RUWAIS LNG PROJECT

FINAL VENDOR DOCUMENTATION REQUIREMENTS SPECIFICATION

COMPANY DOCUMENT REF. RLNG-000-PM-SP-2303

CONTRACTOR DOC. REF.

215122C-000-JSM-2303

REVISION: 1

PAGE 1 OF 18

ADNOC GAS

FINAL VENDOR DOCUMENTATION REQUIREMENTS SPECIFICATION

COMPANY Contract No.

4700022871

JV TJN RUWAIS Contract No

215122C

Document Class

Class 2

Document Category (for Class 1)

OPERATING CENTER Contract No.

OPERATING CENTER Doc Ref.

1

    IFC – Issued for Construction

18-Dec-2024 D.Sivaprakasam A.De-Vandiere

S. Deilles

T. Sakamoto

 K. Fujii

M. Vallivel

0

ICR - Issued for CLIENT Review

08-Aug-2024 D.Sivaprakasam A.De-Vandiere T. Sakamoto M. Vallivel

S. Deilles K. Fujii

Rev.

Revision Purpose

Date

Prepared by

Checked by Approved by

The terms of Contract / Agreement No: CON22 146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

FINAL VENDOR DOCUMENTATION REQUIREMENTS SPECIFICATION

COMPANY DOCUMENT REF. RLNG-000-PM-SP-2303

CONTRACTOR DOC. REF.

215122C-000-JSM-2303

REVISION: 1

PAGE 2 OF 18

Contents

Page

Table of Contents

1.0

INTRODUCTION … 4 1.1 Project Objective and Location … 4 2.0 SCOPE & PURPOSE … 4 3.0 REFERENCES … 4 4.0 DEFINITIONS/ACRONYMS … 5 4.1 Definitions … 5 5.0 LANGUAGE AND UNITS … 5 6.0 PRESENTATION OF DOCUMENTATION … 5 7.0 HARD COPY … 6 7.1 Document Size … 6 7.2 Printing Material … 6 7.3 Description of Binders and Presentations … 6 7.4 External Coversheet (for each volume) Refer to Appendix – 1 … 6 7.5 Internal Front Page (for each volume) Appendix – 1 & 2 … 7 7.6 Partitions … 7 7.7 MDRB & OMM Master … 7 8.0 ELECTRONIC COPY … 7 8.1 Document Format … 7 8.2 External Hard Drive… 8 9.0 FINAL DOCUMENTATION (MDRB & OMM) DISTRIBUTION … 8 10.0 PROCEDURE FOR REVIEW / COMMENTS … 8 11.0 PROCEDURE FOR DISTRIBUTION AND FINAL DISPATCH … 8 11.1 General … 8 11.2 Hard and Electronic Copy Transmission … 8 12.0 PREPARATION OF MANUFACTURING DATA RECORD BOOK … 9 13.0 TABLE 1 - CONTENT OF MANUFACTURING DATA RECORD BOOK (MDRB) & OPERATIONAL &

MAINTENANCE MANUAL (OMM) … 9 14.0 APPENDIXES … 13 APPENDIX 1 - BINDER EXTERNAL & INTERNAL (inside) COVER SHEET FOR MDRB & OMM … 13 APPENDIX 2 - BINDER SPINE (SIDE) COVER SHEET FOR MDRB & OMM … 15 APPENDIX 3 – APPROVED BINDER SPECIFICATION … 16 APPENDIX 4 – ELECTRONIC (HARD DRIVE) EXTERNAL COVER SHEET FOR MDRB & OMM … 17 APPENDIX 5 – MASTER DELIVERABLE INDEX LIST FORMAT … 18

The terms of Contract / Agreement No: CON22 146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

FINAL VENDOR DOCUMENTATION REQUIREMENTS SPECIFICATION

COMPANY DOCUMENT REF. RLNG-000-PM-SP-2303

CONTRACTOR DOC. REF.

