TRACEABILITY OF SHOP & FIELD PIPING MATERIALS Specification
APPROVED BY:
NAME: Abdulmunim Al Kindy TITLE: Executive Director PT&CS EFFECTIVE DATE:
AGES-SP-13-003
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/1840724/11/202124/11/2021
ADNOC Classification: Internal
GROUP PROJECTS & ENGINEERING FUNCTION/ PT&CS DIRECTORATE
CUSTODIAN
Group Projects & Engineering / PT&CS
DISTRIBUTION
Specification applicable to ADNOC & ADNOC Group Companies
REVISION HISTORY
DATE
REV.
NO
9-Sep-2021
1
PREPARED BY (Designation/ Initial) Elsayed Abdelbaky/ QA/QC Specialist
REVIEWED BY (Designation/ Initial) Hussain Al Harthi/ HOD QA/QC- GPE
ENDORSED BY (Designation / Initial) Najem Qambar / VP Group Eng. - GPE
ENDORSED BY (Designation / Initial) Ebraheem AlRomaithi / SVP- GPE
The Group Projects & Engineering Function is the owner of this Specification and responsible for its custody, maintenance and periodic update.
In addition, Group Projects & Engineering Function is responsible for communication and distribution of any changes to this specification and its version control.
This document will be reviewed and updated in case of any changes affecting the activities described in this document.
Document No: AGES-SP-13-003
Rev. No: 01 Page 2 of 24
23/11/2021All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
INTER-RELATIONSHIPS AND STAKEHOLDERS
1.1 The following are inter-relationships for implementation of this Specification:
(a)
(b)
ADNOC Upstream and ADNOC Downstream Industry, Marketing & Trading Directorate
ADNOC Onshore, ADNOC Offshore, ADNOC Sour Gas, ADNOG Gas Processing. ADNOC LNG, ADNOC Refining, ADNOC Fertilisers, Borouge, Al Dhafra Petroleum, Al Yasat
1.2 The following are stakeholders for the purpose of this Specification:
(a)
ADNOC PT&CS Directorate
1.1 This Specification has been approved by the ADNOC PT&CS is to be implemented by each ADNOC Group company included above subject to and in accordance with their Delegation of Authority and other governance-related processes in order to ensure compliance.
1.2 Each ADNOC Group company must establish/nominate a Technical Authority responsible for compliance with this Specification.
Definitions:
‘ADNOC’ means Abu Dhabi National Oil Company.
‘ADNOC Group’ means ADNOC together with each company in which ADNOC, directly or indirectly, controls fifty percent (50%) or more of the share capital.
‘Approving Authority’ means the decision-making body or employee with the required authority to approve Policies and Procedures or any changes to it.
‘Business Line Directorates’ or ‘BLD’ means a directorate of ADNOC which is responsible for one or more Group Companies reporting to, or operating within the same line of business as, such directorate.
‘Business Support Directorates and Functions’ or ‘Non- BLD’ means all the ADNOC functions and the remaining directorates, which are not ADNOC Business Line Directorates.
‘CEO’ means chief executive officer.
‘Group Company’ means any company within the ADNOC Group other than ADNOC.
‘Standard’ means normative references listed in this specification.
‘COMPANY’ means ‘Abu Dhabi National Oil Company or any of its group companies. It may also include an agent or consultant authorized to act for, and on behalf of the COMPANY’.
‘CONTRACTOR’ means the party which carries out the project management, design, engineering, procurement, construction, commissioning for ADNOC projects.
‘SHALL’ Indicates mandatory requirements “Group Company” means any company within the ADNOC Group other than ADNOC.
CONTROLLED INTRANET COPY
The intranet copy of this document [located in the section under Group Policies on One ADNOC] is the only controlled document. Copies or extracts of this document, which have been downloaded from the intranet, are uncontrolled copies and cannot be guaranteed to be the latest version.
