REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
CT-EPC/017/SH/EPM/RPC-X/2023
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 1 / 22
ISSUE 1
VENDOR DOCUMENT MANAGEMENT PROCEDURE
1
0
11/July/2024
24/June/2024
IFF – Issued for Final
V.Petrovic
F. Posocco
F. Ghibaudo
IFR - Issued for Review
R. Montalbano
F. Posocco
F. Ghibaudo
Issue
Date
Reason for Issue – Revision Description
Prepared
Checked
Approved
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent.
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 2 / 22
ISSUE 1
CONTENTS
1 2 3 4
5
6
SCOPE AND PURPOSE …3 REFERENCE DOCUMENTS …3 DEFINITIONS …3 VENDOR’S DOCUMENT SET-UP …4
4.1 4.2 4.3 4.4 4.5 4.6
DOCUMENTATION REQUIREMENTS …4 DOCUMENT CLASSIFICATION …4 VENDOR’S DOCUMENT LIST…5 INSTRUCTION FOR DOCUMENT PREPARATION…6 AS-BUILT…8 QUALITY REQUIREMENTS FOR DOCUMENT PREPARATION …8
VENDOR’S DOCUMENT TRANSMISSION…11
5.1
TRANSMISSION METHODS…11
REVIEW PROCESS OF VENDOR DOCUMENTATION…11
6.1 6.2 6.3 6.4 6.5 6.6
CONTRACTOR REVIEW WORKFLOW…11 ACCEPTANCE STATUS CODES AND CONSEQUENT VENDOR ACTIONS …11 OTHER ISSUES RELEVANT TO COMMENT WORKFLOW…13 RE-ISSUANCE OF VENDOR DOCUMENTS TO CONTRACTOR …13 DOCUMENT SUBMISSION TO CTC …13 SUBMISSION TO ARH…14
7
PREPARATION OF VENDOR DATA BOOK …14
7.1 7.2
PRESENTATION…14 CONTENT …15
8
PROCEDURE FOR REVIEW/COMMENTS OF VENDOR DATA BOOK …17
8.1 8.2 8.3 8.4 8.5
REVIEW OF VENDOR DATA BOOK …17 REVIEW OF PRELIMINARY VENDOR DATA BOOK …18 REVIEW OF VENDOR DATA BOOK AT VENDOR’S PREMISES…18 REVIEW OF EDITABLE/ELECTRONIC COPY OF VENDOR DATA BOOK …18 FINAL DISPATCH OF PAPER AND ELECTRONIC COPIES OF VENDOR DATA BOOK …19
9
TABLES FOR VENDOR REFERENCE …19
ATTACHMENTS: Att.1 – Vendor’s Document List Att.2 – External Access to Maire Tecnimont SharePoint Online Att.3 – Binders Templates Att.4 – Vendor Document Review and Re-Issuance Cycle Att.5 – Indexes of Vendor Data Book Att.6 – Examples
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 3 / 22
ISSUE 1
1
SCOPE AND PURPOSE
This procedure describes the management and review process of vendor documentation for the project
REALISATION EN EPC D’INSTALLATIONS DE PRODUCTION DE LINEAR-ALKYL-BENZENE
<
2
REFERENCE DOCUMENTS
CONTRACTOR DOCUMENTS :
TCM DOC NO 4439-YZ-PC-000000001 4439-PZ-PC-00000000X 4439-SZ-PM-000000005
4439-YZ-PC-000000011
4439-PZ-PW-000000001
3
DEFINITIONS
COMPANY DOC NO
DOCUMENT TITLE
Document Numbering procedure Document Control Procedure ARH DOSSIERS REQUIREMENTS FOR SUPPLIERS Document Drawings Format and Drafting procedure Project WBS structure
CA/COMPANY SONATRACH DC-EPM
CONTRACTOR TECNIMONT SPA
PROJECT
ARH
CTC
VDM
REALISATION EN EPC D’INSTALLATIONS DE PRODUCTION DE LINEAR-
ALKYL-BENZENE <
Vendor Manual
MOM:
Minutes of Meeting
MR
SS
Material Requisition
Supply Specification
VDMS
Vendor Document Management System
PO
WR
VDL
IFI
Purchase Order
Work Requisition
Vendor Document List
Issued For Information
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 4 / 22
ISSUE 1
IFR
IFF
IFC
ASB
Issued For Review
Issued As Final
Issued For Construction
Asbuilt
4
VENDOR’S DOCUMENT SET-UP
4.1 Documentation requirements
The VENDOR shall keep as reference for the definition of its own DOCUMENTS the paragraphs and/or the table dedicated to “VENDOR DOCUMENTS” contained in the signed MR or SS enclosed to the PO, where the requirements relevant to the submission to CONTRACTOR (schedule, soft copies, class) are defined for each DOCUMENT and for the sets of FINAL DOCUMENTATION. Dossier for ARH shall be considered as per concerning procedures.
VENDOR shall also check the requirements relevant to documentation in all the other documents attached to the MR/SS.
4.2 Document Classification
All PROJECT Documentation, according to its typology, shall be attributed a category, which defines the COMPANY requirements about submission, review and approval, the code shall be indicated at least in the Deliverable List and shall be reported as attribute in the CONTRACTOR VDMS.
CONTRACTOR requirement about submission, review and approval, of vendor documentation shall be clearly indicated also in supply specification (refer to “contractor review code” column as per example of table below).
