ABU DHABI NATIONAL OIL COMPANY (ADNOC) GHASHA CONCESSION PROJECTS

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS COMPANY DOC NO: 1-CF0000-59-PRO-0006-00

Rev. 04

ABU DHABI NATIONAL OIL COMPANY (ADNOC) GHASHA CONCESSION PROJECTS

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

Contractor Document Number: CF0000-1009006

04

03

02

Rev

20/05/2024

18/12/2023

30/09/2023

Date (DD/MM/YYYY)

IFU

IFU

IFU

Issued for USE

A. Parlato S. Feliziani P. Santoni

C. Copelli

Issued for USE

A. Parlato S. Feliziani P. Santoni

C. Copelli

Issued for USE

L. Ceoloni S. Feliziani

P. Santoni

P. Santoni

Status

Status Description

PREPARED

CHECKED

APPROVED 1

APPROVED 2

This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.

DOCUMENT CLASS - 1 Page 1 of 29

       Uncontrolled When Printed

ABU DHABI NATIONAL OIL COMPANY (ADNOC) GHASHA CONCESSION PROJECTS

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS COMPANY DOC NO: 1-CF0000-59-PRO-0006-00

Rev. 04

This document is rolled over from PCSA document no. 1-CF0000-59-PRO-0006-00 Rev. 01

Rev

01

00

B1

A1

Date

(DD/MM/YYYY)

17/04/2023

03/04/2023

17/02/2023

26/01/2023

SUMMARY OF DOCUMENT REVISIONS

Status

Status Description

IFU

IFU

IFA

IFR

Issued for USE

Issued for USE

Issued for Approval

Issued for Review

DOCUMENT CLASS - 1 Page 2 of 29

       Uncontrolled When Printed

ABU DHABI NATIONAL OIL COMPANY (ADNOC) GHASHA CONCESSION PROJECTS

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS COMPANY DOC NO: 1-CF0000-59-PRO-0006-00

Rev. 04

HOLD

Section

Description

HOLD LIST

DOCUMENT CLASS - 1 Page 3 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

TABLE OF CONTENTS

PROJECT OVERVIEW … 5

1.1

EPC for HAIL & GHASHA Development Project … 5

PURPOSE … 6

DEFINITIONS AND ABBREVIATIONS … 6

3.1

3.2

Definitions … 6

Abbreviations … 6

REFERENCE DOCUMENTS … 7

DOCUMENT CLASSES … 8

STATUS CODES … 8

DOCUMENT APPROVAL PROCESS … 9

7.1

7.2

7.3

7.4

7.5

Class 1 Documents … 9

Class 2A Documents …10

Class 2B Documents …12

Class 2C Documents …12

Class 3 Documents …14

VENDOR DOCUMENTS …14

REVISION STATUS REQUIREMENTS …15

DOCUMENTATION’S REVISION IDENTIFICATION …16

RESPONSIBILITIES …16

APPENDIX 1 – DOCUMENT CLASSIFICATION …18

APPENDIX 2 – AS-BUILT DOCUMENTATION …27

ATTACHMENTS …29

14.1 Attachment 1 – Comment Resolution Sheet (CRS) …29

DOCUMENT CLASS - 1 Page 4 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

PROJECT OVERVIEW

1.1

EPC for HAIL & GHASHA Development Project

The Hail & Ghasha Development (HGD) Project is of strategic importance to the Emirate of Abu Dhabi. The Project will develop the untapped oil and gas reserves from the highly sour Hail and Ghasha fields. Production is targeted to start by Q4 2027 with sustainable production of 1 BSCFD of Raw Gas, and max production of 82.5 MSBPD of Oil, 76.3 MSBPD of Condensate, 9000 TPD of Sulphur and 5030 TPD of NGL. In addition, Project will capture 1.52 million tonnes of CO 2 per year taking ADNOC’s committed investment for carbon capture capacity. The Hail and Ghasha fields are situated offshore ABU DHABI about 140 km away from ABU DHABI mainland in water depths varying from 0 to 15 meters.

The HGD Project comprises the following:

• Artificial Islands Construction;

• Offshore package – EPC 01: Offshore Drilling Centres (DCs), Subsea Pipelines, Umbilicals, Power Cable Connections, Seawater Intake Structure, Bridges, Risers, Flare Structure, facilities at Ghasha Offshore Processing Plant (“GOP”);

• Onshore package – EPC 02: Manayif Onshore Processing Plant (“OPP”), Manayif

Utilities, Offsite Pipelines & Tie-ins, Main Control and Other Buildings.

The HGD Project will be executed in a single phase approach. It will start production from three Drilling Centres (Reeah, Jzool & Seebah) in Ghasha Field to GOP and from Gaff Island in Hail Field to OPP. Remaining Drilling Centres, gas injection, and other associated facilities will be developed in ‘future’ to sustain production from Hail & Ghasha fields.

Figure 1 - Hail & Ghasha Fields

DOCUMENT CLASS - 1 Page 5 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

PURPOSE

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

The purpose of this document is to describe Document Management and Control process for the project deliverables by CONTRACTOR, VENDORs, SUBCONTRACTORs etc. for the Offshore Package.