Document No: AGES-SP-13-003
Rev. No: 01 Page 3 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
TABLE OF CONTENTS
1.0 GENERAL … 6
1.1
INTRODUCTION … 6
1.2 PURPOSE … 6
1.3 DEFINITIONS … 6
2.0 CODES AND STANDARDS … 8 3.0 REFERENCE DOCUMENTS … 9 4.0 DOCUMENT PRECEDENCE … 9 5.0 DEVIATION/CONCESSION CONTROL … 10 6.0 QUALITY ASSURANCE/QUALITY CONTROL … 10
6.1 QA/QC PROGRAM … 10
6.2 MARKING … 11
6.3 COLOR CODING … 11
6.4 STORE TRACEABILITY CONTROL… 12
6.5 SHOP TRACEABILITY CONTROL … 12
6.6 FIELD TRACEABILITY CONTROL … 13
6.7 AUDITS … 14
6.8 REVIEW, TRANSMITTALS AND SHIPPING … 14
6.9 POSITIVE MATERIAL IDENTIFICATION (PMI) … 14
6.10 CRITICALITY RATINGS … 15
7.0 DOCUMENTATION … 15
7.1 MANUFACTURER’S TEST REPORTS (MTRS) OR CERTIFICATION … 15
7.1.1 Material Test Report (MTR) … 15
7.1.2 Certificates issued by Material Stockists or Agents are not acceptable… 15
7.1.3 EN 10204 Inspection Certificate … 16
7.1.4 Valve MTRs … 16
Document No: AGES-SP-13-003
Rev. No: 01 Page 4 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
7.1.5 Materials involving COMPANY/ CONTRACTOR Inspection… 16
7.1.6 Non-Metallic Materials … 17
7.2 DATA AND INFORMATION TO BE SUBMITTED BEFORE SHIPMENT OF
MATERIALS … 17
7.2.1 Receiving Log … 17
7.2.2 Traceability Documentation (if applicable) … 17
7.3 DATA AND INFORMATION TO BE SUBMITTED (THROUGHOUT OF) / AT THE
PROJECT. … 17
8.0 SUBCONTRACTORS/ SUB VENDORS … 18 9.0 HANDLING … 18
9.1 RECEIVING MATERIALS REQUIRING MTRS AND TRACEABILITY … 18
9.2 RECEIVING MATERIALS REQUIRING MTRS ONLY … 18
9.3 REJECTED MATERIALS … 19
10.0 MANUFACTURERS TEST REPORT (MTR) REVIEW AND ACCEPTABILITY … 19
10.1 MTR REVIEW - SCOPE … 19
10.2 MTR REVIEW - PROCEDURE … 19
10.3 NONCONFORMING MTRS OR CERTIFICATION … 20
11.0 MATERIALS … 21
11.1 MATERIALS REQUIRING MTRS AND TRACEABILITY … 21
11.2 MATERIALS REQUIRING MTRS ONLY … 21
11.3 WELDING MATERIAL CERTIFICATION … 21
12.0 MATERIAL TRACEABILITY … 22
12.1 TRACEABILITY REQUIREMENTS … 22
12.2 SHOP CONTINUITY OF TRACEABILITY … 23
12.3 FIELD CONTINUITY OF TRACEABILITY … 23
13.0 APPENDICES/ATTACHMENTS … 24
Document No: AGES-SP-13-003
Rev. No: 01 Page 5 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
1.0
1.1
GENERAL
INTRODUCTION
This specification establishes documentation, procedures for control and traceability of shop and field
fabricated piping materials for ADNOC facilities. The requirements are indicated for different levels of
compliance for pressure containing piping materials and associated components like Pipes, Valves, Fitting,
Flanges etc.. used in permanent installations of plants.
1.2
PURPOSE
The purpose of this specification is to outline procedures for Piping Material Traceability and to ensure that
at the completion of all fabrication, assembly or installation; the CONTRACTOR/ COMPANY shall have
documentation verifying that correct piping material identification/ utilization has been made.
1.3
DEFINITIONS
Where used in this specification, the following terms shall have the meanings indicated below unless
otherwise clearly indicated by context of their use.
“CERTIFIED/ MATERIAL TEST REPORT (CMTR)” A certificate that provides the capability to identify the
chemical analysis and mechanical properties of materials throughout manufacturing, construction and plant
operation.
“CODIFICATION” The codification system is to be determined by CONTRACTOR. For purchasing purposes,
stock codes must be read in conjunction with the appropriate specifications listed within the requisition.
“COMPANY” means ADNOC, ADNOC Group or an ADNOC Group Company, and includes any agent or
consultant authorized to act for, and on behalf of the COMPANY.
“CONCESSION REQUEST” A deviation requested by the CONTRACTOR, usually after receiving the
contract package or purchase order. Often, it refers to an authorization to use, repair, recondition, reclaim, or
release materials, components or equipment already in progress or completely manufactured but which does
not meet or comply with COMPANY requirements. A CONCESSION REQUEST is subject to COMPANY
approval.
Document No: AGES-SP-13-003
Rev. No: 01 Page 6 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
“CONTRACTOR” The party(s) which carries out all or part of the Design, Engineering, Procurement,
Construction, Commissioning or Management of the PROJECT. CONTRACTOR includes its approved
Manufacturers, Vendors, Suppliers, and Subcontractors. Requirements of this specification shall be enforced
at all levels of the CONTRACTOR’s procurement process. The COMPANY shall have access to all
CONTRACTOR suppliers to the same extent as required of CONTRACTOR.
“ITEM DESCRIPTIONS” The Item Descriptions shown in the Individual PIPING CLASSES are abbreviated
and shall not be used for purchase.
“MANUFACTURER/ VENDOR/ SUPPLIER” The party which manufactures and/or supplies
the
material/equipment, and provides technical documents/drawings and services to perform the duties specified
by COMPANY/ CONTRACTOR. means the Original Equipment Manufacturer (OEM) or MANUFACTURER
of one or more of the component(s) which make up a sub-assembly or item of equipment assembled by the
main SUPPLIER or his nominated SUB-SUPPLIER.
PIPING CLASS: A document which provides an assembly of piping components suitable for a defined service
and design limits in a piping system. The PIPING CLASSES are contained in Piping Material Specification
AGES-SP-09-002.
PROJECT: (To be defined)
PURCHASE DESCRIPTIONS: For Purchase Descriptions, refer to the PROJECT Piping Material
Commodities Catalogue (to be developed during detailed design).
SHALL and SHOULD: The word ‘Shall’ is to be understood as a mandatory and the word ‘Should’ as strongly
recommended to comply with the requirements of this document.
