RUWAIS LNG PROJECT

Inspection and Test Plan for Safety Shower and Eye Wash

COMPANY DOCUMENT REF.

RLNG-000-HS-PP-8888

CONTRACTOR DOC. REF.

215122C-000-ITP-1900-8888

REVISION: 0

PAGE 1 OF 12

ADNOC GAS

Inspection and Test Plan for Safety Shower and Eye Wash

COMPANY Contract No.

4700022871

JV TJN RUWAIS Contract No

215122C

Document Class

Class 2

Document Category (for Class 1)

Criticality Rating: 2
Inspection Class: 2

OPERATING CENTER Contract No.

OPERATING CENTER Doc Ref.

0

IFQ – Issued for Quotation / Enquiry 14-Apr-2025

K. C. Nayak

D. Shah / A. Elaghoury

J. Mendez-Repiso / M. Vallivel

Rev.

Revision Purpose

Date

Prepared by

Checked by

Approved by

The terms of Contract / Agreement No: CON22-146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

Inspection and Test Plan for Safety Shower and Eye Wash

COMPANY DOCUMENT REF.

RLNG-000-HS-PP-8888

CONTRACTOR DOC. REF.

215122C-000-ITP-1900-8888

REVISION: 0

PAGE 2 OF 12

Table of Contents

Contents

Page

1.0

INTRODUCTION… 4 1.1 Project Objective and Location … 4 1.2 Scope of the Document … 4 1.3 Holds List … 5 1.4 References … 5 1.5 Definitions and Abbreviations … 5 2.0 DEFINITION OF PURCHASER’s / COMPANY’s INSPECTION LEVEL OF INVOLVEMENT … 5 3.0 NOTIFICATION FOR INSPECTION … 7 4.0 PERCENTAGE EXTENSION OF INSPECTION … 7 5.0 VENDOR’s FQCP … 7 6.0 VENDOR’S MANUFACTURING AND TESTING DOCUMENTATION OR PROCEDURES … 8 7.0 STATUTORY AND REGULATORY REQUIRED DOCUMENTATION … 8 INSPECTION RELEASE NOTE (IRN) … 8 8.0 INSPECTION AND TEST PLAN … 8 9.0 APPENDIX 1: Inspection and Test Plan for Safety Shower and Eye Wash … 9 APPENDIX 2: Inspection and Test Plan for Painting of Safety Shower and Eye Wash … 12

The terms of Contract / Agreement No: CON22-146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

Inspection and Test Plan for Safety Shower and Eye Wash

COMPANY DOCUMENT REF.

RLNG-000-HS-PP-8888

CONTRACTOR DOC. REF.

215122C-000-ITP-1900-8888

REVISION: 0

PAGE 3 OF 12

Table of Changes compared to previous revision (for Procedures and Job Specifications only)

Paragraph

Modification description

Remarks / Origin

New document – No change from a previous one

The terms of Contract / Agreement No: CON22-146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

Inspection and Test Plan for Safety Shower and Eye Wash

COMPANY DOCUMENT REF.

RLNG-000-HS-PP-8888

CONTRACTOR DOC. REF.

215122C-000-ITP-1900-8888

REVISION: 0

PAGE 4 OF 12

1.0

1.1

INTRODUCTION

Project Objective and Location

The ADNOC Ruwais LNG Project is a two train, near net-zero electrically driven LNG facility, targeting international markets. The feed gas for the project is supplied from the Habshan Gas Processing Plant via a new export gas pipeline. The plant will have two 4.8 MTPA (nominal capacity) electric driven LNG Trains with associated LNG storage/ marine export facilities and utilities.

Figure 1- Project Context

The ADNOC Ruwais LNG Project foresees the following main components at the facility:

• •

• •

Onshore LNG liquefaction facilities for 2 x 4.8 MTPA electrically driven LNG Trains (9.6MTPA total) Common facilities including inlet receiving facilities, LNG storage, BOG handling, flare, refrigerant storage and support buildings Utilities to support the facilities including import power from the national grid. Marine facilities for LNG export and bunkering.

1.2

Scope of the Document

This Inspection and Test Plan (ITP) is an engineering document which, for each type of equipment, defines:

•

•

The minimum type and extent of PURCHASER / PURCHASER’s Representative and COMPANY / COMPANY’s representative involvement in each phase of fabrication, control and testing requiring an inspection, check or documentation review. Unless otherwise noted, COMPANY / COMPANY’s attendance at workshop inspections is of the same level and extent as that PURCHASER / PURCHASER’s Representative The resulting VENDOR contractual obligations, in accordance with applicable Project General Purchase Conditions

This ITP covers the minimum inspection requirements for the Safety Shower and Eye Wash.