DEFINITIONS AND ABBREVIATIONS

3.1

Definitions

COMPANY

Abu Dhabi National Oil Company (ADNOC)

CONTRACTOR

Unincorporated Joint Venture NPCC -SAIPEM

PROJECT

Hail and Ghasha Development Project

SUBCONTRACTOR

VENDOR/SUPPLIER

Any Person approved in writing by the COMPANY to whom execution of any part of the Works is subcontracted by the CONTRACTOR and any other subcontractors of any tier of such Person, and includes its legal successors and/or permitted assigns

A supplier of Materials in connection with the Works including related documentation and services, where necessary.

3.2

Abbreviations

ADNOC

AGES

AGRU

BEDD

BPD

BSCFD

BTEX

BWPD

CCP

CLQ

DC

EPC

GOP

H&MB

HGD

Abu Dhabi National Oil Company

ADNOC Group Engineering Standards and Specifications

Acid Gas Removal Unit

Basic Engineering Design Data

Barrel per Day

Billion Standard Cubic Feet per Day

Benzene, Toluene, Ethyl benzene, Xylenes

Barrels of Water Per Day

Compression Centre Platform

Central Living Quarter

Drilling Centre

Engineering, Procurement, Construction

Ghasha Offshore Processing

Heat & Material Balance

Hail & Ghasha Development

DOCUMENT CLASS - 1 Page 6 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

HIPPS

HP

HPU

LP

MSBPD

MMSCFD

NGL

NORM

NUA

OPP

PWT

SOW

SRU

TDS

TGTU

TPD

TSS

UAE

VRU

High Integrity Pressure Protection System

High Pressure

Hydrogen Production Unit

Low Pressure

Kilo Thousand Standard Barrels per Day

Million Standard Cubic Feet per Day

Natural Gas Liquids

Naturally Occurring Radioactive Materials

Normally Unattended Asset

Onshore Processing Plant

Produced Water Treatment

Scope of Work

Sulphur Recovery Unit

Total Dissolved Solids

Tail Gas Treatment Unit

Ton per Day

Total Suspended Solids

United Arab Emirates

Vapour Recovery Unit

REFERENCE DOCUMENTS

Sl. No.

Document No.

Document Title

1

2

3

1-CF0000-59-PRO-0002-00

1-CF0000-59-PRO-0004-00

1-CF0000-50-PRO-9819-00

PROJECT PROCEDURE FOR DOCUMENT AND DRAWING NUMBERING DOCUMENTS TITLE BLOCKS

DOCUMENT MANAGEMENT AND CONTROL PROCEDURE

DOCUMENT CLASS - 1 Page 7 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

DOCUMENT CLASSES

This document defines the minimum requirements for the handling of review, comment, and approval of documentation on the Offshore Package, and the actions to be taken. The requirements provided herein are minimum requirements. All drawings, documents and manuals submitted shall be classified in one of the following three categories for the purposes of review, comment and approval.

Class 1: All documentation in Class 1 shall require formal COMPANY approval.

Class 2: Documentation in Class 2 shall be issued to COMPANY for comment. If comments are not received within stipulated period, CONTRACTOR may assume that COMPANY has no comments. CONTRACTOR shall inform COMPANY in writing of its intention to proceed with work. There should be 2 days between the written notification and CONTRACTOR proceeding with work.

Class 2 documents shall be further categorized as follows:

• 2A for documents foreseeing only IFR/Final reviews.

• 2B for documents foreseeing IFR/IFA/Final reviews / approval.

• 2C for P&IDs that will be subject to IFR/IFH/IFA/Final reviews / approval.

Class 3: Documentation in Class 3 shall be issued to COMPANY for information only. However, comments made on Class 3 documents shall also be considered when received in a timely manner or advised that they are being developed, again within a reasonable time from issuance.

COMPANY shall require maximum (10) working days for review of all documents for all revisions submitted by CONTRACTOR. At all issue stages as applicable to the document class 2 and 3, CONTRACTOR may proceed if no COMPANY comments are received within timeframe. CONTRACTOR shall however notify COMPANY beforehand, in writing, if it is intending to proceed on this basis.

the above

STATUS CODES

COMPANY’s comments on the submitted documents shall carry one of the following codes:

Code 1

No Comments

Work may proceed

Code 2

Comments as noted

Work may proceed subject to compliance with and incorporation of comments.

Code 3

Rejected

Revise and resubmit. Work shall not proceed.

Code 4

Information only

Accepted for information only.

Note: In case of minor comments, Code 1 can be provided by COMPANY. However, CONTRACTOR will still have to produce CRS (reference shall be made to Attachment 1)

DOCUMENT CLASS - 1 Page 8 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

and demonstrate implementation of comments before final revision. These shall also be part of the document status tracking register that shall be shared with COMPANY.

DOCUMENT APPROVAL PROCESS

All documents prepared shall, depending on their class, pass through the following stages: IDC:

Issued for Inter-Discipline Check (Internal to CONTRACTOR).

IFR:

Issued for COMPANY Review.

Or IFI:

Then IFH:

Then IFA:

Issued for Information - Class 3 or as required and pre-agreed with COMPANY.

Issued for HAZOP Review / SIL Review (if applicable to class).

Issued for Approval (if applicable to class).

Then either, IFP: process - End of document lifecycle.

Issued for Purchase - For documents to be used in the procurement/sub-contract

Or IFU:

Or IFC:

Issued for Use - Final version signifying end of document lifecycle.