SUBCONTRACTOR/ SUBVENDORS: The party(s) which carries out all or part of the design, procurement,
installation and testing of the System(s), as specified by the MANUFACTURER/VENDOR.
Document No: AGES-SP-13-003
Rev. No: 01 Page 7 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
2.0
CODES AND STANDARDS
The following Codes and Standards, to the extent specified herein, form a part of this specification. When an
edition date is not indicated for a code or standard, the latest edition in force at the time of contract award
shall apply.
EUROPEAN COMMITTEE FOR STANDARDIZATION (EN)
BS EN 10204
Metallic Products -Types of Inspection Documents
BRITISH STANDARDS INSTITUTE (BSI)
BS 381C
Specification for colours for identification, coding and special purposes
BS 4800
BS 5383
Paint colors for Building Purposes
Material Identification of Steel, Nickel Alloy and Titanium Alloy Tubes by Continuous
Character Marking and Color Coding of Steel Tubes
INTERNATIONAL STANDARDS ORGANIZATION (ISO)
ISO 9001
ISO 9004
ISO 10474
Quality Management Systems-Requirements
Managing for the Sustained Success of an Organization
Steel and Steel Products-Inspection Documents
ASME B16.20
Metallic gaskets for pipe flanges - Ring joints spiral-wound and jacketed
ASME B 31.3
ASME Code for Pressure Piping, Process Piping
ASME Sec. II
ASME BPVC, Material Specifications
ASME Sec. VIII Div. 1 ASME BPVC, Rules for Construction of Pressure Vessels
ASME Sec. VIII Div. 2 ASME BPVC, Rules for Construction of Pressure Vessels - Alternative Rules
MANUFACTURERS STANDARDIZATION SOCIETY OF THE VALVE & FITTINGS INDUSTRY (MSS)
MSS SP-25
Standard Marking System for Valves, Fittings, Flanges and Unions
Pipe Fabrication Institute
PFI ES-22
Recommended Practice for colour Coding of Piping Materials
Document No: AGES-SP-13-003
Rev. No: 01 Page 8 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
3.0
REFERENCE DOCUMENTS
AGES-GL-13-001
AGES-GL-13-002
AGES-SP-13-001
AGES-SP-13-002
Contractor QA/QC Requirements
Positive Matrial Identification of Equipment & Piping
Criticality Rating Specification
Procurement Inspection & Certification Requirements in Projects
AGES-SP-07-004
Painting & Coating Specification
AGES-SP-07-007
AGES-SP-09-002
Welding & Non Destructive Examination (NDE)
Piping Materials Specification
AGES-SP-09-003
Specification of Manual Piping and Pipeline Valves
AGES-SP-09-005
AGES-SP-09-006
Specification For Fasteners And Gaskets
Piping Support Specification
AGES-SP-09-013
Specification for Pipe Fittings and Flanges
AGES-SP-09-014
AGES-SP-09-015
AGES-SP-09-016
AGES-SP-05-006
Glass Fibre Reinforced Plastic Piping and pipeline system
Specification For Clad Pipes Fittings And Flanges
Specification For Alloy Pipes Fittings And Flanges
Rotating Equipment Minimum General Requirements and System
Integration
4.0
DOCUMENT PRECEDENCE
It shall be the CONTRACTOR/ MANUFACTURER/ VENDOR/ SUBCONTRACTOR’s responsibility to be, or
to become, knowledgeable of the requirements of the referenced Codes and Standards.
The CONTRACTOR shall notify the COMPANY of any apparent conflict between this specification, national
and/or local regulations, the Codes and Standards, and any other specifications noted herein. Resolution
and/or interpretation of precedence shall be obtained from the COMPANY in writing before proceeding with
the design/ manufacturing.
In case of conflict, the order of precedence shall be:
a)
b)
c)
d)
e)
f)
UAE Statutory requirements
ADNOC HSE Standards
Equipment datasheets and drawings
Project Specifications and standard drawings
Company Specifications
National / International Standards
Document No: AGES-SP-13-003
Rev. No: 01 Page 9 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
If some of the requirements, which exist in national and / or local regulations, which are, more stringent than
in this specification, the CONTRACTOR/ VENDOR/ SUBCONTRACTOR shall determine, by careful scrutiny,
which of the requirements are more stringent and which combination of requirements will be acceptable, in
regard to safety, economic and legal aspects.
5.0
DEVIATION/CONCESSION CONTROL
Deviations from this specification are only acceptable where the CONTRACTOR has listed in his quotation
the requirements he cannot, nor does not wish to comply with, and the COMPANY has accepted in writing
the deviations before the order is placed.
In the absence of a list of deviations, it will be assumed that the CONTRACTOR complies fully with this
specification.
Any technical deviations to the Purchase Order and its attachments including, but not limited to, the Piping
Drawings and Project Specifications shall be sought by the VENDOR only through Concession Request
format. Concession Requests require CONTRACTOR’s and COMPANY’s review/ approval, prior to the
proposed technical changes being implemented. Technical changes implemented prior to COMPANY
approval are subject to rejection.
6.0
6.1
QUALITY ASSURANCE/QUALITY CONTROL
QA/QC PROGRAM
CONTRACTOR’s proposed quality system shall fully satisfy all the elements of ISO 9001- ""Quality
Management Systems-Requirements” and ISO 9004-""Managing for the Sustained Success of an
Organization – A Quality Management Approach”. The quality system shall provide for the planned and
systematic control of all quality related activities performed during design.
