RUWAIS LNG PROJECT
Technical Specification & Process Data Sheet - Safety Shower & Eye Wash
COMPANY Document Ref
CONTRACTOR Document Ref
RLNG-000-HS-SP-0006
215122C-000-SP-1900-0006
ADNOC GAS
REVISION : 0
PAGE 1 of 7
Technical Specification & Process Data Sheet - Safety Shower & Eye Wash
COMPANY Contract No.
TJN RUWAIS Contract No.
4700022871
215122C
Document Class
Document Category (for Class 1)
2
N/A
OPERATING CENTER Contract No.
OPERATING CENTER Doc Ref.
215122C-000-PDS-1900-0001
0
ICR – Issued for Client Review
16-Apr-25
DGO / D. Yokanathan
V. Evans/ K. Nitta / D. Shah
S. Deilles / K. Fujii
Rev.
Revision Purpose
Date
Prepared by
Checked by
Approved by
DOCUMENT REVISIONS
The terms of Contract / Agreement No: CON22-146 shall apply for any disclosure of this document to any third party.
Page 1/7
Technical Specification & Process Data Sheet - Safety Shower & Eye Wash
Project Name Client Location
Ruwais LNG Project ADNOC GAS Ruwais, UAE
CPY Doc. No. Requisition No. Document No.
RLNG-000-HS-SP-0006 RLNG-000-HS-R-8851 215122C-000-SP-1900-0006
2
Page Issue Revision
of
7 ICR 0
.
v e R
Standard / Document Number
REFERENCES
Standard / Document Title
ANSI/ISEA Z358.1
American National Standard for Emergency Eyewash and Shower Equipment
AGES-SP-03-001
Escape, Evacuation, Rescue & Life Saving Appliances (EER & LSA) Specification
AGES-SP-03-002
Active Fire Protection System Specification (Part 4)
RLNG-000-PM-BOD-2002
Project Basis of Design
RLNG-000-PM-SP-2002
Site and Utility Data
RLNG-000-PR-BOD-0003
Utility Design Basis
RLNG-000-HS-PP-0001
Design HSE Philosophy
RLNG-000-EL-BOD-0001
Electrical Design Basis
RLNG-000-HS-PP-0301
Hazardous Area Classification Philosophy
RLNG-000-PI-SP-1022
Specification for Piping Material Classes
RLNG-000-PT-SP-0001
Project Specification for Protective Coating of Equipment, Piping & Structures
REVISIONS AND HOLDS
Revision
Description of Changes
0
Not applicable - New document
HOLD
HOLDS
Description
1
Line numbers on the P&IDs for some of the Safety Shower and Eye Wash units to be confirmed later.
The terms of Contract / Agreement No: CON22-146 shall apply for any disclosure of this document to any third party.
Page 2/7
Technical Specification & Process Data Sheet - Safety Shower & Eye Wash
Project Name Client Location
Ruwais LNG Project ADNOC GAS Ruwais, UAE
CPY Doc. No. Requisition No. Document No.
RLNG-000-HS-SP-0006 RLNG-000-HS-R-8851 215122C-000-SP-1900-0006
3
Page Issue Revision
of
7 ICR 0
. v e R
S. No.
General Notes
Environmental Conditions are defined in Project Basis of Design (Doc. No. RLNG-000-PM-BOD-2002). The design of all the outdoor equipment shall address the below normal operating conditions, in particular • High UV radiation levels • High ambient temperature • Marine and Saliferous environment • Dust and sand environment • High humidity and corrosive environment. The requirements of these conditions shall be fully compensated for, both in the design and in the construction materials of equipment. All equipment with associated accessories shall be designed for a period of 30 years in line with Project Basis of Design (Doc. No. RLNG-000-PM-BOD-2002) when maintained in accordance with manuals supplied by the VENDOR.
Each Safety Shower & Eye Wash Unit shall be provided with a dedicated overhead tank, which will be fed from plant potable water supply header.
Safety Shower & Eye Wash Units are placed in the areas which are exposed to direct sunlight. Hence, Safety shower and eye wash unit should be insulated and require a cabinet.
Safety Shower & Eye Wash Unit shall be fitted with a flow switch which is activated when the shower is being used and will raise an alarm in the control room.
Safety Shower & Eye Wash Unit shall be designed in such a way that it shall be possible to operate both Safety Shower and Eye Wash at the same time.
Both Safety shower and Eye wash must be designed such that once opened, the valves remain open without the continuous pressure or action from the operator until intentionally closed.
Painting shall be performed in accordance with ‘Project Specification for Protective Coating of Equipment, Piping & Structures’ (Doc. No. RLNG-000-PT-SP-0001). Supply water filling rate for a unit shall not exceed 10 m3/h, otherwise a restriction orifice shall be supplied by the Vendor to limit the flow.
Operating Instructions (with pictogram) shall be provided in Arabic & English.
Manufacturer’s test certificates/compliance certificate shall be furnished by the Vendor.
Vendor shall submit manufacturing, test, inspection, and welding procedures for CONTRACTOR’s approval prior to manufacturing.