Issued for Construction - End of document lifecycle.

Eventually, all technical documents must reach either IFI, IFP, IFU or IFC, status as appropriate for the type of document.

Note: CONTRACTOR may issue subsequent revisions of IFA documents if required to support its design process, e.g. when VENDOR information becomes available. The following outline procedure shall be followed for the review and approval of documents on the Offshore Package.

Note: For documents rolled over from PCSA phase, the review cycle will be done in continuation with the document status and code number from the PCSA phase. By way of example, if a document has reached a Code 1 status, it will be re-issued in final revision. If the document has reached a Code 2 status, it will be re-issued in the next revision addressing the comments relevant to PCSA phase. When issuing the document to COMPANY, while such document shall refer to the revisions as applicable to EPC phase, following note shall be added to enable COMPANY to refer to PCSA stage last revision: “This document is rolled over from PCSA document no. XXXXX rev. XX”.

7.1

Class 1 Documents

• Class 1 shall be indicated on the document.

DOCUMENT CLASS - 1 Page 9 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

• First issue to COMPANY shall be IFR.

•

•

In the event of Code 3 comment on IFR, reissue as IFR until Code 2 or Code 1 is received.

In the event of Code 1 on IFR, document may be issued IFC/IFP/IFU. In the event of Code 2 comments on IFR, issue as IFA after incorporating comments (this is always valid except with written approval by COMPANY to proceed with final issuance).

• Following Code 1 on IFA, document to be issued IFC/IFP/IFU.

• For Class 1 documents, if COMPANY comments are not received, CONTRACTOR

cannot proceed with next revision.

Refer to Figure 2 for a diagrammatic representation of Class 1 document issue stages.

IDC

Internal to CONTRACTOR

Code 3 COMPANY comments

IFR

CONTRACTOR to wait for Code 1 or code 2 COMPANY comments. Code 1 may proceed direct to IFC/IFP/IFU without IFA issue. Code 2 shall be issued IFA.

Code 2 or Code 3 COMPANY comments

IFA

CONTRACTOR to wait for Code 1 COMPANY comments before issuing IFC/IFP/IFU.

IFC

IFU

IFP

As required to support procurement activities.

Figure 2 – Class 1 Documents Issue Stages

7.2

Class 2A Documents

• Class 2A shall be indicated on the document.

• First issue to COMPANY shall be IFR.

•

In the event of Code 3 comments on IFR, reissue as IFR until Code 2 or Code 1 is received.

DOCUMENT CLASS - 1 Page 10 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

• Following receipt of Code 1 ‘No Comments’ or Code 2 on the IFR, document shall be issued IFC/IFP/IFU. However, there shall be a mutually agreed mechanism to ensure that COMPANY comments are incorporated (as for example CRS, per Attachment 1, signed by both parties may be attached to subsequent revision of the document).

•

•

If Code 2 is given on IFC/IFP/IFU, document shall be re-issued. End of document lifecycle will only be achieved with receipt of Code 1 on IFC/IFP/IFU.

In case COMPANY did not provide comments within stipulated review time, CONTRACTOR can proceed with the next revision after written information with the attention that prior to proceeding is informed to COMPANY.

Refer to Figure 3 for a diagrammatic representation of Class 2A document issue stages.

IDC

Internal to CONTRACTOR

.

IFR

Code 1 or Code 2 (with agreement on CRS) may proceed direct to IFC/IFP/IFU

Code 3 COMPANY comments

IFC

IFU

IFP

As required to support procurement activities.

Figure 3 – Class 2A Documents Issue Stages

DOCUMENT CLASS - 1 Page 11 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

7.3

Class 2B Documents

• Class 2B shall be indicated on the document.

• First issue to COMPANY shall be IFR.

•

•

In the event of Code 3 comments on IFR, reissue as IFR until Code 2 or Code 1 is received.

In the event of Code 1 ‘No Comments’ or Code 2 on IFR, document may be issued IFA.

• Following receipt of Code 1 ‘No Comments’ on the IFA, document shall be issued IFC/IFP/IFU (this is always valid except with written approval by COMPANY to proceed with final issuance even if it is Code 2).

•

•

If Code 2 is given on IFC/IFP/IFU, document shall be re-issued. End of document lifecycle will only be achieved with receipt of Code 1 on IFC/IFP/IFU.

In case COMPANY did not provide comments within stipulated review time, CONTRACTOR can proceed with the next revision after having informed COMPANY.

Refer to Figure 4 for a diagrammatic representation of Class-2B document issue stages.

IDC

IFR

IFA

Upon getting Code 1 or code 2 from COMPANY, CONTRACTOR can proceed to IFA.

Code 1 may proceed direct to IFC/IFP/IFU without IFA issue.

CONTRACTOR may proceed if Code 1 is received.

Code 3 COMPANY comments

Code 2 or Code 3 COMPANY comments

IFC

IFU

IFP

As required to support procurement activities.

Figure 4 – Class 2B Documents Issue Stages

7.4

Class 2C Documents

• Class 2C shall be indicated on the document.

• First issue to COMPANY to be IFR.

DOCUMENT CLASS - 1 Page 12 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

•

In the event of Code 3 comments on IFR, reissue as IFR until Code 2 or Code 1 is received.