215122C-000-JSM-2303

REVISION: 1

PAGE 3 OF 18

Table of Changes compared to previous revision (for Procedures and Job Specifications only)

Paragraph

Modification description

Remarks / Origin

Section 3

Updated

Section 5

Updated

Section 8.1

Updated

Section 9

Updated

Section 10

Updated

Appendix

Updated

The terms of Contract / Agreement No: CON22 146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

FINAL VENDOR DOCUMENTATION REQUIREMENTS SPECIFICATION

COMPANY DOCUMENT REF. RLNG-000-PM-SP-2303

CONTRACTOR DOC. REF.

215122C-000-JSM-2303

REVISION: 1

PAGE 4 OF 18

1.0

1.1

INTRODUCTION

Project Objective and Location

The ADNOC Ruwais LNG Project is a two train, near net-zero electrically driven LNG facility, targeting international markets. The feed gas for the project is supplied from the Habshan Gas Processing Plant via a new export gas pipeline. The plant will have two 4.8 MTPA (nominal capacity) electric driven LNG Trains with associated LNG storage/marine export facilities and utilities.

The ADNOC Ruwais LNG Project foresees the following main components at the facility:

• Onshore LNG Liquefaction facilities for 2 x 4.8 MTPA electrically driven LNG Trains (9.6MTPA

total)

• Common facilities including inlet receiving facilities, LNG storage, BOG handling, flare, refrigerant

storage and support buildings.

• Utilities to support the facilities including import power from the national grid.

• Marine facilities for LNG export and bunkering.

2.0

SCOPE & PURPOSE

This procedure is applicable for the final Vendor’s Documentation required by CONTRACTOR.

This procedure concerns the Manufacturing Data Record Books (MDRB) and Operational & Maintenance Manual (OMM) to be delivered to CONTRACTOR and COMPANY for ADNOC Ruwais LNG Project.

The purpose of this procedure is to outline the requirements to be observed by the Vendor for the supply of the Manufacturing Data Record Book (MDRB) and Operational & Maintenance Manual (OMM) listed on the Requisition.

The required documentation is an integral part of the supply, and its omission shall be considered as a non-fulfilment of the Purchase Order.

This document shall be read in conjunction with the following document:

•

Instructions Concerning Vendor Document Management and Review

Any conflict among the 2 documents shall be reported to CONTRACTOR for resolution.

3.0

REFERENCES

This section lists the documents that shall be referred to when using this document:

Document Number

Project Documents RLNG-000-PM-SP-2302

RLNG-000-PM-SP-6005 Company Specifications/ Agreement Annexures 10F-04-00-0A-Annexure 10F-5

Document Title

Instructions Concerning Vendor Document Management and Review Manufacturing Data Record Book Procedure (MDRB)

Handover Documentation Requirements

The terms of Contract / Agreement No: CON22 146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

FINAL VENDOR DOCUMENTATION REQUIREMENTS SPECIFICATION

COMPANY DOCUMENT REF. RLNG-000-PM-SP-2303

CONTRACTOR DOC. REF.

215122C-000-JSM-2303

REVISION: 1

PAGE 5 OF 18

10F-04-00-0A-Annexure 10F-9 10F-01-00-0A-Annexure 10F-10 10F-01-00-0A-Annexure 10F-12 TE-PR-043 TE-PR-050

Vendor Documents & Manuals Manufacturing Data Report Contents of O&M Manual Projects Asset Information Handover Procedure As Built Procedure

4.0

DEFINITIONS/ACRONYMS

4.1

Definitions

Abbreviation/Acronyms COMPANY

CONTRACTOR

EPC PROJECT Site Vendor

MDRB OMM As Delivered Documents

MR

PO

Meaning

Abu Dhabi National Oil Company (ADNOC) P.J.S.C. TJN Ruwais, Joint Venture of CONTRACTOR France -Abu Dhabi, JGC Corporation and National Marine Dredging Company (NMDC, the then NPCC) Engineering, Procurement and Construction Ruwais LNG Project (EPC) Site means the location where the plant is to be constructed Company having been awarded a Purchase Order for the Design and the Supply of Material and/or Equipment Manufacturing Data Record Books (= Manufacturing Inspection Dossier) Operational & Maintenance Manual

Any modification made to Equipment during the fabrication shall be reflected on all pertinent documents.

