPER DESIGN CALCULATIONS

ROTOR/SHAFT SYSTEM UNBALANCED RESPONSE ANALYSIS

PIPING STRESS ANALYSIS

CRANE FAILURE MODE ANALYSIS

ESD VALVE

RELIEF VALVE & BURSTING DISC CALCS. (REFER F14)

ELECTRICAL PROTECTION STUDY

CURRENT/POTENTIAL (CT/VT) TRANSFORMER CURVES

MOTOR PERFORMANCE CURVES

COMBUSTION GAS TURBINE PERFORMANCE CURVES

CENTRIFUGAL PUMP PERFORMANCE CURVES

ROTARY PUMP CURVES

CENTRIFUGAL COMPRESSOR PERFORMANCE CURVES

FAN PERFORMANCE CURVES

ENGINE PERFORMANCE CURVES

GENERAL PERFORMANCE DATA

SPEED/TORQUE STARTING CURVES

RECIPROCATING PUMP PERFORMANCE CURVES

LIGHTING PERFORMANCE DATA

BATTERY CHARGE/DISCHARGE CALCULATIONS

POWER SYSTEM ANALYSIS DATA

RELIABILITY/AVAILABILITY DATA & CALCULATIONS

PERFORMANCE GUARANTEE

SHORT CIRCUIT CALCULATIONS

NOZZLE LOAD ANALYSIS

SUPPORT CALCULATIONS

MISCELLANEOUS CALCULATIONS

G = HANDLING, INSTALLATION & SITE PRESERVATION

G01

G02

G03

G04

G05

G06

G07

ERECTION & INSTALLATION PROCEDURE

UNPACKING & PRESERVATION PROCEDURE

HANDLING & SHIPPING PROCEDURES

PRE-COMMISSIONING/COMMISSIONING PROCEDURES

ERECTION FASTENERS SUMMARY LIST

SLING/LIFTING ARRANGEMENT

MAINTENANCE PROCEDURE FOR LONG-TERM STORAGE

H = MANUFACTURING / QUALITY PROCEDURES

H01

H02

H03

H04

H05

H06

H07

H08

H09

H10

H11

ISO9000 REGISTRATION CERT. OTHERWISE QA MANUAL INDEX

QUALITY PLAN

INSPECTION & TEST PLAN

PRESSURE TEST PROCEDURES

PERFORMANCE TESTING AND ACCEPTANCE TEST PROCEDURE.

SOFTWARE QUALITY SYSTEM

WEIGHING PROCEDURE

HEALTH SAFETY & ENVIRONMENTAL MANAGEMENT SYSTEM

HEALTH SAFETY & ENVIRONMENTAL PLAN (HS&E PLAN)

PROPOSED SOFTWARE LISTING

NOISE CRITERIA DATA & TEST PROCEDURES

J = COMMISSIONING, OPERATING, MAINTENANCE & SPARES

J01

J02

J03

LUBE OIL &OPERATING FLUID SCHEDULES

RECOMMENDED START-UP & COMMISSIONING SPARES LIST (PRICED)

RECOMMENDED SPARES FOR 2 YEARS OPERATIONS (PRICED)

K = CERTIFICATION

K01

K02

K03

K04

K05

K06

K07

K08

K09

K10

K11

K12

K13

PERFORMANCE TEST REPORT/RESULTS

FACTORY ACCEPTANCE TEST REPORT (FAT)

VIBRATION REPORT

NOISE REPORT

WEIGHING REPORT & CERTIFICATES

DIMENSIONAL REPORT / DRAWINGS

FIRE TEST REPORTS/CERTIFICATES

EQUIPMENT HAZARDOUS AREA CERTIFICATES

HAZOP REPORTS

REGISTER OF SAFETY RELATED DEVICES

SAFETY INTREGRITY LEVEL (SIL) REPORTS

STUDY REPORTS

FUNCTIONAL TEST REPORTS

√

√

√

√

√

√

√

I

H C T A P S D D E D U L C N

I

E B O T

I

R E S S O D

S K E E W + O P

L A U N A M M & O

B R M

e u g o a t a C

l

l

a c

i

n a h c e M

√

√

√

√

√

√

√

√

√

√

I

N O T A T N E M U C O D L A N F

I

I

D B H T W

I

I

W E V E R R O F

I

D E R U Q E R T A M R O F

E

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

6

7

8

1

1

1

1

1

1

4

4

1

3

3

3

3

ANNEXURE 10G, SECTION 03 APPENDIX 1_SUPPLIER DOCUMENT REQUIREMENT LISTING

ABU DHABI NATIONAL OIL COMPANY (ADNOC) GHASHA CONCESSION PROJECTS

Drawing / Document Number, Title and Revision:

Doc Status Code:

Doc. No.:

1-CF0000-59-PRO-0002-00_03

Rev. No. :

03

CODE 1-NO COMMENTS

Doc Class:

Title:

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING

CLASS 1

Discipline:

59-Project Mgt_Quality Mgt_Admin

Pos No.

Page number

COMPANY Comments Description

COMPANY Originator NAME

CONTRACTOR Confirmation / Explanation

ACTION BY CONTRACTOR

1 2 3

File: MacroCommentSheet_EPC

Page 1/1

Project: Q-32855 - Saipem Hail & Ghasha Folder: Reference documents


Loading authentication...

Graph View

Backlinks

  • 00 Index

Created with Infinity Constructor © 2025

  • Elynox | Go Further