• After desktop and design review (e.g. P&ID review) incorporate the comments and

issue IFH.

• Specialist / independent review / HAZOP / SIL comments / actions on IFH Documents

shall be incorporated prior to issuing IFA.

• Following Code 1 on IFA, document to be issued IFC.

•

•

If Code 2 is given on IFC, document shall be re-issued. End of document lifecycle will only be achieved with receipt of Code 1 on IFC.

In case COMPANY did not provide comments within stipulated review time, CONTRACTOR can proceed with the next revision after having informed COMPANY.

Refer to Figure 5 for a diagrammatic representation of Class 2C document issue stages.

IDC

IFR

Code 1 or 2

IFH

Code 1 or 2

Code 3 COMPANY comments

Code 3 COMPANY comments

HAZOP/SIL or other independent review

COMPANY / Independent Reviewer or HAZOP/SIL comments to be incorporated prior to IFA issue.

Code 2 or Code 3 COMPANY comments

IFA

IFC

CONTRACTOR to wait for Code 1 comments before issuing IFC.

Figure 5 – Class 2C Documents Issue Stages (P&IDs)

DOCUMENT CLASS - 1 Page 13 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

7.5

Class 3 Documents

• Class 3 shall be indicated on the document.

• First issue to be IFI/IFC.

•

In the event of COMPANY comments, document to be reissued after incorporating comments.

Refer to Figure 6 for a diagrammatic representation of Class 3 document issue stages.

IDC

Internal to CONTRACTOR

If COMPANY comment on IFI only.

IFI/IFC

Figure 6 – Class 3 Documents Issue Stages

Note: IFC issue is foreseen only for: Isometric Drawings, Piping Arrangement Drawings, Future PFDs, duplicated P&IDs, Piling Layout & Bar Bending Schedule, Pits/Manholes Schedules, Cable Routing Layouts 1 , Lighting Layouts1, Interconnection Diagrams, Telecom Equipment Layouts, Telecom Cables Route Layouts 1, Instrument Index, Loop Diagrams and Schematics, Main Cable Route and Trenches1, Instrument Location plans, Interconnection and Termination Drawings, Instrument Cable Schedule, Installation Drawings, Level Coordination Sketches, Hydraulic tube layout.

VENDOR DOCUMENTS

CONTRACTOR will assign similar classification (Class 1 / Class 2A, 2B, 2C / Class 3) to Vendor documentation. The Supplier Document Requirement List (SDRL) with classification will be submitted for COMPANY approval. Vendor documents with CONTRACTOR’s comments will be made available to COMPANY engineering team for review and, in parallel, they will be sent to VENDOR as advance copy (only for critical documents which need urgent approval). COMPANY’s comments will be integrated in the CONTRACTOR’s comments and sent to VENDOR which will consider this version as final approval.

1 Referring only to Cable routings extracted from 3D model

DOCUMENT CLASS - 1 Page 14 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

For vendor documents that are deemed critical, COMPANY may assign Class 1, and document will be on hold until COMPANY comments are finalized. COMPANY may decide at its sole decision that some Vendor documents are reviewed by CONTRACTOR only and that all documents’ revisions are issued to COMPANY for information. In all cases, it is CONTRACTOR’s responsibility to ensure that all the requirements of the Offshore Package are met including the applicable standards and specifications.

Submission

Partial comments

Consolidated comments

VENDOR

y p o c e c n a v d a

2

d n a

1

e d o C

R O T C A R T N O C m o r f

d e t c e e R 3

j

e d o C

R O T C A R T N O C m o r f

CONTRACTOR

m o r f 2

d n a

1

e d o C

Y N A P M O C d n a R O T C A R T N O C

CONTRACTOR shall submit the commented version to VENDOR and to COMPANY for critical documents only.

COMPANY

COMPANY comments on CONTRACTOR commented copy.

Figure 7 – Vendor Documents Issue Stages

REVISION STATUS REQUIREMENTS

The applicable revision status shall be entered in the document title block for each revision of the document to build up a revision history. The following revision status shall be used.

Revision

Status

Status Description

X1A1, X2A1, X3A1, etc

X1A1, X1A2 etc

X1B1, X1B2 etc

X100 etc

Internal

IDC

CONTRACTOR internal documents not issued to COMPANY; revision begins with Xn followed by A1.

for

Issued Inter Discipline Check; revision begins with a X1 and revision sequential number.

A1, A2, A3, etc

IFR

Issued for COMPANY review.

DOCUMENT CLASS - 1 Page 15 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

Revision

Status

Status Description

H1, H2, H3, etc

B1, B2, B3, etc

E1, E2, E3, etc

00,01,02, etc

Z0, Z1, Z2, etc

CN

IFH

IFA

IFI

IFC

IFP

IFU

AB

ICN

Issued for HAZOP.

Issued for COMPANY approval.

Issued for Information.

Issued for Construction / Purchase / Use

As-Built

Issued for Cancellation / Voided.

DOCUMENTATION’S REVISION IDENTIFICATION

Revisions due to CONTRACTOR/ COMPANY comments or to Project development, shall be indicated in the CONTRACTOR, SUBCONTRACTOR, VENDOR documentation as follows:

• WORD documents: word track changes in the native file, left vertical line along the

modified sections in the acrobat version;

• EXCEL documents: modified cells shall be yellow highlighted and relevant revision

number shall be indicated in the dedicated column;

• DRAWINGs: revised sections shall be “clouded” and a triangle showing the revision

number shall be placed within or adjacent to changed portion.