The CONTRACTOR shall have in effect at all times, a QA/QC Program, which clearly establishes the authority
and responsibility of those responsible for the quality system. Persons performing quality functions shall have
sufficient and well-defined authority to enforce quality requirements, initiate, identify, recommend and provide
solutions to quality problems and verify the effectiveness of the corrective action.
A copy of the MANUFACTURER/ VENDOR/ SUPPLIER’s QA/QC program shall be submitted to the
CONTRACTOR with its quotation for CONTRACTOR’s review and concurrence prior to award. If
MANUFACTURER/ VENDOR/ SUPPLIER’s QA/QC program is ISO 9001 certified, then only a copy of the
MANUFACTURER/ VENDOR/ SUPPLIER’s
ISO 9001 certificate
is
required.
In addition,
if
MANUFACTURER/ VENDOR/ SUPPLIER’s facility is ISO certified, CONTRACTOR’s QA audit requirements
will be waived in favor of ISO 9001 registrar audits, unless the CONTRACTOR’s trend analysis program
indicates areas of concern.
Document No: AGES-SP-13-003
Rev. No: 01 Page 10 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
The MANUFACTURER/ VENDOR/ SUPPLIER shall submit certified reports of production tests as soon as
the tests are completed satisfactorily.
The COMPANY/ CONTRACTOR reserves the right to inspect materials and workmanship at all stages of
manufacture and to witness any or all tests. The MANUFACTURER/ VENDOR/ SUPPLIER, 30 days after the
award but prior to the pre inspection meeting, shall provide the CONTRACTOR with a copy of its
Manufacturing, Inspection and Test Plan for review and inclusion of any mandatory COMPANY/
CONTRACTOR witness points.
6.2
MARKING
All piping bulk materials shall be delivered by maintaing the identification with the original Manufacturer /
Supplier’s markings and be as follows:
▪ Clearly readable.
▪ Compliant with the relevant material specification (e.g., ISO, ASTM).
▪
Include the Manufacturer/Supplier’s applicable identification symbol, matching the identification shown on
the applicable mill test reports.
▪ Be preserved when piping materials are ordered in the blasted and primed condition (e.g., straight length
pipes).
▪ Supplemented by markings applied by stock personnel and Manufacturers/Suppliers (e.g., PO numbers
or Stock codes) if needed.
All components that require machining shall be traceable through the machining process by transfer of the
heat number to the component.
Completed shop fabricated pipe spools shall be fitted with an identification tag identifying at a minimum the
Isometric number and spool number
For ASME Section VIII Div.2 marking and treaceability shall be as per part3, clause 3.2.7.
6.3
COLOR CODING
The painting material used for color coding shall be free of metallic pigments particularly the paint used for
marking of austenitic stainless steels shall not have any properties detrimental to the component for example
shall not contain any tin, copper, lead and zinc, neither shall the paint be chlorinated rubber.
Surface to be color coded shall be clean, dry, and free from grease, rust, scale or other foreign matter, color
coding can be applied on sound primer, flange faces and ends of materials to be welded shall not be painted,
color painting shall not interfere with permanent marking, Material Safety Data Sheet (MSDS) or Safety Data
Sheet (SDS) documentation and paint data sheets shall be available for review by the COMPANY.
Document No: AGES-SP-13-003
Rev. No: 01 Page 11 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
Color coding paint shall be selected to last until fabrication is complete and the spools are ready for blasting
and coating.
Color coding shall be the responsibility of the group performing the PMI (e.g., Manufacturer/Supplier,
warehouse receiving).
Refer to (APPENDIX A) for piping component marking specifications.
Colour standard
The following colour standards should be applied and shall be comply with Painting & Coating specification
AGES-SP-07-004
▪ Pipe Fabrication Institute - PFI ES-22.
▪ British Standards Institution BS 381C.
▪ A suitable identification system or colour standard as approved by the Principal.
6.4
STORE TRACEABILITY CONTROL
Material traceability shall be implemented for all project material either at Company and/ or Contractor
store(s), Project Material shall be clearly identified, inspected when receiving by relevant discipline inspector,
and safely stored with appropriate approved method and in ease retrieving and identified system as per
agreed specifications/ procedures.
All stored Material items should be registered and recorded during Receipt and Release in storgae process
all the time, in ease and computerized system with backup.
Contractor Quality department shall make sure that all released material with complete material identification
& quantity are already inspected during receiving stage, approved by COMPANY for further activities.
The leftover material returned to store shall be identified, traceability and controlled, records shall be
maintained.
6.5
SHOP TRACEABILITY CONTROL
Correct material identification throughout fabrication activities shall be maintained and monitored by the
CONTRACTOR.
At the completion of an individual fabrication stage, the CONTRACTOR shall verify and document that correct
material identification was made on the drawings and traceability record, and ensure that the physical
material identification is implemented and legible. Any discrepancies encountered shall be resolved through
consultation with the concerned authority. Confirming documentation, as necessary, shall be included in the
Traceability Package for the work involved.
Document No: AGES-SP-13-003
Rev. No: 01 Page 12 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
The Fabrication shop shall demand a suitable quantity of material required to execute the Items required to
minimize the leftover material. Contractor quality department shall make sure that all the released material is
already inspected during material receiving stage and released by Company for further activities.
