Episode 9 — Retrospective Ritual (Tecnmont SKIKDA)

Episode 9 — Retrospective Ritual (Tecnmont SKIKDA)

What Worked (SEA)

  • Streamline: CSV SoT created immediately; EP items staged as Parked and mirrored across manifests + CSV Decision_Notes.
  • Enrich: Locked variant (hazardous‑area config), power (heater 240 V 1Φ), with precise offer/spec citations; hazards matrix computed with weakest_link_flag.
  • Accelerate: Spec Cross‑walk built with Section_Title + Page/Line; CPQ list pre‑grouped by subsystem (alarms 24 VDC, Ex e JB, optional Ex d chiller).

What Didn’t / Friction Observed

  • EMC declaration and Ex/IP certificates not attached; reliance on references in the codes index and Vendor Data Book slowed gate confidence.
  • IP minima ambiguity (spec IP65 vs potential outdoor IP66 expectation) needs explicit confirmation or upgrade path.

Standards Deltas (Implemented)

  • CSV coupling: Decision_Notes now consistently mirror EP Item_IDs; kept CSV schema intact.
  • Cross‑walk discipline: Added explicit Section_Title + Page/Line for IP minima (spec), area class minimums, variant/power, and chiller IP/power.
  • Hazards table: Added explicit Ex e JB vs Ex d chiller differentiation; weakest_link_flag set by evidence posture.

Metrics & Signals (qualitative)

  • Evidence completeness: EP items Parked; RFI issued for EMC and ATEX/JB/IP certificates.
  • Gates: variant_locked true; power_decided true; environmental minima cited; regulatory declarations → RFI.
  • CPQ readiness: subsystem mapping covers alarms 24 VDC, Ex e JB, optional Ex d chiller.

Hypotheses for Episode 10

  • If EMC and Ex/IP certificates arrive early, weakest_link_flag can be cleared and statuses flipped to Compliant without rework.
  • Explicit outdoor IP66 confirmation (or upgrade) will preempt TBE queries and stabilize the hazards matrix.

Next Actions (feed to Episode 10 Onramp)

  • Attach vendor EMC declaration (IEC 61000/61326/NAMUR) and ATEX/IECEx certs; update EP statuses from Parked→Attached.
  • Confirm IP target (IP66 vs IP65) and JB/signage Ex/IP specifics; update hazards matrix and Decision Table accordingly.
  • Finalize CPQ mapping with any chiller selection and corresponding power variant.