These documents become “As-Delivered” Documents on completion of all changes. “As-Delivered” Documents shall be updated in higher revision and have to be clearly indicated “As-Delivered” on the Title Block.

Material requisition that includes:

  • Requisition for purchase listing:

The documents relating to the scope of supply, The applicable documents, with their reference number and revisions

  • Scope of supply.

Purchase Order

5.0

LANGUAGE AND UNITS

All Electronic Data Books shall be in ENGLISH. Any certificate in native language shall be made technical translation in English.

6.0

PRESENTATION OF DOCUMENTATION

Final Vendor documentation is split in two data books:

• Manufacturing Data Record Book (MDRB) • Operational & Maintenance Manual (OMM)

The terms of Contract / Agreement No: CON22 146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

FINAL VENDOR DOCUMENTATION REQUIREMENTS SPECIFICATION

COMPANY DOCUMENT REF. RLNG-000-PM-SP-2303

CONTRACTOR DOC. REF.

215122C-000-JSM-2303

REVISION: 1

PAGE 6 OF 18

7.0

HARD COPY

7.1

Document Size

Documents in original size A4 must be printed in A4 and A3 must be printed in A3, black and white and 2 sided prints. Drawings A2, A1 and A0 should be used selectively. All P&IDs, GA drawings shall be printed in A3, black & white and all dimensions, details shall be legible when prints are taken. If documents are not legible in A3, they must be printed in their original size, folded correctly and inserted into A4 sized transparent plastic pockets with the title block visible (one document in a transparent plastic pocket). The documents or drawings can be printed in colour if they have the specific markup or indications which needs to be required for understanding.

Hard copies of all handover documentation must be on International standard sizing listed below shall be applied:

• A4 - 210 X 297 mm

• A3 ‒ 297 X 420 mm

• A2 - 420 X 594 mm

• A1 - 594 X 841 mm

• A0 - 841 X 1189 mm

7.2

Printing Material

All documentation presented as printed material shall utilize paper of suitable quality for long term storage (minimum acceptable quality of paper: 80g/sq. m). All documentation shall be of a suitable quality to provide clear and legible reproduced copies.

7.3

Description of Binders and Presentations

The MDRB and OMM shall consist of one or several binders.

Vendor shall use white PVC Fixed Post Binders with Rigid Covers for all volumes (Refer Appendix – 3). These shall be of a size to readily accommodate A4 size documentation. 4 rings binders shall be used. Binders shall have fixed transparent plastic pockets on their outside front and spine (Side of the Binder) into which cover sheets and spine sheets (printed in colour) shall be inserted.

VENDOR shall submit the draft binder spines and covers sheets to CONTRACTOR for review and approval prior to commencement of compilation.

7.4

External Coversheet (for each volume) Refer to Appendix – 1

It shall be inserted on the front side and spine (Side of the Binder) of the binders and shall include the following information:

  1. COMPANY LOGO
  2. COMPANY NAME
  3. Project Name
  4. AGP Project Number
  5. Agreement Number
  6. Discipline
  7. Package Number
  8. Requisition Number

The terms of Contract / Agreement No: CON22 146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

FINAL VENDOR DOCUMENTATION REQUIREMENTS SPECIFICATION

COMPANY DOCUMENT REF. RLNG-000-PM-SP-2303

CONTRACTOR DOC. REF.

215122C-000-JSM-2303

REVISION: 1

PAGE 7 OF 18

  1. TAG Number
  2. Description
  3. CONTRACTOR Logo & Name
  4. VENDOR Logo & Name
  5. Binder Volume (X of Y)

7.5

Internal Front Page (for each volume) Appendix – 1 & 2

A front page shall contain the following indications.

  1. COMPANY LOGO
  2. COMPANY NAME
  3. Project Name
  4. AGP Project Number
  5. Agreement Number
  6. Discipline
  7. Package Number
  8. Requisition Number
  9. TAG Number
  10. Description
  11. CONTRACTOR Logo & Name
  12. VENDOR Logo & Name
  13. Binder Volume (X of Y)

7.6

Partitions

Each volume shall have durable plastic dividers for sections and subsections.