The vendor document requirement list to be present in supply specification shall be mainly as per example below:
Example of vendor deliverable list
Pos.
description
Document category (*): For Approval (1) For Review (2) For information (3)
Contractor review code (**): For Approval (A) for Review (R) for (I)
information
For propos al
N° of copies
Req’ d Date
As buil t
L E U N A M
“
I
G N R E E N G N E
I
n
i
(
”
I
I
E R E N E G N
I ’
D
d e r i u q e R
X
3
2
3
A
A
R
2
Design Drawing & Documents Nozzle 1 orientation Process basis design Piping line and list Special
of
3
,
E G A T N O M
E D
L E U N A M
“
n
i
,
E G A K C O T S
) L A U N A M
d e r i u q e R
T E
I
N O T A R E P O
,
I
N O T A L L A T S N
I
,
E G A R O T S
(
,
I
N O T A L L A T S N
I
”
E C N A N E T N A M
I
,
Y L B M E S S A
Note
E C N A N E T N A M
I
D N A
I
N O T A R E P O
L E U N A M
“
n
i
) L A U N A M
d e r i u q e R
”
I
R U E S S N R U O F
I
N O T C E P S N
I ’
D
) L A U N A M N O T C E P S N
I
I
R O D N E V
(
H R A R E S S O D
I
n
i
d e r i u q e R
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 5 / 22
ISSUE 1
Note
H R A R E S S O D
I
n
i
d e r i u q e R
) L A U N A M N O T C E P S N
I
I
R O D N E V
(
For propos al
N° of copies
Req’ d Date
As buil t
L E U N A M
“
I
G N R E E N G N E
I
n
i
(
”
I
I
E R E N E G N
I ’
D
d e r i u q e R
,
E G A T N O M
E D
L E U N A M
“
n
i
,
E G A K C O T S
) L A U N A M
d e r i u q e R
T E
I
N O T A R E P O
,
I
N O T A L L A T S N
I
,
E G A R O T S
(
,
I
N O T A L L A T S N
I
”
E C N A N E T N A M
I
,
Y L B M E S S A
E C N A N E T N A M
I
D N A
I
N O T A R E P O
L E U N A M
“
n
i
) L A U N A M
d e r i u q e R
”
I
R U E S S N R U O F
I
N O T C E P S N
I ’
D
Pos.
description
Document category (*): For Approval (1) For Review (2) For information (3)
Contractor review code (**): For Approval (A) for Review (R) for (I)
information
R
R
Piping (SP) list Instrumentation
item
4
5
3
2
up
Instrument process hook drawing Control/Sh utdown Philosophy and block Logic Diagrams
Notes:
(*) Document Category:
Vendor to note that the reason for issue indicated in the template (title block) of the Vendor documentation is referred to the COMPANY requirement about document submission (e.g. “Document Category”).
(**) Contractor review code:
CONTRACTOR requirement about document submission (e.g. “Contractor review code”) in some cases may be different from COMPANY requirement (“Document Category”), hence the reason for issue indicated in the template (title block) of the Vendor documentation could create misunderstanding. For these cases, Vendor to note that CONTRACTOR requirement about document submission (e.g. “Contractor review code”) is the most stringent, hence the review cycle of the vendor document shall be as per “Contractor review code”. Consequently, Vendor document stages and revision indexes shall be implemented in compliance with above mentioned review cycle.
4.3
VENDOR’S Document List
The VENDOR shall transmit for approval, within 15 calendar days from PO date, a detailed Document List, as per Attachment 1, with indication of the references to the “VENDOR DOCUMENTS” listed in the signed MR or SS enclosed to the PO.
The document list, relevant to the whole MR, shall be arranged per item or per type of material (only for bulk materials). See in ATTACHMENT 1 the instructions for filling up the VENDOR’s Document List.
Document List shall be firstly filled up with all the data requested in the Section 1; the Section 2 shall be filled during Project Development, while the Section 3 of the list shall be filled in preparation of the final issue, included in the FINAL DOCUMENTATION.
VENDOR shall send the Document list duly updated together with each transmission of DOCUMENTS, clearly highlighting in the last column any addition / modification / deletion of DOCUMENTS.
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 6 / 22
ISSUE 1
4.4
INSTRUCTION FOR DOCUMENT PREPARATION
4.4.1 Production software
The software to be used including its version has to be in compliance with the table below:
Function
Drawings General Graphics Spreadsheets Text documents PDF
Software
Version / Release
AutoCAD Rel. 2022 Microsoft PowerPoint Office 365 Office 365 Microsoft Excel Office 365 Microsoft Word Rel. 9.0 or later Adobe Acrobat 2020 or above BlueBeam Revu
4.4.2 Language
French is the contractual language between TCM and the CLIENT.
Any document by Vendor that is necessary for the proper transportation, storage, installation, operation and maintenance of the relevant scope of supply shall be dual language (French and English).
Documents to be submitted to Algerian Authorities have to be issued in the language defined by 4439- SZ-PM-000000005 as from their first issue.
All translations have to perfectly match the original versions. Partial translations will be rejected.
An exception is made to the below mentioned documents, which can be written in English only:
Inspection certificates
• • Welding Procedure Specification (WPS) and Procedure Qualification Record (PQR) • Calculation Notes. • Data sheets (API motors type). • Material Certificates • Reports
4.4.3 Identification and numbering system – CONTRACTOR CODE
The CONTRACTOR CODE to be applied on the VENDOR DOCUMENT shall be in compliance with Tecnimont Standard TM061 and Tecnimont procedure PR-Q03. It is made by alphanumeric fields, separated by dashes, as indicated here below:
4439 - XX - VD - TTMMMPPPPPPNNN
Job
N°
Type
EC
Job: EC:
4439 The EC field shall be equal to the one of the relevant MR (for Vendors’ documents) or to the one of the relevant WR (for Construction Subcontractors’ documents) assigned by Contractor
Type: document type always equal to VD N°:
identification number, composed as follows:
TT is the VENDOR DOCUMENT Typology code (2 letters, see TABLE A) MMM is the Number of the relevant MR (or WS) (three numbers) assigned by Contractor
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 7 / 22
ISSUE 1
PPPPPP is an alphanumeric code (6 characters), identifying the item/material within the MR, for example the item code, or the position in the MR, or other; to be omitted for MR relevant to bulk materials (piping, electrical, etc). Refer note below. NNN is a serial number (3 digits). Refer note below.