The use of refurbished and re-use of metallic materials is prohibited.
Vendor shall perform Tests and / or inspections under the Vendor’s own quality control. The Quality plan and Inspection and Test Plan shall be submitted to CONTRACTOR for review.
Any deviation from the requirements mentioned in this specification shall be duly informed and shall be approved by CONTRACTOR/ COMPANY.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
The terms of Contract / Agreement No: CON22-146 shall apply for any disclosure of this document to any third party.
Page 3/7
Technical Specification & Process Data Sheet - Safety Shower & Eye Wash
Project Name Client Location
Ruwais LNG Project ADNOC GAS Ruwais, UAE
CPY Doc. No. Requisition No. Document No.
RLNG-000-HS-SP-0006 RLNG-000-HS-R-8851 215122C-000-SP-1900-0006
4
Page Issue Revision
of
7 ICR 0
.
v e R
GENERAL
Type of unit
Manufacturer
Model No.
Design Code
Installation Location
Operating Mechanism
Safety Shower and Eye Wash unit (cabinet type) with dedicated Overhead tank and Chiller unit. Refer to TYPICAL ARRANGEMENT DRAWING in Sheet 6.
Vendor To Advise
Vendor To Advise
ANSI/ISEA Z358.1
Outdoor
Pull Rod for Safety Shower / Foot Pedal for Eye Wash
Insulation of the Pipes and Tanks
Yes ; Cold Insulation
Cabinet
Yes ; covered on three sides and around the tank
AMBIENT & DESIGN CONDITIONS
Ambient Temperature
Design Temperature
Humidity
Atmosphere
°C
°C
%
Minimum
Maximum
4.1
4
3
51.2
87
100
Marine, Saliferous, Dust and Sand
SERVICE CONDITIONS
Operation (Continuous or Intermittent)
Service
Safety Shower Capacity
litre / min
Eye Wash Capacity
litre / min
Operation Time of Safety Shower & Eye Wash
minutes
Required temperature of the flushing water
°C
Potable Water
Intermittent
76.0
11.4
15
26.0
Required pressure of the flushing water
barg
As per ANSI/ISEA Z358.1
POTABLE WATER SUPPLY CONDITIONS
Minimum
Normal
Maximum
Potable Water Supply Temperature
°C
Potable Water Supply Pressure
barg
Mechanical Design Temperature
°C
Mechanical Design Pressure
barg
16
2.0
25
3.0
4 / 87
9.8
Potable Water Supply Line Insulation
Yes ; Cold Insulation
38
4.5
POTABLE WATER SUPPLY CONNECTION
Potable Water Supply Line Connection Size
inch
1
Potable Water Supply Line Connection Type
ASME B16.5, #150, Raised Face Flange
Potable Water Supply Line Material
SS316/316L
OVERHEAD TANK
Overhead Tank capacity
litre
Drain line
Overflow line
CHILLER UNIT
Required temperature of the chilled water
Operating Limits
°C
°C
Nominal Cooling Duty
kW
Power supply
V / Ph / Hz
Control Panel IP Classification
Power Consumption
kW
1400 (minimum)
Yes ; with ball valve closed
Yes
0 to 60
26
Vendor To Advise
415 / 3 Phase / 50
IP66
Vendor To Advise
The terms of Contract / Agreement No: CON22-146 shall apply for any disclosure of this document to any third party.
Page 4/7
Technical Specification & Process Data Sheet - Safety Shower & Eye Wash
Project Name Client Location
Ruwais LNG Project ADNOC GAS Ruwais, UAE
CPY Doc. No. Requisition No. Document No.
RLNG-000-HS-SP-0006 RLNG-000-HS-R-8851 215122C-000-SP-1900-0006
5
Page Issue Revision
of
7 ICR 0
. v e R
ACCESSORIES AND OTHER REQUIREMENTS
Audible Alarm / Visual Alarm
Flow Switch for Activation Alarm
Explosion Rating
Junction Box
Scald Valve
Light inside the Cabinet
Water Level Indicator for the Tank
Temperature Gauge for the Tank
Water Level Switch
Overflow nozzle
Drain Sump and Grating
Tag & Name Plate
Safety Sign with name
Fixation Materials / Anchor Bolt / Nut
Gasket / Bolt / Nut at the potable water supply tie-in
Inspection Hatch
Lifting lugs
Protective Painting
Shower Head
Eye Wash
Eye Wash Dust Cap
NO
YES
YES; Zone 1, IIB, T3
YES NO; Scalding protection is provided by means of temperature controlled chiller unit. Additional scald valve is not required. YES; Zone 1, IIB, T3
YES
YES
NO
YES
YES; with 6” outlet (Bell & Spigot joint) connected to GRE pipe (AC network)
Yes, in SS316
YES; As per ISO 7010 with English and Arabic Text
YES; To be supplied by vendor
YES; To be supplied by vendor
YES
YES YES, as per Manufacturer’s Standard suitable for the ambient conditions mentioned in Sheet 4.