In case of limited updates to any document from the FEED stage, track changes / revision clouds as specified above shall be used to allow quick turn over of documents.

RESPONSIBILITIES

• The responsibility for ensuring COMPANY receives all relevant documents rests with CONTRACTOR. CONTRACTOR shall be responsible for replacing documents lost or damaged in transit at no extra cost to COMPANY.

• COMPANY’s Project Management shall inform CONTRACTOR in advance in writing

of any changes in COMPANY documentation requirements.

• CONTRACTOR shall be responsible for specifying the review classification for each document in accordance with the Offshore Package requirements and, if Class 1 or 2A, 2B, 2C, stating the stipulated COMPANY response period.

DOCUMENT CLASS - 1 Page 16 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

• Approval by COMPANY of CONTRACTOR documentation shall be in writing but such approval or any review shall not in any way relieve CONTRACTOR of any of its responsibilities or liabilities under the AGREEMENT or the law.

•

If any document is rejected by COMPANY, COMPANY will provide a written explanation of the reasons therefore CONTRACTOR shall reissue documents with amendments as may be necessary to reflect COMPANY’s requirements.

• CONTRACTOR shall investigate the root cause analysis of any rejected documents

and initiate a corrective action. RCA shall be part of the resubmission.

• All documentation requiring COMPANY’s approval shall first be submitted to COMPANY for review and comment. After resolution/incorporation of COMPANY’s comments, the documentation shall then be re-submitted for COMPANY approval. Once such approval has been given in writing, CONTRACTOR may issue the documentation for detailed engineering, procurement, construction, or other purposes as required to support the WORKS.

• CONTRACTOR shall be responsible

for

the VENDOR/SUBCONTRACTOR

submissions, comments consolidation (along with COMPANY), and closure.

• CONTRACTOR shall provide a steady load per discipline and per class for documents review and approval. Any unplanned peaks per discipline, COMPANY will have the rights to extend the approval cycle for all document classes.

DOCUMENT CLASS - 1 Page 17 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

APPENDIX 1 – DOCUMENT CLASSIFICATION

The appended Document Classification Table provides guidelines to be adopted for classification of documents on the Offshore Package.

DOCUMENT DESCRIPTION

DOC. CLASS

SR No.

1.0 CORRESPONDANCE

2.0 GENERAL

Project Execution Manual (Containing All Project Procedures)

CONTRACTOR’s RACI Matrix

IDC Matrix

Interface Responsibility Matrix

Distribution Matrix

Minutes of Meeting

Project Coordination Procedure

Detailed Procedure for Services

Standard, Design Guides and Procedures

Project Organization and Manning

Asset Register

Project Close-out Report

Design Books

VENDOR/SUBCONTRACTOR Equipment Operating and Maintenance Manuals

Mechanical Catalogues

Manufacturing Record Books INDEX

Manufacturing Record Books

Vendor Data Book

As-Built Drawings

Safety Plan and Manual

VENDOR/SUBCONTRACTOR Shop Inspection and Quality Control Manual

Spare parts List

Quality Control Manuals

Drawing Schedule

Corporate SPECIFICATION Schedule

Organization Chart

Overall Project Schedule

Variations

Technical Bid Evaluation for Services

Technical Bid Evaluation for Materials

1

1

1

1

1

2A

1

2B

1

2B

2B

3

3

3

3

1

1

1

3

1

1

2B

2

2

3

1

1

1

3

2A

DOCUMENT CLASS - 1 Page 18 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

SR No.

DOCUMENT DESCRIPTION

3.0

PROCUREMENT & SUBCONTRACTING

DOC. CLASS

CONTRACTOR’S final Bidders List for Materials and Services for Cost Plus Items

Tenderer’s List for procurement of Materials and Equipment

Material Requisitions

Recommendations for award to VENDORS – (Unpriced) for RVL Items

Recommendations for award to SUBCONTRACTORS

Expediting Reports

VENDOR/SUBCONTRACTOR Schedules

Procurement Status Report

VENDOR/SUBCONTRACTOR Manufacturing Quality Plans

Inspection Plan and Schedules Subcontractor Inspection and Test Plan Vendor Inspection and Test Plan CR 1/CR2/CR3 Vendor Inspection and Test Plan CR 4

Inspection Reports

Testing Reports FAT/IFAT/YAT/SAT reports

Inspection Status Report

Spare Parts List for Two Years

List of Construction Spares

Inspection Release Reports (for Shipping)

Transportation Plan and Procedures

Shipping Forecast

Shipping Progress Reports

Copy of Bill of Lading

Delivery Certificate to SITE

List of Claims for Damages

Purchase Orders (Unpriced)

4.0

ENGINEERING

4.1 General

Basis of Design

General Specifications

Project Specifications Project Philosophies

HAZOP Procedure

List of CONTRACTOR’S Drawings and Documentation

4.2

Process Engineering

1

1

2A

2A

1

3

3

3

1

1 1 1 2A

3

2A 1

2B

2B

2A

2A

2B

2A

3

3

3

3

3

1

1

1 2B

1

3

DOCUMENT CLASS - 1 Page 19 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

SR No.