Note: In case 2 digit serial number (NN) is consider for any of the MR, MR owner shall increase the alphanumeric code (PPPPPPP) by one digit to keep the overall count of Vendor document typology + number of relevant MR/WS + alphanumeric code + serial numbers to 14 characters i.e., TTMMMPPPPPPNNN or TTMMMPPPPPPPNN.
Detailed instructions for fields PPPPPPP and NN shall be defined by Contractor, who shall inform the VENDOR accordingly.
4.4.4 Sub-Vendor’s Documents Identification and Numbering System
When Vendor submits Sub-Vendor’s documents to CONTRACTOR, CONTRACTOR document numbers shall also be assigned to them in accordance with above paragraph.
4.4.5 Rule of indication for Reference Documents
Referenced document must be mentioned using CONTRACTOR CODE FIRST, and TITLE, eg: 4439-YZ-PC-000000003 “Vendor document management procedure”
4.4.6 Electronic document file naming
Files must be named as per CONTRACTOR syntax 000000003_IS0.docx)
requirements
(e.g. 4439-YZ-PC-
4.4.7 Documents and Drawing sizes
All PROJECT DOCUMENTATION shall be in accordance with International standard sizes:
Size A4 A3 A2 A1 A0
Dimension (mm) 210 x 297 297 x 420 420 x 594 594 x 841 841 x 1189
•
•
• •
A1 will be used for Plot Plans, P&ID, etc. A1 documents shall be created in order to remain legible if printed in A3 format. This will permit reproduction with standard photocopiers and computer printers whilst remaining readable. A3 will be used for standard diagrams and drawings. A3 documents shall be created in order to remain legible in A4 format. A4 will be used for all other documents. A0 size is allowed.
4.4.8 Documents/Drawings Project formats
For documents/Drawings Projects Formats refer to 4439-YZ-PC-000000011 Document Drawing format and Drafting Procedure.
4.4.9 Remarks for multi sheet documents
Each drawing sheet (size A1 to A2) shall be considered as a separate drawing and shall be assigned unique CONTRACTOR number.
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 8 / 22
ISSUE 1
Multiple sheets DOCUMENTS are allowed for A3 and A4 size drawings, and one CONTRACTOR number shall be assigned to the whole DOCUMENT. In case each drawing sheet is liable of separate revision (e.g. electrical and instrumentation schemes, material list, typical drawings), a table must be inserted in first or second sheet, showing the list of the following sheets with the issue status of them; such cover sheets shall be revised in case of any revision of any of the following sheets.
4.4.10 Measurement Units
Units of measurement shall be Metrics as defined in Basic Engineering Design Data except the following:
• • • • •
Pipe size (inches, nominal) Flange rating (pound per square inch) Wire size (Birmingham wire Gage) Anchor bolts (diameter in inches) Stud bolts (inches)
4.5 AS-BUILT
For Equipment or Factory Assembled Items Purchase Orders, upon completion of shop fabrication and inspection, As-built documents will be requested from Vendor once IFC/IFI revision is returned code A by Contractor (“As-built” documents shall contain all changes made during fabrication and inspection, if any, as well as CONTRACTOR’s comments given at the IFA/IFR/IFI/IFF/IFC stage).
This requirement is applicable to drawings (ref. to yellow highlight in table A) and diagrams (ref to green highlight in table A).
This information shall be mentioned on the VDL. ASB revisions will follow Contractor review cycle. ASB revisions shall be issued with native files to Contractor for review.
Formal As-Built release might be avoided by Vendor in particular cases upon agreement with Contractor. In such a case, IFC/IFF revisions will be considered as final revisions, therefore these shall be issued with native files.
ASB revisions – at least IFC stamped – will be inserted into Vendor Data Book. Vendor shall be responsible for the provision of As-built Documents showing any previously agreed changes, carried out to the equipment / materials supplied. This responsibility shall extend through the warranty period for any subsequent installation and commissioning work and subsequent hand-over to Plant Operations that may be carried out by or on behalf of Vendor. Revised documents / data shall be submitted with the same quantities, codes and sequences, as final drawings, and should be accompanied by a statement describing the reason for the change and the source of authority for the change.
4.6 Quality Requirements for DOCUMENT Preparation
4.6.1 Date and Names
Dates shall always indicated in the format: DD Mmm YYYY, e.g. 15 Jan 2023.
Personnel working on the DOCUMENT shall be identified with Name (at least first letter) and Surname.
4.6.2 Description of issue
The Description of the each issue (to be indicated in the revision table) must clearly individuate the level of development / the intended use of the DOCUMENT in compliance with table below:
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 9 / 22
ISSUE 1
Reason for Issue Revision Description Revision number
IFA
IFR
IFI
IFC
IFF
CAN
SPD
ASB
Issued for Approval
0, 1, 2, 3, …
Issued for Review
0, 1, 2, 3, …
Issued for Information
0, 1, 2, 3, …
Issued for Construction
0, 1, 2, 3, …
Issued as Final
0, 1, 2, 3, …
Cancelled
0, 1, 2, 3, …
Superseded
0, 1, 2, 3, …
As Built
50, 51, …
Category 1 1
Stages IFA – Issued for Approval IFA – Issued for Approval
2 2
3 3
IFR – Issued for Review IFR – Issued for Review
IFI – Issued for Information IFI – Issued for Information
Rev. index Rev. 0 Rev. 1, 2, 3, etc. Rev. 0 Rev. 1, 2, 3, etc. Rev. 0 Rev. 1, 2, 3 etc.