Each main chapter and its different sub-chapters shall be preceded by a presentation page containing the title of the concerned chapter/sub-chapter. For “Not Applicable” chapters, the mention N/A shall appear in the Presentation Page.

7.7

MDRB & OMM Master

The MDRB and OMM masters shall be started as soon as possible and ready when the first vendor documents are issued for CONTRACTOR review or information.

When a document is stamped “CODE 3” or accepted “For information” to CONTRACTOR it will be immediately put in place in the MDRB and OMM master.

The MDRB and OMM Masters are to be assembled and maintained throughout the work and can be shown to the CONTRACTOR inspector/representative at every inspection time, whenever required.

8.0

ELECTRONIC COPY

8.1

Document Format

Documents shall be submitted both in Native and PDF Files. PDF shall be formatted in Adobe 8 Version & above, refer to “RLNG-000-PM-SP-2302, Instructions Concerning Vendor Document Management and Review”. As much as possible, PDF format documents shall be ORC (Optimal Character Recognition) ready. Comment Track Changes shall not appear in the Final Revision. Documents are to be listed in the index with hyperlinks.

The terms of Contract / Agreement No: CON22 146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

FINAL VENDOR DOCUMENTATION REQUIREMENTS SPECIFICATION

COMPANY DOCUMENT REF. RLNG-000-PM-SP-2303

CONTRACTOR DOC. REF.

215122C-000-JSM-2303

REVISION: 1

PAGE 8 OF 18

8.2

External Hard Drive

Vendor shall provide one external hard drive for the whole documentation.

Data needs to be encrypted if provided using HDD/SSD or any media.

9.0

FINAL DOCUMENTATION (MDRB & OMM) DISTRIBUTION

Manufacturing Data Record Book (MDRB)

Operational & Maintenance Manual (OMM)

Requirement

Hard Copy

Electronic Copy (Hard Disk)

Hardcopy

Electronic Copy (Hard Disk)

COMPANY

CONTRACTOR

Total from VENDOR

2

0

2

2

1

3

2

0

2

0

1

1

10.0

PROCEDURE FOR REVIEW / COMMENTS

The Procedure for review / comments of Manufacturing Data Record Books and Operational & Maintenance Manuals are as follows:

• Vendor forwards MDRB, OMM Indexes to CONTRACTOR for review and comments

before preparation of soft copy of the documents.

•

Indexes are reviewed by CONTRACTOR and approved. Once the Indexes are approved, Vendor is electronically notified.

• Vendor sends MDRB & OMM to CONTRACTOR for review and comments.

• CONTRACTOR then sends it back with comments to the Vendor.

If a subsequent updating is necessary, it will be at Vendor care to revise the MDRB and OMM indexes and send the updated one together with the revised drawings.

MDRB including “as fabricated” and OMM “For Review” (IFR)” shall be received in CONTRACTOR within the dates specified in the Requisition.

11.0

PROCEDURE FOR DISTRIBUTION AND FINAL DISPATCH

11.1 General

Vendor shall supply MDRB and OMM per equipment and it will consist of one or several binders.

Vendor shall supply both hard and electronic copies of MDRB and OMM per equipment. In particular, even if equipment is duplicated A / B / C etc., documentation will have to be duplicated and dedicated to each items A / B / C etc., and Final documentation has to be delivered for each item A / B / C etc.,

11.2 Hard and Electronic Copy Transmission

Vendor shall be required to distribute MDRB and OMM to the various recipients. The number of copies to be forwarded and the address of each recipient are mentioned in Section 9.

Upon dispatch, Vendor shall forward a copy of the transmittals to CONTRACTOR as well as evidence of the shipment vouchers (parcel delivery company certificate…).

The terms of Contract / Agreement No: CON22 146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

FINAL VENDOR DOCUMENTATION REQUIREMENTS SPECIFICATION

COMPANY DOCUMENT REF. RLNG-000-PM-SP-2303

CONTRACTOR DOC. REF.