DOCUMENT DESCRIPTION

DOC. CLASS

Mass, Heat and Utility Balances

Process Flow Diagrams (PFDs)

Future Process Flow Diagrams

Piping and Instrument Diagrams (P&IDs)

Battery Limits Piping and Instrument Diagrams

Duplicated P&IDs (Wells)

Cause and Effect Charts (Plant and Package Units) Process Studies and Reports Process Description, Narrative and Philosophy Process Summary and List

4.3 Civil / Structural Engineering

Plot Plans

Building Plans

Design Specifications for Civil Works and structures

Foundation Layout Drawings

Design and Drawings for Pipe Sleepers, Pipe Rack and Supports

Engineering Design Calculation

Design Drawings for Concrete, Reinforced Concrete and Steel Structures

Foundation Drawings for Steel Structures

Construction Specifications for Civil Work and structures Deliverables for heliports Grading Plans Drawings Fencing, Roads, Paved Areas, Parking Bays, Sumps, Trenches and Crossovers Drawings Tank Foundations Drawings Equipment Foundations and Equipment Shelter Drawings Architectural Work Drawings Plumbing/Sanitary Work Drawings Underground Drainage Work Drawings

4.4

Piping Engineering

SITE Plan

Materials Selection for Pipe and Components

Pipe Sizing, W/T, Insulation Thickness and Rating Calculations

Piping Routing Studies

Plot Plans and Equipment Layouts

Drawings Index / key plans

General Arrangement Drawings

Piping Stress Calculations

2B

1

3

2C

3

3

2B 2B 2B 2B

1

2A

1

3

2A

2A

2A

2A

2A 2A 2A 2A 2A 2A 2A 2A 2A

1

1

2B

3

1

2A

3

2A

DOCUMENT CLASS - 1 Page 20 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

SR No.

Line List

DOCUMENT DESCRIPTION

DOC. CLASS

Data Sheets for Piping Components

Piping Specifications

Piping Standards

Electronic 3D Model Development Reports

Isometric Drawing with BOM

Tie-in Drawings Piping MTO

4.5

Vessels / Tanks Engineering

Updated Vessel / Tank Type and Material Selection

Sizing, Design Calculations

Updated Data Sheets

General Arrangement Drawings (if required)

Design Drawings

  • Nozzle Orientation and Support Clips

  • Flanges and Internals

Ladders and Platforms

VENDOR/SUBCONTRACTOR Data and Drawings for Special Technology Equipment, Vessel under Pressure above 40bar and/or temp over 200°C or below 0°C, storage tanks for hydrocarbon and chemicals

Design Analysis Reports for Tanks (submitted before calculations) - if required for design

4.6 Heat Transfer Equipment Engineering

Equipment Type and Material Selection

Sizing

Data Sheets

Standard Drawings

General Arrangement Drawings

Design Drawings

  • Nozzle Orientation and Support Clips

  • Flanges and Internals

VENDOR Data and Drawings for Special Technology Equipment like Furnaces and Heaters, Waste Heat Boilers, Incinerators, Heat Exchangers and Air Coolers above 40bar pressure and/or temp over 200°C or below 0°C

4.7 Rotating Machines Engineering

Equipment Type and Material Selection

Sizing Calculations

3

2A

1

2A

2A 2A

3

2B 3

2B

2A

2A

3

2A

2A

2A

2B

3

2A

3

3

2A

2A

2B

2A

DOCUMENT CLASS - 1 Page 21 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

SR No.

Data Sheets

Specifications

DOCUMENT DESCRIPTION

DOC. CLASS

Development of Operational, Safety and Control System

Machine and Auxiliary Layout

Machine Characteristic Curves

P&IDs

MR Inspection and test Plan

Review of VENDOR Data and Drawings

Inspection and Testing Procedures at VENDORS works

VENDOR Data and Drawings of Critical Equipment e.g. Compressors, Pumps with Speed Over 3,600rpm, Temperature over 225°C or below 0°C, Pressure over 180bar, Multistage Pumps, Pumps of Special Design, Cooling and Fire Water Pumps

4.8

Electrical Engineering

Drawings/Doc Schedule

Specifications and Philosophies, including interface philosophies

Data Sheets

Power system Studies/Calculations

Single Line Diagrams

Equipment Sizing calculations

Area Classification Drawings and Schedules

Electrical Load Summary (Substation wise)

Substation Layouts

Equipment Numbering (including substations) / Cable Numbering System

Earthing Layouts

Lighting Layouts / Panel Schedules

Power Layouts

Cable Schedules

Interconnection Diagrams

Motor List

Cable routing layouts

Installation Standards Block Diagrams including ECEMS Architectural dwgs

Trace heating Layouts I/O lists Updated interface deliverables MTOs

4.9

Instrumentation and Control Systems Engineering

2A

2B

2A

3

2A

2B

2B

2B

2B

2B

2A

2B

2A

2B

1

2B

2B

2B

2B

2A

3

3

3

2A

3

3

3

3 2B

3 2B 2B 3

DOCUMENT CLASS - 1 Page 22 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

SR No.