All Category IFF – Issued as Final All Category IFF – Issued as Final
All Category IFC – Issued for Construction Rev. 1 Rev.2, All Category IFC - Issued for Construction etc. Rev 1 Rev 2, 3 etc. Rev. 50 Rev. 51, 52, etc.
All Category As-Built (ASB) All Category As-Built (ASB)
3
Note
Any other issues after incorporation of initial comments
Any other issues after incorporation of initial comments
Any other issues after incorporation of initial comments
Any other issues after initial “Issued for Construction”
Any other issues after initial “Issued as Final”
Any other issues after initial “As Built”
The VENDOR has the obligation to transmit without delay any revision of the DOCUMENTS, including those “as-built”, allowing the CONTRACTOR to upload them in the electronic document management system, so providing the Project Teams at Head Office and Site with updated information.
4.6.3 Document Checking
All VENDOR DOCUMENTS shall be prepared in compliance with VENDOR’s certified quality system, incorporating the requirements set-up in the MR.
Check of documentation during preparation shall be carried out according to quality procedure of the VENDOR, which shall be shown on request of CONTRACTOR’s Inspector or Auditor.
The VENDOR shall also check with same criteria the DOCUMENTS issued by his Sub-vendors before sending them to CONTRACTOR.
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 10 / 22
ISSUE 1
4.6.4 “HOLDS” Management
When details of a DOCUMENT have not been finalized, but issue is required for other purposes, the area of the DOCUMENT not finalized shall be clearly identified as “HOLD”.
4.6.5 Revision of Documents
When any revision is made, the revised portion of a document and drawing shall be clearly identified in accordance with the following manners. And old revision marks or indications shall be removed upon further revision.
For Documents prepared in MS Word Format
The revised portion, line or paragraph, shall be identified with a line on left side of the text modified.
For documents prepared in MS Excel Format
Changes shall be highlighted by placing the appropriate revision number in the revision column adjacent to the updated data
For drawings extracted from the Project designated software, such as SmartPlant P&ID, E3D, etc.
The specific revision marks or indications provided in the respective seed files shall be applied.
For CAD drawings
The implemented modifications on the relevant drawings must be clearly identified by clouds and marked with a triangle with the revision letter. Example of rev B: B
For multiple sheets documents
Cover sheet and index sheets of the multi-sheets documents will be always revised, with indication of individual sheet revision. And revision of multiple sheets documents shall in principal be issued in total, i.e. including pages which are not changed.
4.6.6 Document Filling /Archiving
The VENDOR has the responsibility to file and archive orderly the Project DOCUMENTS in accordance with the relevant documented procedures set-up in its certified quality system.
The VENDOR shall keep in his file for 10 years at least the originals of DOCUMENTS issued, including all the FINAL DOCUMENTATION.
5
VENDOR’S DOCUMENT TRANSMISSION
5.1
Transmission methods
Vendor shall use CONTRACTOR’s Vendor Document Management (VDM) System for exchange of electronic documentation with CONTRACTOR.
Kindly refer Vendor Manual (Attachment-6) for details regarding the Vendor Document Management system to be followed.
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 11 / 22
ISSUE 1
6
REVIEW PROCESS OF VENDOR DOCUMENTATION
6.1 CONTRACTOR review workflow
CONTRACTOR and COMPANY, within the stipulated period, shall Comment, Approve, or Reject VENDOR’s documentation. The stipulated period is 15 working days unless a different period is specified in Supply Specification. The CONTRACTOR shall attach the commented DOCUMENTS to a transmittal, indicating Communications or Comments (if any) and the Acceptance Status Code for each DOCUMENT reviewed. Transmittals and Commented documents are sent to the VENDOR usually in electronic form only.
Acceptance of DOCUMENTS (without any comment) has to be communicated in any case to the VENDOR by transmittal. VENDOR is requested to acknowledge by e-mail the receipt of such transmittals/email.
6.2 Acceptance Status Codes and consequent VENDOR actions
The vendor document review will contain the following levels coding:
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 12 / 22
ISSUE 1
Code A
Code AC
Codes
Meaning
Action
Accepted
further comments. Work
No may proceed
Accepted with Resubmit
comments,
resubmit
The VENDOR shall revise the DOCUMENT according to the CONTRACTOR comments and shall it within 10 working days after receipt of the comments and in the meanwhile can the consequent activities.
proceed
with
Code CR
Commented – Resubmit for Acceptance
The VENDOR shall revise the DOCUMENT according to the CONTRACTOR comments and shall resubmit it
within 10 working days after receipt of the comments but must DOCUMENT acceptance to proceed with the consequent activities
wait
Code NA
Not accepted, Resubmit
serious
The DOCUMENT is rejected, due to or incompleteness, the VENDOR shall revise
error then
to
and/or complete it and submit it again the CONTRACTOR within 10 working days from the rejection. VENDOR date of the cannot activities defined
proceed with
Code INF
Not Reviewed – for information only
in the DOCUMENT itself. If the rejected, its is DOCUMENT be not shall transmission considered as fulfilment of contractual obligations
The DOCUMENT has not been it has been reviewed since considered for information only. Any data/information contained the document has been in full considered responsibility of the vendor.
under
CONTRACTOR shall also indicate one of the following Acceptance Status Codes in the Acceptance Status box (here below) present on each reviewed DOCUMENT:
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 13 / 22
ISSUE 1
Acceptance status code
Eng.