Under no circumstance shall this ITP be used as a substitute for VENDOR’s own Fabrication and Quality Control Plan (FCQP).

This ITP defines neither the type nor the extent of tests VENDOR shall carry out which, shall comply with applicable codes, standards, and Purchase Order (PO) specifications.

The terms of Contract / Agreement No: CON22-146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

Inspection and Test Plan for Safety Shower and Eye Wash

COMPANY DOCUMENT REF.

RLNG-000-HS-PP-8888

CONTRACTOR DOC. REF.

215122C-000-ITP-1900-8888

REVISION: 0

PAGE 5 OF 12

1.3

Holds List

HOLD

DESCRIPTION

1

Nil

1.4

References

[1] RLNG-000-HS-SPP-0001 – Process Data Sheet - Safety Shower & Eye Wash

1.5

Definitions and Abbreviations

CPY

CTR

VENDOR SUBVENDOR MANUFCATURER PURCHASER MR

ITP

PO FQCP PIM IRN

COMPANY - ABU DHABI NATIONAL OIL COMPANY (ADNOC) P.J.S.C. CONTRACTOR - TJN Ruwais, Joint Venture of Technip Energies France- Abu Dhabi, JGC Corporation and National Marines Dredging Company (NMDC). Supplier of Material or Equipment A supplier of a VENDOR Party in charge of the manufacturing of the Material or Equipment CONTRACTOR in charge of procurement activities Material Requisition Inspection and Test Plan by CONTRACTOR to specify scope of Inspection, Criticality Rating and Inspection Classes along with the Material Requisition Purchase Order Fabrication and Quality Control Plan Pre- Inspection Meeting Inspection Release Note

2.0

DEFINITION OF PURCHASER’s / COMPANY’s INSPECTION LEVEL OF INVOLVEMENT

PURCHASER’s / COMPANY’s Inspection Level of involvement is indicated in the ITP by means of the below letters with following definition.

A = APPROVE

A point at which relevant documents or test results shall be approved by the Concerned party per the approved Inspection & Test Plan (ITP) prior to proceeding with further activities.

R = REVIEW

A point at which relevant documents or test results shall be reviewed by the Concerned party per the approved Inspection & Test Plan (ITP) prior to proceeding with further activities.

H = HOLD

The terms of Contract / Agreement No: CON22-146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

Inspection and Test Plan for Safety Shower and Eye Wash

COMPANY DOCUMENT REF.

RLNG-000-HS-PP-8888

CONTRACTOR DOC. REF.

215122C-000-ITP-1900-8888

REVISION: 0

PAGE 6 OF 12

An Inspection point, at which the concerned party shall perform 100% inspection & clear the activity as per the approved Inspection & Test Plan (ITP). No further activities shall proceed without prior written permission; Inspection Notification is mandatory.

W = WITNESS (100%)

An inspection point at which the concerned party shall witness the activity as per the approved Inspection & Test Plan (ITP); Inspection Notification is mandatory.

The MANUFACTURER/ VENDOR shall:

• Not proceed the activity until the notification time agreed is lapsed.

• Proceed with the activity if COMPANY abstained without any information. In this case, the

CONTRACTOR shall inform COMPANY immediately via e-mail.

WR: WITNESS RANDOM

An inspection point at which the CONTRACTOR/ COMPANY shall witness the activities as per the approved Inspection & Test Plan (ITP). Items selected at random from the inspection lot (of each specification and dimensions) that are to be witnessed as per the approved Inspection and Test Plan (ITP), witness point (as a minimum) shall be carried out as per the following table:

No. of items in group

2 to 4

5 to 8

9 to 12

13 to 40

Over 40

Min. number of item to be inspected

2

4

6

9

25%

Wherever Witness Random inspection interventions are marked up in the approved ITP, it is the responsibility of CONTRACTOR/ VENDOR / MANUFACTURER to ensure that sample items for random or percentage basis inspection are offered to COMPANY for selection from the lot, and such sampling lot are offered on progressive basis based on the percent completion of items manufactured.

For Witness Random inspection interventions, it is VENDOR / MANUFACTURER responsibility to perform internal inspection / test for total (100%) quantity and reports/ records shall be made available to CONTRACTOR and COMPANY for review prior to selection of samples for witness. WR is not applicable to MANUFACTURER / VENDOR

On random or percent witness inspections if there is any failure or rejection occurs, the extent of inspection shall be doubled and in case of further failure or rejection extent of CONTRACTOR witness shall be increased to 100%. Same control may apply to COMPANY Inspection interventions.