DOCUMENT DESCRIPTION

DOC. CLASS

Updated Definition of operating and Control Philosophy

Definition of Emergency Shutdown System

General Specification for Instrumentation Shutdown System

General Specification for Packaged Unit Instruments

DCS Specification

System Configuration Diagrams

APC Strategies (as applicable)

Management Information System (MIS) Specifications (as applicable)

PLC Specification

Flow Element, Safety/Control Valve Sizing Calculations

Instrument Index

Instrument Purchase Specifications/Data Sheets

Control Room Layouts / Equipment Room Layouts

Control Panel Layouts

Loop Diagrams and Schematics

Mimic Sketches

Format for Report of Log, Alarm, Trip, etc.

Safety and Shutdown Logic Diagrams

Main Cable Route and Trenches

Instrument Location plans

Interconnection and Termination Drawings

Instrument Cable Schedule

Installation Drawings

Construction/Installation Specifications

MTO for Installation Materials

ICSS Architecture Diagrams (DCS, ESD, F&G)

4.10 Communications and Surveillance Engineering

Communications and Surveillance Specifications/Data Sheets

Hardware Configuration Diagrams

Wiring List

Equipment Location and Installation Plans

Interconnection Diagrams

Formats for Reports of Log, Alarm, Trip, etc.

Mimic Sketches

Construction/Installation SPECIFICATIONS

Design Calculations

2B

2B

2B

2B

1

1

1

2A

1

2A

3

2A

2B

2A

3

2B

2B

2A

3

3

3

3

3

2

3

1

2A

2A

3

3

3

2B

2B

2B

3

DOCUMENT CLASS - 1 Page 23 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

SR No.

DOCUMENT DESCRIPTION

DOC. CLASS

4.11 Corrosion Control Engineering

Material Selection and Corrosion Control Audit

Updated Material Selection Guides and Material Selection Diagrams

Cathodic Protection System Design and Specifications

Protective Coating and Lining Specifications

Corrosion Monitoring Specifications

Technical Deviations on Materials

CVs of Metallurgical/Corrosion Engineering on the Project

Corrosion Control Manual

4.12 HVAC Engineering

Design Criteria for HVAC System Design

Design Load Calculations

Optimization and Selection of HVAC System

Sizing of Equipment

Project Specification for HVAC System

Data Sheets

Specification for Performance Testing

VENDOR Data and Drawings

4.13 Environmental Engineering

Environmental Impact assessment

Effluent Disposal System Emission inventory report

Gas Dispersion and Environmental Pollution

FACILITIES and Community Noise

Noise Abatement Designs

4.14 Fire and Safety Engineering

Fire Protection Philosophy Update

Equipment and Facilities Spacing Criteria

Gas and Fire Detection System

Design Calculation Optimization

Equipment Specifications

Data Sheets

Operation and Control Schemes

Logic Diagram, Cause and Effect Matrix

Interconnection and Termination Drawings

Equipment Location Drawings

2B

2B

2B

2A

2A

1

1

1

2B

2A

2A

3

1

2A

2A

3

1

1 1

1

2A

2A

1

1

2B

2A

2B

2A

2B

2B

3

2A

DOCUMENT CLASS - 1 Page 24 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

SR No.

DOCUMENT DESCRIPTION

DOC. CLASS

VENDOR Data and Drawings F&G layout Fire safety layout

4.15 Offshore structural engineering Basis of Design and Specifications Engineering Design Calculation reports Padeye / Lifting trunnions drawings All other drawings Weight control reports MTO reports

5.0

PROJECT CONTROLS

Project Work Program

Detailed Schedule/CPM Networks

Detailed Procurement Schedule

Detailed Engineering Schedule

Detailed Construction Schedule

Detailed Contracting Schedule

Detailed Control Logs/Schedule

Detailed COMMISSIONING/Pre-commissioning Schedule

Summary Bar Chart, S-Curves, Manpower Loading Charts

Physical Progress Measurement System

Planning Dossier

Planning Procedures

Scheduling Procedures

Reporting Procedures

Schedule Trend Reports

Forecasts for Completion

Recovery Plan

Scheduling Studies

Risk Analysis

Code of Accounts

Weekly/Monthly Progress Reports

Time Analysis Report

Invoicing Procedure

Invoices

Invoices Status Report

3 1 1

1 2B 1 2B 2A 3

1

2B

2B

2B

2B

2B

2B

2B

2B

1

2B

2B

1

1

3

2B

1

1

1

2B

2B

3

2B

2B

3

Bank Bonds and Guarantees (between COMPANY and CONTRACTOR)

2B

DOCUMENT CLASS - 1 Page 25 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

SR No.

DOCUMENT DESCRIPTION

DOC. CLASS

Acceptance Certificates

PO and Contracts Status report (unpriced)

6.0 CONSTRUCTION, COMMISSIONING, OPERATION AND MAINTENANCE

6.1 Construction Planning

Detailed Construction Plan

Detailed Construction Strategies Project Construction Quality Plan Construction Quality Control and testing procedures

Inspection and Test Plans

Prequalification of SUBCONTRACTORS

Approved SUBCONTRACTORS List

Construction Bid Packages (unpriced)

Technical Appraisal of Bids

Construction Subcontract (unpriced)

Pre and Post Award Minutes of Meeting

Plan for Temporary Facilities, Camp and Work Areas

Construction Organization (Field Supervision)

Construction Logistic Study

Construction Manual

Technical Subcontracts, Variations and Change Orders (unpriced)