Dept.
Date
Comment status code: A – Accepted AC – Accepted with Comment, Resubmit
CR–Commented-Resubmit for Acceptance NA – Not accepted, Resubmit INF – Not reviewed, for information only
IMPORTANT: CONTRACTOR acceptance of this Document does not relieve the VENDOR from full compliance with contractual obligation
6.3 Other issues relevant to comment workflow
• When some CONTRACTOR’s information is not yet defined at the time of DOCUMENT
review (for instance the orientation of nozzles), the CONTRACTOR shall clearly indicate it as a “HOLD” in the commented DOCUMENT. The VENDOR shall revise the DOCUMENT at the receipt of the “HOLD” information.
•
•
•
•
Contractor’s comments on submitted Vendor’s documents are not to be considered as authorization to change the scope of work. After receiving the CONTRACTOR comments the VENDOR must carefully analyze them. In case comments have significant impacts on contractual obligations (such as technical guarantees, delivery terms, etc.), the VENDOR must inform immediately in writing the CONTRACTOR SPECIALIST to due clarifications and agreement before proceeding with such work.
In case the VENDORS’ DOCUMENTS are found by CONTRACTOR not compliant with contractual requirements even at the second review, VENDOR may be requested to attend a meeting at CONTRACTOR’s office for definition of pending points.
In case the VENDOR modifies DOCUMENTS already “Accepted”, CONTRACTOR has the right to back charge the VENDOR of the ensuing costs, if any, e.g. for revising design documents.
The CONTRACTOR’s acceptance of VENDORS’ DOCUMENTS does not relieve the VENDOR from full compliance with contractual obligation, technical mistakes or inconsistencies, nor from his whole liability, and permission to proceed does not constitute acceptance or approval of design details, calculations, analyses, test methods or materials developed or selected by the VENDOR.
6.4 Re-issuance of Vendor Documents to CONTRACTOR
Refer to attachment 4.
6.5 Document submission to CTC
Some vendor documents shall be submitted to CTC’s approval by Contractor.
CTC’s Comments, even received after the completion periods between Vendors and Contractor, will have to be taken into account by the Vendor, which will be obliged to re-issued a new revision of the document.
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 14 / 22
ISSUE 1
When issuing the documents in numerical revision the Vendor shall take into account possible comments and indicate in the title block in description area the CTC’s report number with the mention like “Document issued for construction” - Approval dated by CTC.
6.6
Submission to ARH
Refer to instructions 4439-SZ-PM-000000005 ARH DOSSIERS REQUIREMENTS FOR SUPPLIERS.
When an ARH dossier is necessary, the vendor shall identify the doc in its VDL (both preliminary and final).
7
PREPARATION OF VENDOR DATA BOOK
This chapter is a description of Vendor Data Book preparation requirements to Vendor and checking points to be done by Contractor.
« Preliminary Vendor data-book » means an editable/electronic file of each data-book identified by an alphabetic revision (A, B, C…) in IFR status, for review by the Contractor.
« Final Vendor data-book » means an editable/electronic file of each data-book identified by a numerical revision (0, 1, 2…) in IFC status for review and approval by the Contractor.
Submission of Preliminary Vendor data-book is allowed once:
•
•
•
The Final data-book INDEX is reviewed without comment and returned code A by the Contractor All Vendor Data Book’s documents are reviewed without comments (code A) in their ultimate issue status (IFC/IFF or ASB) After the Final Inspection, FAT and delivery of I.R.N for the “Manuel d’Inspection Fournisseur” (Vendor Inspection Manual)
On Vendor’s request, the TCM Discipline Leader will send the “Register” report from VDL, which lists the status of each document of the PO.
When Contractor’s review is closed, the VDB front sheet is returned with a punch list to Vendor. Contractor has to reserve its right not to return the paper copy to Vendor.
7.1
Presentation
7.1.1 Binders
Vendor shall provide Vendor Data Book in .pdf files ready to be printed out hard copy by Contractor.
Vendor Data Book shall consist of the following volumes (Title shall be both in English & French): Green for the “MANUEL D’INGENIERIE” (ENGINEERING MANUAL) – VOLUME 1 • Red for the “MANUEL DE STOCKAGE, MONTAGE, INSTALLATION, OPERATION ET • MAINTENANCE” INSTALLATION, OPERATION AND MAINTENANCE MANUAL) – VOLUME 2 Blue for the “MANUEL D’INSPECTION FOURNISSEUR” (VENDOR INSPECTION MANUAL) – VOLUME 3
(STORAGE, ASSEMBLY,
•
In addition to Vendor Data Book volumes listed here above, Vendor shall prepare the FINAL / TECHNICAL ARH DOSSIER as per instructions provided in 4439-SZ-PM-000000005 ARH DOSSIERS REQUIREMENTS FOR SUPPLIERS, if applicable.
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 15 / 22
ISSUE 1
The ARH dossier must be systematically stand alone.
Cover sheet and spine model for binders and model for CD Rom will be as per Attachment 3. Each volume shall include a volume index.
7.1.2 Filing By Type
Each PART (PART I …), each chapter (1, 2, 3 …) and sub-chapter (1.1, 1.2, 1.3 …) shall be divided and identified by a divider bearing the title of the corresponding section.
The Vendor, if necessary, shall adjust the split per volume.