Released Material list from the store shall show the Company acceptance treacibility records with complete
material identification & quantity.
The leftover material from the fabrication shop shall be controlled. All the treacibility & quantity shall be
availabe in case eather it will be scrapped or returned back to the store.
In case of the left over material will be used for another items or in another work shop without returning to the
store, Contractor quality department shall agree & accept and record.
The heat number shall be transferred before materials are cut
The complet identification & color coding shall transfer to all the cut pieces with the same manufacturing
procedure or as agreed with Company prior to cutting.
Temporary materials which will be welded directly to the project material or if it will be apart from any lifting
activity shall be treaced with complete identification.
Leftover material/surpluse/ off-cuts which have not any identifications shall not reuse in any of Company
projects.
6.6
FIELD TRACEABILITY CONTROL
Correct material identification throughout field fabrication, assembly and installation activities shall be
maintained and monitored by the CONTRACTOR conducting the work.
At the completion of an individual field fabrication, assembly or installation, the CONTRACTOR shall verify
and document that correct material identification has been made on the drawings and that the physical
material identification is legible. Any discrepancies encountered shall be resolved through consultation with
the concerned authority. Confirming documentation, as necessary, shall be included in the Traceability
Package for the work involved. Non-conforming material shall be identified and clearly segregated.
Alloy components and carbon steel components shall be traceable to their source from procurement through
final installation as follows; (the same shall be applied for shop treaceability control too -clause 6.5)
▪ The heat numbers on completed piping spools shall be 100 % verified prior to release of the spools
for painting and/or field installation.
▪ The heat numbers shall be copied onto the relevant shop fabrication isometric/weld map, written on
a tag applied/secured to the spool, or hard stamped (when permitted).
▪ Verification of heat numbers and heat number transfer shall be included as a hold point on the piping
Inspection and Test Plan (ITP).
▪ The heat number shall be transferred before materials are cut.
▪ Verification in the field that the components have been installed per requirements.
Document No: AGES-SP-13-003
Rev. No: 01 Page 13 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
CONTRACTOR shall maintain
relevant
records
including material
traceability of all approved
drawings/documents for all completed field fabrication items. Subsequent field assembly and installation
activities shall be according to the approved procedure for recording and maintaining documented material
traceability continuity up to the completion of final field installation.
Piping components in which identification markings or colour coding are maintained through pipe spool
fabrication may be released for painting as long as all components have been welded on and all relevant
NDE, including PMI, is complete. The spool shall then be tracked by the spool tagging number and isometric.
A tag plate identification, hard or soft shall be provided & attached to the Items after painting for idetification,
these tages can be removed after installation or assembly with other item/s, hence, another tag is required.
The attached tag shall represent all identification required.
The material stock quantity shall be maintained and available at any time. For all material in sec 11.1 the
quantity per each PO. item shall be maintained all the time.
6.7
AUDITS
CONTRACTOR shall conduct audits and surveillance visits on quality, accuracy, continuity, and any
corrective actions necessary for maintenance and documentation of traceability requirements. COMPANY
reserves the right to participate in such audits. The proposed audit plan shall be submitted for COMPANY
review and approval, the audit plan shall be consistent with the project execution schedule.
6.8
REVIEW, TRANSMITTALS AND SHIPPING
MANUFACTURER/ VENDOR/ SUPPLIER shall review certifications for acceptability, legibility and
completeness of data to avoid any delay in acceptance.
Certification review shall be traced by stamp/signature of documents.
Documentation as specified in section 7.0 shall be available to CONTRACTOR’s Inspectors and COMPANY
authorized agent (TPI- Third Party Inspection) for review and authorization during inspection.
6.9
POSITIVE MATERIAL IDENTIFICATION (PMI)
PMI testing shall be performed when required in accordance with AGES-SP-13-003 (Positive Metrial
Identification of Equipment & Piping).
Document No: AGES-SP-13-003
Rev. No: 01 Page 14 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
6.10
CRITICALITY RATINGS
The Criticality Rating Specification (CR) as defined by AGES-SP-13-001 and listed on Line list shall be used
to determine factory inspection and testing requirements as required.
7.0
7.1
DOCUMENTATION
MANUFACTURER’S TEST REPORTS (MTRS) OR CERTIFICATION
7.1.1 Material Test Report (MTR)
Minimum certification requirements for materials and final products shall be as specified in the material
Requisition descriptions and specifications. Material inspection documents or material test certificates shall
comply with ISO 10474 or EN 10204. Certificates for final products (such as welded fittings) shall include
certification of the base material and a copy of the welding procedure qualification applied. The MTR
document shall originate from the manufacturer, and shall identify the following (as applicable):
▪ Manufacturer Name & symbol
▪ Project name
▪ Purchase Order
▪ Heat Number (or lot number for non-metallic components)
▪ Chemical analysis and mechanical properties of the metallic materials.
▪ Heat treatment certificate (if applicable)
▪ NDE test results e.g. ultrasonic testing
▪ Any testing results requested in the purchase order or purchasing requisition.
MTRs shall be either original or photocopy of the original, duly endorsed as certified true copy of the original
by the Manufacturer. Fax copy of the MTR is not acceptable.