MATERIAL
SS316
SS316
Manufacturer’s Standard
Pipe
As per Piping Class N104, Stainless Steel S-40S
Corrosion Allowance mm.
0
Valve
Tank
As per Piping Class N104, Ball Valve (SS316)
Medium density PE with GRP jacket and Polyurethane insulation
Accessories (Pull Rod / Foot Pedal / Spring etc.)
Cabinet
Cabinet Frame and Legs
Drain Sump
Drain Sump Grating and Frame
SS316
GRP
Galvanized Mild Steel
GRP
Galvanized Mild Steel
DIMENSIONS & WEIGHT
Dimensions (LxWxH)
Weight
Vendor To Advise
Vendor To Advise
TESTS & APPROVAL
Hydrostatic Test
Performance Test
Approval
Vendor Standard
As per ANSI/ISEA Z358.1
ANSI/ISEA Z358.1
The terms of Contract / Agreement No: CON22-146 shall apply for any disclosure of this document to any third party.
Page 5/7
Technical Specification & Process Data Sheet - Safety Shower & Eye Wash
Project Name Client Location
Ruwais LNG Project ADNOC GAS Ruwais, UAE
CPY Doc. No. Requisition No. Document No.
RLNG-000-HS-SP-0006 RLNG-000-HS-R-8851 215122C-000-SP-1900-0006
6
of
Page Issue Revision
7 ICR 0
. v e R
TYPICAL SCHEMATIC OF SAFETY SHOWER & EYEWASH UNIT
TYPICAL ARRANGEMENT OF DRAIN SUMP AND OUTLET CONNECTION
The terms of Contract / Agreement No: CON22-146 shall apply for any disclosure of this document to any third party.
Page 6/7
Technical Specification & Process Data Sheet - Safety Shower & Eye Wash
Project Name Client Location
Ruwais LNG Project ADNOC GAS Ruwais, UAE
CPY Doc. No. Requisition No. Document No.
RLNG-000-HS-SP-0006 RLNG-000-HS-R-8851 215122C-000-SP-1900-0006
7
of
Page Issue Revision
7 ICR 0
. v e R
QUANTITY AND TAG NUMBERS OF SAFETY SHOWER AND EYE WASH UNITS
TAG NO.
P&ID No.
Rev.
Line No.
INLET FACILITIES AREA
010-SS-501
010-SS-502
010-SS-503
LNG STORAGE TANK AREA
RLNG-000-PR-PID-5007
020-SS-001
RLNG-000-PR-PID-8005
REFRIGERANT STORAGE AREA
035-SS-501
035-SS-502
035-SS-503
035-SS-504
035-SS-505
CHILLED WATER UNIT AREA
044-SS-501
044-SS-502
BOG COMPRESSION AREA
060-SS-001
060-SS-002
UTILITY & POTABLE WATER AREA
076-SS-501
076-SS-502
FIRE WATER SYSTEM AREA
RLNG-000-PR-PID-5007
RLNG-000-PR-PID-5008
RLNG-000-PR-PID-8005
RLNG-000-PR-PID-5008
077-SS-501
RLNG-000-PR-PID-5008
SANITARY SEWER / SEWAGE TREATMENT AREA
079-SS-501
079-SS-502
LIQUEFACTION TRAIN 1
111-SS-101
111-SS-102
111-SS-103
111-SS-104
111-SS-105
LIQUEFACTION TRAIN 2
211-SS-101
211-SS-102
211-SS-103
211-SS-104
211-SS-105
Notes:
RLNG-000-PR-PID-5008
RLNG-101-PR-PID-0611
RLNG-201-PR-PID-0611
Total No. of Units = 28
0
0
0
0
0
0
0
0
0
0
2”-010-PW-XXXX-N104-C
2”-010-PW-XXXX-N104-C
2”-010-PW-XXXX-N104-C
2”-020-PW-XXXX-N104-C
2”-035-PW-XXXX-N104-C
2”-035-PW-XXXX-N104-C
2”-035-PW-XXXX-N104-C
2”-035-PW-XXXX-N104-C
2”-035-PW-XXXX-N104-C
2”-044-PW-XXXX-N104-C
2”-044-PW-XXXX-N104-C
2”-060-PW-XXXX-N104-C
2”-060-PW-XXXX-N104-C
2”-076-PW-XXXX-N104-C
2”-076-PW-XXXX-N104-C
2”-077-PW-XXXX-N104-C
2”-079-PW-XXXX-N104-C
2”-079-PW-XXXX-N104-C
2”-101-PW-0201-N104-C
2”-101-PW-0202-N104-C
2”-101-PW-0203-N104-C
2”-101-PW-0204-N104-C
2”-101-PW-0205-N104-C
2”-201-PW-0201-N104-C
2”-201-PW-0202-N104-C
2”-201-PW-0203-N104-C
2”-201-PW-0204-N104-C
2”-201-PW-0205-N104-C
The terms of Contract / Agreement No: CON22-146 shall apply for any disclosure of this document to any third party.
Page 7/7