7.1.3 Front Page Identification
Each document included in the Vendor Data Book shall have a front page (using the Contractual form as per 4439-YZ-PC-0000000011, identified as minimum by the following references:
• • • •
Number of the page / total number of pages (per document), Contractor Purchase Order number, PO description, name of Vendor PO Item number (or Tag number).
CONTRACTOR title block – coversheet duly completed with the CONTRACTOR return code “A” (approved) & signature.
7.2 Content
7.2.1 “MANUEL D’INGENIERIE” (ENGINEERING MANUAL)
The compilation of VENDOR’s drawings and data will be made by VENDOR in accordance with CONTRACTOR requirements. It shall provide sufficient information about design data and technical information of the supplied equipments.
The Engineering Data Book “As-Built” duly approved shall be available AT DAY OF FINAL INSPECTION and the required editable/electronic files shall be provided in accordance with contractual date of requisition.
In case of package or complex equipment, each part will include the required documents of each equipment and material.
7.2.2 “MANUEL DE STOCKAGE, MONTAGE, INSTALLATION, OPERATION ET
MAINTENANCE” (STORAGE, ASSEMBLY, INSTALLATION, OPERATION AND MAINTENANCE MANUAL)
The Storage, Assembly, Installation, Operation Manual and the Maintenance Manual (two separate manuals) shall give sufficient information to allow plant operators to install, to start-up, to operate, to monitor under normal conditions, and to shut-down the equipment efficiently and safely.
These manuals will be based on recognized international standards and codes.
They shall also warn the plant operators against any actions having serious consequences as far as health, safety and performance are concerned, and give sufficient information for actions to be taken in cases of emergency.
The Storage, Assembly, Installation, Operation Manual and the Maintenance Manual duly approved shall be available AT DAY OF FINAL INSPECTION and the required editable/electronic files shall be
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 16 / 22
ISSUE 1
provided in accordance with contractual date of requisition.
7.2.2.1 Storage. Erection and installation instructions
Storage & Erection store/install/erect the equipment.
instructions shall
include all procedures and drawings necessary
to
A detailed schedule shall be prepared beginning with handling & lifting drawings, erection sequence, inspection, tests, cleaning and flushing, alignment and running in of pumps and compressors, burner checks, instrument calibrations, electrical continuity checks, filling of lube and circulating systems, etc. to actual start-up. The manual shall include simplified sketches and diagrams showing procedural steps and references to more detailed literature on drawings.
Operating instructions shall include:
• Simplified flow diagrams of equipment and instructions required for starting and stopping
equipment.
• Descriptions of how the equipment operates, as well as normal operating conditions to be
expected, alarm conditions and abnormal operating parameters.
Caution notes as to dangerous or critical situations which may occur due to poor operating procedures or malfunction of equipment.
• Trouble-shooting check lists and guides.
• Shut-down under normal and emergency conditions and prepared for maintenance. This chapter will include the specific operations concerning activities during first start up, as well as the activities for preparation of the first start up.
• Safety alarms and shut-down.
7.2.2.2 Presentation of the operation instructions
The data and the specifications will be collected and presented as follows :
- Data and technical specification
- Operational information
- Technical descriptions
7.2.2.3 Maintenance instructions
The maintenance instructions must transmit clearly to all staff members on different levels required and sufficient information in order to ensure correct and effective maintenance of all equipment, systems or unit under safe conditions. It will be based on recognized international standards or codes. The Contractor advices the Operating Company which standard or code should be proposed before start of the establishment of the Manual. Maintenance instruction shall clearly specify the VENDOR recommendations for the equipment maintenance. It shall include as a minimum
a. Pictures and diagrams showing means of assembly and disassembly for all components, b. Description of calibration, repair, adjustment procedures, c. Expanded views with parts lists of each item of assembled equipment, d. Normal routine preventative maintenance procedures and scheduling, e. List of special tools, f. Spare Part List
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 17 / 22
ISSUE 1
g. List of lubrification sheets
7.2.3 “MANUEL D’INSPECTION FOURNISSEUR” (VENDOR INSPECTION MANUAL)
The Vendor Inspection Manual covers all aspects related to mill materials, fabrication, construction and certification aspects of the equipment ordered.
The content of the Vendor Inspection Manual will vary dependent upon the type, size and complexity of the equipment but it shall contain all documentation referenced in the Inspection Test Plan and all records of testing required by the Purchase Order/Material Requisition and listed in the Vendor Document List.
The Vendor Inspection Manual duly approved shall be available AT DAY OF SHIPMENT and the required editable/electronic files shall be provided in accordance with contractual date of requisition.
The Vendor Inspection Manual shall be prepared with following index and include both numbering Contractor & Company:
Refer to Attachment 6.
7.2.4 ARH Dossier
Preparation and compilation of ARH dossier is subject to a specific instruction.
Refer to 4439-SZ-PM-000000005 ARH/DGM DOSSIERS REQUIREMENTS FOR SUPPLIERS
8
PROCEDURE FOR REVIEW/COMMENTS OF VENDOR DATA BOOK
The Vendor shall start preparation and compilation of Vendor Data Book at day of PO award. It will allow a continuous monitoring of design, engineering, manufacturing, maintenance and local regulation operations.
Vendor shall be responsible for ensuring that the provision of quality assurance and quality control by any Sub vendor satisfies the quality and the certification requirements of the order.
8.1 Review of Vendor Data Book
Vendor Data Book Index shall be transmitted in accordance with contractual date of the requisition, for review of the concerned discipline.
For Review, index shall be prepared with the external cover sheet(s) of the VDB, spine cover sheet(s), internal front page(s) duly completed and Index of each volume.
Typical index are given in Attachment 6 of this specification and the Vendor is requested to issue its own Vendor Data Book Index, based on this Typical.