7.1.2 Certificates issued by Material Stockists or Agents are not acceptable.
The certificates of pipe and piping components shall be either original mill certificate or certified copy of
the original mill certificate issued by the Manufacturer.
Document No: AGES-SP-13-003
Rev. No: 01 Page 15 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
7.1.3 EN 10204 Inspection Certificate
As a minimum, all pressure-containing and load-bearing materials shall be supplied with an EN 10204 as per
AGES-SP-13-002
The certificate shall be in the English language or in other languages where they are accompanied by an
endorsed, stamped and dated English translation of the original certificate, signed by the authorized person
and shall state at least the following:
▪ Mill’s name and symbol.
▪ Certificate identification number and date of issue.
▪ Quantity covered.
▪ Charge or heat number
▪ Material and manufacturing standard.
▪ Chemical analysis.
▪ Mechanical test results.
▪ Temperature of heat treatment (when applicable).
▪ Results of the examinations, mentioned in the material standard and additional requirements.
▪ Dimensions, including pipe schedule or specified wall thickness (mm).
▪ Number of different samples tested, mentioned in the material standard and additional requirements.
▪ PMI in the case of Corrosion Resistance Alloy (CRA) material
▪ Chemical analysis from a local approved laboratory
▪ Mechanical tests from a local approved laboratory
▪ HIC and SSC tests for sour service material from a local approved laboratory
▪ RT and UT tests of the components for laminations and wall thickness conformity
7.1.4 Valve MTRs
As a minimum, MANUFACTURER’S Test Reports for valves shall include the bodies, bonnets (or equivalent
components). Valves shall be tarceble by its MTR and Data Sheet issued by the OEM
For valve body, trim and bonnet bolting, the inspection certificate type will be defined based on the criticality
rating of the valves
7.1.5 Materials involving COMPANY/ CONTRACTOR Inspection
MANUFACTURER/ VENDOR/ SUPPLIER shall
take
into account all comments of COMPANY/
CONTRACTOR representative while processing documentation.
Document No: AGES-SP-13-003
Rev. No: 01 Page 16 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
7.1.6 Non-Metallic Materials
Non-metallic materials shall be supplied with an EN 10204 inspection certificate, the certifcation type shall be
comply with AGS-SP-13-002.
7.2
DATA AND
INFORMATION TO BE SUBMITTED BEFORE SHIPMENT OF
MATERIALS
MANUFACTURER/ VENDOR/ SUPPLIER shall transmit MANUFACTURERs Test Reports or Certification to
CONTRACTOR prior to shipment, in accordance with the requirements outlined in Paragraphs 11.1 and 11.2.
7.2.1 Receiving Log
The CONTRACTOR (of shop and/or field construction) shall implement and maintain a Material Receiving
Control Log throughout the performance of the PROJECT. The CONTRACTOR shall establish a system to
provide traceability between documentation and weld testing before fabrication starts.
7.2.2 Traceability Documentation (if applicable)
The CONTRACTOR (of shop and/or field construction) shall implement and maintain Identification
Assignment Records throughout the performance of the PROJECT (see Paragraphs 12.2 and 12.3).
7.3
DATA AND INFORMATION TO BE SUBMITTED (THROUGHOUT OF) / AT THE
PROJECT.
CONTRACTOR will consolidate, maintain and transmit all records concerning MANUFACTURERs Test
Reports and Traceability as required by this specification to COMPANY at the conclusion of the PROJECT
for permanent reference.
7.4
TECHNICAL DEVIATION DOCUMENTS
If appropriate, the MANUFACTURER/ VENDOR/ SUPPLIER shall issue a Concession Request, showing
each deviation from the Purchase Order.
Document No: AGES-SP-13-003
Rev. No: 01 Page 17 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
8.0
SUBCONTRACTORS/ SUB VENDORS
The MANUFACTURER/VENDOR/SUPPLIER shall assume unit responsibility and overall guarantee for the
compliance to this specification.
The CONTRACTOR shall transmit all relevant documents and specifications to his SUBCONTRACTORs.
It is the CONTRACTOR’s responsibility to enforce all Specification requirements on SUBCONTRACTORs.
The MANUFACTURER/ VENDOR/ SUPPLIER shall submit all relevant drawings and engineering data from
his SUBCONTRACTORS to the CONTRACTOR.
The MANUFACTURER/ VENDOR/ SUPPLIER shall obtain and transmit all warranties to the CONTRACTOR
in addition to the system warranty.
9.0
9.1
HANDLING
RECEIVING MATERIALS REQUIRING MTRs AND TRACEABILITY
Materials requiring Manufacturer’s Test Reports and Traceability (see Paragraph 11.1) shall be placed in a
receiving hold area, separated from all other materials, in order to proceed with traceability check. This
separation shall be maintained throughout all receiving and dispensing activities and the area shall be
identified with a clear tagging.
The responsible receiving agent shall check for receipt of accepted certification corresponding to the materials
received. Materials without the required certification shall remain in the initial receiving hold areas until the
necessary accepted certification is received.
Materials with accepted certification on hand shall be examined by the responsible receiving agent, to verify
that traceable heat number matches the accepted certification. Acceptable materials shall be placed in
receiving release areas ready for fabrication.