M: MONITORING

An Inspection point, at which the CONTRACTOR / COMPANY will visit any work to inspect the activity during processing as per the approved Inspection & Test Plan (ITP).

F: FIRST OF A KIND

Witnessing of the specified First Kind / Instance of the activity by CONTRACTOR / COMPANY ‘s Inspector is not mandatory, but optional. If CONTRACTOR / COMPANY elects to not witness the activity, VENDOR may proceed with its own inspection, provided control and test records are made available to CONTRACTOR / COMPANY’s Inspector for review. CONTRACTOR / COMPANY’s level of involvement in subsequent

The terms of Contract / Agreement No: CON22-146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

Inspection and Test Plan for Safety Shower and Eye Wash

COMPANY DOCUMENT REF.

RLNG-000-HS-PP-8888

CONTRACTOR DOC. REF.

215122C-000-ITP-1900-8888

REVISION: 0

PAGE 7 OF 12

activities will either be M (Monitoring) in case of satisfactory results or W (Witness) in case of dissatisfactory results.

*/V: VIRTUAL REMOTE

The various levels of this nature of involvement are H/V (Hold/Virtual), W/V (Witness/Virtual), M/V(Monitoring/Virtual) and F/V (First of a Kind/Virtual). The specified test or control will be attended by CONTRACTOR/COMPANY either entirely remotely or with a CONTRACTOR/COMPANY representative in attendance at VENDOR’s premises as well as attendance remotely by CONTRACTOR/COMPANY. CONTRACTOR/COMPANY may request VENDOR to organize a trial inspection run in order to ensure demonstrate effectiveness of remote activities

3.0

NOTIFICATION FOR INSPECTION

VENDOR shall notify PURCHASER for attendance at the dedicated inspection activity as per requirements given in the PO regarding mode and timeliness. Unless otherwise indicated in the PO, notifications for inspection are generally submitted via email or Project communication tool and at least seventeen (17) calendar days in advance.

Inspection notifications shall be submitted for all Inspection levels of involvement; Approve (A) and Review (R) points excluded. Inspection notifications shall hence be submitted for H, W, F, M, H/V, W/V, F/V and M/V points.

4.0

PERCENTAGE EXTENSION OF INSPECTION

When a percentage value is indicated opposite the inspection level of involvement eg., W 10% the inspection activity will be spot witnessed as per percentage indicated. Unless otherwise defined during the PIM or in the PO, sampling criteria will be at the discretion of PURCHASER’s inspector and generally will be based on the VENDOR’s manufacturing system.

5.0

VENDOR’S FQCP

VENDOR must issue a Fabrication and Quality Control Plan (FQCP) for each equipment and Material of its scope of supply. VENDOR’s FQCP is a document which defines in a chronological manner the list of the operations pertaining to fabrication, controls and tests in accordance with its own “know-how” and with the requirements specified in Material Requisition.

As a minimum, the following information shall be clearly specified for each operation:

• • • •

• •

Progressive identification number for each Inspection and Testing activity Reference documents (drawings, procedures, specifications etc.) Acceptance criteria (code, etc.) Recording documents for controls and tests. It shall be understood by VENDOR that, unless otherwise indicated, all controls and tests carried out by VENDOR shall be documented (certificate to be given). Involvement of VENDOR’s and / or its SUV-VENDOR’s Quality Control department Separate columns foresee involvement of VENDOR, SUB-VENDOR, PURCHASER, COMPANY and INSPECTOR, as well as the level of involvement of said parties (eg. Hold, Witness, etc.) and percentage (e.g. 30%), if less than 100%.

VENDOR’s FQCP will have to include all inspection activities defined in this ITP as well as all inspection activities scheduled by the CONTRACTOR.

The terms of Contract / Agreement No: CON22-146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

Inspection and Test Plan for Safety Shower and Eye Wash

COMPANY DOCUMENT REF.

RLNG-000-HS-PP-8888

CONTRACTOR DOC. REF.

215122C-000-ITP-1900-8888

REVISION: 0

PAGE 8 OF 12

For equipment having inspection levels 1, 2 and 3, VENDOR’s FQCP shall be submitted to PURCHASER for review before any Pre-Inspection Meeting (PIM) is held. Refer to RLNG-000-PM-SP-6004 “VENDOR PERFORMENCE MANAGEMENT (VPM) REQUIREMENTS FOR SUPPLIERS”.