215122C-000-JSM-2303

REVISION: 1

PAGE 9 OF 18

12.0

PREPARATION OF MANUFACTURING DATA RECORD BOOK

Refer to RLNG-000-PM-SP-6005 - Manufacturing Data Record Book Procedure (MDRB)

13.0

TABLE 1 - CONTENT OF MANUFACTURING DATA RECORD BOOK (MDRB) & OPERATIONAL & MAINTENANCE MANUAL (OMM)

The documents shall meet the recognized industry standard and the format to be in accordance with the PROJECT standard as detailed in the Material Requisition / Purchase Order as per COMPANY requirements.

VENDOR shall submit minimum Documents as listed below. COMPANY have right to additional documents other than listed below during project execution.

Documents to be Included in Manufacturing Record Book (MDRB) (Refer to RLNG-000- PM-SP-6005)

Documents to be Included in Operational & Maintenance Manual (OMM)

(Refer to RLNG-000- PM-SP-6005)

X

X X X

X X X

X X X X X

To Be Submitted by VENDOR

CONTROL DOCUMENTS DRAWING DOCUMENT SCHEDULE FABRICATION PRODUCTION SCHEDULE SUB ORDER SCHEDULE / COPY OF SUB ORDERS BI-WEEKLY PROGRESS REPORT CONTRACT SPECIFIC INSPECTION & TEST PLAN CERTIFICATE OF APPROVAL QUALITY MANUAL SPECIFIC QUALITY PLAN ARRANGEMENTS GENERAL ARRANGEMENTS INTERFACE AND CONNECTION SCHEDULE UTILITY REQUIREMENTS FOUNDATION REQUIREMENTS SCHEMATICS PFD’s AND HEAT AND MASS BALANCE P&ID (Including vendor package P&IDs) CAUSE AND EFFECT CHART OPERATION/CONTROL PHILOSOPHY & BLOCK LOGIC DIAGRAM DATA SHEETS EQUIPMENT DATA SHEETS / DESIGN SPECIFICATION MOTOR DATA SHEET(S) INSTRUMENT DATA SHEET(S) NOISE DATA SHEET(S) COMPONENT/ AUXILIARY DATA SHEET(S) DATA SHEETS/SPECIFICATIONS OF SUB- VENDOR SUPPLIED ITEMS (e.g., Strainers, Steam traps, Spring Hangers, Expansion Joints, (special pipe supports)

CALCULATIONS & PERFORMANCE DATA

The terms of Contract / Agreement No: CON22 146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

FINAL VENDOR DOCUMENTATION REQUIREMENTS SPECIFICATION

COMPANY DOCUMENT REF. RLNG-000-PM-SP-2303

CONTRACTOR DOC. REF.

215122C-000-JSM-2303

REVISION: 1

PAGE 10 OF 18

(Refer to RLNG-000- PM-SP-6005)

DESIGN / CODE CALCULATION PROCESS / UTILITY CALCULATION STRUCTURAL STEEL/ CONCRETE SUPPORT AND FOUNDATION LOADING DATA AND CALCULATIONS DESIGN CALCULATIONS FOR STRUCTURAL ITEMS ROTATING ELEMENT CALCULATION INSTRUMENT SIZING CALCULATION PIPING STRESS ANALYSIS MECHANICAL EQUIPMENT PERFORMANCE CURVES/TABLES ELECTRICAL CURVES RELIABILITY & AVAILABILITY / HAZOP STUDY PULSATION STUDIES HEAT DISSIPATION PIPE WALL THICKNESS CALCULATIONS DETAIL MECHANICAL DRAWINGS EQUIPMENT DETAIL DRAWINGS ANCILLARY PIPING DRAWINGS CROSS SECTION PARTS LIST / BILL OF MATERIAL SEAL DETAIL INSULATION/LINING DETAIL EQUIPMENT LIST LINE DESIGNATION TABLE DETAIL INSTRUMENT DRAWINGS INSTRUMENT LOCATION DRAWING INSTRUMENT SCHEDULE PANEL WIRING SCHEMATIC DIAGRAM PANEL / JB TERMINATION DETAILS PANEL / CABINET LAYOUT LOGIC DIAGRAM HOOK- UP DIAGRAM LOOP DIAGRAM CABLE BLOCK DIAGRAM INSTRUMENT OUTLINE DRAWING SERIAL LINK GRAPHICS DETAIL ELECTRICAL DRAWINGS ELECTRICAL SINGLE LINE DIAGRAMS ELECTRICAL LAYOUT DRAWING SCHEDULE OF ELECTRICAL EQUIPMENT CABLE SCHEDULE INTERCONNECTION DIAGRAM TERMINAL BLOCK DIAGRAM DISTRIBUTION BOARD SCHEDULE MANUFACTURING PROCEDURES WELD PROCEDURES (WPS & PQR) NDE PROCEDURES HEAT TREATMENT PROCEDURES (INCLUDING PWHT)