9.2
RECEIVING MATERIALS REQUIRING MTRs ONLY
Materials requiring Manufacturer’s Test Reports only (see Paragraph 11.2) shall be placed in receiving
release areas ready for fabrication.
Document No: AGES-SP-13-003
Rev. No: 01 Page 18 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
9.3
REJECTED MATERIALS
Materials rejected at the fabrication shop or job site with a nonconforming certificate shall be identified by
marking or tagging and segregated from acceptable material, placed in special hold areas and subsequently
processed similarly as other non-conformances (see Paragraph 10.3).
The Manufacturer/Supplier, shop Fabricator, or field Fabricator, as applicable, shall submit a non-
conformance report (NCR) per the project quality procedures.
If an item from a representative sample is rejected, the following additional testing shall be carried out:
a) Examine 100 % of the remaining components of the lot from which the sample was taken;
b) Examine 100 % of
the same component
types
from
the next delivery
from
the same
Manufacturer/Supplier;
c) Return the level of examination to the originally specified level if examination of the next lot does not
identify any similar non-conformance.
10.0
10.1
MANUFACTURERS TEST REPORT (MTR) REVIEW AND ACCEPTABILITY
MTR REVIEW - SCOPE
Manufacturer’s Test Reports (MTRs) shall be reviewed by CONTRACTOR and COMPANYapproved
inspector(s) at the MANUFACTURER’S facility prior to shipment.
Subject to COMPANY approval, if review of the documentation at the MANUFACTURER’S facility is not
practical, original or red stamped verified copies of the MTR shall be reviewed by CONTRACTOR and
COMPANY approved inspector(s), prior to shipment from the MANUFACTURER’S facility.
10.2
MTR REVIEW - PROCEDURE
All MTRs shall be reviewed for compliance. Test reports indicating chemical analysis and mechanical
properties shall be verified as complying with the required specifications. Any materials with nonconforming
MTRs shall not be allowed to ship from the MANUFACTURER pending resolution of the nonconformance.
▪ MTRs that have been verified as complete and correct shall be stamped “ACCEPTED”. The stamp
shall also include the reviewer’s name, discipline and date of review.
▪ MTRs for materials requiring traceability shall also be stamped “TRACEABILITY REQUIRED”.
▪ Each MTR which reviewed shall be stamped, stamping on the cover sheet or MTRs list only is not accepted. The number of MTRs per each Po. shall be recorded. A list of MTRs shall submit with the MTRs and to be review and stamped by the manufacturer.
Document No: AGES-SP-13-003
Rev. No: 01 Page 19 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
Copy of the accepted MTR shall be distributed as follows
▪ One copy to accompany shipment
▪ One copy for Inspection File
▪ One copy to CONTRACTOR Technical Document Control
10.3
NONCONFORMING MTRS OR CERTIFICATION
10.3.1
MANUFACTURER’S Test Reports or Certification is nonconforming and unacceptable when
any of the following conditions exist:
▪ Missing data
▪
▪
Incorrect data
Illegible documents
▪ Documents with pertinent data “cut off” in the course of copying
10.3.2
Resolved Non-conformances
All technical non-conformances shall be resolved as specified in Paragraphs 4.0 and 5.0.
For nontechnical corrections to the documents concerning the Purchase Order number, item or quantity,
a notification (without further documentation) is acceptable, provided the addition or correction has been
verified with the MANUFACTURER.
When a nonconformance has been satisfactorily resolved, the documents, including certifications, shall
be handled the same as accepted certifications.
10.3.3
Unresolved Non-conformances
When the non-conformance cannot be resolved, the certification documents shall be marked “non-
conforming” and the MANUFACTURER shall be notified of the non-conformance.
Document No: AGES-SP-13-003
Rev. No: 01 Page 20 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
11.0
11.1
MATERIALS
MATERIALS REQUIRING MTRS AND TRACEABILITY
11.1.1
Piping components (pipe, fittings, flanges, etc.) for the following shall require Manufacturer’s Test
Reports (MTRs) and total Traceability:
▪ Low-temperature Carbon Steel and Carbon Steel in sour services
▪ Ferritic alloy ( 1-1/4 Chrome through 9 Chrome)
▪ Austenitic alloy (300 series Stainless Steels)
▪ High alloys (90-10 Cupronickel, Hastelloy, Inconel, Monel, 254 SMO, etc.)
▪ Clad Piping.
▪ All valves
▪ Carbon steel piping components other than specified in section 11.2
▪ Steel structure (plate, sections, etc. ) according to class.
▪ Pipe line
11.1.2
For Traceability requirements and procedures, refer to Paragraph 12.0.
11.2
MATERIALS REQUIRING MTRS ONLY
Piping components (pipe, fittings, flanges, etc.) for the following shall require Manufacturer’s Test Report
only:
▪ Carbon Steel piping components (general, hydrogen and steam services)
▪ Components of engineered items in all materials including, but not limited to, blinds and expansion
joints
▪ All flange bolting materials
▪ Non-metallic piping components
11.3
WELDING MATERIAL CERTIFICATION
Certification or MTR and Traceability for welding consumables shall be in accordance with the applicable
welding specification.
All welding consumables shall be individually marked and supplied with an inspection certificate type 3.1
according to EN 10204 for both mechanical properties and chemical composition. The lot classification and
level of testing shall be as specified in the relevant welding specification.