6.0

VENDOR’S MANUFACTURING AND TESTING DOCUMENTATION OR PROCEDURES

VENDOR shall take note of requirements in the PO regarding submittal to PURCHASER of any manufacturing and testing documentation or procedure as well as the submittal dates therefore: e.g welding, post weld heat treatment and non-destructive examination procedures etc.

7.0

STATUTORY AND REGULATORY REQUIRED DOCUMENTATION

VENDOR shall take note of requirements in the PO regarding submittal to PURCHASER of any statutory and regulatory documentation required by local authorities as well as the submittal dates, therefore.

8.0

INSPECTION RELEASE NOTE (IRN)

This document is issued by PURCHASER’s Inspector and marks the conclusion of all inspection activities. The IRN allows VENDOR to proceed with packing operations.

9.0

INSPECTION AND TEST PLAN

APPENDIX 1: Inspection and Test Plan for Safety Shower and Eye Wash

APPENDIX 2: Inspection and Test Plan for Painting of Safety Shower and Eye Wash

Note: Notification point can be modified and substituted by another where (*) is mentioned visible in the column for the step proposed.

The terms of Contract / Agreement No: CON22-146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

Inspection and Test Plan for Safety Shower and Eye Wash

COMPANY DOCUMENT REF.

RLNG-000-HS-PP-8888

CONTRACTOR DOC. REF.

215122C-000-ITP-1900-8888

REVISION: 0

PAGE 9 OF 12

APPENDIX 1: Inspection and Test Plan for Safety Shower and Eye Wash

CRITICALITY RATING : 2

DESCRIPTION

INSPECTION CLASS: 2 (*) FOR INSPECTION CLASS: 3

APPLICABLE DOCUMENTS

Before Fabrication

INSPECTION INTERVENTION LEVEL

CTR

CPY

REMARKS/ NOTES

H

A

A

A

A

R

A

R

R

A

R

R

R

R

Pre-Inspection Meeting (PIM)

Review and approval of supplier’s fabrication quality control plan (FQCP)

Review of NDT Procedures and NDT maps (Piping / Structure)

Review and approval of Manufacturer personnel qualifications & certificates (WPS + PQR + Weld Map)

Review of Welding books (for all type of items : Piping, structure, valve, etc.)

Review of Sub-Vendor List

Review of vendor documents / drawings

Review of Sub-Vendor Specifications for major components

Inspection of material on receipt of sub-ordered components

H

A

A

A

A

R

A

R

R

Positive Material Identification (PMI) Test

RLNG-000-MT-SP-6303

W

Review of Material Test Certificates

Qualifications / Competencies of Personnel involved in IEC Ex Activities

Explosion Proof certificates / IECEx checklist template

Testing and Calibration reports for Instruments

Repair Procedure for welds

Surface Preparation and Painting Procedure

Review of Painting QCP

Packing, Storage and Preservation Procedure

Test Procedures (including hydraulic and pneumatic and leak test procedure and factory acceptance test procedures)

During Fabrication and Assembly

Stage Inspection (Raw material, NDE, welding, fabrication etc.)

Non-Conformity / Major weld repairs

Verification of IECEx & ECAS certificates of components

Electrical and Instrument Installation

Inspection of Electrical and instrument installation, hook with Ex regulation.

up, compliance

‐

Insulation Resistance test

Wiring Check, Instrument Cabling, Hook-up check, Grounding check

Functional Test

R

R

R

R

A / R*

A / R*

A

A

A

A

A / R*

A / R*

A / R*

A / R*

WR

W

WR

W

R

R

W / R*

WR / R*

R

W

W

R

W / WR*

W

Required for the PIM

For Alloy materials

Type EN 10204-3.1 for metallic items (Structural Steel parts) and EN 10204-2.2 for non-metallic items (Cables, switch gear Controls)

Wherever applicable

Calibration certificates not less than 6 months old

Applicable for all on skid major welds & Lifting Lugs

Loop and function test of all instruments, valves and controls

Piping, Valves and Supports

The terms of Contract / Agreement No: CON22-146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

Inspection and Test Plan for Safety Shower and Eye Wash

COMPANY DOCUMENT REF.

RLNG-000-HS-PP-8888

CONTRACTOR DOC. REF.