The terms of Contract / Agreement No: CON22 146 shall apply for any disclosure of this document to any third party.

X X

X X

X X X X X

X X X X X

X

X X X X X X X X X X X

X X X X

X X

RUWAIS LNG PROJECT

FINAL VENDOR DOCUMENTATION REQUIREMENTS SPECIFICATION

COMPANY DOCUMENT REF. RLNG-000-PM-SP-2303

CONTRACTOR DOC. REF.

215122C-000-JSM-2303

REVISION: 1

PAGE 11 OF 18

(Refer to RLNG-000- PM-SP-6005)

SURFACE PREPARATION, PAINTING & COATING SCHEDULE TEST PROCEDURES FUNCTIONAL & PERFORMANCE TEST PROCEDURES HYDROSTATIC / PNEUMATIC TEST PROCEDURES MATERIAL TEST PROCEDURES FACTORY ACCEPTANCE TEST PROCEDURE SITE ACCEPTANCE TEST PROCEDURE CERTIFICATION MANUFACTURING RECORD BOOK INDEX MANUFACTURING RECORD BOOK MATERIAL CERTIFICATES HAZARDOUS AREA CERTIFICATES CODES/STANDARD/COMPLIANCE CERTIFICATES TEST RESULTS SPECIFICATION WAIVERS TYPE TEST CERTIFICATES INSPECTION RELEASE NOTE HANDLING & SITE INSTALLATION DOCUMENTS TRAVELLING WITH GOODS PACKING, SHIPPING, PRESERVATION, HANDLING & STORAGE PROCEDURES FIELD FABRICATION ITEMS TRANSPORTATION DRAWING INSTALLATION INSTRUCTIONS OPERATING INSTRUCTIONS SPARE PARTS LISTS OR DATA PACKAGES OPERATING & MAINTENANCE MANUAL VENDOR CATALOGUE LUBRICATION SCHEDULE G-SPIR Package for Two Years Operating Spares CIVIL/STRUCTURAL/ARCHITECTURAL STATEMENT OF DESIGN CODES TO BE USED LIST OF COMPUTER SOFTWARE TO BE USED LIST OF ITEMS TO BE PRE-CAST LIST OF ITEMS TO BE PRE-STRESSED UNDERGROUND SERVICES DATA BUILDING PLANS DETAIL FABRICATION DRAWINGS ERECTION DRAWINGS BILL OF QUANTITIES LIST OF APPROVED CONCESSION AND DEVIATIONS Project Management of Change Records DCA Register CTN Register SOR Register Addendums to AGES Asst Integrity Process Safety Information Package Toxicity and Permissible Exposure Limits.

The terms of Contract / Agreement No: CON22 146 shall apply for any disclosure of this document to any third party.

X

X

X

X X X X

X X

X X

X

X X X X

X

RUWAIS LNG PROJECT

FINAL VENDOR DOCUMENTATION REQUIREMENTS SPECIFICATION

COMPANY DOCUMENT REF. RLNG-000-PM-SP-2303

CONTRACTOR DOC. REF.

215122C-000-JSM-2303

REVISION: 1

PAGE 12 OF 18

(Refer to RLNG-000- PM-SP-6005)

Physical Data and Reactivity Data Corrosivity Data Thermal and Chemical Stability Data Hazardous effects of inadvertent mixing of different materials (Safety Data Sheet used for compliance).