Document No: AGES-SP-13-003
Rev. No: 01 Page 21 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
12.0
12.1
MATERIAL TRACEABILITY
TRACEABILITY REQUIREMENTS
This section is applicable only for materials listed in Paragraph 11.1.
In order to maintain traceability continuity of piping components, the following are required upon receipt of
materials and during fabrication.
12.1.1 Marking - General
Unique permanent marking of material for total traceability, such as an identification or heat number that can
be traced back to the Material Test Report, material specification/designation, and wall thickness/schedule
are required. Marking shall be accomplished by the use of “low stress” steel die stamps, producing a round
bottom impression or by electro etching. Electro etching may be done by either the stylus or chemical method
(chemicals shall not contain chlorides, sulfur or nitrogen compounds). Material with a nominal wall thickness
of 5.1 mm (0.200”) or less shall be electro etch marked. The depth of marks shall not infringe on minimum
wall thickness determined from the project design basis, data sheets, and the applicable material
specifications and standards.
Marking shall be applied such that abrasions and oxidation encountered during shipping, storing, handling,
fabrication and installation will not obliterate the identifying marks. Should fabrication or installation
operations (examples: welding, grinding and cutting) obliterate the heat number; the part of piece shall be re-
marked accordingly.
12.1.2 Marking - Pipe
In order to maintain traceable continuity, each length of pipe is required to be marked by “low stress” die
stamping or electro etching approximately 300 mm
from
the end of
the pipe by
the
MANUFACTURER/VENDOR as required by the applicable specifications.
Shop and field receiving authorized personnel shall verify that all pipes are properly identified. Unidentified
materials shall be considered as “scrap” until such time that physical and chemical tests can affirm material
composition, CONTRACTOR shall develop and establish a procedure of re-certification the unidentified
“scrap” materials.
12.1.3 Marking - Pipe/Fittings which have been cut
Markings on material that is subsequently cut into smaller pieces (examples: pipe and odd angle elbows)
shall be transferred to each cut piece immediately in order to maintain traceable continuity. Transfer of
marking to be done by authorized personnel only.
Document No: AGES-SP-13-003
Rev. No: 01 Page 22 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
12.1.4 Drawing Requirements
Heat numbers and welder’s identification shall be transferred to:
▪ Shop orthographic or pipe spool drawings after shop fabrication.
▪
Isometric drawings (or pipe rack drawings if there are no isometric drawings) after field fabrication.
12.2
SHOP CONTINUITY OF TRACEABILITY
12.2.1 The necessary traceable identification assignment of materials to production drawings may occur
before or after release of drawings for fabrication. In any case Identification Assignment Records shall be
implemented and maintained throughout the duration/performance of this PROJECT (refer to Paragraph
12.1).
12.2.2 After review and acceptance by CONTRACTOR’s Inspection Engineer, the MANUFACTURER/
VENDOR/ SUPPLIER shall transmit to CONTRACTOR’s Technical Document Control, a copy of “accepted”
drawing and certification documents for each fabricated spool piece on the same day of shipment. Another
copy of the documents shall accompany the shipment
12.3
FIELD CONTINUITY OF TRACEABILITY
The necessary traceable identification assignment of materials to production drawings may occur before or
after release of drawings for field fabrication, assembly or installation. In any case identification assignment
records shall be implemented and maintained throughout the performance of this PROJECT (refer to
Paragraph 12.1).
Document No: AGES-SP-13-003
Rev. No: 01 Page 23 of 24
All parties consent to this document being signed electronically -PT&CS/GP/INT/2021/18407
ADNOC Classification: Internal
13.0
APPENDICES/ATTACHMENTS
APPENDIX A PIPING COMPONENT MARKING SPECIFICATIONS
Component Marking
Pipe (1),(2)
Each length of pipe shall be painted over the entire length with a 12 mm (0.5 in) to a 40 mm (1.6 in) wide stripe, depending on the pipe size.
a) Each socket weld fitting, swage or pipe nipple shall be dabbed with a spot of
Fittings (1),(2)
paint 12 mm (0.5 in) to 25 mm (1 in) in diameter.
b) The entire length of each butt weld fitting shall be painted on the outside surface
with a 12 mm (0.5 in) to 40 mm (1.6 in) wide stripe, depending on size.
Flanges (1),(2)
The outer peripheral edge of each flange shall be painted with a spot of paint on the outer surface.
Plate (1),(2)
A stripe shall be painted across from corner to corner.
a) Each welded or flangeless (wafer type) valve shall be dabbed with a spot of paint
12 mm (0.5 in) to 25 mm (1 in) in diameter.
Valves (1),(2)
b) Each flanged valve shall be dabbed with a spot of paint 12 mm (0.5 in) to 25 mm
(1 in) in diameter on the top side of one flange.
c) For flanges thicker than 25 mm (1 in), the width of the band may be limited to 25
mm (1 in).
Bolts (1),(2)
Each stud bolt shall be dabbed with a spot of paint on each end.
Notes:
-
Identifying paint is not applied to the following: inside surfaces of pipe, flanges or fittings a) b) threads c) weld bevels d) symbols or markings which would obliterate identification e) Gasket seating surface.
-
Apply colour codes to specialty carbon steels.
Document No: AGES-SP-13-003
Rev. No: 01 Page 24 of 24