215122C-000-ITP-1900-8888

REVISION: 0

PAGE 10 OF 12

INSPECTION CLASS: 2 (*) FOR INSPECTION CLASS: 3

APPLICABLE DOCUMENTS

INSPECTION INTERVENTION LEVEL

CTR

CPY

REMARKS/ NOTES

CRITICALITY RATING : 2

DESCRIPTION

Hydrostatic testing of all pipework and pressure containing components

NDE testing of all pipework and pressure containing components

Verification of material test certificates for all components

Verification of Valves and certification

Regulating Pressure Setting Test

Seat Leakage Test

Checking of the tubing assembly / connection, Flange surfaces, alignment and bolt tensions

Leak test of assembled piping systems

Package Baseplate and Structure

Raw material test Certificate Review

Baseplate material test certificates

Baseplate fabrication, NDE, dimensional, visual inspection before painting

Final Inspection

test inspection of assembled package, including piping, valves, air

Pre leak test, package structure and including validation of safety and shutdown functions.

‐

Mechanical Completion checks

Completion of IECex check sheet

Visual, Dimensional and Welding check

Lifting Lugs Test

Final inspection (complete assembly) and functional test of each skid

Final inspection of package including P&ID conformity check, equipment tagging, Nameplate check, bolt torqueing check, labelling and warning signs, Cleanliness and Dryness check, review of all Loose ship Items (including spares) and Special tools

W

W

R

R

R

R

R

W

R

R

W

W

W

W

W

W

W

W

W

W

R

R

R

R

R

W

R

R

W / WR*

R

W / WR*

W / WR*

W / WR*

W / WR*

W

W

W

Check rust prevention, blanketing, etc., depending on package complexity and preservation requirement)

Packing, Preservation and Marking Identification

RLNG-000-PM-SP-6006

W

Painting Inspection, DFT Check & Adhesion

W

W / WR*

Refer Painting ITP in Appendix 2

Certificate of compliance

Final Documentation Review

Final Documentation

Manufacturing Data Record Book (MDRB Check)

RLNG-000-PM-PP-6005

Paint Reports

Deviation / Concession request / Non-conformity Repair / Closure of punch list

R

A

A

A

A

R

A

A

A

A

Statement of Manufacturers compliance with Code, Specification and PO requirements.

The terms of Contract / Agreement No: CON22-146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

Inspection and Test Plan for Safety Shower and Eye Wash

COMPANY DOCUMENT REF.

RLNG-000-HS-PP-8888

CONTRACTOR DOC. REF.

215122C-000-ITP-1900-8888

REVISION: 0

PAGE 11 OF 12

CRITICALITY RATING : 2

DESCRIPTION

APPLICABLE DOCUMENTS

Inspection release note

IEC Ex & ECAS Dossier

WIN / UTC / CMMS DATA Sheet (To Be Completed by Vendor Wherever Applicable)

INSPECTION CLASS: 2 (*) FOR INSPECTION CLASS: 3

INSPECTION INTERVENTION LEVEL

CTR

CPY

A

R

A

R

R

A

REMARKS/ NOTES

IRN will be issued after closure of punch list

The terms of Contract / Agreement No: CON22-146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

Inspection and Test Plan for Safety Shower and Eye Wash

COMPANY DOCUMENT REF.

RLNG-000-HS-PP-8888

CONTRACTOR DOC. REF.

215122C-000-ITP-1900-8888

REVISION: 0

PAGE 12 OF 12

APPENDIX 2: Inspection and Test Plan for Painting of Safety Shower and Eye Wash

CRITICALITY RATING : 2

DESCRIPTION

APPLICABLE DOCUMENTS

INSPECTION CLASS: 2

INSPECTION INTERVENTION LEVEL

CTR

CPY

REMARKS/ NOTES

Before Manufacturing

Painting Pre-Job Meeting

Painting Procedure and Painting Quality (ITP)

Pre-Qualification of products

Pre-Qualification Test (PQT) when required

Qualification of Operators / Supervisor

Valid calibration certificate for all equipment

Storage of Painting Materials, verification of shelf-life validity

During Fabrication

Activities before Blasting:

  • Steel Surface Preparation (Welding and imperfections)
  • Pre-cleaning of surface before blasting
  • Check of abrasives, including conductivity check
  • Blotter test
  • Check of environmental conditions Blasting and Post Blasting activities:
  • Surface cleanliness after blasting
  • Assessment of dust on surface
  • Anchor Profile check
  • Water soluble salts tests

WFT layer (Primer – Intermediate – Final)

DFT layer (Primer – Intermediate)

Curing test for IOZ

Final Painting Check

  • Visual examination check
  • DFT final layer
  • RAL final layer
  • Touch-up & Repaired Area Check

Adhesion Test

Final Testing

H

R

R

W

R

M

M

W

R

R

W

R

M

M

W/R

W/R

W/R

W/R

R

M

M

W

W

R

M

M

W

W

The terms of Contract / Agreement No: CON22-146 shall apply for any disclosure of this document to any third party.