The Vendor Data Book Index will be recorded in the Vendor documents Management System and reviewed by relevant discipline. The Vendor Data Book Index duly commented or reviewed without comments will be returned to Vendor, with duly completed Vendor Data Book Comment Sheet, either in Code A (reviewed without comments) , CA (reviewed with comments) and NA (rejected).
In case of code NA, Vendor Data Book Index is rejected, means that VENDOR is required to resubmit Vendor Data Book Index after modification.
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 18 / 22
ISSUE 1
8.2 Review of Preliminary Vendor Data Book
For equipment with Quality Category CQ1 and CQ2, one complete documentation review of Vendor Data Book will be done at Vendor’s premises.
For each level of inspection and once the Vendor Data Book Index is reviewed without comments and no later than 6 weeks before final inspection, VENDOR shall supply CONTRACTOR with one editable/electronic copy of the Preliminary Vendor Data Book for review. If some documents commented, Vendor shall draw up list of outstanding documents.
The Preliminary Vendor Data Book will be recorded in the Engineering Document Management System and reviewed by relevant discipline. The Preliminary Vendor Data Book will be checked by Contractor and will be returned to Vendor with comments.
In case of code NA, Vendor Data Book is not accepted means that VENDOR is required to resubmit the Vendor Data Book after modification.
8.3 Review of Vendor Data Book at Vendor’s Premises
At time of Intermediate or Final Inspection or upon request of Inspector, VENDOR DATA BOOK will be reviewed by Contractor.
The inspector nominated by CONTRACTOR will review during inspection status of Vendor Data Book and Vendor shall make available Vendor Data Book, duly prepared.
Upon request of Contractor, additional review of VDB could be achieved by Inspector.
At day of Final Inspection, the assigned Inspector will review the VDB updated according to the Vendor Data Book comments. Inspection Release Note will be issued by Inspector once Inspection will be found satisfactory: inspections of goods are found satisfactory and documentation review is found satisfactory. VENDOR will then transmit the Inspection Release Note to Contractor.
If Vendor Data Book is not prepared, compiled as requested, Inspector will not issue the Inspection Release Note and Vendor will be requested a recovery plan within 8 days after breach notification.
8.4 Review of editable/electronic copy of vendor data book
Native files are requested for:
• Drawings • Datasheet Lists. • • OPERATION MANUAL & MAINTENANCE MANUAL • Spare parts lists
The architecture of electronic copies shall strictly follow the VDB index, based on signets (bookmarks) or files architecture.
One general scan without any files or signets will be automatically rejected.
Editable/electronic files will also include additional files (in native format).
• VDB index
Spine and front page of VDB for each data book
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 19 / 22
ISSUE 1
8.5
Final Dispatch of paper and electronic copies of vendor data book
Vendor Data Book shall be provided by Vendor in 10 nos. paper hard copies and 3 nos. electronic copies in the form of hard disk drives. Both hard and electronic copies shall be delivered to construction site by Vendor. Electronic soft copies shall be properly formatted and filed to be ready to be printed out as hard copies. Electronic soft copies will be made once all comments on Vendor Data Book comment sheet have been closed by Vendor and reviewed without comments by Contractor, and all documentation successfully completed.
Vendor will then provide the final editable/electronic files as per Contract requirements and Post Order Manager instructions. Dispatch of the editable/electronic files shall be done in accordance with the contractual date of the requisition. Vendor is responsible to respect the allowed duration time.
9
TABLES FOR VENDOR REFERENCE
Below tables are provided for vendor reference:
• TABLE A – TECNIMONT VENDOR DOCUMENTS TYPOLOGY
TABLE A – TECNIMONT VENDOR DOCUMENTS TYPOLOGY
CLASS CODE VENDOR DOCUMENTS TYPOLOGY
P
PROJECT MANAGEMENT / PLANNING / PROCUREMENT DOCUMENTS / QUALITY ASSURANCE / HSE ASSURANCE
PL
PP
PS
PQ
Document List; Document Issuing Plan
Manufacturing schedule; Fabrication Plan; Progress Reports
List of Subvendors/Subcontractors; List of Suborders; Copy of suborders
Quality Assurance Documents (Quality Plan, Site Quality Plan, Organization Chart, Audit plans)
PH
HSE Assurance Documents (HSE Plan, Site HSE Plan)
Q
QUALITY CONTROL/INSPECTION & TESTING
QC
QS
QP
Inspection & Test Plan (Quality Control Plan)
Site (Construction) Inspection & Test Plan
Inspection and Testing procedures (functional, performance, material, pressure (hydraulic) tests)
F
B
QT
Factory Acceptance Test Procedures / Site Acceptance Test Procedures
FABRICATION & WELDING
FW Welding Books: Welding Process Specifications (WPS), Welding Process Qualifications (PQR), Welding maps; Welding Certificates; Welding Repair Procedures; NDE Procedures; Heat Treatment Procedures
FO
FP
BC
Description of the fabrication cycle, Other Manufacturing Procedures (casting, etc.)