Process Flow Diagrams and material and energy balances including rated maximum capacity or throughput for continuous flow and batch processes

Maximum intended inventory of hazardous substances and rationale for managing inventories

Process steps, AIPS operational information, safe operating envelopes, and consequences of deviations from safe operating envelopes

Operating procedures / manuals Lists of HSECES Process and Instrumentation Diagrams Equipment specifications, drawings, and data sheets Design codes and standards Materials of construction specifications and piping specifications Relief system design basis and calculation performed to verify relief device settings, and relief lines stress analyses

Ventilation system design basis, design codes and standards used HSEIA / COMAH Dossier, including the Hazard Identification and Risk Analysis studies Risk registers, SBRA reports (as applicable). Technical Loss prevention and safety documents (e.g. HSE and loss prevention philosophies and design basis, hazardous area classifications, F&G layouts, escape route drawings, building fire and safety reviews)

Escape evacuation and rescue measures, ERP arrangements and ERP plans.

X X X X

X

X

X

X X X X X

X

X

X

X

X

X

The terms of Contract / Agreement No: CON22 146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

FINAL VENDOR DOCUMENTATION REQUIREMENTS SPECIFICATION

COMPANY DOCUMENT REF. RLNG-000-PM-SP-2303

CONTRACTOR DOC. REF.

215122C-000-JSM-2303

REVISION: 1

PAGE 13 OF 18

14.0 APPENDIXES

APPENDIX 1 - BINDER EXTERNAL & INTERNAL (INSIDE) COVER SHEET FOR MDRB & OMM

MANUFACTURING DATA RECORD BOOK (MDRB) COVER SHEET

The terms of Contract / Agreement No: CON22 146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

FINAL VENDOR DOCUMENTATION REQUIREMENTS SPECIFICATION

COMPANY DOCUMENT REF. RLNG-000-PM-SP-2303

CONTRACTOR DOC. REF.

215122C-000-JSM-2303

REVISION: 1

PAGE 14 OF 18

OPERATIONAL & MAINTENANCE MANUAL (OMM) COVER SHEET

The terms of Contract / Agreement No: CON22 146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

FINAL VENDOR DOCUMENTATION REQUIREMENTS SPECIFICATION

COMPANY DOCUMENT REF. RLNG-000-PM-SP-2303

CONTRACTOR DOC. REF.

215122C-000-JSM-2303

REVISION: 1

PAGE 15 OF 18

APPENDIX 2 - BINDER SPINE (SIDE) COVER SHEET FOR MDRB & OMM

The terms of Contract / Agreement No: CON22 146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

FINAL VENDOR DOCUMENTATION REQUIREMENTS SPECIFICATION

COMPANY DOCUMENT REF. RLNG-000-PM-SP-2303

CONTRACTOR DOC. REF.

215122C-000-JSM-2303

REVISION: 1

PAGE 16 OF 18

APPENDIX 3 – APPROVED BINDER SPECIFICATION

The terms of Contract / Agreement No: CON22 146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

FINAL VENDOR DOCUMENTATION REQUIREMENTS SPECIFICATION

COMPANY DOCUMENT REF. RLNG-000-PM-SP-2303

CONTRACTOR DOC. REF.

215122C-000-JSM-2303

REVISION: 1

PAGE 17 OF 18

APPENDIX 4 – ELECTRONIC (HARD DRIVE) EXTERNAL COVER SHEET FOR MDRB & OMM

The terms of Contract / Agreement No: CON22 146 shall apply for any disclosure of this document to any third party.

RUWAIS LNG PROJECT

FINAL VENDOR DOCUMENTATION REQUIREMENTS SPECIFICATION

COMPANY DOCUMENT REF. RLNG-000-PM-SP-2303

CONTRACTOR DOC. REF.

215122C-000-JSM-2303

REVISION: 1

PAGE 18 OF 18

APPENDIX 5 – MASTER DELIVERABLE INDEX LIST FORMAT

The terms of Contract / Agreement No: CON22 146 shall apply for any disclosure of this document to any third party.