6.2

Pre-commissioning and COMMISSIONING/Operation and Maintenance

Pre-commissioning and COMMISSIONING Procedures

Procedure and Log Sheet for Test Runs

Maintenance Manual for Test Runs

Pre-commissioning and COMMISSIONING Manual

Plans for Operator/Maintenance Personnel Training

Organization Chart for Operations and Maintenance

Schedule of Lubricants

Operating Philosophy and Procedures

Operating and Maintenance Manual

Field Performance Test Reports

1

3

2B

1 1 1

1

1

1

3

3

2B

3

2B

1

2B

3

3

1

1

2B

2B

2B

2B

3

1

1

3

DOCUMENT CLASS - 1 Page 26 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

APPENDIX 2 – AS-BUILT DOCUMENTATION

“As Built” revisions shall be produced for the following documentation originated by CONTRACTOR, VENDORS, SUBCONTRACTORS, THIRD PARTY etc.:

General:

  1. P&IDs, PFDs / UFDs

  2. Electronic Model(s), 3D Model, SmartPlant and other databases.

  3. All underground systems for all disciplines including Foundations.

  4. Plot plans, piping GADs/Layouts, Line List, Piping Isometrics & pipe support drawings.

  5. VENDOR data / documents as per SDRL Supplier Document Requirement List

  6. Safety systems

  7. Steel structure drawings, including equipment supports, pipe racks, equipment platforms.

  8. Non-Process Building layouts and details.

  9. Operation and maintenance manuals

Electrical:

  1. Single line diagrams.

  2. Cable schedule.

  3. I/O lists

  4. Scheme drawings

  5. Interconnection and Termination Drawings.

  6. Protection logic diagrams.

  7. Substation layouts.

  8. Cable routing drawings

  9. Equipment Layout Drawing

  10. Electrical power system study reports and power system study models.

  11. Lighting Layout Drawings.

  12. Earthing Layout Drawings.

  13. Protection setting and coordination drawings.

DOCUMENT CLASS - 1 Page 27 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

Instruments & Telecoms:

  1. Instrument data sheets.

  2. I/O lists

  3. Cause and Effect Diagrams

  4. Junction box wiring diagrams / interconnection diagrams (Vendor documents)

  5. Marshalling Cabinet wiring diagrams.

  6. Cable Schedule.

  7. Instrument database (SPI)

  8. Loop diagrams.

  9. Control and sequence narratives.

  10. IES equipment layouts.

  11. F&G layouts.

  12. Telecoms layouts.

  13. ICCS and subsystem software files (Electronic Format).

  14. Equipment Data Sheet

  15. Instrument and JB Layout

  16. Instrument Indices

  17. Cable routing layout (UG/AG) and sections

DOCUMENT CLASS - 1 Page 28 of 29

       Uncontrolled When Printed

COMPANY PROJECT No: 4700021770

CONTRACTOR PROJECT No: 67-00106 COMPANY DOCUMENT NO. 1-CF0000-59-PRO-0006-00

ATTACHMENTS

HAIL & GHASHA DEVELOPMENT PROJECT PACKAGE 1 – OFFSHORE FACILITIES

Rev

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

04

14.1

Attachment 1 – Comment Resolution Sheet (CRS)

DOCUMENT CLASS - 1 Page 29 of 29

       Uncontrolled When Printed

ABU DHABI NATIONAL OIL COMPANY (ADNOC) GHASHA CONCESSION PROJECTS

Drawing / Document Number, Title and Revision:

Doc Status Code:

Doc. No.:

A-BBCCDD-EE-FFF-NNNN-MM

Rev. No. :

XX

Title:

NNNNNNNNNNNNNNNNNNNNNNNNNNNNNNNNNNN

Discipline:

EE According to 1-CF0000-59-PRO-0002-00

CODE according to 1-CF0000-59- PRO-0006-00

Doc Class:

Class X according to 1-CF0000-59- PRO-0006-00

Pos No.

Page number

COMPANY Comments Description

COMPANY Originator NAME

CONTRACTOR Confirmation / Explanation

XX XX XX

nnnnnnnnnnnn nnnnnnnnnnnn nnnnnnnnnnnn

nnnnn nnnnn nnnnn

nnnnnnnnnnnn nnnnnnnnnnnn nnnnnnnnnnnn

1 2 3 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20

ACTION BY CONTRACTOR

nnnnn nnnnn nnnnn

File: 1-CF0000-59-PRO-0006-00_04_Att1.xlsx

Page 1/1

ABU DHABI NATIONAL OIL COMPANY (ADNOC) GHASHA CONCESSION PROJECTS

Drawing / Document Number, Title and Revision:

Doc Status Code:

Doc. No.:

1-CF0000-59-PRO-0006-00

Rev. No. :

03

CODE 1-NO COMMENTS

Doc Class:

Title:

PROJECT DOCUMENTATION - REVIEWS, COMMENTS AND APPROVALS

CLASS 1

Discipline:

59-Project Mgt_Quality Mgt_Admin

Pos No.

Page number

COMPANY Comments Description

COMPANY Originator NAME

CONTRACTOR Confirmation / Explanation

ACTION BY CONTRACTOR

1

NO COMMENTS

File: MacroCommentSheet_EPC 6

Page 1/1