Coating and Painting Procedures
BASIC AND PROCESS DATA / PERFORMANCE DESIGN DATA
Heat/Material Balance; Thermal Calculations; Utilities calculation/consumption; Effluent/Waste List; Functional sizing calculations; Process Calculations, Performance Curves; Reliability & Availability Analysis
BO
Description of working; Cause/effect diagrams
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 20 / 22
ISSUE 1
CLASS CODE VENDOR DOCUMENTS TYPOLOGY
BD
Process Flow Diagrams; Piping & Instrument Diagrams; Machinery Circuits diagrams (lubrication / hydraulic / pneumatic)
BUILDING
Building Architecture
Building HVAC
Building Electrical
Building Instrumentation
Building Plumbing
Building Telecom
Building Equipment
Building Fire and Gas
Building HSE
GENERAL CONFIGURATION - EQUIPMENT LIST/DATA SHEETS
Equipment List; Auxiliary and other Components lists
Equipment Data Sheets/Specifications
Fire Fighting Equipment Data Sheets and Drawings
BB
BH
BN
BJ
BU
BT
BQ
BK
BS
GE
GS
GH
GP
Spare Parts Lists, SPIR forms, Spare Parts Drawings (precomm / comm / capital / operation spare parts)
GL
GT
LG
Lubricants Lists and Quantities (Schedules), Lubricant Specifications
List of special tools (erection, testing, operation)
LAYOUTS / GENERAL ARRANGEMENTS / FOUNDATION DATA
Equipment layout, General Arrangements (with data for foundations); Plot plans, Layouts and requirements for UG services (sewers, piping / cable routing), Instrument/Electrical location layouts
LF
Foundations (or Process concrete structures) / Supports Calculations & Design
HSE DESIGN
HG Material Safety Data Sheets
HN
HF
SC
SD
SS
RC
RD
Noise Source Data Sheets
Sources or Areas of Release Data Sheets, Hazardous Areas Classification Drawings
MECHANICAL DESIGN (STATIC COMPONENTS)
Mechanical Calculations (Design/Code)
Vessels / Tanks / other Pressure Equipment Drawings - Nozzle Orientation
Auxiliary Steel Structures Specifications & Drawings
MECHANICAL DESIGN (ROTATING COMPONENTS)
Mechanical Calculations (rotating elements, vibrations, etc)
Machinery / Rotating Equipment Drawings
RM Other Mechanical Equipment Drawings incl. Component Cross-sectional Drawings
PIPING DESIGN
Piping Calculations (design, stress)
Piping Arrangement/Layouts, Piping Isometrics, Tie-in drawings
Piping Components General Specifications / Classes; Supports Specifications & Drawings
PC
PD
PG
INSTRUMENTATION / AUTOMATION & PROCESS CONTROL DESIGN
IC
Instrumental Calculations (instrument sizing, SIL, etc)
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
G
L
H
S
R
P
I
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 21 / 22
ISSUE 1
CLASS CODE VENDOR DOCUMENTS TYPOLOGY
IS
IL
IP
IV
Instrument Data Sheets & Specifications
Instrument list, I/O lists, Alarm and trip lists
Instrumentation / Instrumental Panels Construction Drawings
Instrumental component drawings (instrumentation, valves, etc)
IW Instrumental wiring diagrams: Interconnection diagrams, DCS/PLC interfacing diagrams
ID
Logic Diagrams, Loop Diagrams, Description of operating sequences, Lists of alarm and interlocks
E
ELECTRICAL DESIGN
EC
EU
ES
EE
EL
ED
AC
AE
AS
AJ
A
Electrical Calculations; Electrical Curves
List of Electric Users / Electrical Consumptions
Motors, Switchgears, Variable Speed Drivers, other Electrical Equipment Data Sheets / Specifications
Motors, Switchgears, Variable Speed Drivers, other Electrical Equipment Drawings
List of cables (Electrical/Instrumental)
Electric operating diagrams, one-line and interconnection diagrams, typical wiring diagrams, electric tracing diagrams
CIVIL DESIGN / STEEL STRUCTURES DESIGN
Steel Structures Calculation reports
Steel Structures Assembly Drawings
Steel Structures Shop Drawings
Steel Structures Joint Detail Drawings
AM Steel Structures Mark Lists
AA
Steel Structures Accounting
D
TRANSPORTATION, STORAGE, PRESERVATION & SITE INSTALLATION
DP
DT
DS
DI
DB
DL
OI
OP
Packing Lists
Shipping and Handling Instructions / Transportation drawings
Storage and Preservation Instructions / Drawings
Installation, Field Assembling, Precommissioning Instructions/Drawings
DESIGN FINAL DOCUMENTATION
MANUFACTURER DATA BOOK - or any subtype of
MANUFACTURER DATA BOOK – Index of Contents
OPERATION AND MAINTENANCE
Operating Instructions (Start-up and Operation)
Maintenance Instructions / Procedures
OM Installation, Operation and Maintenance Manual (IOM) - or any subtype of
OL
Installation, Operation and Maintenance Manual (IOM) – Index of Contents
CERTIFICATION OF MANUFACTURING/ERECTION
Certification Dossier (Collection of Certification for Equipment/Materials)
Certification dossier - index of content
CONSTRUCTION PLANS, SPECIFICATIONS, SCHEDULES & FINAL DOSSIER
Site Construction Procedures (HSE / Quality / Other)
Temporary Facilities Layouts and Drawings
Construction Execution Plans
MB
ML
CP
CT
CE
O
M
C
This document is property of Tecnimont S.p.A. and cannot be used by others for any purpose, without prior written consent
VENDOR DOCUMENT MANAGEMENT PROCEDURE
REALISATION EN EPC
D’INSTALLATIONS DE PRODUCTION
DE LINEAR-ALKYL-BENZENE <
TCM IDENTIFICATION CODE
4439-YZ-PC-000000103
SHEET 22 / 22
ISSUE 1
CLASS CODE VENDOR DOCUMENTS TYPOLOGY
CS
CG
Construction Schedules
Construction General Specifications
CM Method Statements
CJ
CA
CD
Job Safety & Environmental Analysis
MAR (Material Approval Requests)
Field Inspection & Certification Dossier (Collection of Certification for Site Erection / Construction)